MCDD_PS4_FINAL_Technical Specifications_Apr2023.pdf
PDF 4 MB Posted
- Attached to
- PUMP STATION #4 TRASH RAKE REPLACEMENT PROJECT
- Solicitation number
- S-C26014-00005371
- Issued by
- Multnomah County, Oregon
About this file
This document is a technical specification for the Pump Station #4 Trash Rake Replacement Project for the Multnomah County Drainage District located in Portland, Oregon. The work includes demolition of an existing mechanical raking system, installation of new mechanical trash rakes and associated hydraulic and electrical components, replacement of existing pump bay access hatches, and removal and reinstallation of the existing walkway with a new support structure. The project must be completed by October 1, 2023 prior to the onset of the wet season to ensure the stormwater pump station remains operational. Key constraints include minimizing disruptions to the active pump station facility, controlling construction debris from entering the adjacent Columbia Slough, and adhering to specified work hours.
The technical specification provides detailed requirements for various bid items including mobilization, demolition, installation of the new trash rake equipment, hydraulic systems, electrical components, structural work, and start-up/testing/commissioning. Pricing is structured as a combination of lump sum and unit price items. The Owner will provide the new trash rake equipment to the Contractor for installation. The project will be awarded to a single Contractor, and no incumbents are identified. Funding sources and amounts are not specified.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N223527OR.01 Flysheet
TECHNICAL SPECIFICATIONS
FOR
CONSTRUCTION OF
PUMP STATION #4 TRASH RAKE REPLACEMENT
MULTNOMAH COUNTY DRAINAGE DISTRICT
APRIL 10, 2023
Consor North America, Inc.
1 SW Columbia Street, Suite 1700, Portland, OR 97204
(503) 225-9010
N223527OR.01 Seals Page
00 01 07 - 1
SECTION 00 01 07 - SEALS PAGE
FOR
PUMP STATION #4 TRASH RAKE REPLACEMENT PROJECT
See Table of Contents for author of each specification section, identified by author’s initials as follows:
AUTHOR’S NAME = INITIALS
WILLIAM AUSTIN RAMBIN = WAR
MIKE E. WALLIS = MEW
EDWARD F. LING = EFL
Jim E. Mitchell William A. Rambin
Edward F. Ling
RENEWS: 12/31/24
Michael E. Wallis
MICHAEL E. WALLIS = MEW
N223527OR.01 Table of Contents
00 01 10 - 1
SECTION 00 01 10 – TECHNICAL SPECIFICATIONS TABLE OF CONTENTS
FOR
PUMP STATION #4 TRASH RAKE REPLACEMENT PROJECT
TECHNICAL SPECIFICATIONS
Person
Section Responsible Title Page
Division 01 - General Requirements
01 10 00 WAR Summary of Work 1-6
01 12 16 WAR Work Sequence 1-3
01 14 14 WAR Control of Work 1-3
01 22 50 WAR Measurement and Payment 1-5
01 31 19 WAR Project Meetings 1-6
01 33 00 WAR Submittal Procedures 1-11
01 41 20 WAR Seismic Requirements for Non-Structural Components and Systems 1-4
01 45 00 WAR Quality Control 1-3
01 50 00 WAR Temporary Facilities and Controls 1-6
01 66 00 WAR Delivery, Storage, and Handling 1-3
01 70 00 WAR Execution and Closeout Requirements 1-9
01 75 00 WAR Testing, Training, and Commissioning 1-5
01 78 23 WAR Operation and Maintenance Data 1-2
Division 02 - Existing Conditions
02 41 00 WAR Demolition 1-3
Division 03 - Concrete
03 60 00 EFL Grouting 1-6
Division 04
NOT USED
Division 05 - Metals
05 50 00 EFL Metal Fabrications 1-15
Division 06
NOT USED
Division 07 - Thermal and Moisture Protection
07 92 00 WAR Sealants and Caulking 1-3
N223527OR.01 Table of Contents
00 01 10 - 2
Division 08
NOT USED
Division 09 - Finishes
09 90 00 WAR Painting and Coating 1-9
Division 10 through Division 25
NOT USED
Division 26 - Electrical
26 05 00 MEW General Requirements for Electrical Work 1-19
26 05 05 MEW Selective Demolition for Electrical 1-2
26 05 19 MEW Low-Voltage Conductors, Wires, and Cables 1-31
26 05 29 MEW Hangers and Supports for Electrical Systems 1-5
26 05 33 MEW Raceways, Boxes, and Fittings 1-20
26 05 53 MEW Identification for Electrical Systems 1-12
Division 27 through Division 39
NOT USED
Division 40 - Process Integration
40 05 10 WAR Process Piping and Fitting General Requirements 1-4
40 05 13.07 WAR Hangers and Supports for Process Piping 1-6
40 61 13 MEW Process Control System General Provisions 1-12
40 61 21 MEW Process Control System Testing 1-17
40 61 26 MEW Process Control System Training 1-5
40 67 16 MEW Control Panels 1-6
40 67 33 MEW Panel Wiring 1-6
40 78 53 MEW Relays and Terminal Blocks 1-6
Division 41 through Division 45
NOT USED
Division 46 – Water and Wastewater Equipment
46 05 13 WAR General Requirements for Equipment 1-5
46 21 71 WAR Trash Raking Equipment 1-5
Division 47 through Division 48
NOT USED
END OF SECTION
N223527OR.01 Summary of Work
01 10 00 - 1
SECTION 01 10 00 – SUMMARY OF WORK
PART 1 GENERAL
1.1 SUMMARY
A. Section Includes:
1. Work covered by Contract Documents.
2. Site access.
3. Owner-furnished products.
4. Contractor's use of Site
5. Work sequence.
6. Owner occupancy.
7. Permits.
8. Specification conventions.
9. Prevailing wage rates for public works contracts in Oregon.
10. Oregon products.
11. Use of explosives.
12. Contaminated material.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Work to take place at Owner’s Pump Station #4, which is an active stormwater pump station that protects surrounding areas from flooding. During typical years, the pump station is operational from late-September through early summer. Work includes demolition of an existing mechanical raking system; installation of new mechanical trash rakes and associated hydraulic and electrical appurtenances; replacement of the existing pump bay access hatches;
and removal and reinstallation of the existing walkway with a new support structure.
B. The defined Work elements are a general outline of principal features of the Work and does not in any way limit the responsibility of the Contractor(s) to perform all Work and furnish all equipment, labor, and materials required by the Contract Documents.
1.3 SITE ACCESS
A. General: Contractor shall have limited use of the Project site for construction operations as indicated on Drawings and as indicated by requirements of this Section.
B. Use of Site: Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Driveways, Walkways and Entrances: Keep driveways, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
01 10 00 - 2
1.4 WORK BY OWNER OR OTHERS – NOT USED
1.5 OWNER-FURNISHED PRODUCTS
A. Owner's Responsibilities:
1. Arrange for and deliver Owner-reviewed Shop Drawings and Product Data to Contractor.
2. Arrange and pay for delivery of trash raking equipment and related appurtenances to
Owner’s main office at 1880 NE Elrod Drive, Portland, OR, 97211.
3. Upon delivery, inspect products jointly with Contractor.
4. Submit claims for transportation damage and replace damaged, defective, or deficient items.
5. Arrange for Manufacturers' warranties in coordination with Contractor.
B. Contractor's Responsibilities:
1. Review Owner-reviewed Shop Drawings and Product Data.
2. Receive and unload products at Owner’s main office; inspect for completeness or damage jointly with Owner.
3. Handle, store, and install products. At Contractor's request, Owner will consider storage of
Owner supplied equipment at their main office until Site is ready for installation.
4. Repair or replace items damaged after receipt. Contractor is responsible for equipment supplied by Owner after initial inspection at Owner’s main office. Damage incurred by transport to the Project Site, unloading, or installation of the equipment shall be repaired or replaced by Contractor.
C. Items furnished by Owner for installation by Contractor:
1. Mechanical trash rake system including hydraulic power units; hydraulic lines and fittings;
interior and exterior control panels; and related appurtenances.
1.6 CONTRACTOR’S USE OF SITE
A. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.
Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdiction.
B. Provide not less than 7-day notice to Owner of activities that will affect Owner’s operations.
C. Utility Outages and Shutdown:
1. Coordinate and schedule electrical and other utility outages with Owner.
2. Outages: Allowed only at previously agreed upon times.
01 10 00 - 3
3. At least one week before scheduled outages, submit Outage Request Plan to Owner itemizing the dates, times, and duration of each requested outage.
D. Construction Plan: Before start of construction, submit three copies of the construction plan regarding access to Work, use of Site, and utility outages for acceptance by Owner. After acceptance of plan, construction operations shall comply with accepted plan unless deviations are approved by Owner in writing.
E. All work shall be conducted between the hours of 7:00 a.m. and 6:00 p.m. on non-holiday weekdays only. No weekend work will be allowed. Requests for variations in work hours shall be made in writing for consideration by the Owner. No work shall be conducted outside of the above-described days and hours without prior approval of the Owner.
1.7 WORK SEQUENCE
A. Refer to section 01 12 16 Work Sequence.
1.8 OWNER OCCUPANCY
A. Owner will occupy Site during entire period of construction to conduct normal operations.
Normal operations for the identified construction window include rounds to check equipment statuses, resetting of alarms, and review of site security. Owner’s operations crew will periodically make these rounds, but the need to pump stormwater is highly unlikely during the identified construction window.
B. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.
C. Schedule the Work to accommodate Owner occupancy.
1.9 PERMITS
Unless provided for otherwise in these Contract Documents, all permits, licenses, and fees shall be obtained by the Contractor and all costs shall be borne by the Contractor. Contractor shall pay all plan check fees and other fees necessary to obtain permits. Contractor shall be responsible for compliance with all permit provisions and shall accommodate all special inspections required thereof, all at no additional expense to the Owner beyond prices as bid.
1.10 SPECIFICATION CONVENTIONS
These Specifications are written in imperative mood and streamlined form. This imperative language is directed to Contractor unless specifically noted otherwise. The words "shall be" are included by inference where a colon (:) is used within sentences or phrases.
1.11 PREVAILING WAGE RATES FOR PUBLIC WORKS CONTRACTS IN OREGON
The Contractor shall abide by Oregon Revised Statutes (ORS) 279C.800 through 279C.870 which relate to the prevailing wage rates for the building and construction trades in the State of Oregon.
These prevailing wage rates are shown in the Bureau of Labor and Industries document which is included elsewhere in these Contract Documents.
01 10 00 - 4
1.12 OREGON PRODUCTS
Contractor's attention is directed to the provisions of Oregon Law, ORS 279A.120, regarding the preference for products that have been manufactured or produced in Oregon. Contractor shall use
Oregon-produced or manufactured materials with respect to common building materials such as cement, sand, crushed rock, gravel, plaster, etc., and Oregon-manufactured products in all cases where price, fitness, availability, and quality are otherwise equal.
1.13 USE OF EXPLOSIVES
The use of explosives shall not be allowed on this Project.
1.14 CONTAMINATED MATERIAL
A. General
It is possible that the Contractor may encounter contaminated material (soil and/or water) during execution of the Work. This specification identifies requirements for handling and disposing contaminated media.
B. Definitions
1. “Contaminated material” is defined as soil, water, free product, Underground Storage
Tanks (UST), buried abandoned utility lines containing residual or free product, solid waste, treated wood waste, chemical containers, or other solid, liquid, or gas substances with contamination levels above background levels.
2. “Hazardous substances” shall mean those substances or materials defined in the
ORS 465.200, as amended.
3. “Release” shall have the meaning as defined in ORS 465.200, as amended.
4. “Environmental laws” shall mean any applicable statute, law, ordinance, order, consent decree, judgment, permit, license, code, covenant, deed, common law, treaty, convention, or other requirement pertaining to protection of the environment, health or safety, natural resources, conservation, wildlife, waste management or disposal, hazardous substances, or pollution, including but not limited to regulation of releases to air, land, water, and groundwater.
C. Execution
1. Discovery of Contaminated Material
In the event that the Contractor, during the course of construction or during any other activities authorized under this contract, should encounter suspected contaminated material or any other materials suspected of posing a threat to human health and the environment, the Contractor shall notify the Engineer immediately and manage according to requirements identified below.
2. Discovery of Contaminated Soil
01 10 00 - 5
Contractor shall note evidence of contamination (odor, visual staining of soil, free liquid product seeping from soil, sheen on groundwater, etc.) and note location of evidence on a sketch of the excavation and provide to the Engineer.
Contractor shall report the discovery to the Engineer immediately. Contractor shall stop all excavation activities and secure the site to prevent entry by the public. The excavation shall not be backfilled. Protect all open excavations with berms, plates, and fencing. Contractor may continue with work in other non-contaminated areas.
Contractor shall assist Engineer in collecting sample(s) of suspected contaminated media for testing and characterization. Contractor shall allow 21 days, at no cost to Owner, for testing, results, and instructions as to how to proceed with contaminated materials.
The Contractor shall obtain a copy of an approved soil disposal/acceptance permit
(Disposal/Treatment Facility requires transporter to have a copy of the permit.)
Contractor will transport and dispose of contaminated material at an approved disposal/treatment facility.
Contractor shall provide the Engineer with a copy of the contaminated soil disposal receipt.
3. Handling of Contaminated Soil
After approval from the Engineer, excavate the soil in a manner that prevents commingling of contaminated and non-contaminated soil. Engineer will make determination (based on soil saturation) if contaminated soil can be directly transported to a treatment or disposal facility, or if soil needs to be stockpiled to reduce water content. Engineer will determine when stockpiled soil can be transported off-site.
Contractor will be responsible for stockpiling contaminated soil in containers or on impervious surface to prevent the spread of contamination. Any water runoff from the contaminated soil stockpile area(s) must be contained by Contractor and handled as contaminated water.
Minimize movement of excavation equipment over or through contaminated soil to prevent movement of contaminated soil into areas where no contaminated soil exists.
Stockpiles will be created on an approved site and shall be surrounded by a fence to limit access. The stockpiles must be covered and bermed during periods of rainfall to prevent run-on and run-off. The stockpiles shall be covered with a minimum 10-mil high density polyethylene (HDPE) plastic during periods of strong winds, nightfall, over the weekends, or during extended work stoppages. If dust is observed coming from the stockpiles, the stockpiles shall be either covered or the dust controlled with water.
Maintain excavation equipment in good working order. Prevent spillage of oil, fuel, or hazardous substances from equipment. In particular, promptly repair oil leaks from equipment and clean up any contaminated soil.
4. Transport of Contaminated Materials
01 10 00 - 6
Contractor shall comply with all applicable Federal, State, or local laws, codes, and ordinances that govern or regulate contaminated substance transportation. Contaminated soils placed in stockpiles shall be loaded into trucks in a manner that prevents the spilling or tracking of contaminated soil into areas of the site with uncontaminated soil. Loose material falling onto the exterior of the truck during loading shall be removed before the truck leaves the loading area. Any material collected in the loading area shall either be placed back into the truck or back into the stockpile. If loading areas are unpaved, the surface soil shall be sampled at the conclusion of the loading activities to confirm that contaminated soil is not present. If loading areas are paved, any loose soil shall be cleaned from the pavement at the conclusion of the loading activities.
Specific truck haul routes shall be established before beginning off-site contaminated media transport. On-site truck routes shall be established to minimize or prevent movement of trucks over contaminated soils. Off-site truck routes shall be established to reduce the risk of releases of contaminated soils and impact on local traffic. The Contractor shall be responsible for ensuring that loaded truck weights are within acceptable limits. All trucks shall be covered before they leave the loading area.
The Contractor shall ensure that all drivers of vehicles transporting contaminated substances have in their possession during transport all applicable Oregon State and local vehicle insurance requirements, valid driver's license, and vehicle registration and license.
The Contractor shall be responsible for informing all drivers of transport vehicle about:
a. The nature of the material transported.
b. Required routes to and from the off-site thermal treatment or disposal facility.
c. Applicable County street regulations and requirements, and State of Oregon
Department of Transportation codes, regulations, and requirements.
d. The County's requirement for proper handling and transportation of the substances.
The Contractor shall not allow contaminated substances to be spilled or tracked off-site at any time during the Project. Trucks used for the transportation of contaminated substances off-site shall be watertight, substance compatible, licensed, insured, and permitted pursuant to federal, state, and local statutes, rules, regulations, and ordinances.
If contaminated media is discarded prior to removal of contaminated material, the price per cubic yard of soil materials and price per 100 gallons of contaminated water will be negotiated with Owner.
PART 2 PRODUCTS - Not Used
PART 3 EXECUTION - Not Used
N223527OR.01 Work Sequence
01 12 16 - 1
SECTION 01 12 16 - WORK SEQUENCE
PART 1 GENERAL
1.1 SUMMARY
A. This Section includes general sequencing, project phasing, and coordination requirements for the Work.
B. Contract Requirements:
1. Owner’s Pump Station #4 receives stormwater runoff from areas that drain to the
Columbia Slough. It is imperative that the Work is complete and the pump station is operational prior to the onset of the wet season, which is identified as the October 1, 2023. Plan and prosecute the Work such that a complete and operable trash rake system is installed by this deadline in accordance with the Contract Documents.
2. Pumping disruptions could potentially result in flooding of nearby properties and roads.
3. Control any and all construction debris from entering the Columbia Slough resulting from or integral to construction activities. Provide devices required to control, stop, divert, or dispose of any and all construction debris. Such devices may consist of tarps or netting to protect the Slough from falling debris. Provide a Spill Prevention Plan for review and approval by Owner prior to starting the Work.
4. Owner may determine the order of precedence and the time and season at which any portion or portions of the Work shall be commenced and carried on in order to ensure proper completion of the Contract, proper operation of the stormwater pump station, or compliance with Permit conditions.
1.2 SUBMITTALS
A. Section 01 33 00, Submittal Procedures: Requirements for submittals.
B. Work Sequencing Plan, at a minimum, to include the following:
1. Complete sequence of construction for all activities contained herein.
2. Major work activities to occur.
3. Contingency plan identifying what action will be taken if construction cannot be completed within the allotted timeframe.
C. Spill Prevention Plan
1.3 PROJECT SPECIFIC WORK CONSTRAINTS
A. Constraints primarily relate to the potential need to receive and pump stormwater before the complete facility has been constructed, tested, commissioned, and accepted by Owner.
B. Constraints listed below involve limits on activities during construction. These limits relate to the critical nature of the new trash rake system.
01 12 16 - 2
1. Coordinate construction schedule and operation with Owner.
2. Schedule the constructing, testing, and commissioning of the new trash rake system such that pump station is operational by the date identified in paragraph 1.1.B.
1.4 GENERAL WORK CONSTRAINTS
A. Constraints primarily relate to interfacing with and tying into existing power supplies, equipment, and other aspects of the operating pump station facility.
B. Make every effort to give proper attention to each of these items so as to minimize interruptions of the existing facilities and avoid delays that may result if the constraints are not observed.
C. Constraints listed below involve limits on activities during construction. These limits relate to the critical nature of the pump station facility.
1. Coordinate construction schedule and operation with Owner.
2. Coordinate proposed work with Owner, Engineer, and facility operations personnel before implementing any shutdowns. Under no circumstances cease Work at the end of a normal working day if such actions may inadvertently cause a cessation of any facility operating process; in which case, remain on site until necessary Work and/or repairs are complete.
3. Owner recognizes portions of the facility and facility operations will have to be interrupted or shut down in order to accommodate construction activities. Owner will, through its personnel, attempt to accommodate Work, provided that proper notification is given. Owner reserves the right to deny permission for interruption or shutdown on any day.
4. Do not operate any of the existing equipment without written permission from Owner naming the specific piece of equipment, operator(s), and dates equipment may be used.
Contractor is liable for any loss or damage caused to property or equipment or any personal injury resulting from or related to this usage.
D. Extended Working Hours: If it is desired to perform any Work outside the specified working hours, obtain written permission from Owner and all necessary permitting agencies, and make all necessary arrangements prior to commencing.
1.5 TEMPORARY SHUTDOWNS – NOT USED
1.6 INTERRUPTION OF UTILITY SERVICE
A. Indicate required shutdowns of existing utilities or interruptions of existing operations on the
Progress Schedule. Interruptions to utility service will be allowed to the extent that customer service will not be adversely compromised.
B. Submit requests for interruptions to utility service not less than five business days in advance of the date scheduled for the interruption.
01 12 16 - 3
C. Following receipt of the request, Engineer will notify Contractor if the requested date will be permitted. Evaluation of the request will be based upon the availability of the utility owner’s personnel to assist and monitor utilities during the shutdown period and impact to customer service.
D. Minimize the period of interruption by thorough advance planning. Procure and provide all required materials, equipment, and labor on site during the shutdown.
E. Do not begin interruption until written authorization is received from Owner.
PART 2 PRODUCTS - (Not Used)
PART 3 EXECUTION
3.1 CONSTRUCTION COMPLETION AND TIMING
A. Complete construction and testing and obtain Owner’s acceptance of the facility prior to the date specified in paragraph 1.1.B.
3.2 POST CONSTRUCTION INSPECTION
A. After the trash rake system is installed and tested, provide underwater inspection of each pump intake bay and remove any debris encountered to protect pumps.
N223527OR.01 Control of Work
01 14 14 - 1
SECTION 01 14 14 - CONTROL OF WORK
PART 1 GENERAL
1.1 OCCUPYING PRIVATE LAND
A. The Contractor shall not (except after written consent from the proper parties) enter or occupy with men, tools, materials, or equipment any land outside the rights of way or property of the
Owner. A copy of the written consent shall be given to the Owner.
1.2 PIPE LOCATIONS
A. The exact location of small interior piping is to be determined in the field. Piping shall be arranged in a neat, compact, and workmanlike manner, with a minimum of crossing and interlacing, so as not to interfere with equipment or access ways, and, in general, without diagonal runs.
1.3 DIMENSION OF EXISTING STRUCTURES
A. Where the dimensions and locations of existing structures are of importance in the installation or connection of any part of the Work, the Contractor shall verify such dimensions and locations in the field before the fabrication of any material or equipment which is dependent on the correctness of such information.
1.4 OPEN EXCAVATIONS – NOT USED
1.5 TEST PITS – NOT USED
1.6 INTERFERENCE WITH STREETS AND WALKWAYS
A. The Contractor shall not close or obstruct any portion of a street, road, or private way without obtaining permits therefor from the proper authorities. If any street, road, or private way shall be rendered unsafe by the Contractor's operations, make such repairs, or provide such temporary ways or guards as required by the proper authorities.
B. Streets, roads, private ways, and walks not closed shall be maintained passable and safe by the
Contractor, who shall assume and have full responsibility for the adequacy and safety of provisions made therefor.
C. The Contractor shall, at least 48 hours in advance, notify the Police and Fire Departments in writing, with a copy to the Engineer and Owner if the closure of a street or road is necessary.
The Contractor shall cooperate with the Police and Fire Departments in the establishment of alternate routes and shall provide adequate detour signs, plainly marked and well lighted, in order to minimize confusion.
1.7 CARE AND PROTECTION OF PROPERTY
A. The Contractor shall be responsible for the preservation of all public and private property and shall use every precaution necessary to prevent damage thereto. If any direct or indirect damage is done to public or private property by or on account of any act, omission, neglect, or misconduct in the execution of the work on the part of the Contractor, such property shall be
01 14 14 - 2 restored by the Contractor, at their expense, to a condition similar or equal to that existing before the damage was done, or they shall make good the damage in other manner acceptable to the Owner.
B. The project site is an active stormwater pump station located in an environmentally sensitive area on the Columbia Slough. Contractor shall protect slough from any foreign matter including construction debris, trash, fluids, etc. Contractor shall prepare a Spill Prevention Plan for review and approval by Owner and Engineer that details protection of the Columbia Slough from falling construction debris, actions required should a spill occur, and parties to contact in the event of a spill. Contractor shall be responsible for fines and clean-up should a spill occur.
1.8 PROTECTION AND RELOCATION OF EXISTING STRUCTURES AND UTILITIES
A. The Contractor shall assume full responsibility for the protection of all buildings, structures, and utilities, public or private, including poles, signs, services to buildings, utilities in the street, gas pipes, water pipes, hydrants, sewers, drains, and electric and telephone cables, whether or not they are shown on the Drawings. Contractor shall carefully support and protect all such structures and utilities from injury of any kind and repair at own expense any resulting damage.
B. The Contractor shall bear full responsibility for obtaining all locations of underground structures and utilities (including existing water services, drain lines, and sewers). Services to buildings shall be maintained, and all costs or charges resulting from damage thereto shall be paid by the Contractor.
C. Protection and temporary removal and replacement of existing utilities and structures as described in this Section shall be a part of the work under the Contract and all costs in connection therewith shall be included in the Total Price Bid in the Bid Form.
D. The Contractor shall notify all utility companies in writing at least 72 hours (excluding
Saturdays, Sundays, and Legal holidays) before excavating in any public way. Contractor shall also notify the Oregon Utility Notification Center, telephone number 811, at least 72 hours prior to start of work.
1.9 CLEANUP AND DISPOSAL OF EXCESS MATERIAL
A. During the course of the work, the Contractor shall keep the site of their operations in as clean and as neat a condition as is possible. They shall dispose of all residue resulting from the construction work and, at the conclusion of the work, they shall remove and haul away any surplus excavation, broken pavement, lumber, equipment, temporary structures, and any other refuse remaining from the construction operations, and shall leave the entire site of the work in a neat and orderly condition.
B. In order to prevent environmental pollution arising from the construction activities related to the performance of this Contract, the Contractor and their subcontractors shall comply with all applicable Federal, State, and local laws, regulations concerning waste material disposal, the
Spill Prevention Plan as approved by Owner, as well as the requirements of this work.
01 14 14 - 3
PART 2 PRODUCTS- (Not Used)
PART 3 EXECUTION- (Not Used)
N223527OR.01 Measurement and Payment
01 22 50 - 1
SECTION 01 22 50 - MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 MEASUREMENT AND PAYMENT
A. This Section defines the work and materials included in the items listed in the Bid Schedule, and how they will be used to determine measurement and payment for each item. Part 2 includes Bid Item Descriptions that outline the required work for each item and Part 3 describes the required procedures for monthly payments to the Contractor. This section is supplemental to Section 00720 – General Conditions. Where any conflicts arise, the General Conditions shall govern.
B. Payment will be made for items listed in the Bid Schedule and designated with LS (lump sum) in accordance with Part 2 of this Section. The lump sum price shall constitute full compensation for the work required by the Contract Documents.
C. Payment will be made for items listed in the Bid Schedule and designated with EA (each) and
FT (feet) units in accordance with Part 2 of this Section.
D. Contractor shall provide a breakdown of the contract price for each lump sum item as required by section 01 33 00, Submittal Procedures, paragraph 2.2.
PART 2 CONTRACT REQUIRED WORK/BID ITEM DESCRIPTIONS
A. Mobilization (Bid Item No. 1)
1. Method of Payment – Lump Sum
2. Method of Measurement – Percent Complete
3. Description: Payment for work necessary in advance of construction operations and for work necessary during project close-out will be made on a lump sum basis. This work may include but is not limited to procurement of required bonds, insurance, and permits;
mobilizing workers and equipment; general cost of works in advance of construction;
preparation and Owner or Engineer approval of non-product submittals required by
Section 01 33 00, Submittal Procedures, Part 2; demobilizing workers; moving equipment and excess materials off site; and general cost of works to close out construction.
B. Demolish Existing Rake System and Related Appurtenances (Bid Item No. 2)
1. Method of Payment – Lump Sum
2. Method of Measurement – Percent Complete
3. Description: Payment for work necessary to demolish and dispose of the existing trash raking system and appurtenances identified in the Drawings and Section 02 41 00, Demolition will be made on a lump sum basis. Work includes but is not limited to demolishing the trash rake components including the horizontal beam and rail; support columns, rake heads, chassis, and booms; control panels; and related conduit, conductors, and electrical components. Payment for removal of the existing walkway and guardrail is covered by this item; however, reinstallation is covered under a separate bid item.
01 22 50 - 2
C. Install New Trash Rakes and Support Structure (Bid Item No. 3)
1. Method of Payment – Lump Sum
2. Method of Measurement – Percent Complete
3. Description: Payment for installation of Owner-supplied trash rake equipment including four (4) trash rakes and support structure will be made on a lump sum basis. Work includes but is not limited to exterior installation of the equipment including anchorage of the support structure to the wing walls and intermediate piers. Equipment Manufacturer’s approved shop drawings are included in the Supplemental Information for reference. Work required to prepare the wing walls and intermediate piers for anchoring the rake support structure is covered under separate bid items.
D. Install Hydraulic Power Units, Including Conduit and Conductors (Bid Item No. 4)
1. Method of Payment – Each
2. Method of Measurement – Per each hydraulic power unit installed
3. Description: Payment for installation of Owner-supplied hydraulic power units (HPUs) will be made on a per each basis. Work includes but is not limited to installation of four (4)
HPUs, including Owner-supplied anchorage, and Contractor-supplied conduit and conductors for a fully operational hydraulic power system. Hydraulic lines and fittings external to the HPUs are covered under separate bid items.
E. Install Interior and Exterior Control Panels, Including Conduit and Conductors (Bid Item No. 5)
1. Method of Payment – Lump Sum
2. Method of Measurement – Percent Complete
3. Description: Payment for installation of Owner-supplied control panels will be made on a lump sum basis. Work includes but is not limited to installation of an interior main control panel and exterior local control panel including Contractor-supplied anchorage, conduit, and conductors.
F. Install Hydraulic Lines and Fittings (Bid Item No. 6)
1. Method of Payment – Lump Sum
2. Method of Measurement – Percent Complete
3. Description: Payment for installation of Owner-supplied hydraulic lines and fittings will be made on a lump sum basis. Work includes but is not limited to installation of hydraulic lines and fittings from the HPUs to the trash rakes. Horizontal and vertical hydraulic line supports are covered under separate bid items. If required due to field changes, additional
Contractor-supplied hydraulic lines and fittings are covered under a separate bid item.
G. Furnish and Install Hydraulic Support Frame in Debris Deck Area (Bid Item No. 7)
1. Method of Payment – Lump Sum
2. Method of Measurement – Percent Complete
01 22 50 - 3
3. Description: Payment for furnishing and installation of the hydraulic support frame in the debris deck area will be made on a lump sum basis. Work includes but is not limited to furnishing and installation of steel angles, posts, strut, plates, anchorage, and related hardware for a fully functioning support frame anchored to the pump station exterior wall and rake support frame.
H. Furnish and Install Horizontal Supports for Hydraulic Lines (Bid Item No. 8)
1. Method of Payment – Each
2. Method of Measurement – Per each support installed
3. Description: Payment for furnishing and installation of horizontal supports for hydraulic lines will be made on a per each basis. Work includes but is not limited to furnishing and installation of horizontal strut supports, anchorage, and related appurtenances.
I. Furnish and Install Hydraulic Line Bulkhead in Pump Station Wall, Including 3-inch Wall Core
(Bid Item No. 9)
1. Method of Payment – Each
2. Method of Measurement – Per each bulkhead installed
3. Description: Payment for furnishing and installation of hydraulic line bulkheads will be made on a per each basis. Work includes but is not limited to coring the pump station wall;
and furnishing and installation of bracket plates, bulkhead fittings, and foam insulation for four (4) wall penetrations.
J. Remove Debris Deck Floor Hatches, Furnish and Install New Hatches (Bid Item No. 10)
1. Method of Payment – Each
2. Method of Measurement – Per each hatch installed
3. Description: Payment for removing the existing floor hatches and furnishing and installation of new hatches will be made on a per each basis. Work includes but is not limited to demolition and removal of four (4) existing floor hatches; furnishing and installation of four (4) new hatches including grinding concrete to countersink the hatch frames, accessory hardware, anchorage, and related appurtenances for fully functioning hatches that are flush with the debris deck.
K. Structural Work for East and West Wing Walls (Bid Item No. 11)
1. Method of Payment – Each
2. Method of Measurement – Per each wing wall
3. Description: Payment for structural improvements to the east and west wing walls, total of two (2), will be made on a per each basis. Work includes but is not limited to furnishing and installation of thick steel plates, threaded rod, anchorage, and related hardware to prepare the wing walls for anchoring the trash rake support structure.
01 22 50 - 4
L. Structural Work for Intermediate Piers (Bid Item No. 12)
1. Method of Payment – Each
2. Method of Measurement – Per each intermediate pier
3. Description: Payment for structural improvements to the three (3) intermediate piers will be made on a per each basis. Work includes but is not limited to furnishing and installation of thick steel plates, threaded rod, anchorage, and related hardware to prepare the piers for anchoring the trash rake support structure.
M. Reinstall Existing Walkway and Guardrail; Furnish and Install Walkway Supports and Guardrail
(Bid Item No. 13)
1. Method of Payment – Lump Sum
2. Method of Measurement – Percent Complete
3. Description: Payment for work required for this item will be made on a lump sum basis.
Work includes but is not limited to reinstallation of the existing walkway and guardrail;
furnishing and installation of steel walkway support base plates, steel support framing, anchorage, guardrails, and related hardware for a complete and fully functioning walkway.
N. Furnish and Install Level Transducers and Current Sensing Relays, Including Stilling Well and
Related Appurtenances (Bid Item No. 14)
1. Method of Payment – Each
2. Method of Measurement – Per each level transducer
3. Description: Payment for work required for this item will be made on a per each basis for four (4) level transducers and related appurtenances. Work includes but is not limited to demolishing and removing existing pump bay level switches and related appurtenances, furnishing and installation of level transducers, termination boxes, current sensing relays, stilling wells (partially underwater), related hardware, anchorage, conduit, and conductors for a complete and fully functioning level sensing system for all four (4) pump intake bays.
O. Balance of Project Electrical (Bid Item No. 15)
1. Method of Payment – Lump Sum
2. Method of Measurement – Percent Complete
3. Description: Payment for work required for this item will be made on a lump sum basis.
Work includes but is not limited to furnishing and installation of conduit and conductors not included in other bid items, plus complete testing of electrical components not included in other bid items as required by the Contract Documents.
P. Start-up, Testing, Commissioning, and Training (Bid Item No. 16)
1. Method of Payment – Lump Sum
01 22 50 - 5
2. Method of Measurement – Percent Complete
3. Description: Payment for work required for this item will be made on a lump sum basis.
Work includes but is not limited to start-up and testing of all equipment for proper functionality and performance; site and operational acceptance testing; submission of operation and maintenance data; training for Owner’s operations staff; underwater inspection of each of the four (4) pump intake bays and debris removal; and commissioning of the entire trash rake system demonstrating all aspects of the work are functioning as designed. Owner’s on-call system integrator shall provide process control system PLC, SCADA, and OIT application programming under a separate contract. Costs for the
Equipment Manufacturer’s site visit for installation acceptance and training for the trash rake system are included under Owner’s contract. Refer to Section 46 21 71, Trash Raking
Equipment for more information related to this site visit.
Q. Furnish and Install Additional Hydraulic Lines and Fittings (Bid Item No. 17)
1. Method of Payment – Foot
2. Method of Measurement – Per each foot installed
3. Description: Payment for furnishing and installation of additional hydraulic lines and fittings will be made on a per foot basis as needed. Work includes but is not limited to furnishing and installation of hydraulic lines and fittings that are supplemental to the lines and fittings provided by the Equipment Manufacturer. Additional hydraulic lines and fittings shall be stainless steel, size 12x1.5 by Parker. This bid item will be used on an as-needed basis to accommodate field changes or insufficient material quantities received from the Equipment Manufacturer. As such, the quantity for this bid item is not based on actual lines and fittings shown on the Drawings.
R. Transport Trash Rake Equipment from Owner’s Main Office to Project Site (Bid Item No. 18)
1. Method of Payment – Lump Sum
2. Method of Measurement – Percent Complete
3. Description: Payment for transporting the trash rake equipment to the project site will be made on a lump sum basis. Work includes but is not limited to transporting the trash rake equipment containers from Owner’s main office and shop site located at 1880 NE Elrod Dr, Portland, OR 97211 and delivering to the Project Site at 17700 NE Marine Dr, Portland, OR
97230. For the basis of the bid price, Contractor shall assume the equipment will be packaged in two (2) 40-ft containers.
PART 3 EXECUTION
A. Payment Requirements – Refer to Part 10, Payment, of the General Conditions.
N223527OR.01 Project Meetings
01 31 19 - 1
SECTION 01 31 19 – PROJECT MEETINGS
PART 1 GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplemental
Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section specifies administrative and procedural requirements for project meetings, including, but not limited to, the following:
1. Pre-construction meeting.
2. Progress meetings.
3. Monthly construction schedule meetings.
4. As-built update meeting.
5. Coordination meetings.
6. Commissioning meetings.
7. Project closeout meetings.
8. Owner training meetings.
1.3 PRECONSTRUCTION MEETING
A. The Owner will schedule a preconstruction meeting before starting construction, at a time convenient to the Contractor and the Owner, but no later than fifteen (15) days after the Notice to Proceed. The meeting will be held at the Project Site, or another convenient location as selected by Owner.
B. Attendance is required of the following:
1. Owner and Owner’s consultants.
2. Owner Representatives.
3. Contractor’s Superintendent and Project Manager. Contractor’s QC Representative if different individual than the Project Manager.
4. Major subcontractors.
5. Others, as requested.
C. Discussion will cover items of significance, including the following:
1. Communication chain and persons authorized to direct changes.
01 31 19 - 2
2. The Work.
3. Site Representative’s roles.
4. Work hours, sequence, phasing, and occupancy.
5. Special project procedures.
6. Procedures and processing:
a. Application for payments.
b. Amendments.
c. Change Orders (CO).
d. Field Order (FO).
e. Construction Change Directive (CCD).
f. Proposal Request (PR).
g. Requests for Information (RFI).
h. Field decisions.
i. Submittals.
j. Others as appropriate.
7. Project Management Software access, use, and permissions.
8. Project record documents including review of as-builts on a regular basis during construction.
9. Construction facilities and controls.
10. Temporary utilities.
11. Safety plans and procedures.
12. Security procedures.
13. Housekeeping procedures.
14. Utility shutdowns / Outage Request Form.
15. Parking.
16. Equipment deliveries and priorities.
17. Schedule Review.
18. Contractor’s Quality Control System:
01 31 19 - 3
a. CQC Representative.
b. CQC daily report.
19. Hazardous material abatement procedures, if any.
20. Use of site and premises by Owner and Contractor.
21. Others, as appropriate.
D. The Owner will:
1. Conduct the meeting to review contract administration requirements.
2. Record, produce, and distribute copies of the meeting notes to all attendees within two (2) working days of the meeting.
3. The Contractor shall be responsible for distributing copies to all other subcontractors.
1.4 PROGRESS MEETINGS
A. For purposes of coordination and scheduling after start of the work, weekly Progress Meetings will be held to enable an orderly review of the construction progress and to provide for systematic discussion and analysis of concerns that may arise relative to execution of the work.
B. Contractor, and subcontractors as required, shall incorporate attendance at these meetings as part of the Base Bid of the project - no overtime payments will be authorized for Contractor or subcontractors to attend weekly Progress Meetings or other special meetings if required.
C. Meeting Locations: At Owner’s request, meetings will be in person or virtual.
1. If in person, locations include ADA accessible Contractor’s project field office, Owner provided meeting room, or unless otherwise agreed.
2. Virtual meetings will be held using Microsoft Teams, Zoom, or similar video conferencing software.
D. Attendance: Representatives attending meetings are required to be qualified and authorized to act on behalf of their firms. Attendance shall include:
1. Owner’s consultants, as appropriate.
2. Owner Representatives.
3. Contractor’s Superintendent, Project Manager, and QC Representative.
4. Subcontractors, as appropriate.
5. Suppliers, as appropriate.
6. Others, as appropriate.
E. Agenda: Discussion will pertain to items, such as:
01 31 19 - 4
1. A list of attendees and companies they represent.
2. Review and approve notes of previous meeting; written corrections, additions and/or deletions to previous notes acknowledged.
3. Review Outages.
4. Review construction schedule; confirm current status of work.
5. Present corrective measures and procedures to regain project schedule, as applicable.
6. Present field observations, problems, and conflicts; discuss concerns pertaining to:
a. Structural items.
b. Mechanical items.
c. Electrical items.
7. Discuss problems impeding progress schedule.
8. Review Contractor’s quality control system; discuss any concerns and corrective measures.
9. Review submittal schedules and logs, present methods to expedite as required.
10. Review off-site fabrication.
11. Review procurement and delivery schedules.
12. Review outstanding RFIs.
13. Review proposed changes for:
a. Effect on construction schedule and on completion date.
b. Effect on any other contracts of the project.
14. Review CO log, change management, CCDs.
15. Confirm status of the “as-built” drawings and review required revisions to Project Record
Documents.
16. Confirm status of shop drawing submittals and approvals.
17. Review project safety.
18. Review any outstanding Non-Compliance Notices.
19. Review any tenant impacts.
20. Review any other business.
21. Confirm next meeting date, location, and time plus those requested to be in attendance.
01 31 19 - 5
F. Owner will:
1. Administer weekly Progress Meetings throughout work progress.
2. Record and distribute the following by e-mail within three (3) working days after the meeting: meeting notes, RFI, Submittal/Shop Drawing and Cost Change logs. Distribution to include all attendees. The Contractor is responsible for distributing copies to all other subcontractors as required.
3. Provide paper copies of the meeting notes, RFI, CCD, Submittal/Shop Drawing and Cost
Change logs to attendees at the next meeting.
4. Ascertain that work is prosecuted consistently with contract documents and construction schedules.
G. At Contractor's option, weekly progress meetings can be held integrally with monthly
Construction Scheduling Meetings and As-Built Update meetings specified herein.
H. Contractor shall be responsible for providing the following at each meeting:
1. Current (and updated if necessary) construction schedule which includes the past week and three (3) week ‘look ahead’.
2. Current (and updated if necessary) submittal schedule.
1.5 MONTHLY CONSTRUCTION SCHEDULE MEETINGS, REPORTING
A. In addition to specific coordination meetings for each element of work, initial schedule meeting, and other regular project meetings for other purposes, hold general scheduling meetings each month to review status according to recent updated schedule reports.
B. Require each entity then involved in planning, coordination, or performance of work to be properly represented at each meeting. Review each entity's present and future needs including interface requirements, time, sequences, deliveries, access, site utilization, temporary facilities and services, hours of work, hazards and risks, housekeeping, change orders, and documentation of information for payment requests.
C. Discuss whether each element of current work is ahead of schedule, on time, or behind time in relation with updated progress schedule. Determine how behind-time work will be expedited, and secure commitments from entities involved in doing so.
D. Discuss whether schedule revisions are required to ensure that current work and subsequent work will be completed within Contract Time.
E. Review everything of significance which could affect progress of the Work.
F. Owner will take meeting notes of each meeting and distribute copies to everyone in attendance. Contractor shall distribute copies of meeting notes to all others affected by decisions or actions resulting from each meeting.
01 31 19 - 6
1.6 AS-BUILT UPDATE MEETING
Following each monthly scheduling meeting, Contractor shall meet with all major subcontractors whose work is in progress at the site, including but not limited to mechanical, electrical, structural, and as otherwise designated, to review and verify incorporation of all revisions of the previous month and transfer all non-recorded installed record information to the day-by-day working set of "Project
Record Copy" blueprints or electronic drawings on the Project Management Software Program, with all revisions clearly indicated. Refer also to Section 01 70 00 - Execution and Closeout Requirements, for basic required information and other provisions related to ‘as-built’ requirements.
1.7 NOT USED
1.8 COMMISSIONING MEETINGS
A. Refer to respective sections of the various general, mechanical, and electrical Divisions of the