Second_Draft_Attachment_03_-_Meeting_List_150107.docx

DOCX document 46 KB Posted

Attached to
Amphibious Combat Vehicle (ACV) 1. 1
Solicitation number
M67854-15-R-0001
Issued by

About this file

Second Draft Attachment 03 - Meeting List 150107

View the file

Other files

File Type Posted
Attachment_01_-_COVER_150316.docx DOCX document
Attachment_15__-_ACV_Fielding_Table_(150129).docx DOCX document
Attachment_22_-_2015_01_30_ACV_1_1_Integrated_Program_Plan.pptx PPTX presentation
Attachment_10.3_-_GFI.xlsx XLSX spreadsheet
3rd_Draft_RFP_Cover_Letter.pdf PDF
Attachment_28_-_COVER.docx DOCX document
Attachment_06.3_-_CSDR_Graphical_Representation.pptx PPTX presentation
Attachment_13_-_Cataloging_Schema_for_Logistics_and_Technical_Data_-_150130.pdf PDF
Attachment_06.2_-_ACV_CSDR_PLAN_PD_Contract_Plan_N-14-H-C1.pdf PDF
Third_DRAFT_M67854-15-R-0001.doc DOC document
Attachment_22_-_COVER.docx DOCX document
Attachment_02_-_COVER_150227.docx DOCX document
Attachment_10.2_-_GFP_Report_ACV_2015_03_20.pdf PDF
Attachment_11-Test_Schedules_and_Test_Locations_-_150303.docx DOCX document
Attachment_01_1_-_MASTER_SOW_-_150316.docx DOCX document
Attachment_16_-_Cover.docx DOCX document
Attachment_20_-_CM_Plan_ACV-PLN-02001_v1.0_Signed.pdf PDF
Attachment_21_-_ACV_1.1_Attribute_Selection_Sheet.pdf PDF
Attachment_10_-_COVER_-_GFP_GFI_List.docx DOCX document
Attachment_06.1_-_ACV_PLAN_EMD_Signed_Approved_Contract_Plan_N-14-G-C1.pdf PDF
Attachment_16_-_TMCR_150202.docx DOCX document
Attachment_04_-_CDRL_Submission_Instructions_-_150225.docx DOCX document
Attachment_28_-_ACV_1.1_CWBS_Dictionary.xlsx XLSX spreadsheet
Attachment_06_-_COVER.docx DOCX document
Attachment_05.1_-_ACV1_1_IMP_v2.0_031015.pdf PDF
Attachment_30_-Cover_-__Integrated_Data_Environment_Contract_Requirements.docx DOCX document
Attachment_23_-_COVER.docx DOCX document
Attachment_05_-_COVER.docx DOCX document
Attachment_24_-_Reserved_for_Contract_Data_Assertion_List.docx DOCX document
Attachment_03_-_Meeting_List_150316.docx DOCX document
Attachment_16.3-TABLE_A-IV.__Combined_Maint_and_Maint_w_Parts_Rqmts.docx DOCX document
Attachment_10.1.xlsx XLSX spreadsheet
Section_L_Attachment_3_-_Proposal_Requirements_Cross_Reference_Matrix.xlsx XLSX spreadsheet
Section_L_Attachment_1_-_ACV_1.1_Solicitation_-_Questions_Answer_Log.xlsx XLSX spreadsheet
Second_Draft_Attachment_01.1_-_MASTER_SOW_-_150108.docx DOCX document
Second_Draft_Attachment_23_-_COVER.docx DOCX document
Second_Draft_Attachment_20_-_ACV1.1_CM_Plan_Draft_v0.3_22Dec.docx DOCX document
Second_Draft_Attachment_13_-_Cataloging_Schema_for_Logistics_and_Technical_Data.docx DOCX document
Second_Draft_Attachment_06.2_-_ACV_CSDR_PLAN_PD_Contract_Plan_N-14-H-C1.pdf PDF
Second_Draft_Attachment_22.1_-_2014_12_10_ACV_1_1_Integrated_Program_Plan.pptx PPTX presentation
Second_Draft_Attachment_16_-_Technical_Manual_Contract_Requirement_(TMCR).docx DOCX document
Second_Draft_Attachment_26.1_-_Cost_Incurred_Report_Template_-_17_Sep_14.xlsx XLSX spreadsheet
Second_Draft_Attachment_27.1_-_AAA-FRM-02002_v1_0_06_Prohibited_Matl.pdf PDF
Section_J_MASTER_-_150108.docx DOCX document
Second_Draft_Attachment_23.1_-_ACV_1_1_RFP_DD254_15-R-0001_Signed.pdf PDF
Second_Draft_Attachment_14_-_ACV_IUID_Plan_Signed.pdf PDF
Second_Draft_Attachment_26_-_Cover.docx DOCX document
Second_Draft_Attachment_09_-_Failure_Definition_Scoring_Criteria_(FDSC).docx DOCX document
Second_Draft_Attachment_22_-_COVER.docx DOCX document
M67854-15-R-0001_SECOND_DRAFT.doc DOC document
Show 40 more

Latest 50 of 108 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

M67854-15-R-0001 Section J

Attachment 03 Meeting List Document Identification Number ACV-SPE-02003 07 Jan 2015

M67854-15-R-0001
Section J

Attachment 03 – Meeting List

Type of Activity
Paragraph Number
Location
Duration
Deliverable
Due Date
Program Protection Review Meetings
3.1.4.1
Contractor Facility
1 day
Agenda/Minutes
#1: 285 calendar days after contract award.

#2: 520 calendar days after contract award #3: 780 calendar days after contract award

Post Award Conference (PAC) for the EMD Vehicle Build CLINS (Government Led)
3.2.2.1.1
Government

Facility

No more than 1 day
Agenda/Minutes
Within 20 calendar days after contract award

Contract Option Post Award Conference for LRIP/FRP Build CLINs. (Government Led)

3.2.2.1.2
Government

Facility

No more than 1 day
Agenda / Minutes
Within 20 calendar days after option exercise
Program Management Reviews (Government Led)
3.2.2.3
Government Facility
1 day
Minutes; Deliverables per SOW
For EMD, within 67-72 calendar days after execution of the EMD Vehicle Build CLINS and quarterly thereafter. For LRIP/FRP, 60 days after execution of the LRIP/FRP Build CLINS (Options, if Exercised) and quarterly thereafter, until the delivery of the last LRIP vehicle
Integrated Program Management Report Review
3.2.6.5
Government Facility
1 day
Minutes; Deliverables per SOW
1st meeting, 60 days after contract award and monthly thereafter
Earned Value Management Program Management Review
3.2.6.5
Government Facility
1 day
Minutes
90 days after contract award and quarterly thereafter during the EMD Contract
Integrated Baseline Review
3.2.7
Government Facility
1 day
Agenda/Minutes
180 days after contract award and 60 days after notice by the Government upon contract modification or restructure.
Cost and Software Data Reporting Post Award Conference
3.2.8.1
Government Facility
1 day
Agenda/Minutes
Within 20 days after contract award in conjunction with the Post Award Conference
System Requirements Review-II
3.3.1.1
Government Facility
1 day
Agenda/Minutes
One (1) calendar day following the Post Award Conference

Preliminary Design Review (PDR)/Critical Design Review (CDR)

3.3.1.2, 3.4.2.1

Government Facility
2 days
Deliverable per CDRL: Conference Presentation Materials and SOW
No sooner than 100 days after contract award, but no later than 105 days after contract award

System Verification Review (SVR)

3.3.1.4
Government Facility
1 day
CDRL: System Verification Review and SOW
70-80 days after completion of the last system verification test
Production Readiness Review
3.3.1.5
Contractor Facility
2 days
PRR Presentation and CDRL Deliverable
10 Months Prior to

MS C

Functional Configuration Audit (FCA)
3.3.10.1
Government Facility
2 Days
CDRLs
TBD
Physical Configuration Audit (PCA)
3.3.10.2
Government Facility
2 days
Agenda/Minutes/

Action Items

TBD

Government Safety Reviews and Audits
3.3.14.2
Government Facility
1 day
Per MIL-STD-882E. Task 104: 104.1-104.2.2
Two (2) Weapon System Explosive Safety Review Board (WSESRB) Conferences

One (1) Laser Safety Review Board (if required during EMD Phase)

MRA MS C Capstone Meeting
3.4.2.2
CONUS Location
2 Days
Assessment according to CDRL: Manufacturing Readiness Self-Assessment
Six (6) months prior to MS C approval
MRA FRP Capstone Meeting
3.4.2.3
CONUS Location
2 Days
Assessment according to CDRL: Manufacturing Readiness Self-Assessment
FRP: Eight (8) months prior to FRP (Option, if Exercised)

Acceptance Test Readiness Review

(ATRR)

3.4.7.6
Contractor Facility
2 Days
Agenda/Minutes
30 days prior to initiation of the AT for the first vehicle that completes EMD production
Government Developmental Test (GDT) Readiness Review (DTRR) #2
3.5.1.8.1
Contractor Facility
1 day
CDRL: Test Readiness Review and SOW
60 days prior to first GDT event
DTRR #3
3.5.1.8.1
Government

Facility

1 day
CDRL: Test Readiness Review and SOW
30 days prior to first GDT event
LFT&E IPT Meeting
3.5.1.8.2
Government Facility
1 day
Technical Support
As needed to support
Government Live Fire Test Readiness Review
3.5.1.8.3
Government Facility
1 day
Documentation per SOW
60 and 30 calendar days prior to the start of each Live Fire Event
Pre-Logistics Demonstration Planning Meeting
3.5.3.1.3
Government Facility
1 day
Deliverable per CDRL and Conference Presentation Materials and Minutes
Within 90 days of LRIP (Option, if Exercised
Logistics Program Management Meetings
3.6.1
Government Facility
1 Day
Agenda/Minutes
TBD
Provisioning Guidance Conference (PGC)
3.6.4.2
Government Facility
1 day
CDRL: Contractor’s Provisioning Requirements Statement
Associated with PMR for LRIP/FRP; 60 days after execution of the LRIP/FRP Build CLINS (Options, if Exercised)
Provisioning Technical Conference (PTCs)
3.6.4.2
Government Facility
Three (3) Conferences, 3 Days Each
Agenda/Minutes/

Action Items

LRIP (2), FRP (1)

In-Process Review
3.6.6.1.2
Contractor’s Facility
No more than 2 days Each
Training Lesson Plans, Student Handouts, Visual Aids
EMD (4), LRIP (2), FRP (2)

Technical Manual In-Process Reviews (IPRs)

3.6.7.2
Contractor’s Facility
Three (3) Conferences, 1 Day Each
Agenda/Minutes/

Action Items One Conference Each:

EMD, LRIP, FRP

ACV-SPE-02003 v0.X Page A-4