Second_Draft_Attachment_06.2_-_ACV_CSDR_PLAN_PD_Contract_Plan_N-14-H-C1.pdf

PDF 881 KB Posted

Attached to
Amphibious Combat Vehicle (ACV) 1. 1 Federal contract opportunity
Solicitation number
M67854-15-R-0001
Issued by
United States Marine Corps

About this file

Second Draft Attachment 06.2 - ACV CSDR PLAN_PD_Contract Plan_N-14-H-C1

View the file

Other files for this federal contract opportunity

Other files attached to Amphibious Combat Vehicle (ACV) 1. 1, newest first.
File Type Posted
Attachment_13_-_Cataloging_Schema_for_Logistics_and_Technical_Data_-_150130.pdf PDF
Attachment_02_-_COVER_150227.docx DOCX document
Attachment_16_-_Cover.docx DOCX document
Attachment_21_-_ACV_1.1_Attribute_Selection_Sheet.pdf PDF
Attachment_20_-_CM_Plan_ACV-PLN-02001_v1.0_Signed.pdf PDF
Attachment_15__-_ACV_Fielding_Table_(150129).docx DOCX document
Attachment_05_-_COVER.docx DOCX document
Attachment_10.1.xlsx XLSX spreadsheet
Attachment_03_-_Meeting_List_150316.docx DOCX document
Attachment_16.3-TABLE_A-IV.__Combined_Maint_and_Maint_w_Parts_Rqmts.docx DOCX document
Attachment_24_-_Reserved_for_Contract_Data_Assertion_List.docx DOCX document
Attachment_22_-_2015_01_30_ACV_1_1_Integrated_Program_Plan.pptx PPTX presentation
Section_L_Attachment_3_-_Proposal_Requirements_Cross_Reference_Matrix.xlsx XLSX spreadsheet
Second_Draft_Attachment_09_-_Failure_Definition_Scoring_Criteria_(FDSC).docx DOCX document
Second_Draft_Attachment_10.1_-GFP-GFI_-__12-9-14_V2.docx DOCX document
Second_Draft_Attachment_06.1_-_ACV_CSDR_PLAN_EMD_Contract_Plan_N-14-G-C1.pdf PDF
Second_Draft_Attachment_10_-_COVER_-_GFP_GFI_List.docx DOCX document
Second_Draft_Attachment_05.1_-_ACV_1._1_Integrated_Master_Plan.pdf PDF
Second_Draft_Attachment_04_-_CDRL_Submission_Instructions.docx DOCX document
ACV_CDRLs_Combined_01082015.pdf PDF
Second_Draft_Attachment_17_-_Technical_Data_Package.docx DOCX document
Second_Draft_Cover_Letter.pdf PDF
Second_Draft_Attachment_05_-_COVER.docx DOCX document
Second_Draft_Attachment_01.1_-_MASTER_SOW_-_150108.docx DOCX document
Second_Draft_Attachment_13_-_Cataloging_Schema_for_Logistics_and_Technical_Data.docx DOCX document
Second_Draft_Attachment_23_-_COVER.docx DOCX document
Second_Draft_Attachment_16_-_Technical_Manual_Contract_Requirement_(TMCR).docx DOCX document
Second_Draft_Attachment_22.1_-_2014_12_10_ACV_1_1_Integrated_Program_Plan.pptx PPTX presentation
SECTION_M_dated_6_Nov_2014_M.7_updated_-_Final.docx DOCX document
Attachment_23_-_COVER.docx DOCX document
Attachment_22_-_COVER.docx DOCX document
Attachment_06.2_ACV_CSDR_Contract_Plan_RDTEN_-_EMD_Phase.pdf PDF
Attachment_01_141105_-_MASTER_SOW_-_For_RFP_First_Draft_Release.docx DOCX document
Attachment_13_-_Cataloging_Schema_for_Logistics_and_Technical_Data.docx DOCX document
Attachment_18_-_COVER_-_Ships_Loading_Characteristics_Pamphlet_(SLCP).docx DOCX document
Attachment_24_-_COVER_-_RWS_ICD.docx DOCX document
Attachment_15__-_ACV_Fielding_Table.docx DOCX document
Attachment_04.1_-_CDRL_Submission_Instructions_(CDRL_List).xlsx XLSX spreadsheet
Attachment_04_-_CDRL_Submission_Instructions_.docx DOCX document
Attachment_20_-_Configuration_Management_Plan_(CMP).docx DOCX document
Attachment_22_-_ACV__Integrated_Program_Plan.pptx PPTX presentation
Attachment_06.1_ACV_CSDR_Program_Plan.pdf PDF
Attachment_16_-_Technical_Manual_Contract_Requirement_(TMCR).docx DOCX document
Attachment_14_-_Implementation_Plan_for_Item_Unique_Identification_(IUID)_of_Tangible_Items.docx DOCX document
Attachment_05_-_ACV_1._1_Integrated_Master_Plan.pdf PDF
Attachment_05_-_COVER_-_ACV_1.1_Integrated_Master_Plan.docx DOCX document
Attachment_12_-_COVER_-_Concept_of_Employment_(COE).docx DOCX document
SECTION_M_dated_5_Nov_2014_-_Final.docx DOCX document
Attachment_11_-_Test_Schedules_and_Test_Locations.docx DOCX document
Attachment_21_-_ACV_1.1_Attribute_Selection_Sheet.pdf PDF
Show all 50

Amphibious Combat Vehicle (ACV) 1. 1 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OFFICE OF THE SECRETARY OF DEFENSE

1800 DEFENSE PENTAGON

WASHINGTON. D.C. 20301·1800

COST ASSESSMENT AND

PROGRAM EVALUATION

MEMORANDUM FOR PM AMPHIBIOUS COMBAT VEHICLE

SUBJECT: Amphibious Combat Vehicle (ACV) Contract Cost and Software Data Reporting (CSDR) Plan, N-14-H-Cl

We have reviewed the Amphibious Combat Vehicle (ACV) Program Phase 1 Increment 1 Contract CSDR Plan in accordance with the CSDR Manual DoDM 5000.04-M-l. This plan is consistent with the guidance provided in the Work Breakdown Structure (WBS), MIL-STD-881 C, and the program plan N-14-H. This plan also satisfies current Cost Assessment (CA) and Navy data requirements during the Full Rate Production phase for CSDR report content and frequency. Please note the following instructions for this CSDR Plan:

• The current CSDR Manual, DoDM 5000.04-M-l, dated November 4,2011 governs the application of CSDR requirements on all ACA T I Programs. The Data Item Descriptions (DIDs) for CCDRs, CWBS Dictionaries, and SRDRs that must be used on new contracts are dated May 2011. The dollar thresholds governing the application of CSDRs to individual contracts and subcontracts are established in Interim DoDI 5000.02, Operation of the Defense Acquisition System, dated November 26,2013.

• Submit a copy of the pertinent Contract Data Requirement Lists (CDRLs) to the Defense Cost and Resource Center (DCARC) within 30 days after the contract modification containing such requirements is awarded. This document must provide evidence that the CSDR requirements, as specified in the attached Contract CSDR Plan, were placed on contract.

• Contractors and subcontractors are required to submit the contract WBS (CWBS) Index and Dictionary to the DCARC when the first report is due, or as specified in the CSDR plan. The CWBS Dictionary must be maintained and updated throughout the life ofthe contract and resubmitted to the DC ARC with CSDR submissions as changes occur.

• A CA-approved Contract CSDR Plan must be included in all RFPs for contracts subject to CSDR reporting requirements per DF ARS Section 234.710 I. An contractors' and subcontractors' Contract CSDR Plans are to be submitted to DCARC for approval at least 60 days before issuing the solicitation to industry. Any changes to Contract CSDR Plans must be submitted to the DCARC for CA approval as individual contracts change. Contract CSDR Plans and subsequent changes must be approved prior to contract award, modification, or exercise of a contract option.

Contract CSDR Plans will also be updated to reflect current policies regarding CSDR requirements before a new contract or major modification is made.

• Any RFP and ensuing contract for CSDRs must include the following requirement:

CSDRs must be submitted electronically to DCARC as stand-alone Excel-compatible files and as DCARC approved Extensible Markup Language (XML) files by report upload to the DCARC's CSDR Submit-Review system. PDF format is not acceptable. The DCARC web site (http://dcarc.cape.osd.mil) contains information about delivery methods and submission instructions.

• The Contract CSDR Plan uses the event field as the driver for the submission of reports, not the "as of date." The "as of date" is based on current knowledge (when the CSDR Plan is developed) and is used for tracking purposes. If the event slips, it is the responsibility of the program office (PO) and/or Contractor to inform the DCARC via the CSDR Submit-Review of the event slippage and allow DCARC to update the tracking system with the new event date. The DCARC will determine if a revised Contract CSDR Plan is required. If the PO and/or Contractor do not inform DCARC, the submission will be treated as being late. Event slippages generally do not require that a revised Contract CSDR Plan be submitted. However, a Contract CSDR Plan revision is required to add new events.

• As referenced in CSDR Manual DoDM 5000.04-M-l, DD Form 1921-3, "Contract Business Data Report" is required on all contracts issued after April 2, 2009 that contain CCDR requirements. This form must be submitted to DCARC in accordance with DI-FNCL-81765B.

Any future correspondence relating to the subject Contract CSDR Plan should reference the assigned Plan number, N-14-H-Cl. Questions may be directed to Mr. Michael Augustus,

(571) 372-4267.

Attachments:

Contract CSDR Plan: N-14-H-CI cc: CA (Mark Mutschler) NCCA (Kristin Cowell, Carlton Lavinder, Daniel Schluckebier) PM AAA (Damien Woodley, James Myers)

Richard P. Burke Deputy Director Cost Assessment http:http://dcarc.cape.osd.mil

COST AND SOFTWARE DATA REPORTING PLAN I Form Approved OMS No, 0704-0188

The public reporting burden for this collection of infomlation is estimated to average 8 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information, Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Executive Services Directorate (0704-0188), Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any panalty for failing to comply with a collection of information if it does not display a currently valid OMB control number, PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ORGANIZATION,

1. MAJOR PROGRAM a. NAME AmphibiOUS Combat Vehicle (ACV) b, PHASE/MILESTONE c. PRIME MISSION PRODUCT 2, WBS SYSTEM TYPE 3. SUBMISSION TYPE 4. CURRENT SUBMISSION DATE 5. LAST APPROVED PLAN DATE

R:re-A Fx1~-LRIP FYC-FRP Amphibious Combat Vehicle (ACV) System, ~,INITIAL (YVYYMMDD) (YVYYMMDD)

Increment 1,1 Surface Vehicle System 20141014

O&S CHANGE

6a. POINT OF CONTACT (POC) NAME AND ADDRESS (Include ZIP Code) 6b, TELEPHONE NUMBER (Include Area Code) 6c. FAX NUMBER (Include Area Code) 6d. E-MAIL ADDRESS

James Myers

(703) 784-1454 james,a,myers2@usmc.mil105 Tech Parkway, Suite 101

Stafford, VA. 22556-8618

7. PLAN TYPE S. PREPARING 9a, CONTRACTOR NAME/ADDRESS 9b. CONTRACT NUMBER 9c, APPROPRIA110N 10. APPROVED PLAN NUMBE o PROGRAM ORGANIZA110N i-tgCONTRACT (PRIME) i. PERFORMING ORGANIZATION ii. DIVISION ~ RDT&E

CONTRACT (SUB)

TBD ~ PROCUREMENT

N-14-H-Cl

PM-AM TBD TBD O&M

i-

11, WBS ELEMENT CODE

13, REPORTS REQUIRED

DO 1921-3 (CBDRI: 0

12.

(X if applicable) a, PROGRAM!

b. CONTRACT!

WBS REPOR11NG ELEMENTS

a.CWBS b, DO 1921 c. DO 1921·1 d. DO 1921-2 e. DO 19214 f.SRDRCONTRACT!

SUBCONTRACT SUBCONTRACT DIC110NARY (CDSR) (FCHR) (PCR) (CSR) FORMATS

1,0 1.0 AmphibiOUS Combat Vehicle (ACV) System, Increment 1,1 X X X X 1,1 1,1 Primary Vehicle - Personnel Variant X X X X 1,1,1 1.1,1 Vehicle Integration, Assembly, Test and Checkout X X X X

1.1.1 1,1,1,1 Material Inspection and Handling X X X 1,1.1 1,1,1,2 Vehicle Assembly X X X 1.1,1 1,1,1,3 Vehicle Disassembly X X X 1.1,1 1,1,1.4 Production Special Equipment X X X 1,1,1 1.1.1.5 Functional Integration X X X 1.1,1 1,1.1,6 Final Inspection X X X 1.1,1 1.1 ,1.7 Break-In Testing/Shake·Down Testing X X X 1,1,1 1.1.1,8 Acceptance Testing X X X 1,1.2 1,1.2 Hull!Frame/Body/Cab X X X X 1,1.2 1,1.2.1 Hull Integration, Assembly, Test & Checkout X X X

1.1.2 1,1,2,2 Hull Systems Engineering/Program Management X X X 1,1,2 1,1.2,3 Hull Weldmen! X X X 1.1,2 1,1.2.4 Hull Hatches & Panels X X X

1,1.2 1,1.2,5 Integral Hull Armor X X X 1.1,2 1.1 ,2,6 Hull Accommodations X X X

1.1.2 1.1 ,2,7 Stock List Type 3 (SL·3) X X X 1,1.2 1,1.2,8 Other Hull Parts X X X 1.1,3 1,1.3 System Survivability X X X X

1,1.3 1,1,3,1 System Survivability Integration, Assembly, Test & Checkout X X X 1,1,3 1.1,3,2 System Survivability Systems Engineering/Program Management X X X

1,1,3 1,1,3,3 Non-Integral Hull Armor X X X 1,1,3 1.1 ,3,4 Non·lntegral Weapon Station Armor X X X 1,1.3 1,1,3,5 Other External Armor X X X

1,1,3 1,1,3,6 Automatic Fire Extinguishing System X X X

1,1.3 1,1.3,7 Ballistic Crew and Troop Seats X X X

DO FORM 2794, MAY 2()11 PREVIOUS EDmON IS OBSOLETE Page 1 of 13

13. REPORTS REQUIRED

11. WBS ELEMENT CODE DO 1921-3 (CBDR): [3]

(X if applicable) 12.

WBS REPORTING ELEMENTS a. PROGRAM/

b. CONTRACT/ a. CWBS b. DO 1921

c. DO 1921-1

d. DO 1921-2

e. DO 1921-4

f. SRDRCONTRACT/

SUBCONTRACT DICTIONARY (CDSR) (FCHR) (PCR) (CSR) FORMATSSUBCONTRACT

1.1.3 1.1.3.8 Electronic Countenneasures X X

1.1.3 1.1.3.9 Obscurant System X

1.1.3 1.1.3.10 Indentified Freind or Foe System X

1.1.3 1.1.3.11 Other System Survivability X

1.1.4 1.1.4 Turret Assembly - Remote Weapon Station (RWS) Assembly X

1.1.4 1.1.4.1 RWS Integration. Assembly. Test & Checkout X

1.1.4 1.1.4.2 RWS Systems Engineering/Program Management X

1.1.4 1.1.4.3 RWS Control Systems X

1.1.4 1.1.4.4 Weapon Station Mechanical Interface X

1.1.4 1.1.4.5 Integral Weapon Station Armor X

1.1.4 1.1.4.6 Other RWS Parts and Systems X

1.1.5 1.1.5 Suspension/Steering X

1.1.5.1 1.1.5.1 Land Suspension System X

1.1.5.1 1.1.5.1.1 Land Suspension System Integration, Assembly, Test & Checkout X

1.1.5.1 1.1.5.1.2 Land Suspension Systems Engineering/Program Management X

1.1.5.1 1.1.5.1.3 Suspension System X

1.1.5.1 1.1.5.1.4 Land Steering System X

1.1.5.1 1.1.5.1.5 Brake System X

1.1.5.1 1.1.5.1.6 Tire Inflation System X

1.1.5.1 1.1.5.1.7 Wheels and Tires X

1.1.5.1 1.1.5.1.8 Other Land Suspension Parts and Systems X

1.1.5.2 1.1.5.2 Hydrodynamic Appendages and Steering X

1.1.5.2 1.1.5.2.1 Hydrodynamic Appendages and Steering Integration, Assembly, Test & Checkout X

1.1.5.2 1.1.5.2.2 Hydrodynamic Appendages and Steering Systems Engineering/Program Manageme X

1.1.5.2 1.1.5.2.3 Bow System X

1.1.5.2 1.1.5.2.4 Marine Steering System X

1.1.5.2 1.1.5.2.5 Other Hydrodynamic Appendages and Steering Parts and Systems X

1.1.6 Vehicle Electronics 1.1.6 X

1.1.6.1 Vehicle Electronics Integration, Assembly, Test & Checkout1.1.6 X

Vehicle Electronics Systems Engineering/Program Management 1.1.6 1.1.6.2 X

Electronic Vehicle Control Systems 1.1.6 1.1.6.3 X

Vehicle Control Networks and Data Buses 1.1.6 1.1.6.4 X

1.1.6 1.1.6.5 Integrated GFE Network and Data Buses X

1.1.6 1.1.6.6 Electrical Power Management X

1.1.6.7 Harnesses and Cabling 1.1.6 X

1.1.6.8 Integrated GFE Hamess and Cabling 1.1.6 X

1.1.6.9 Sensors, Switches, and Other Hardware 1.1.6 X

Power Package/Drive Train 1.1.7 1.1.7 X

1.1.7.1 1.1.7.1 Engine System X

1.1.7.1 1.1.7.1.1 Engine Integration, Assembly, Test & Checkout X

1.1.7.1 1.1.7.1.2 Engine Systems Engineering/Program Management X

1.1.7.1 1.1.7.1.3 Primary Engine System X

1.1.7.1 1.1.7.1.4 Engine Cooling System X

Engine Air Induction System 1.1.7.1 1.1.7.1.5 X

Engine Exhaust System 1.1.7.1 1.1.7.1.6 X

Vehicle Fuel System 1.1.7.1 1.1.7.1.7 X

Auxiliary Power Unit 1.1.7.1 1.1.7.1.8 X

Other Engine Parts and Systems 1.1.7.1 1.1.7.1.9 X

Automotive Drive Train System 1.1.7.2 1.1.7.2 X

Automotive Drive Train Integration, Assembly, Test & Checkout1.1.7.2 1.1.7.2.1 X

DO FORM 2794, MAY 2011 PREVIOUS EDITION IS OBSOLETE Page 2 of 13 http:1.1.3.11 http:1.1.3.10

11. WBS ELEMENT CODE

12.

WBS REPORTING ELEMENTS

13. REPORTS REQUIRED

(X if applicable)

DO 1921-3 (CBDR): 0

a. PROGRAM/

CONTRACT/

SUBCONTRACT

b. CONTRACT/

SUBCONTRACT

a. CWBS

DICTIONARY

b. DO 1921

(CDSR)

c. DO 1921-1

(FCHR)

d. DO 1921-2

(PCR)

e. DO 19214

(CSR)

f.SRDR

FORMATS

1.1.7.2 1.1.7.2.2 Automotive Drive Train Systems Engineering/Program Management X X X

1.1.7.2 1.1.7.2.3 Drive Shaft System X X X

1.1.7.2 1.1.7.2.4 Driver's Automotive Controls System X X X

1.1.7.2 1.1.7.2.5 Transmission System X X X

1.1.7.2 1.1.7.2.6 Wheel Drive System X X X

1.1.7.2 1.1.7.2.7 Power Transfer Module/Power Take Off System X X X

1.1.7.2 1.1.7.2.8 Other Automotive Drive Train Parts and Systems X X X

1.1.7.3 1.1.7.3 Water Propulsion System X X X X

1.1.7.3 1.1.7.3.1 Water Propulsion System Integration, Assembly, Test & Checkout X X X

1.1.7.3 1.1.7.3.2 Water Propulsion Systems Engineering/Program Management X X X

1.1.7.3 1.1.7.3.3 Water Propulsion Power System X X X

1.1.7.3 1.1.7.3.4 Water Propulsors Assembly X X X

1.1.7.3 1.1.7.3.5 Other Water Propulsion Parts & Systems X X X

1.1.8 1.1.8 Auxiliary Automotive X X X X

1.1.8 1.1.8.1 Auxiliary Automotive Integration, Assembly, Test & Checkout X X X

1.1.8 1.1.8.2 Auxiliary Automotive Systems Engineering/Program Management X X X

1.1.8 1.1.8.3 Hydraulic System X X X

1.1.8 1.1.8.4 Bilge System X X X

1.1.8 1.1.8.5 Environmental Control System X X X

1.1.8 1.1.8.6 Lighting Systems X X X

1.1.8 1.1.8.7 Other Auxiliary Automotive Parts and Systems X X X

1.1.9 1.1.9 Fire Control X X X X

1.1.9 1.1.9.1 Fire Control System Integration, Assembly, Test & Checkout X X X

1.1.9 1.1.9.2 Fire Control Systems Engineering/Program Management X X X

1.1.9 1.1.9.3 Fire Control Integration Software X X X

1.1.9 1.1.9.4 Other Fire Control Parts and Systems X X X

1.1.10 1.1.10 Armament X X X X

1.1.10 1.1.10.1 Arm"ment Integration, Assembly, Test & Checkout X X X

1.1.10 1.1.10.2 Armament Systems Engineering/Program Management X X X

1.1.10 1.1.10.3 Primary Weapon X X X

1.1.10 1.1.10.3.1 M2 HBMG (.50 cal) X X X

1.1.10 1.1.10.3.2 MK19 40mm AGL X X X

1.1.10 1.1.10.4 Other Armament Parts and Systems X X X

1.1.11 1.1.11 Automatic Ammunition Handling X N/A

1.1.12 1.1.12 Navigation and Remote Piloting X X X X

1.1.12 1.1.12.1 Navigation and Remote Piloting System Integration, Assembly, Test & Checkout X X X

1.1.12 1.1.12.2 Navigation and Remote Piliting Systems Engineering/Program Management X X X

1.1.12 1.1.12.3 Vision Systems X X X

1.1.12 1.1.12.4 Navigation Systems X X X

1.1.12 1.1.12.5 Other Navigation Systems X X X

1.1.13 1.1.13 Special Equipment X X X X

1.1.13 1.1.13.1 Special Equipment Integration, Assembly, Test & Checkout X X X

1.1.13 1.1.13.2 Special Equipment Systems Engineering/Program Management X X X

1.1.13 1.1.13.3 Nuclear, Biological, & Chemical (NBC) Detection & Warning System X X X

1.1.13 1.1.13.4 Chemical Detection System X X X

1.1.13 1.1.13.5 Other Special Equipment Systems X X X

1.1.14 1.1.14 Communications X X X X

1.1.14 1.1.14.1 Communications System Integration, Assembly, Test & Checkout X X X

1.1.14 1.1.14.2 Communications Systems Engineering/Program Management X X X

1.1.14 1.1.14.3 Radio System X X X

DO FORM 2794, MAY 2011 PREVIOUS EDITION IS OBSOLETE Page 3 of 13

WBS REPORTING ELEMENTS

13. REPORTS REQUIRED

(X if applicable)

DO 1921-3 (CBDR): [2]

a.PROGRAMI

CONTRACTI

SUBCONTRACT

b. CONTRACTI

SUBCONTRACT

a.CWBS DICnONARY

b. DO 1921

(CDSR)

c. DO 1921-1

(FCHR)

d. DO 1921-2

(PCR)

e. DO 1921-4

(CSR)

f. SRDR

FORMATS

1.1.14 1.1.14.4 Antennas X X X

1.1.14 1.1.14.5 Vehicle Intercom System X X X

1.1.14 1.1.14.6 Processors, Displays, and Applications X X X

1.1.14 1.1.14.7 Racks X X X

1.1.14 1.1.14.8 Other Communications Systems X X X

1.1.15 1.1.15 Vehicle Software Release 1...n X X X X

1.1.15.1 1.1.15.1 Vehicle Application Software X X X X

1.1.15.1 1.1.15.1.1 Vehicle Application Software Integration. Assembly. Test & Checkout X X X

1.1.15.1 1.1.15.1.2 Vehicle Application Software Systems Engineering/Program Management X X X

1.1.15.1 1.1.15.1.3 Mobility, Power, and Auxiliary (MPA) Software X X X

1.1.15.1 1.1.15.1.4 Command and Control Software X X X

1.1.15.1 1.1.15.1.5 Controls and Displays (C&D) Software X X X

1.1.15.1 1.1.15.1.6 Software Loader Verifier (SLV) X X X

1.1.15.2 1.1.15.2 Vehicle System Software X X X X

1.1.15.2 1.1.15.2.1 Vehicle System Software Integration. Assembly. Test & Checkout X X X

1.1.15.2 1.1.15.2.2 Vehicle System Software Systems Engineering/Program Management X X X

1.1.15.2 1.1.15.2.3 System Software (Operating Systems) X X X

1.1.15.2 1.1.15.2.4 Software Development Environment X X X

1.1.15.2 1.1.15.2.5 Software Test Environment X X X

1.1.16 1.1.16 Other Vehicle Subsystems 1 ...n (Specify) X X X X

1.2 1.2 Remote Control System (UGV specific) X N/A

1.2.1 1.2.1 Remote Control System Integration. Assembly. Test and Checkout X N/A

1.2.2 1.2.2 Ground Control Systems X N/A

1.2.3 1.2.3 Command and Control Subsystem X N/A

1.2.4 1.2.4 Remote Control System Software Release 1 ...n X N/A

1.2.5 1.2.5 Other Remote Control System Ln (Specify) X N/A

1.3 1.3 Secondary Vehicle - Command Variant X N/A

1.3.1 1.3.1 Vehicle Integration, Assembly, Test and Checkout X NIA

1.3.1 1.3.1.1 Material Inspection and Handling X N/A

1.3.1 1.3.1.2 Vehicle Assembly X N/A

1.3.1 1.3.1.3 Vehicle Disassembly X N/A

1.3.1 1.3.1.4 Production Special Equipment X N/A

1.3.1 1.3.1.5 Functional Integration X N/A

1.3.1 1.3.1.6 Final Inspection X N/A

1.3.1 1.3.1.7 Break-in Testing/Shake-Down Testing X N/A

1.3.1 1.3.1.8 Acceptance Testing X N/A

1.3.2 1.3.2 HulVFrameiBody/Cab X NIA

1.3.2 1.3.2.1 Hullinlegretion. Assembly, Test & Checkout X N/A

1.3.2 1.3.2.2 Hull Systems Engineering/Program Management X N/A

1.3.2 1.3.2.3 Hull Weldmant X N/A

1.3.2 1.3.2.4 Hull Hatches & Panels X N/A

1.3.2 1.3.2.5 Integral Hull Armor X N/A

1.3.2 1.3.2.6 Hull Accommodations X N/A

1.3.2 1.3.2.7 Stock List Type 3 (SL-3) X N/A

1.3.2 1.3.2.8 Other Hull Parts X NIA

1.3.3 1.3.3 System Survivability X N/A

1.3.3 1.3.3.1 System Survivability Integration. Assembly, Test & Checkout X N/A

1.3.3 1.3.3.2 System Survivability Systems Engineering/Program Management X N/A

1.3.3 1.3.3.3 Non-Integral Hull Anmor X N/A

1.3.3 1.3.3.4 , Non-Integral Weapon Station Anmor X N/A

DO FORM 2794, MAY 2011 PREVIOUS EDmON IS OBSOLETE Page 4 or 13

11. WBS El.EMENT CODE

WBS REPORTING El.EMENTS

13. REPORTS REQUIRED

(X if applicable)

DO 1921·3 (CBDR): 0

a. PROGRAMI

CONTRACT!

SUBCONTRACT

b. CONTRACT!

SUBCONTRACT

a. cwes

DICTIONARY

b. DO 1921

(CDSR)

C. DO 1921·1

(FCHR)

d. DO 1921-2

(PCR)

e. DO 1921-4

(CSR)

f. SRDR

FORMATS

1.3.3 1.3.3.5 Other External Annor X N/A

1.3.3 1.3.3.6 Automatic Fire Extinguishing System X N/A

1.3.3 1.3.3.7 Ballistic Crew and Troop Seals X NlA

1.3.3 1.3.3.8 Electronic Countermeasures X N/A

1.3.3 1.3.3.9 Obscurant System X N/A

1.3.3 1.3.3.10 Indentifled Freind or Foe System X NIA

1.3.3 1.3.3.11 Other System Survivability X NIA

1.3.4 1.3.4 Turret Assembly· Remote Weapon Station (RWS) Assembly X NIA

1.3.4 1.3.4.1 RWS Integration, Assembly, Test & Checkout X NIA

1.3.4 1.3.4.2 RWS Systems EngineeringlProgram Management X NIA

1.3.4 1.3.4.3 RWS Control Systems X NIA

1.3.4 1.3.4.4 Weapon Station Mechanical Interlace X NIA

1.3.4 1.3.4.5 Integral Weapon Station Annor X NIA

1.3.4 1.3.4.6 Other RWS Parts and Systems X NIA

1.3.5 1.3.5 SuspensionlSteering X NIA

1.3.5.1 1.3.5.1 Land Suspension System X NIA

1.3.5.1 1.3.5.1.1 Land Suspension System Integration, Assembly. Test & Checkout X NIA

1.3.5.1 1.3.5.1.2 Land Suspension Systems Engineering/Program Management X NIA

1.3.5.1 1.3.5.1.3 Suspension System X NIA

1.3.5.1 1.3.5.1.4 Land Steering System X NIA

1.3.5.1 1.3.5.1.5 Brake System X NIA

1.3.5.1 1.3.5.1.6 Tire Inflation System X NIA

1.3.5.1 1.3.5.1.7 Wheels and TIres X NIA

1.3.5.1 1.3.5.1.8 Other Land Suspension Parts and Systems X NIA

1.3.5.2 1.3.5.2 HydrodynamiC Appendages and Steering X NIA

1.3.5.2 1.3.5.2.1 Hydrodynamic Appendages and Steering Integration. Assembly, Test & Checkout X NIA

1.3.5.2 1.3.5.2.2 Hydrodynamic Appendages and Steering Systems Engineering/Program Manageme X NIA

1.3.5.2 1.3.5.2.3 Bow System X NIA

1.3.5.2 1.3.5.2.4 Marine Steering System X N/A

1.3.5.2 1.3.52.5 Other Hydrodynamic Appendages and Steering Parts and Systems X NIA

1.3.6 1.3.6 Vehicle Electronics X NJA

1.3.6 1.3.6.1 Vehicle Electronics Integration, Assembly, Test & Checkout X NJA

1.3.6 1.3.6.2 Vehicle Electronics Systems Engineering/Program Management X NIA

1.3.6 1.3.6.3 Electronic Vehicle Control Systems X NIA

1.3.6 1.3.6.4 Vehicle Control Networks and Data Buses X NIA

1.3.6 1.3.6.5 Integrated GFE Network and Data Buses X NIA

1.3.6 1.3,6.6 Electrical Power Management X N/A

1.3.6 1.3.B.7 Hamesses and Cabling X NIA

1.3.6 1.3.6.8 Integrated GFE Hamess and Cabling X NJA

1.3.6 1.3.6.9 Sensors, Switches, and Other Hardware X NIA

1.3.7 13.7 Power PackagelDrive Train X NIA

1.3.7.1 1.3.7.1 Engine System X NIA

1.3.7.1 1.3.7.1.1 Engine Integration, Assembly, Test & Checkout X NIA

1.3.7.1 1.3.7.1.2 Engine Systems EngineeringlProgram Management X N!A

1.3.7.1 1.3.7.1.3 Primary Engine System X NIA

1.3.7.1 1.3.7.1.4 Engine Cooling System X N/A

1.3.7.1 1.3.7.1.5 Engine Air Induction System X NIA

1.3.7.1 1.3.7.1.6 Engine Exhaust System X NIA

1.3.7.1 1.3.7.1.7 Vehicle Fuel System X NJA

1.3.7.1 1.3.7.1.8 Auxiliary Power Unit X NIA

DO FORM 2794, MAY 2011 PREVIOUS EDI110N IS OBSOl.ETE Page 5 of 13

13. REPORTS REQUIRED

(X if applicable)

DO 1921·3 (CBDR): 0

a. PROGRAMI

CONTRACT/

SUBCONTRACT

b. CONTRACT/

SUBCONTRACT

WBS REPORTING ELEMENTS

a.CweS

DICTIONARY

b. DO 1921

(CDSR)

c. DO 1921-1

(FCHR)

d.DD 1921-2

(PCR)

e. DO 1921-4

(CSR)

f.SRDR

FORMATS

1.3.7.1 1.3.7.1.9 Other Engine Parts and Systems X NIA

1.3.7.2 1.3.7.2 Automotive Drive Train System X N/A

1.3.7.2 1.3.7.2.1 Automotive Drive Train Integration. Assembly. Test & Checkout X N/A

1.3.7.2 1.3.7.2.2 Automotive Drive Train Systems Engineering/Program Management X N/A

13.7.2 1.3.7.2.3 Drive Shaft System X N/A

1.3.7.2 1.3.7.2.4 Drivefs Automotive Controls System X N/A

1.3.7.2 1.3.7.2.5 Transmission System X N/A

1.3.7.2 1.3.7.2.6 Wheel Drive System X NIA

1.3.7.2 1.3.7.2.7 Power Transfer Module X N/A

1.3.7.2 1.3.7.2.8 Other Automotive Drive Train Parts and Systems X N/A

1.3.7.3 1.3.7.3 Water Propulsion System X N/A

1.3.7.3 1.3.7.3.1 Water Propulsion System Integration, Assembly. Test & Checkout X N/A

1.3.7.3 1.3.7.3.2 Water Propulsion Systems Engineering/Program Management X N/A

1.3.7.3 1.3.7.3.3 Water Propulsion Power System X NIA

1.3.7.3 1.3.7.3.4 Water Propulsors Assembly X N/A

1.3.7.3 1.3.7.3.5 Other Water Propulsion Parts & Systems X N/A

1.3.8 1.3.8 Auxiliary Automotive X N/A

1.3.8 1.3.8.1 Auxiliary Automotive Integration, Assembly. Test & Checkout X N/A

1.3.8 1.3.8.2 Auxiliary Automotive Systems Engineering/Program Management X N/A

1.3.8 1.3.8.3 Hydraulic System X N/A

1.3.8 1.3.8.4 Bilge System X N/A

1.3.8 1.3.8.5 Environmental Control System X N/A

1.3.8 1.3.8.6 Other Auxiliary Automotive Parts and Systems X NIA

1.3.9 1.3.9 Fire Control X N/A

1.3.9 1.3.9.1 Fire Control System Integration, Assembly, Test & Checkout X N/A

1.3.9 1.3.9.2 Fire Control Systems Engineering/Program Management X N/A

1.3.9 1.3.9.3 Fire Control Integration Software X N/A

1.3.9 1.3.9.4 Other Fire Control Parts and Systems X NIA

1.3.10 1.3.10 Armament X N/A

1.3.10 1.3.10.1 Armament Integration, Assembly, Test & Checkout X N/A

1.3.10 1.3.10.2 Armament Systems Engineering/Program Management X N/A

1.3.10 1.3.10.3 Primary Weapon X NIA

1.3.10 1.3.10.3.1 M2 HBMG (.50 cal) X N/A

1.3.10 1.3.10.3.2 MK19 40mm AGL X N/A

1.310 1.3.10.4 Other Armament Parts and Systems X N/A

1.3.11 1.3.11 Automatic Ammunition Handling X N/A

1.3.12 1.3.12 Navigation and Remote Piloting X N/A

1.3.12 1.3.12.1 Navigation and Remote Piloting System Integration, Assembly, Test & Checkout X N/A

1.3.12 1.3.12.2 Navigation and Remote Piliting Systems Engineering/Program Management X N/A

1.3.12 1.3.12.3 Vision Systems X N/A

1.3.12 1.3.12.4 Navigation Systems X N/A

1.3.12 1.3.12.5 Other Navigation Systems X N/A

1.3.13 1.3.13 Special Equipment X N/A

1.3.13 1.3.13.1 Special Equipment Integration. Assembly. Test & Checkout X N/A

1.3.13 1.3.13.2 Special Equipment Systems Engineering/Program Management X N/A

1.3.13 1.3.13.3 Nuclear. Biological, & Chemical (NBC) Detection & Warning System X N/A

1.3.13 1.3.13.4 Chemical Detection System X N/A

1.3.13 1.3.13.5 Other Special Equipment Systems X N/A

1.3.14 1.3.14 Communications X NIA

1.3.14 1.3.14.1 Communications System Integration, Assembly. Test & Checkout X N/A

DO FORM 2794, MAY 2011 PREVIOUS EDmON IS OBSOLETE Page 6 of13

13. REPORTS REQUIRED

IX if applicable)

001921·3 (CBOR): 0

a. PROGRAM/

CONTRACTI

SUBCONTRACT

b. CONTRACT/

SUBCONTRACT

WBS REPORTING ELEMENTS

a.CWBS

DICTIONARY

b. 00 1921

(COSR)

c. 00 1921·1

(FCHR)

d. 00 1921·2

(PCR)

e. 001921-4

(CSR)

f. SROR

FORMATS

1.3.14 1.3.14.2 Communications Systems Engineering/Program Management X NIA

1.3.14 1.3.14.3 Radio System X N/A

1.3.14 1.3.14.4 Antennas X NIA

1.3.14 1.3.14.5 Vehicle Intercom System X NIA

1.3.14 1.3.14.6 Processors. Displays. and Applications X NIA

1.3.14 1.3.14.7 Racks X NIA

1.3.14 1.3.14.8 Other Communications Systems X NIA

1.3.15 1.3.15 Vehicle Software Release l ... n X NIA

1.3.15.1 1.3.15.1 Vehicle Application Software X NIA

1.3.15.1 1.3.15.1.1 Vehicle Application Software Integration, Assembly, Test a Checkout X NIA

1.3.15.1 1.3.15.1.2 Vehicle Application Software Systems Engineering/Program Management X N/A

1.3.15.1 1.3.15.1.3 Mobility, Power, and Auxiliary (MPA) Software X NIA

1.3.15.1 1.3.15.1.4 Command and Control Software X N/A

1.3.15.1 1.3.15.1.5 Controls and Displays (CaD) Software X N/A

1.3.15.1 1.3.15.1.6 Software Loader Verifier (SLV) X N/A

1.3.15.2 1.3.15.2 Vehicle System Software X N/A

1.3.15.2 1.3.15.2.1 Vehicle System Software Integration, Assembly. Test a Checkout X N/A

1.3.15.2 1.3.15.2.2 Vehicle System Software Systems Engineering/Program Management X N/A

1.3.15.2 1.3.15.2.3 System Software (Operating Systems) X NlA

1.3.15.2 1.3.15.2.4 Software Development Environment X NlA

1.3.15.2 1.3.15.2.5 Software Test Environment X NlA

1.3.16 1.3.16 Other Vehicle Subsystems 1 ... n (SpecilY) X NlA

1.4 1.4 Tertiary Vehicle· Recovery Variant X N/A

1.4.1 1.4.1 Vehicle Integration, Assembly. Test and Checkout X NIA

1.4.1 1.4.1.1 Material Inspection and Handling X N/A

1.4.1 1.4.1.2 Vehicle Assembly X NIA

1.4.1 1.4.1.3 Vehicle Disassembly X NIA

1.4.1 1.4.1.4 Production Special Equipment X NIA

1.4.1 1.4.1.5 Functional Integration X N/A

1.4.1 1.4.1.6 Final Inspection X N/A

1.4.1 1.4.1.7 Break·ln Testing/Shake·Down Testing X NIA

1.4.1 1.4.1.8 Acceptance Testing X NIA

1.4.2 1.4.2 HulliFramelBodylCab X NIA

1.4.2 1.4.2.1 Hull Integration. Assembly, Test a Checkout X NIA

1.4.2 1.4.2.2 Hull Systems Engineering/Program Management X NIA

1.4.2 1.4.2.3 Hull Weldmant X NIA

1.4.2 1.4.2.4 Hull Hatches a Panels X NIA

1.4.2 1.4.2.5 Integral Hull Annor X NIA

1.4.2 1.4.2.6 Hull Accommodations X NlA

1.4.2 1.4.2.7 Stock List Type 3 (SL·3) X N/A

1.4.2 1.4.2.8 Other Hull Parts X NIA

1.4.3 1.4.3 System Survivability X NIA

1.4.3 1.4.3.1 System Survivability Integration, Assembly, Test & Checkout X N/A

1.4.3 1.4.3.2 System Survivability Systems Engineering/Program Management X N/A

1.4.3 1.4.3.3 Non.lntegral Hull Armor X N/A

1.4.3 1.4.3.4 Non·lntegral Weapon Station Armor X N/A

1.4.3 1.4.3.5 Other External Armor X N/A

1.4.3 1.4.3.6 Automatic Fire Extinguishing System X NIA

1.4.3 1.4.3.7 Ballistic Crew and Troop Seats X NIA

1.4.3 1.4.3.8 Electronic Countermeasures X NlA

00 FORM 2794, MAY 2011 PREVIOUS EDmON IS OBSOLETE Page 7 of 13

WBS REPORTING ELEMENTS

13. REPORTS REQUIRED

(X if applicable)

DO 1921·3 (CBDR): 0

a. PROGRAM/

CONTRACT/

SUBCONTRACT

b. CONTRACT/

SUBCONTRACT

a.CWBS

DICTIONARY

b. DO 1921

(CDSR)

c. DO 1921·1

(FCHR)

d. DO 1921·2

(PCR)

e. DO 1921-4

(CSR)

f.SRDR

FORMATS

1.4.3 1.4.3.9 Obscurant System X N/A

1.4.3 1.4.3.10 Indentified Freind or Foe System X N/A

1.4.3 1.4.3.11 Other System Survivability X NIA

1.4.4 1.4.4 Turret Assembly - Remote Weapon Station (RWS) Assembly X NIA

1.4.4 1.4.4.1 RWS Integration, Assembly, Test & Checkout X NIA

1.4.4 1.4.4.2 RWS Systems Engineering/Program Management X N/A

1.4.4 1.4.4.3 RWS Control Systems X N/A

1.4.4 1.4.4.4 Weapon Station Mechanical Interface X N/A

1.4.4 1.4.4.5 Integral Weapon Station Armor X NIA

1.4.4 1.4.4.6 Other RWS Parts and Systems X N/A

1.4.5 1.4.5 Suspension/Steering X NIA

1.4.5.1 1.4.5.1 Land Suspension System X N/A

1.4.5.1 1.4.5.1.1 Land Suspension System Integration, Assembly, Test & Checkout X NIA

1.4.5.1 1.4.5.1.2 Land Suspension Systems Engineering/Program Management X N/A

1.4.5.1 1.4.5.1.3 Suspension System X N/A

1.4.5.1 1.4.5.1.4 Land Steering System X N/A

1.4.5.1 1.4.5.1.5 Brake System X N/A

1.4.5.1 1.4.5.1.6 Tire Inflation System X NIA

1.4.5.1 1.4.5.1.7 Wheels and Tires X N/A

1.4.5.1 1.4.5.1.8 Other Land Suspension Parts and Systems X N/A

1.4.5.2 1.4.5.2 Hydrodynamic Appendages and Steering X N/A

1.4.5.2 1.4.5.2.1 Hydrodynamic Appendages and Steering Integration, Assembly, Test & Checkout X N/A

1.4.5.2 1.4.5.2.2 Hydrodynamic Appendages and Steering Systems Engineering/Program Managem, X NIA

1.4.5.2 1.4.5.2.3 Bow System X NIA

1.4.5.2 1.4.5.2.4 Marine Steering System X NIA

1.4.5.2 1.4.5.2.5 Other Hydrodynamic Appendages and Steering Parts and Systems X N/A

1.4.6 1.4.6 Vehicle Electronics X N/A

1.4.6 1.4.6.1 Vehicle Electronics Integration. Assembly, Test & Checkout X N/A

1.4.6 1.4.6.2 Vehicle Electronics Systems Engineering/Program Management X N/A

1.4.6 1.4.6.3 Electronic Vehicle Control Systems X N/A

1.4.6 1.4.6.4 Vehicle Control Networks and Data Buses X NIA

1.4.6 1.4.6.5 Integrated GFE Network and Data Buses X NIA

1.4.6 1.4.6.6 Electrical Power Management X N/A

1.4.6 1.4.6.7 Harnesses and Cabling X NIA

1.4.6 1.4.6.8 Integrated GFE Harness and Cabling X N/A

1.4.6 1.4.6.9 Sensors, Switches, and Other Hardware X N/A

1.4.7 1.4.7 Power Package/Drive Train X N/A

1.4.7.1 1.4.7.1 Engine System X N/A

1.4.7.1 1.4.7.1.1 Engine Integration, Assembly, Test & Checkout X N/A

1.4.7.1 1.4.7.1 .• Engine Systems Engineering/Program Management X N/A

1.4.7.1 1.4.7.1.3 Primary Engine System X N/A

1.4.7.1 1.4.7.1.4 Engine Cooling System X NIA

1.4.7.1 1.4.7.1.5 Engine Air Induction System X N/A

1.4.7.1 1.4.7.1.6 Engine Exhaust System X NIA

1.4.7.1 1.4.7.1.7 Vehicle Fuel System X NIA

1.4.7.1 1.4.7.1.8 Auxiliary Power Un it X NIA

1.4.7.1 1.4.7.1.9 Other Engine Parts and Systems X N/A

1.4.7.2 1.4.7.2 Automotive Drive Train System X N/A

1.4.7.2 1.4.7.2.1 Automotive Drive Train Integration, Assembly, Test & Checkout X N/A

1.4.7.2 1.4.7.2.2 Automotive Drive Train Systems Engineering/Program Management X N/A

DO FORM 2794, MAY 2011 PREVIOUS EDITION IS OBSOLETE Page 8 of 13

13. REPORTS REQUIRED

(X if applicable)

DO 1921·3 (CBDR): 0

-a. PROGRAMI

CONTRACTI

SUBCONTRACT

b. CONTRACTI

SUBCONTRACT

wes REPORTING ELEMENTS a.CWes

DICTIONARY

b. DO 1921

(CDSR)

c. DO 1921·1

(FCHR)

d. DO 1921·2

(PCR)

e. DO 1921-4

(CSR)

f.SRDR

FORMATS

1.4.7.2 1.4.7.2.3 Drive Shaft System X N/A

1.4.7.2 1.4.7.2.4 Driver's Automotive Controls System X N/A

1.4.7.2 1.4.7.2.5 Transmission System X N/A

1.4.7.2 1.4.7.2.6 Wheel Drive System X N/A

1.4.7.2 1.4.7.2.7 Power Transfer Module X N/A

1.4.7.2 1.4.7.2.8 Other Automotive Drive Train Parts and Systems X N/A

1.4.7.3 1.4.7.3 Water Propulsion System X N/A

1.4.7.3 1.4.7.3.1 Water Propulsion System Integration, Assembly, Test & Checkout X N/A

1.4.7.3 1.4.7.3.2 Water Propulsion Systems Engineering/Program Management X N/A

1.4.7.3 1.4.7.3.3 Water Propulsion Power System X N/A

1.4.7.3 1.4.7.3.4 Water Propulsors Assembly X N/A

1.4.7.3 1.4.7.3.5 Other Waler Propulsion Parts & Systems X N/A

1.4.8 1.4.8 Auxiliary Automotive X N/A

1.4.8 1.4.S.1 Auxiliary Automotive Integration, Assembly, Test & Checkout X N/A

1.4.8 1.4.8.2 Auxiliary Automotive Systems Engineering/Program Management X N/A

1.4.8 1.4.S.3 Hydraulic System X N/A

1.4.8 l.4.S.4 Bilge System X N/A

1.4.8 1.4.8.5 Environmental Control System X N/A

1.4.8 1.4.8.6 Other Auxiliary Automotive Parts and Systems X N/A

1.4.9 1.4.9 Fire Control X N/A

1.4.9 1.4.9.1 Fire Control System Integration, Assembly, Test & Checkout X N/A

1.4.9 1.4.9.2 Fire Control Systems Engineering/Program Management X N/A

1.4.9 1.4.9.3 Fire Control Integration Software X N/A

1.4.9 1.4.9.4 Other Fire Control Parts and Systems X NIA

1.4.10 1.4.10 Armament X N/A

1.4.10 1.4.10.1 Armament Integration, Assembly, Test & Checkout X N/A

1.4.10 1.4.10.2 Armament Systems Engineering/Program Management X N/A

1.4.10 1.4.10.3 Primary Weapon X N/A

1.4.10 1.4.10.3.1 M2 HBMG (.50 cal) X N/A

1.4.10 1.4.10.3.2 MK1940mmAGL X N/A

1.4.10 1.4.10.4 Other Armament Parts and Systems X N/A

1.4.11 1.4.11 Automatic Ammunition Handling X NIA

1.4.12 1.4.12 Navigation and Remote Piloting X NIA

1.4.12 1.4.12.1 Navigation and Remote Piloting System Integration, Assembly, Test & Checkout X NIA

1.4.12 1.4.12.2 Navigation and Remote Piliting Systems Engineering/Program Management X NIA

1.4.12 1.4.12.3 Vision Systems X NIA

1.4.12 1.4.12.4 Navigation Systems X N/A

1.4.12 1.4.12.5 Other Navigation Systems X N/A

1.4.13 1.4.13 Special Equ ipment X N/A

1.4.13 1.4.13.1 Special Equipment Integration, Assembly, Test & Checkout X N/A

1.4.13 1.4.13.2 Special Equipment Systems Engineering/Program Management X N/A

1.4.13 1.4.13.3 Nuclear, Biological. & Chemical (NBC) Detection & Warning System X N/A

1.4.13 1.4.13.4 Chemical Detection System X NIA

1.4.13 1.4.13.5 Hydraulic Crane System X N/A

1.4.13 1.4.13.6 Recovery Winch System X NIA

1.4.13 1.4.13.7 Air Compressor System X N/A

1.4.13 1.4.13.8 Welder & Welder Power Supply System X NIA

1.4.13 1.4.13.9 Other Special Equipment X NIA

1.4.14 1.4.14 Communications X N/A

1.4.14 1.4.14.1 Communications System Integration, Assembly, Test & Checkout X NIA

DO FORM 2794. MAY 2011 PREVIOUS EDITION IS OBSOLETE Page 9 of 13

11. WBS ELEMENT CODE DO 1921-3 (CBDR): 0

(X if applicable) 12.

WBS REPORTING ELEMENTS a. PROGRAM/ b. CONTRACT/ b. DO 1921

c. DO 1921-1

d. DO 1921-2

e. DO 1921-4

f. SRDRa.CweSCONTRACT/

(PCR) FORMATSSUBCONTRACT DICTIONARY (CDSR) (FCHR) (CSR)

SUBCONTRACT

1.4.14 1.4.14.2 Communications Systems EngineeringiProgram Management X

NJA

1.4,14,31,4.14 Radio System NJAX

1.4.14 1.4,14.4 Antennas X

1.4.14 1.4,14,5 Vehicle Intercom System X

1.4,14 1.4.14,6 Processors. Displays, and Applications N/AX

1.4,14 1.4,14,7 Racks X N/A

1.4,14 1.4,14,8 Other Communications Systems X N/A

1.4,15 1.4,15 Vehicle Software Release 1..,n X N/A

1.4,15.1 1.4.15,1 Vehicle Application Software X

1.4,15,1 1.4,15,1,1 N/AVehicle Application Software Integration. Assembly. Test & Checkout X

1,4,15,1,21.4,15.1 Vehicle Application Software Systems Engineering/Program Management X

1.4,15,1 1.4.15,1.3 Mobility. Power, and Auxiliary (MPA) Software X N/A

1.4,15.1 1.4,15,1.4 Command and Control Software X

1.4,15.1 1.4.15,1,5 Controls and Displays (C&D) Software N/AX

1.4.15,1 1.4,15.1,6 Software Loader Verifier (SLV) X

1.4,15.2 Vehicle System Software 1.4.15.2 X

NJA

1.4,15.2 1.4.15.2,1 Vehicle System Software Integration. Assembly, Test & Checkout X

NJA

1.4,15.2 1.4.15.2,2 Vehicle System Software Systems Engineering/Program Management NJAX

1.4,15,2 1.4,15,2,3 System Software (Operating Systems) X

NJA

1.4,15,2 1.4,15,2.4 Software Development Environment X N/A

1.4,15,2,51.4.15,2 Software Test Environment X N/A

1.4,16 1.4,16 Other Vehicle Subsystems 1 ".n (Specify) X N/A

1,5 1.5 System Engineering X X X

1,5,11,5 Systems Engineering Management X

1,5 1,5.2 Requirements. Interface. Architecture Management X

1.5 1.5.3 Reliability. Availability. Maintainability (RAM) Engineering X

1.5 1.5.4 Human Factors and Safety Engineering X

System Analysis 1.5 1.5.5 X

Modeling & Simulation 1.5 1.5.6 X

1.5 1.5.7 Configuration Management X

Program Management 1.6 1.6 X

1,6 1.6.1 Contracts Management X

1.6.2 Program Control/Buisness Management 1.6 X

X

1,6,31.6 Schedule Management X

1.6,4 Supply Chain Management 1.6 X

1,6.51.6 Logistics Management & Supportability X

1.6 1.6.5.1 Logistics Management X

1.6.5,21,6 Supportability AnalysiS X

1,6 1.6.5,3 Supply Support X

1,6 1.6.5,4 Training Development X

1,6 1.6.5,5 Packaging, Handling, Storage, and Transportation (PHST) X

1,7 1,7 System Test and Evaluation X

1,7,1 1,7.1 Development Test and Evaluation X

Operational Test and Evaluation 1.7,2 1.7.2 X

X

1,7,3 Mock-ups / System Integration Labs (SILs) 1.7.3 X

1,7,4 Test and Evaluation Support X

1.7.4 X

1,7.4.1 T&E Support Prototype Vehicles 1,7.4 X

1,7.4,1.1 T&E Management Support 1.7.4 X

1.7.4.1.2 Developmental Testing Onsite Support 1,7.4 X

X

1,7,4,1,3 Operational Testing Onsile Support 1.7.4 X

DO FORM 2794. MAY 2011 PREVIOUS EDITION IS OBSOLETE Page 10 of 13

11. WBS ELEMENT CODE DO 1921·3 (CBDRl: (2]

(X if applicable) 12.

WBS REPORTING ELEMENTS e, PROGRAM!

b. CONTRACT! a.CWBS b. DO 1921 c, DO 1921·1 d. DO 1921·2 e. DO 1921-4 f.SRDR

CONTRACT!

DICTIONARY (CDSRl (PCR) (CSR) FORMATSSUBCONTRACT {FCHRl

SUBCONTRACT

1.7.4 1.7.4.1.4 Live Fire Test & Evaluation Onsite Support X

1.7.4 1.7.4.1.5 T&E Spare & Repair Parts X

1.7.4 1.7.4.2 T&E Support Production Vehicles X

1.7.4 1.7.42.1 T&E Management Support X

X

1.7,4 Developmental Testing Onsite Support U.4.2.2 X X X

1.7,4 X

1.7.4.2.3 Operational Testing Onsite Support X

X

1.7.4 1.7.4.2.4 Live Fire Test & Evaluation Onsite Support X

T&E Spare & Repair Parts 1.7.4 1.7.4.2.5 X

X

Test Facilities 1.7.5 1.7.5 X

Training1.8 1.8 X

X

1.8.1 1.8.1 Equipment X X X

1.8.2 1,8.2 Services X X X

1.8.3 Facilities1.8.3 X

X X

1.9 1.9 Data X

Technical Publications 1.9.1 1.9.1 X

X

Engineering Data 1.9.2 1.9.2 X X X

Management Data 1.9.3 1.9.3 X

1.9.4 Support Data 1.9.4 X

X

1.9.5 Data Depository 1.9.5 X

Peculiar Support Equipment 1.10 1.10 X

X

1.10.1 Test and Measurement Equipment 1.10.1 X

1.10,21.10.2 Support and Handling Equipment X

X

1.11 1.11 Common Support Equipment X X X

1.11.1 1.111 Test and Measurement Equipment X X X

1.11.2 1112 Support and Handling Equipment X X X

1,12 1.12 Operational/Site Activation X

1.12,1112.1 System Assembly, Installation and Checkout on Site X

X

1.12.2 1.12.2 Contractor Technical Support X

1,12,3 Site Construction 1.12.3 X

X

1.12.4 1.12.4 Site/ShipNehicie Conversion X

1.12.5 Sustainment/Interim Contractor Support 1.12.5 X

X

1.13 1.13 Industrial Facilities X

1.13.1 Construction/Conversion/Expansion1.13.1 X

X

1.13.2 1.13.2 Equipment Acquisition or Modernization X

1.13.3 Maintenance (Industrial Facilities) 1.13.3 X

X

1.14 1.14 Initial Spares and Repair Parts X

Subtotal Cost X

Reporting Contractor G&A X

Reporting Contractor Undistributed Budget X

Reporting Contractor Management ReselVe X

Reporting Contractor FCCM X

Total Cost X

Reporting Contractor Profit/Loss or Fee X

Total Price X

00 FORM 2794. MAY 2011 PREVIOUS EDmON IS OBSOLETE Page 11 of 13

14. CSDR SUBMISSION OATES

a.

SUBMISSION

b.

FORM(S)

c.

EVENT

d.ASOFDATE

(YVYYMMDD)

e. DUE DATE

(YYVYMMDD)

1 1921.1921-1 CIT Awd Est for MSC R&D (R&O CCORs) 20151201 20160131

2 1921.1921-1 Ctr Awd Est for LRIP1 (PROC CCORs) 20151201 20160131

3 1921,1921-1 Ctr Awd Est for LRIP2 (PROC CCORs) 20151201 20160131

4 1921.1921-1 CIf Awd Est for FRP1 (PROC CCORs) 20151201 20160131

5 1921, 1921-1 CIT Awd Est for FRP2 (PROC CCORs) 20151201 20160131

6 1921,1921-1 Ctr Awd Est for FRP3 (PROC CCORs) 20151201 20160131

7 1921,1921-1 Completion of EMO Build (R&D CCORs) 20170101 20170303

8 1921,1921-1 Completion of Compo T&E (R&D CCORs) 20180101 20180303

9 1921,1921-1,1921-2 Start of FUSL Build (R&D CCDRs) 20180301 20180501

10 1921,1921-1,1921-2 Completion of FUSL Build (R&D CCORs) 20181101 20190101

11 1921. 1921-1, 1921-2 Completion of Down-8elect T&E (R&D CCORs) 20200101 20200302

12 CWBS Dictionary Start of LRIP Lot 1 (CWBS Dictionary) 20180301 20180501

13 1921,1921-1,1921-2 Start of LRIP Lot 1 (PROC CCORs) 20180301 20180501

14 1921,1921-1,1921-2 Completion of LRIP Lot 1 (PROC CCORs) 20200401 20200601

15 1921,1921-1,1921-2 Start of LRIP Lot 2 (PROC CCORs) 20190101 20190303

16 1921,1921-1,1921-2 Completion of LRIP Lot 2 (PROC CCORs) 20211201 20220131

17 CWBS Dictionary Start of FRP Lot 1 (CWBS Dictionary) 20200401 20200601

18 1921,1921-1,1921-2 Start of FRP Lot 1 (PROC CCORs) 20200401 20200601

19 1921,1921-1,1921-2 Completion of FRP Lot 1 (PROC CCORs) 20220401 20220601

20 1921.1921-1.1921-2 Start of FRP Lot 2 (PROC CCDRs) 20210101 20210303

21 1921,1921-1.1921-2 Completion of FRP Lot 2 (PROC CCDRs) 20230101 20230303

22 1921,1921-1,1921·2 Start of FRP Lot 3 (PROC CCORs) 20220101 20220303

23 1921.1921-1.1921-2 Completion of FRP Lot 3 (PROC CCDRs) 20240101 20240302

15. REMARKS

NON·RECURRING/RECURRING DEFINITIONS

The contractor will utilize the specific definitions and requirements in the CSDR Manual (DoD 5000.04·M·1) and the definitions in the DIDs for the forms 1921 r 1921·1 rand 1921·2 to segregate Recurring and Nonrecurring costs discretely and not as an aggregate, Refinements or expansions to these definitions are TBD pending the pre-contract or post contract award conference.

COST ACCOUNTING STANDARDS (CAS) DISCLOSURE STATEMENT

Describe Significant accounting changes from previous accounting period in the Remarks section of the reports, if applicable.

00 FORM 2794, MAY 2011 PREVIOUS EDmON IS OBSOLETE Page 12 of13

1921·3 CONTRACTOR BUSINESS DATA REPORT

The DD Form 1921-3 is a mandatory requirement for all prime contractors and subcontractors performing work on contract which contain CSDR requirements.

a. The Contractor Business Data Report Is prepared by and for the business entity (e.g., business unit, segment, or site) responsible for submitting the Forward Pricing Rate Proposal (FPRP) representing the basis for Forward Pricing Rate Agreement (FPRA) negotiations with the government.

b. Reports are submitted annually at the end of the contractor's fiscal year.

c. Data for Future Years should be reflective of the number of years contained in the most current document, i.e., the FPRP or the FPRA. If the document applies to more than three future years, attach additional future year sheets as required. In the absence of these documents, estimates should be provided for three future years.

1921-2 PROGRESS CURVE REPORT

All DD Form 1921-2 must be reported on a UNIT basis. 1921-2 will be required for each production lot (e.g., LRIP Lot 1, LRIP Lot 2, FRP Lot 1, etc.). The vehicles per unit cost within each lot must be reported on the 1921·2 (e.g., if 30 units are completed for LRIP Lot 1, Submission # 12, Completion of LRIP Lot 1, should capture costs associated with each completed unit discretely on the 1921-2 reports in Columns A1-A30 (COMPLETED UNITS/LOTS).

CCDR REPORTING REQUIREMENT FOR CLINs

Per DoDM 5000.04-M·1 "Cost and Software Data Reporting (CSDR) Manual";

a) For CCDR purposes, contract value shall represent the estimated price at contract completion (i.e., initial contract award plus all expected authorized contract changes) and be based on the assumption that all contract options shall be exercised.

b) Contractors shall report all costs associated with the contract, including advance procurement, long lead materials, multiyear procurement, inter-division or inter-company work orders, foreign military sales, warranty, etc. Costs should not be omitted based on contract line item number (CLIN) structure or definition. Contractors shall report the CLINs reported within each CSDR in the DD·Form 1921 remarks section.

Per this definition, any changes/modifications to the CLiN structure to include (but not limited to) addition of new CLINs or the removal of CLiNs shall be reported/reflected in the CCDR submissions.

DO FORM 2794, MAY 2011 PREVIOUS EDI110N IS OBSOLETE Page 13 of 13