M95494-20-R-0008 QA Document 0002.xlsx
XLSX spreadsheet 11 KB Posted
- Attached to
- MARFORPAC Professional Services IDIQ Federal contract opportunity
- Solicitation number
- M95494-20-R-0008
- Issued by
- United States Marine Corps
About this file
This document contains a request for proposal and related questions and answers. The United States Marine Corps Forces, Pacific is seeking professional services support through an indefinite delivery, indefinite quantity contract to conduct operational and strategic planning, research and analysis. Services include strategic planning, force structure advocacy, command and control system oversight, amphibious integration, logistics planning, and administrative programs. The work will support headquarters and expeditionary forces based in Hawaii and elsewhere in the Indo-Pacific region. The solicitation number is M95494-20-R-0008, with a response due date of May 18, 2020. The document answers questions on experience equivalencies, subcontractor past performance submissions, work hours definitions, controlled unclassified information markings, and past performance questionnaire submissions.
View the file
Other files for this federal contract opportunity
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| RFP M95494-20-R-0008 MARFORPAC MAC IDIQ | |||
| QUESTION # | PAGE/SECTION | QUESTIONS | RESPONSES |
| 1 | PWS Section 6 / Attachment 6 | Will the govt please define degree + number of years experience for equivalency to BA/BS and MA/MS degrees. (i.e, Associates and 4 years experience or 6 years experience can be substituted for a Bachelors degree, Bachelors and 8 years experience or 12 years experience can be substituted for a Master’s degree similar to those noted in the OASIS GWACs) | Yes, the Government will allow experience substitutions for degree requirements. See Amendment 0002 and revised Attachment 6 with chart added. |
| 2 | 52.212-1 | If our subcontractors do not want to share their CPARS with us (as the Prime Contractor submitting the proposal), can they submit their CPARS directly to the Government? | All proposal documentation needs to be submitted electronically per the RFP instructions. Your subcontractor can email their CPARS directly to the Government if they don’t want to submit it to you as the prime contractor -- All the same RFP instructions apply to them (due date/time/who to email it to.) See Amendment 0002. |
| 3 | Attachment 6 | Attachment 6 specifies 2080 hours as 1 FTE. A typically recognized year of work would be 1880 given the number of workdays in a year and an 8 hour work-day. Would you consider changing your Attachment to 1880 (and multiples thereof) vice 2080? | The RFP and Attachment 6 both specify that these are estimated labor hours for evaluation purposes only. We are not mandating that companies use 2080 annual hours per FTE in future task orders. Each company typically has their own standard annual FTE hours and the Government will evaluate those proposed hours at the task order level. Therefore no changes to the annual hours in Attachment 6 are being made." |
| 4 | 52.212-1 | 52.212-1 notes the requirement to mark our proposal as CUI. CUI is defined by the DFARs and the NIST as government originated information. A business proposal does not qualify as government originated information, thus our proposal cannot be CUI if your solicitation is not CUI. Can you provide a secure means of submitting them to you in order to meet the requirements of the NIST for transmission of CUI information? | The RFP states that "The Contractor must apply the appropriate controlled unclassified information (CUI) markings to their proposals". CUI classification does not just apply to government generated documents, see CFR 2002.4(h) for the definition of CUI. For example: Contractor's proposals may include proprietary information and it is up to the Contractor to mark it as such. It is up to the Contractor to decide the appropriate CUI marking to their own proposal. This does not require an alternate means of submitting proposals to the Government from the current electronic submission method (email) required by the RFP. |
| 5 | The Government's answer to question 10 on Q&A Document 0001 notes that “The only thing submitted for Vol II should be CPARS and/or Performance questionnaires.” The solicitation says the POC for each questionnaire should submit the questionnaire directly to you. Are you telling us to put in a Blank Questionnaire or one with header info (what contract and who it was sent to)? | No, we are not looking for blank questionnaires to be submitted by an Offeror. Per the RFP instructions, if you are submitting CPARS, that should be coming from the OFFEROR submitting the proposal as part of Volume III. If you are requesting that your past performance references complete and submit Attachment 4 "Past Performance Questionnaire" instead of CPARS -- the questionnaires need to be submitted by your reference, not the Offeror. The CPARS and/or Performance Questionnaires received make up Volume III. |