Second_Draft_Attachment_27.1_-_AAA-FRM-02002_v1_0_06_Prohibited_Matl.pdf

PDF 35 KB Posted

Attached to
Amphibious Combat Vehicle (ACV) 1. 1 Federal contract opportunity
Solicitation number
M67854-15-R-0001
Issued by
United States Marine Corps

About this file

Second Draft Attachment 27.1 - AAA-FRM-02002_v1 0 06 Prohibited Matl

View the file

Other files for this federal contract opportunity

Other files attached to Amphibious Combat Vehicle (ACV) 1. 1, newest first.
File Type Posted
Attachment_22_-_2015_01_30_ACV_1_1_Integrated_Program_Plan.pptx PPTX presentation
Attachment_10.2_-_GFP_Report_ACV_2015_03_20.pdf PDF
Attachment_16_-_TMCR_150202.docx DOCX document
Attachment_06_-_COVER.docx DOCX document
Attachment_05.1_-_ACV1_1_IMP_v2.0_031015.pdf PDF
Attachment_23_-_COVER.docx DOCX document
Attachment_01_-_COVER_150316.docx DOCX document
Attachment_13_-_Cataloging_Schema_for_Logistics_and_Technical_Data_-_150130.pdf PDF
Attachment_02_-_COVER_150227.docx DOCX document
Attachment_16_-_Cover.docx DOCX document
Attachment_21_-_ACV_1.1_Attribute_Selection_Sheet.pdf PDF
Attachment_20_-_CM_Plan_ACV-PLN-02001_v1.0_Signed.pdf PDF
Section_L_Attachment_3_-_Proposal_Requirements_Cross_Reference_Matrix.xlsx XLSX spreadsheet
Second_Draft_Attachment_22.1_-_2014_12_10_ACV_1_1_Integrated_Program_Plan.pptx PPTX presentation
Second_Draft_Attachment_23.1_-_ACV_1_1_RFP_DD254_15-R-0001_Signed.pdf PDF
Second_Draft_Attachment_14_-_ACV_IUID_Plan_Signed.pdf PDF
M67854-15-R-0001_SECOND_DRAFT.doc DOC document
Second_Draft_Attachment_11-_Test_Schedules_and_Test_Locations_25_Nov_14.docx DOCX document
Second_Draft_Attachment_15__-_ACV_Fielding_Table.docx DOCX document
Second_Draft_Attachment_27_-_COVER.docx DOCX document
Second_Draft_Attachment_21_-_ACV_1.1_Attribute_Selection_Sheet.pdf PDF
Second_Draft_Attachment_06.2_-_ACV_CSDR_PLAN_PD_Contract_Plan_N-14-H-C1.pdf PDF
Second_Draft_Attachment_20_-_ACV1.1_CM_Plan_Draft_v0.3_22Dec.docx DOCX document
Second_Draft_Attachment_09_-_Failure_Definition_Scoring_Criteria_(FDSC).docx DOCX document
Second_Draft_Attachment_10.1_-GFP-GFI_-__12-9-14_V2.docx DOCX document
Second_Draft_Attachment_06.1_-_ACV_CSDR_PLAN_EMD_Contract_Plan_N-14-G-C1.pdf PDF
Second_Draft_Attachment_10_-_COVER_-_GFP_GFI_List.docx DOCX document
Second_Draft_Attachment_05.1_-_ACV_1._1_Integrated_Master_Plan.pdf PDF
SECTION_M_dated_6_Nov_2014_M.7_updated_-_Final.docx DOCX document
Attachment_21_-_ACV_1.1_Attribute_Selection_Sheet.pdf PDF
Attachment_10_-_COVER_-_Government_Furnished_Equipment_(GFE)___Government_Furnished_Information_(GFI)_List.docx DOCX document
ACV_CDRLs_A001-A116_1st_DRAFT_17_Oct_2014.pdf PDF
1st_DRAFT_RFP_Cover_Letter_Signed.pdf PDF
Attachment_08_-_Operational_Mode_Summary_Mission_Profile_(OMS_MP).docx DOCX document
Attachment_06_-_COVER_-_Cost_and_Software_Data_Reporting_(CSDR)_Plan_.docx DOCX document
Attachment_17_-_Technical_Data_Package.docx DOCX document
Attachment_01_-_COVER_-_ACV_Statement_of_Work_(SOW).docx DOCX document
Attachment_02_-_COVER_-_ACV_System_Performance_Specification.docx DOCX document
Attachment_10_-_Government_Furnished_Equipment_(GFE)_Government_Furnished_Information_(GFI)_List.docx DOCX document
Attachment_23_-_ACV_1_1_RFP_DD254_15-R-0001_Signed.pdf PDF
ACV_1.1_1st_DRAFT_RFP_Comment_Recommend_Log.xlsx XLSX spreadsheet
Attachment_23_-_COVER.docx DOCX document
Attachment_22_-_COVER.docx DOCX document
Attachment_06.2_ACV_CSDR_Contract_Plan_RDTEN_-_EMD_Phase.pdf PDF
Attachment_01_141105_-_MASTER_SOW_-_For_RFP_First_Draft_Release.docx DOCX document
Attachment_13_-_Cataloging_Schema_for_Logistics_and_Technical_Data.docx DOCX document
Attachment_18_-_COVER_-_Ships_Loading_Characteristics_Pamphlet_(SLCP).docx DOCX document
Attachment_24_-_COVER_-_RWS_ICD.docx DOCX document
Attachment_15__-_ACV_Fielding_Table.docx DOCX document
Attachment_04.1_-_CDRL_Submission_Instructions_(CDRL_List).xlsx XLSX spreadsheet
Show all 50

Amphibious Combat Vehicle (ACV) 1. 1 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAA-FRM-02002 v1.0 Page 1 of 3

Request for Use of Prohibited Materials

1. General Information Requesting Company:

Date of Request:

Point of Contact:

Vehicle:

Contract Number:

PM AAA Prohibited material for which waiver is requested:

2. Explanation of Use Instructions: Provide a description of the parts/processes where the prohibited material will be used. Identify all components/parts which will contain the prohibited materials upon vehicle delivery including quantities of these parts.

Identify whether or not the material will be required for operation or maintenance (including during vehicle rebuild). A separate spreadsheet may be attached listing the specific parts/processes, if needed.

3. Health Hazard

Instructions: Provide an explanation of any health hazards associated with the use or presence of the prohibited material. Include likely routes of exposure to both the operator and the maintainer. Identify if any Personal Protective Equipment (PPE) that would be required as a result of using this material. Include the type of PPE and under what circumstances it would be required (manufacturing, operation, maintenance, etc.).

AAA-FRM-02002 v1.0 Page 2 of 3

4. Analysis of Alternatives

Instructions: Identify all alternative which were considered for the prohibited material. If the alternative is only for specific applications, identify what type of parts it is a potential alternative for. Include explanation as to why each cannot be implemented.

5. Technical Justification

Instructions: Provide technical justification for the use of prohibited material.

Explain why it is necessary and why it cannot be eliminated.

6. Program Risk

Instructions: Describe the program risk(s) (cost, schedule, and performance) associated with denial of this request by the Government.

7. Get Well Plan

Instructions: Identify which parts where an alternative may be integrated at a later date. Provide a get well plan explaining how this will be accomplished. Also, indicate which parts you will not be able to eliminate and provide a brief explanation.

AAA-FRM-02002 v1.0 Page 3 of 3

The following Sections will be filled in by the Government

8. Environment, Safety, and Occupational Health Working Group (ESOH WG) Evaluation/Recommendation

Instructions: Government ESOH WG will provide evaluation of the above information and a recommendation to the Product Director/Project Manager regarding approval/disapproval of the prohibited material request.

{ Name } Date Chairman, ESOH WG

9. Concurrence I concur that use of the prohibited material as described above is acceptable and justified:

Lead Engineer, { Vehicle }

Assistant Program Manager, Engineering

Assistant Program Manager, Life Cycle Logistics

10. Approval Upon the basis of the findings above, I hereby determine that use of the prohibited material in the parts identified in Section 1 is acceptable and justified.

Program Manager, Advanced Amphibious Assault

File details come from the government source that posted it. Updated .