190509_19R1566_PC_GEN_SA_Q_and_A_PreSol.pdf
PDF 346 KB Posted
- Solicitation number
- M67854-19-R-1566
- Issued by
-
United States Marine Corps
About this file
This document contains questions and answers pertaining to presolicitation notice M67854-19-R-1566 for Plate Carrier Generation III Soft Armor. The U.S. Marine Corps requires ballistic material and a cloth cover to meet the specified performance requirements in the PC Gen III Soft Armor Performance Specification. Source selection samples and test reports will need to be resubmitted as the specification is anticipated to change. While previous contract M67854-18-R-1305 deliverables will be included, quantities will consider items not purchased to date. The draft RFP is expected within three weeks and will address proposal submission requirements.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question # Date Received
1 27-Mar-19
2 27-Mar-19
3 27-Mar-19
4 27-Mar-19
5 8-May-19
M67854-19-R-1566- PC GEN III Soft Armor
Pre-Solicitation Questions and Answers
Question
Pertaining to submission requirements, if an offeror submitted samples (sources selection samples and shootpacks) for the previous RFP M67854-18-R-1305, and they were found compliant, will the offeror be required to submit more samples as outlined in the RFI?
Will the government accept test reports, if they were found compliant, that were submitted for RFP M67854-18-R-1305?
Pertaining to M67854-18-R-1305 will the deliverables on that contract still be delivered or are those now included in the new opportunity M67854-19-R-1566?
Could you please tell me if the Presolicitation posted as solicitation number M6785419R1566 on FBO contains requirements similar to any work performed currently or in the past, or will this be a new requirement?
1. Is the DoD willing to accept a proposal for a plate insert that is slightly heavier than the specified weight requirements outlined in the Performance Specification document?
Answer
The draft RFP documents should be out in about 3 weeks or so, which will address the requirements for proposal submissions.
As we anticipate some changes to the specification, offerors will be required to submit new source selection samples as well as test reports. The quantities to be purchased will take into consideration the quantities not purchased under the current soft armor contract.
See answer to question 1
See answer to question 1
This requirement will be similar to work performed on previous contract number M67854-19-D-1509.
Source selection samples shall meet the requirement for areal density found in the Performance Specification.