Summary of MDNR Heart of the Great Turtle Island Construction Bidding Documents

This is a comprehensive bidding package prepared by the Michigan Department of Natural Resources (MDNR) in partnership with the Department of Technology, Management and Budget (DTMB) State Facilities Administration for a major construction project titled "Heart of the Great Turtle Island / Gchi Mshiikenh Deh Minising" located in Moran Township, Michigan at Father Marquette National Memorial. The project involves construction of a new Learning Commons building, Powwow Grounds pavilion structures, and associated site and utility work. Bids were due electronically through the SIGMA VSS website by 2:00 p.m. Eastern Time on December 18, 2024, with a mandatory pre-bid conference and optional site tour scheduled for December 6, 2024 at Straits State Park Headquarters. The contract award date was expected on or before February 19, 2025, with construction commencing on April 15, 2025 and substantial completion targeted for July 15, 2026 (15 months of construction), followed by final completion by August 15, 2026. All bids must remain open for acceptance for a minimum of 60 calendar days after bid opening, with the Owner retaining the right to extend the bid hold period without increasing the bid price or contract time.

The bidding documents establish standard Michigan construction contract terms using MICHSPEC Division 0 Specifications from the 2008 version. Bid security of five percent (5%) of the bidder's Base Bid is required, either in certified check form or as a bonded bid. The project is funded in whole or in part by federal State and Local Fiscal Recovery Funds (SLFRF) and includes a grant from the National Endowment for the Humanities, bringing the Build America, Buy America Act (BABA) requirements into effect, mandating that all iron, steel, manufactured products, and construction materials used in the project be produced in the United States. The contract includes prevailing wage requirements under both state law (2023 PA 10) and federal Davis-Bacon Act provisions, with comprehensive wage rate schedules provided for various construction classifications in the Mackinac County area. Performance and Payment Bonds are required for all bids over $50,000, along with comprehensive insurance coverage including Commercial General Liability limits of $2,000,000 each occurrence and Builders Risk Insurance at 100% of actual cash replacement value. The project includes specifications for soil erosion and sedimentation control compliance, hazardous materials procedures, and waste management planning with emphasis on minimizing landfill disposal through recycling and reuse initiatives.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

This is a Cover Sheet to the State’s Owner and Contractor Standard Construction Contract, known as the MICHSPEC Division 0 Specifications. The MICHSPEC Division 0 Specifications have been developed from the FORMSPEC Michigan Model, 1997 Edition. Although the State’s 2008 Version of the Division 0 Specifications are written as simply as practical, it is nonetheless advisable to consult with companion Guide to Specifiers when preparing specifications for a specific project. These Division 0 Specifications were developed by incorporating provisions and requirements furnished by the State into the FORMSPEC Michigan Model. These Division 0 Specifications have undergone detailed technical reviews by Department of Technology, Management and Budget, State Facilities Administration representatives and detailed legal reviews by the Department of the Attorney General for the State of Michigan. Specifiers are encouraged to consult with a Division 0 specifications specialist or an attorney knowledgeable in public contracts when preparing specifications for a specific project.

STATE OF MICHIGAN

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

STATE FACILITIES ADMINISTRATION

MICHSPEC 2008 VERSION, OWNER AND CONTRACTOR

STANDARD CONTRACT FORMS AND CONDITIONS OF THE CONTRACT

MICHSPEC No. 97.0820 − 00020 THROUGH 97.0820 − 00440

RELEASED ON NOVEMBER 1, 1997.

Developed from

Contract Forms and Conditions of the Contract

FORMSPEC Michigan Model and suggested for use with

Bidding Requirements

File No. 751/18297.ABG

Department of Natural Resources

Heart of the Great Turtle Island / Gchi Mshiikenh Deh Minising

Moran Township, Michigan

November 20, 2024

Bidding

1997 Edition/R 02/24 Version

STATE OF MICHIGAN (OWNER & CONTRACTOR) TABLE OF CONTENTS

MICHSPEC DTMB 00010 − 1 (R 02/24)

SECTION 00010 TABLE OF CONTENTS

SECTION/PAGE NO.

SUBJECT INDEX

SECTION 00020 GLOSSARY ............................................................................................................................................. 00020 - 1

SECTION 00030 ADVERTISEMENT .................................................................................................................................. 00030 - 1

SECTION 00100 INSTRUCTIONS TO BIDDERS ............................................................................................................... 00100 - 1

ARTICLE 1 BIDDING DOCUMENT INTERPRETATIONS .................................................................................................. 00100 - 1

ARTICLE 2 QUALIFICATIONS OF BIDDERS ..................................................................................................................... 00100 - 1

ARTICLE 3 BIDDING DOCUMENTS; SITE CONDITIONS; SAFETY REQUIREMENTS; LAWS ....................................... 00100 - 2

ARTICLE 4 INTERPRETATIONS; ADDENDA .................................................................................................................... 00100 - 3

ARTICLE 5 BID SECURITY ................................................................................................................................................ 00100 - 3

ARTICLE 6 CONTRACT TIME; LIQUIDATED DAMAGES .................................................................................................. 00100 - 4

ARTICLE 7 MATERIALS AND EQUIPMENT ...................................................................................................................... 00100 - 4

ARTICLE 8 SUBCONTRACTORS ...................................................................................................................................... 00100 - 5

ARTICLE 9 BID FORM AND BID FORM ATTACHMENTS ................................................................................................. 00100 - 5

ARTICLE 10 PREPARATION AND SUBMISSION OF BIDS.................................................................................................. 00100 - 6

ARTICLE 11 BID WITHDRAWAL; BID MODIFICATION ........................................................................................................ 00100 - 6

ARTICLE 12 BID OPENING; OBJECTION TO THE AWARD ................................................................................................ 00100 - 7

ARTICLE 13 BIDS TO REMAIN OPEN .................................................................................................................................. 00100 - 7

ARTICLE 14 AWARD OF THE CONTRACT .......................................................................................................................... 00100 - 7

ARTICLE 15 EXECUTION OF THE AGREEMENT ................................................................................................................ 00100 - 9

ARTICLE 16 MOBILIZATION PAY ITEM ............................................................................................................................. 00100 -10 ARTICLE 17 SOIL EROSION AND SEDIMENTATION CONTROL–FINE FOR NON-COMPLIANCE .................................. 00100 -10 ATTACHMENT A TO SECTION 00100: BIDDER'S CHECK LIST........................................................................................ 00110 - 1

SECTION 00120 SUPPLEMENTARY INSTRUCTIONS ..................................................................................................... 00120 - 1

SECTION 00210 INFORMATION FOR BIDDERS .............................................................................................................. 00210 - 1

SECTION 00300 BID SUMMARY ...................................................................................................................... 00300 - SUMMARY

SECTION 00300 BID FORM ............................................................................................................................................... 00300 - 1

ARTICLE 1 THIS BID IS SUBMITTED TO THE STATE OF MICHIGAN ("THE OWNER"). ................................................. 00300 - 1

ARTICLE 2 THE BIDDER'S REPRESENTATIONS ............................................................................................................... 00300 - 1

ARTICLE 3 TIME OF COMPLETION ..................................................................................................................................... 00300 - 2

ARTICLE 4 ATTACHMENTS INCLUDED WITH THIS BID .................................................................................................... 00300 - 2

ARTICLE 5 DEFINED TERMS ............................................................................................................................................... 00300 - 2

ARTICLE 6 BID SCHEDULE .................................................................................................................................................. 00300 - 3

ARTICLE 7 SCHEDULE OF CHANGE ORDER PRICES ...................................................................................................... 00300 - 5

ARTICLE 8 BID SUBMITTED ON ......................................................................................................................................... 00300 - 6

SECTION 00310 BID BOND ............................................................................................................................................... 00310 - 1

SECTION 00320 NONCOLLUSION AFFIDAVIT ................................................................................................................ 00320 - 1

SECTION 00410 BID BREAKDOWN ................................................................................................................................. 00410 - 1

SECTION 00420 QUESTIONNAIRE ................................................................................................................................... 00420 - 1

ARTICLE 1 ORGANIZATION ............................................................................................................................................... 00420 - 1

ARTICLE 2 SPECIALTY CONTRACTOR LICENSES .......................................................................................................... 00420 - 1

ARTICLE 3 EXPERIENCE ................................................................................................................................................... 00420 - 1

ARTICLE 4 ADDITIONAL QUALIFICATIONS ...................................................................................................................... 00420 - 2

ARTICLE 5 REFERENCES .................................................................................................................................................. 00420 - 2 REFERENCES ATTACHMENT ......................................................................................................................... 00420 - 3

SECTION 00430 LIST OF SUBCONTRACTORS ............................................................................................................... 00430 - 1

SECTION 00440 SCHEDULE OF MATERIALS AND EQUIPMENT .................................................................................. 00440 - 1

ARTICLE 1 BID MATERIALS AND EQUIPMENT −LISTED (NAMED OR SPECIFIED) ITEMS ........................................... 00440 - 1 ARTICLE 2 BID MATERIALS AND EQUIPMENT − OPEN SPECIFICATIONS .................................................................... 00440 - 3

SECTION 00500 AGREEMENT .......................................................................................................................................... 00500 - 1

ARTICLE 1 THE CONTRACT; THE PROJECT; THE WORK .............................................................................................. 00500 - 1

ARTICLE 2 CONTRACT DOCUMENTS .............................................................................................................................. 00500 - 1

ARTICLE 3 CONTRACT PRICE ........................................................................................................................................... 00500 - 2

ARTICLE 4 CONTRACT TIME; LIQUIDATED DAMAGES ................................................................................................... 00500 - 2

ARTICLE 5 PAYMENTS TO CONTRACTOR ...................................................................................................................... 00500 - 3

MICHSPEC DTMB 00010 − 2 (R 02/24)

ARTICLE 6 THE PROFESSIONAL SERVICES CONTRACTOR ......................................................................................... 00500 - 3

ARTICLE 7 CONTRACTOR'S REPRESENTATIONS .......................................................................................................... 00500 - 3

ARTICLE 8 MISCELLANEOUS ............................................................................................................................................ 00500 - 3

ARTICLE 9 NOTICE AND SERVICE .................................................................................................................................... 00500 - 4

SECTION 00520 ATTACHMENT “A” TO AGREEMENT ................................................................................................... 00520 - 1

SECTION 00610 PERFORMANCE BOND ........................................................................................................................ 00610 - 1

SECTION 00620 PAYMENT BOND ................................................................................................................................... 00620 - 1

SECTION 00700 GENERAL CONDITIONS ........................................................................................................................ 00700 - 1

ARTICLE 1 INTERPRETATIONS ........................................................................................................................................... 00700 - 1

1.1 Section 00020 Glossary:............................................................................................................................................... 00700 - 1

1.2 Intent of the Contract Documents: ................................................................................................................................ 00700 - 1

1.3 Priority of the Contract Documents: .............................................................................................................................. 00700 - 2

1.4 Interpretation of Indemnification Provisions: ................................................................................................................. 00700 - 2

1.5 Additional Interpretations: ............................................................................................................................................. 00700 - 2

1.6 Ownership and Use of the Contract Documents: .......................................................................................................... 00700 - 3

1.7 Copies of the Contract Documents: ............................................................................................................................... 00700 - 3

ARTICLE 2 THE OWNER−GENERAL PROVISIONS .......................................................................................................... 00700 - 3

2.1 Availability of Lands, Areas, Properties and Facilities: ................................................................................................. 00700 - 3

2.2 Reference Points; Base Lines and Benchmarks: .......................................................................................................... 00700 - 3

2.3 Stop Work Order: .......................................................................................................................................................... 00700 - 3

2.4 Limitations on the Owner’s Responsibilities: ................................................................................................................ 00700 - 4

2.5 Additional General Provisions: ...................................................................................................................................... 00700 - 4

2.6 Partnering Charter: ....................................................................................................................................................... 00700 - 4

ARTICLE 3 THE PROFESSIONAL − GENERAL PROVISIONS .......................................................................................... 00700 - 4

3.1 Owner’s Representative: ............................................................................................................................................. 00700 - 4

3.2 Clarifications and Interpretations: ................................................................................................................................. 00700 - 4

3.3 Minor Variations and No-Cost Changes; Minor Delays:................................................................................................ 00700 - 5

3.4 Determinations by the Professional: ........................................................................................................................... 00700 - 5

3.5 Limitations on the Professional’s Responsibilities: ....................................................................................................... 00700 - 5

ARTICLE 4 CONTROL OF WORK − GENERAL PROVISIONS ........................................................................................... 00700 - 5

4.1 Review of the Contract Documents: ............................................................................................................................. 00700 - 5

4.2 Management, Supervision, and Personnel: .................................................................................................................. 00700 - 5

4.3 Materials and Equipment: ............................................................................................................................................. 00700 - 6

4.4 Concerning Control of Work: ........................................................................................................................................ 00700 - 6

4.5 Patent Fees and Royalties: ........................................................................................................................................... 00700 - 7

4.6 Use of Premises: .......................................................................................................................................................... 00700 - 7

4.7 Record Documents: ...................................................................................................................................................... 00700 - 7

4.8 Emergencies: ................................................................................................................................................................ 00700 - 8

4.9 Indemnification: ............................................................................................................................................................ 00700 - 8

ARTICLE 5 SUBCONTRACTORS AND SUPPLIERS .......................................................................................................... 00700 - 8

5.1 Employment of Subcontractors: .................................................................................................................................... 00700 - 8

5.2 "Or Equal" and Substitute Materials and Equipment:.................................................................................................... 00700 - 9

5.3 The Contractor’s Continuing Responsibilities: ............................................................................................................ 00700 - 9

ARTICLE 6 SUBMITTALS .................................................................................................................................................... 00700 - 9

6.1 Shop Drawing, Sample and Other Technical Submittals: ............................................................................................. 00700 - 9

6.2 Review and Return of Technical Submittals: .............................................................................................................. 00700 - 10

6.3 Progress Schedule Submittals: ................................................................................................................................... 00700 - 10

6.4 Review and Return of Progress Schedule Submittals: ............................................................................................... 00700 - 10

6.5 Additional Provisions Concerning Submittals: ............................................................................................................ 00700 - 10

ARTICLE 7 LEGAL REQUIREMENTS; INSURANCE ........................................................................................................ 00700 - 11

7.1 Laws; Permits (Which Include Approvals and Licenses): ........................................................................................... 00700 - 11

7.2 Sales and Use Tax and Other Similar Taxes: ............................................................................................................. 00700 - 12

7.3 Safety and Protection: ................................................................................................................................................ 00700 - 12

7.4 Bonds and Insurance - General Requirements: .......................................................................................................... 00700 - 12

7.5 The Contractor’s Liability Insurance:......................................................................................................................... 00700 - 12

7.6 Pollution Liability Insurance: ....................................................................................................................................... 00700 - 13

7.7 Property Insurance (Builder's All Risk Insurance): ...................................................................................................... 00700 - 13

7.8 Waiver of Rights: ........................................................................................................................................................ 00700 - 13

7.9 Receipt and Application of Proceeds: ......................................................................................................................... 00700 - 13

MICHSPEC DTMB 00010 − 3 (R 02/24)

7.10 Unfair Labor Practice: ................................................................................................................................................. 00700 - 13

7.11 Michigan Right-To-Know Law: .................................................................................................................................... 00700 - 13

7.12 Nondiscrimination: ...................................................................................................................................................... 00700 - 14

7.13 Michigan Residency for Employees: .......................................................................................................................... 00700 – 14

7.14 Prevailing Wages: ...................................................................................................................................................... 00700 – 14

ARTICLE 8 PROSECUTION; SUBSTANTIAL COMPLETION ........................................................................................... 00700 - 15

8.1 Starting the Work: ....................................................................................................................................................... 00700 - 15

8.2 Revision 0 (Rev. 0) Schedule and Cost Submittals: ................................................................................................... 00700 - 15

8.3 Compliance with Contract Time Requirements: .......................................................................................................... 00700 - 15

8.4 Substantial Completion: .............................................................................................................................................. 00700 - 15

8.5 Partial Use: ................................................................................................................................................................. 00700 - 16

8.6 Division of Responsibilities: ........................................................................................................................................ 00700 - 16

8.7 Suspension of Work: .................................................................................................................................................. 00700 - 16

8.8 Sharing of Total Float on Non-Critical Paths: .............................................................................................................. 00700 - 16

ARTICLE 9 WARRANTY; TESTS, INSPECTIONS, AND

APPROVALS; CORRECTION OF WORK ....................................................................................................... 00700 - 17

9.1 Warranty: ................................................................................................................................................................... 00700 - 17

9.2 Tests, Inspections and Approvals: ............................................................................................................................. 00700 - 17

9.3 Uncovering Work: ...................................................................................................................................................... 00700 - 17

9.4 Correction of Work: .................................................................................................................................................... 00700 - 17

9.5 Special Correction Period Requirements: .................................................................................................................. 00700 - 18

9.6 Special Maintenance Requirements: ......................................................................................................................... 00700 - 18

ARTICLE 10 CHANGES ..................................................................................................................................................... 00700 - 19

10.1 Changes in the Work: ................................................................................................................................................ 00700 - 19

10.2 Differing Subsurface or Physical Site Conditions: ...................................................................................................... 00700 - 19

10.3 Responsibilities for Underground Utilities: ................................................................................................................. 00700 - 20

10.4 Hazardous Material Conditions: ................................................................................................................................. 00700 - 20

10.5 Incidents with Archaeological Features: .................................................................................................................... 00700 - 20

10.6 Unit Price Work: ......................................................................................................................................................... 00700 - 21

10.7 Cash Allowances; Provisionary Allowances: ............................................................................................................. 00700 - 21

10.8 Change Orders; Change Authorizations: ................................................................................................................... 00700 - 21

ARTICLE 11 CHANGES IN CONTRACT PRICE; CHANGES IN

CONTRACT TIME ......................................................................................................................................... 00700 - 22

11.1 General Provisions: ................................................................................................................................................... 00700 - 22

11.2 Changes in Contract Time: ........................................................................................................................................ 00700 - 22

11.3 Methods for Making Adjustments in Contract Price: .................................................................................................. 00700 - 22

11.4 Labor, Subcontract and Material/Equipment Costs: .................................................................................................. 00700 - 23

11.5 Construction Equipment Costs: ................................................................................................................................. 00700 - 23

11.6 Rented or Leased Construction Equipment: .............................................................................................................. 00700 - 23

11.7 Owned Construction Equipment: ............................................................................................................................... 00700 - 24

11.8 General Conditions Costs: ......................................................................................................................................... 00700 - 24

11.9 Limitations on Allowable Costs: ................................................................................................................................. 00700 - 24

11.10 Costs Covered by the Fee for the Work Involved (and not Allowable as Cost of the Work Involved): ........................ 00700 - 24

11.11 Limits on the Fee for the Work Involved: .................................................................................................................... 00700 - 25

11.12 Fee for Unabsorbed Home Office Overhead: ............................................................................................................. 00700 - 25

11.13 Changes in Contract Time for Early Completion: ........................................................................................................ 00700 - 25

11.14 Access to Records: ..................................................................................................................................................... 00700 - 26

11.15 Price Reduction for Defective Cost and Pricing Data: ................................................................................................ 00700 - 26

ARTICLE 12 PROGRESS PAYMENTS; FINAL PAYMENT ............................................................................................... 00700 - 26

12.1. Schedule of Values: ................................................................................................................................................... 00700 - 26

12.2 Requests for Payment: .............................................................................................................................................. 00700 - 27

12.3 Review of Request for Payment; Intent of Review: .................................................................................................... 00700 - 27

12.4 Refusal to Make or to Recommend Payment: .......................................................................................................... 00700 - 27.

12.5 Final Request for Payment: ....................................................................................................................................... 00700 - 27

12.6 Final Payment and Acceptance: ................................................................................................................................ 00700 - 28

12.7 Contractor’s Continuing Obligation: ......................................................................................................................... 00700 - 28

12.8 Waiver of Claims: ...................................................................................................................................................... 00700 - 28

ARTICLE 13 OTHER WORK .............................................................................................................................................. 00700 - 28

13.1 Related Work at Site: ................................................................................................................................................. 00700 - 28

13.2 Coordination Requirements: ...................................................................................................................................... 00700 - 29

13.3 Claims Between the Contractor and Other Parties: ................................................................................................. 00700 - 29

MICHSPEC DTMB 00010 − 4 (R 02/24)

ARTICLE 14 TERMINATION .............................................................................................................................................. 00700 - 29

14.1 Notice Requiring Assurance of Due Performance: .................................................................................................... 00700 - 29

14.2 Contractor Default and Termination for Cause: ........................................................................................................ 00700 - 30

14.3 Surety Default: ........................................................................................................................................................... 00700 - 31

14.4 Termination for Convenience of the Owner: .............................................................................................................. 00700 - 31

14.5 The Contractor May Suspend Work: ....................................................................................................................... 00700 – 31

ARTICLE 15 DISPUTES .................................................................................................................................................... 00700 - 31

15.1 Claims Under This Article: ......................................................................................................................................... 00700 - 31

15.2 Requirement for Certification of Contractor Claims: ................................................................................................. 00700 - 32

15.3 Recommendations or Decisions from the Professional:........................................................................................... 00700 - 32

15.4 Determinations by the Director-DCD: ....................................................................................................................... 00700 - 32

15.5 Supplements to AAA Arbitration: ............................................................................................................................... 00700 - 33

15.6 Interest on a Judgment; Payment of Judgment: ........................................................................................................ 00700 - 33

15.7 Venue; Flow-Through Provision: ............................................................................................................................... 00700 - 33

SECTION 00800 SUPPLEMENTARY CONDITIONS ....................................................................................................... 00800 - 1

SECTION 01310 PROGRESS SCHEDULE ...................................................................................................................... 01310 - 1

TECHNICAL SPECIFICATIONS

DIVISION 1 General Requirements

01 56 39 Temporary Tree and Plant Protection

DIVISION 3 CONCRETE

03 30 00 Cast-In-Place Concrete

DIVISION 4 MASONRY

04 20 00 Unit Masonry 04 22 00 Stone Veneer

DIVISION 5 STRUCTURAL STEEL

05 12 00 Structural Steel Framing 05 73 00 Metal Railings – Wire Mesh

DIVISION 6 WOOD AND PLASTICS

06 10 00 Rough Carpentry

06 17 00 Prefabricated Structural Wood

06 20 00 Finish Carpentry

06 30 00 Composite Decking

06 41 00 Architectural Casework

DIVISION 7 THERMAL AND MOISTURE PROTECTION

07 20 00 Thermal Insulation

07 24 13 Exterior Insulation and Finish System with Moisture Draining

07 40 00 Metal Roof Panels

07 46 00 Metal Siding System

07 60 00 Flashing and Sheet Metal

07 92 00 Sealant

DIVISION 8 DOORS AND WINDOWS

08 11 13 Metal Doors and Frames

08 41 13 Aluminum-Framed Entrances and Storefronts

08 61 00 Windows

08 71 00 Finish Hardware

DIVISION 9 FINISHES

09 29 00 Gypsum Wallboard

09 90 00 Painting

DIVISION 10 SPECIALITES

10 21 13 Toilet Compartments

MICHSPEC DTMB 00010 − 5 (R 02/24)

10 28 13 Toilet Accessories 10 44 13 Fire Extinguisher Cabinet 10 44 16 Fire Extinguishers

DIVISION 12 FURNISHINGS

12 93 00 Site Furnishings

DIVISION 22 PLUMBING

22 10 00 Basic Plumbing Materials and Methods

DIVISION 23 MECHANICAL

23 10 00 Basic Mechanical Materials and Methods

DIVISION 26 ELECTRICAL

26 10 00 Basic Electrical Materials and Methods

DIVISION 31 EARTHWORK

31 10 00 Site Clearing

31 20 00 Earth Moving

DIVISION 32 EXTERIOR IMPROVEMENTS

32 12 16 Asphalt Paving

32 13 13 Concrete Paving

32 32 53 Stone Retaining Walls

32 91 13 Soil Preparation

32 92 00 Turf and Grasses

DIVISION 33 UTILITIES

33 14 00 Water Utility Transmission and Distribution

33 31 00 Sanitary Sewerage Utilities

33 31 23 Sanitary Sewerage Forcemain Piping

33 32 13 Packaged Sewage Pumping Stations

33 42 00 Stormwater Conveyance

DRAWINGS - BOUND SEPARATELY

Cover Sheet Index Sheet

Learning Commons Project

Civil / Landscape Architecture C1.0 LC Existing Conditions Plan C2.0 LC Soil Erosion & Sedimentation Control Plan C2.1 LC Soil Erosion & Sedimentation Control Details C3.0 LC Demolition Plan C4.0 LC Layout & Materials Plan C5.0 LC Grading Plan C6.0 LC Utilities & Stormwater Management Plan C7.0 Site Details C7.1 Site Details C7.2 Site Details L1.0 LC Landscape Plan

Architectural F1.0 LC Code Analysis G1.0 LC General Information A1.0 LC First Floor Plan A1.1 LC Basement Floor Plan A2.0 LC First Floor Reflected Ceiling Plan A2.1 LC Basement Reflected Ceiling Plan

MICHSPEC DTMB 00010 − 6 (R 02/24)

A3.0 LC Roof Plan A4.0 LC Exterior Elevation / North A4.1 LC Exterior Elevation / West A4.2 LC Exterior Elevation / South A4.3 LC Exterior Elevation / East A5.0 LC Building Section A5.1 LC Building Section A5.2 LC Building Section A5.3 LC Building Section at Entry A5.4 LC Entry Details A6.0 LC Details A6.1 LC Details A7.0 LC Interior Elevations A7.1 LC Interior Elevations A7.2 LC Interior Elevations A8.0 LC Door Schedule A8.1 LC Window Schedule A9.0 LC Interior Finish Schedules

Structural S0.1 LC Structural General Notes S0.2 LC Structural Details S1.0 LC First Floor Structural Plan S1.1 LC Basement Footing & Foundation Plan

Electrical E1.1 Electrical Notes & Details E2.1 Basement Lighting Plan E2.2 First Floor Lighting Plan E3.1 Basement Power & Communications Plan E3.2 First Floor Power & Communications Plan E4.1 Mechanical Electrical Plans

Plumbing P0.1 LC Plumbing Schedules P1.0 LC Plumbing First Floor Plan P1.1 LC Basement Plumbing Floor Plan

Mechanical M0.1 LC Mechanical Schedules M1.0 LC Mechanical First Floor Plan M1.1 LC Basement Mechanical Floor Plan

Powwow Grounds Project

Civil / Landscape Architecture C1.0 PW Existing Conditions Plan C2.0 PW Soil Erosion & Sedimentation Control Plan C3.0 PW Demolition Plan C4.0 PW Layout & Materials Plan C5.0 PW Grading Plan C6.0 PW Utilities & Stormwater Management Plan C6.10 PW Utilities Plan & Profile C6.11 PW Utilities Plan & Profile C6.20 PW Utilities Details L1.0 PW Landscape Plan

Electrical E1.1 PW Electrical Plans & Notes E1.2 PW Riser, Panel Schedules, Electrical Details

Architectural Entry Structure A1.0 ES Entry Structure Floor Plan & Elevation A2.0 ES Entry Structure Details A3.0 ES Entry Structure Platform Details

MICHSPEC DTMB 00010 − 7 (R 02/24)

Drum Circle Structure A1.0 DS Drum Circle Structure Floor Plan & Elevation A2.0 DS Drum Circle Structure Details

STATE OF MICHIGAN (OWNER AND CONTRACTOR) GLOSSARY

MICHSPEC DTMB 00020 - 1 (R 02/24)

SECTION 00020 GLOSSARY

1.1 Defined Terms:

1.1.1. The following terms or relative pronouns used in

Division 0 of the Specifications have these intent and meanings:

Activity− An element in the Progress Schedule establishing a requisite step, or the time and resources required, for completing the part of the Work associated with that Activity.

Addenda− Written instruments that are used by the Owner and/or Professional to incorporate interpretations or clarifications, modifications, and other information into the Bidding Documents. An Addendum issued after Bid opening to those Bidders who submitted a Bid, for the purpose of rebidding the Work without readvertising, is referred to as a post-Bid Addendum.

Agreement− The written agreement between the Owner and Contractor covering the Work to be furnished and performed.

Alternate− Refers to Work specified in the Bidding Documents for which the Bidder shall bid a Bid Price in the space provided in the Schedule of Alternates in Section 00300 Bid Form.

Apparent Low Bidder:- Those Bidders whose Base Bid, when added to those specific Alternates the Owner intends to accept, yields the three lowest sums of Base Bid and Alternates. Additional Bidders may be considered Apparent Low Bidders if their Base Bid, when added to those specific Alternates the Owner intends to accept, yields a sum within 10% of the lowest of the Apparent Low Bidder’s sum. If a qualified disabled veteran meets the requirements of the contract solicitation and with the veteran’s preference is the lowest Bidder is considered the Apparent Low Bidder.

Archaeological Feature− Any prehistoric or historic deposit of archaeological value, as determined by a representative of a State agency that is duly authorized to evaluate such findings and render such judgments. An Archaeological Feature deposit may include, but is not limited to Indian habitations, ceremonial sites, abandoned settlements, treasure trove, artifacts, or other objects with intrinsic archaeological value and that relate to the history and culture of the State of Michigan.

As-Planned Schedule− The Contractor’s Revision 0 Progress Schedule returned to the Contractor as "Resubmittal Not Required," with or without comments or objections noted.

Authorized Technical Data− Information and data contained in a report of exploration and tests of subsurface conditions that are expressly designated in paragraph 2.0 of Section 00210 Information for Bidders. Also, any physical data (dimension, location, conditions, etc.) contained in those drawings of physical conditions of existing surface and subsurface facilities identified in paragraph 3.0 of Section 00210 Information for Bidders.

Bar Chart Schedule− Activity schedule, in a bar chart format, that accounts for the entire Work at a level of detail commensurate with the Progress Schedule requirements of the Contract Documents.

STATE OF MICHIGAN MODEL

Developed from FORMSPEC Michigan Model.

Bid− Written offer by a Bidder for the Work, as specified, which designates the Bidder’s Base Bid and Bid Prices for all Alternates. The term Bid includes a Rebid.

Bidder− The Person acting directly, or through an authorized representative, who submits a Bid directly to the Owner.

Bidding Documents− The proposed Contract Documents as advertised, and all Addenda issued before Bid opening, and after Bid opening, if the Work is rebid without readvertising.

Bid Price− The Bidder's price for a lump sum item of Work, or the product of the Bidder's unit price for an item of Unit Price Work times the quantity given on the Bid Form for that item.

Bid Security− A security serving as a guarantee that the Bidder will conform to all conditions requisite for its return or as liquidated damages in the event of failure or refusal to conform.

Bidding Requirements− The Advertisement, Instructions to Bidders (including Attachment A), Supplementary Instructions, Information for Bidders, Bid Form, Bid Form Attachments and Qualification Submittals, as advertised and as modified by Addenda, and any other Section included within Division 0 of the Bidding Documents for the purpose of governing bidding and award of the Contract.

*AD Board− The Administrative Board of the State of Michigan.

Bonds− Section 00310 Bid Bond, Section 00610 Performance Bond and Section 00620 Payment Bond are security furnished by the Contractor, as required by the Contract Documents.

Business Day− Any Day except Saturdays, Sundays and holidays observed by the Owner.

Bulletin− A standard DTMB or other PSC form used by the PSC & Owner to describe a change in the Work under consideration by the Owner and to request the Contractor to submit a proposal for the corresponding adjustment in Contract Price and/or Contract Time, if any.

Calendar Day− Every day shown on the calendar, Saturdays, Sundays, and holidays included.

Cash Allowance− An Owner-specified sum included within the Contract Price to reimburse the Contractor for the actual purchase/furnished cost of materials and/or equipment or other designated items, as specifically provided in the Contract Documents. Although the scope (e.g., the required quantity) of any Work covered by a Cash Allowance is sufficiently

MICHSPEC DTMB 00020 - 2 (R 02/24)

detailed in the Contract Documents for the purposes of bidding the required labor costs, Subcontract costs, construction equipment costs and general conditions costs and Fee, it is understood that the required materials, equipment or other designated items are of uncertain purchase cost at the time of Bid or are yet to be specified in more detail by the Professional as to quality, appearance, durability, finish and such other necessary features affecting purchase price.

Change Authorization− A written order issued and signed by the Professional, which directs changes in the Work that require no adjustment in Contract Price or Contract Time, or which allows for variations in the quantities of Unit Price Work.

Change Order− A written order issued and signed by the Owner, which amends the Contract Documents for changes in the Work or an adjustment in Contract Price and/or Contract Time, or both.

Construction Mechanic− A skilled or unskilled mechanic, laborer, worker, helper, assistant, or apprentice working on a state project but shall not include executive, administrative, professional, office, or custodial employees

Contact Person− Individual in the employ of the Professional or the Owner who is designated as the sole point of contact for prospective Bidders for requests or inquiries concerning the Work and/or the Bidding Documents.

Contract− Refer to the definition in paragraph 1.1 of Section 00500 Agreement. The term “Contract” encompasses the legal obligations of the Owner and Contractor, as defined by the Contract Documents.

Contract Award− The official action of the Board, the Director-SFA or the Director-DCD awarding the Contract to the Contractor.

Contract Documents− Those documents itemized or designated in paragraphs 2.2 through 2.4 of Section 00500 Agreement.

Contract Float− Calendar Days between the Contractor's anticipated date for early completion of the Work, or of a specified portion of the Work, if any, and the corresponding Contract Time.

Contract Price− The Contract price for the Work, or a designated portion of the Work, as designated in Section 00500 Agreement or elsewhere in the Contract Documents, is the total compensation, including authorized adjustments, payable by the Owner to the Contractor (subject to provisions for Unit Price Work).

Contract Times− The Contract Times for the entire Work are the periods allowed, including authorized adjustments, for Substantial Completion and final completion of the Work. The Contract Times for a designated portion of the Work are the periods allowed for Substantial Completion and final completion of any such portion of the Work, as specified in the Contract Documents.

Contractor− Person named "the Contractor" in Section 00500 Agreement with whom the Owner has entered into the Contract.

Correction Period− The period during which the Contractor shall, in accordance with the Contract Documents, (a) correct or, if rejected, remove, and replace Defective Work, and (b) maintain warranties for materials and equipment in full force and effect.

Cost of the Work Involved− The sum of all costs that would be, or were, necessarily incurred by the Contractor in providing any Work Involved with the related change, less the costs that would be, or would have been, incurred by the Contractor to provide such Work without the related change.

CPM Schedule− Computerized, Activity-based Progress Schedule, using Critical Path Method (CPM) techniques, and accounting for the entire Work at a level of detail commensurate with the Progress Schedule requirements of the Contract Documents.

Critical Path Method (CPM)− The Critical Path Method of planning and scheduling. The term “Critical Path” denotes a sequence of Activities controlling achievement of a specified Contract Time.

Date of Commencement of the Contract Time− The date when the Contract Time starts to run.

Defective− An adjective which when referring to or when applied to the term “Work” refers to (a) Work not conforming to the Contract Documents or not meeting the requirements of any inspection, test, or approval, or (b) Work itemized in a Punch List which the Contractor fails to complete or correct within a reasonable time after issuance of the Punch List by the Professional.

Defective Work/Non-Compliance Notice – A DTMB-0499 form or equivalent issued to identify defective or non-compliant conditions requiring response and remedy by the Contractor.

Delay− Any act or omission or other event that in any manner adversely affects or alters the schedule, progress or completion of all or any part of the Work. Delay is a generic term intended to include deferral, stoppage, slow down, interruption and extended performance, and all related hindrance, rescheduling, disruption, interference, inefficiency and productivity and production losses.

*Department (DTMB)− Department of Technology, Management and Budget of the State of Michigan. Director is the Director of the Department.

Director-SFA- The Director of DTMB State Facilities Administration.

Director-DCD- The Director of DTMB State Facilities Administration, Design and Construction Division

Division− Each of the numbered, distinct parts (starting with Division 0) into which the Specifications are divided.

MICHSPEC DTMB 00020 - 3 (R 02/24)

Drawings− Part of the Contract Documents showing the Work.

Drawings shall neither serve nor be used as Shop Drawings.

Early (Late) Dates− Early (late) times of performance for the Activities.

Emergency− A condition affecting the safety or protection of persons, or the Work, or property at or adjacent to the site.

Fee for the Work Involved (Fee)− A negotiated, percentage mark-up on the Cost of the Work Involved which is allowed to the Contractor for (a) reasonable administrative costs, and (b) negotiated, reasonable profit on the Cost of the Work Involved.

General Requirements− Division 1 of the Specifications.

Hazardous Material− Asbestos, ACBMs, PCBs, petroleum products, such construction materials as paint thinners, solvents, gasoline, oil, etc., and any other like material the manufacture, use, treatment, storage, transportation, or disposal of which is regulated by federal, State, or local Laws governing the protection of public health, natural resources, or the environment.

State Facilities Administration- Entity in the Department of Technology, Management and Budget responsible for design, construction, and operations and maintenance of facilities and capital renewal.

State Facilities Administration Representative- Designated DTMB-SFA Design and Construction Division Project Director (a) Responsible for directing and supervising the Professional’s services during the period allowed for completion of the Work; and/or (b) Acting as representative for the Owner and for the enforcement of the Contract Documents, approving payment to the Contractor and coordinating the activities of the State, Owner, Professional and Contractor.

Law(s)− Means federal, state, and local…