E1 - Questions and Answers.docx
DOCX document 22 KB Posted
- Attached to
- Marine Barracks Washington Window Tint Federal contract opportunity
- Solicitation number
- M549004590712
- Issued by
- United States Marine Corps
About this file
This document contains Questions and Answers related to a federal contract opportunity for window tinting services at Marine Barracks Washington. The key details are:
The window tinting will be applied to both the interior and exterior of the windows, with the specified film type being Dusted Crystal. Manufacturer recommendations for lift plans should be followed, at a minimum complying with EM-385-1-1. The period of performance has been extended to April 25, 2025 to accommodate weather restrictions, with a preference to complete the west/parade deck work first. The exterior work will require permits from the Department of Public Works and Transportation, while interior restrooms will be available for contractor use. This document does not contain the full details of the required products or services, as it is solely a set of Questions and Answers and not the full solicitation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A1 - Window Layout (Final).pdf | ||
| C - Wage Determination DC20230002 (Final).pdf | ||
| E1 - SF30 (Modified Copy).pdf | ||
| A1 - Window Tinting Details (Final).xlsx | XLSX spreadsheet | |
| A1 - PWS (Final).docx | DOCX document | |
| E1 - SF30 (Conformed Copy).pdf | ||
| E1 - Marine Barracks Washington Site Visit.docx | DOCX document | |
| A1 - Window Tinting Details.pdf | ||
| A3 - Brand Name (Signed).pdf | ||
| C - Wage Determination 2015-4281.pdf | ||
| D1 - M0026424QD011.pdf | ||
| A1 - Window Layout.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
Question 1.) Will the tint application be on the inside or outside?
Answer 1.) Both. Please review the documented titled “A1 Window Tinting Details (Final)” for specifications.
Question 2.) Do we need to split the panes with two types of film, for a total of 3?
Answer 2.) No, we are eliminating the mirror privacy film because it will not provide adequate privacy during non-daylight hours; instead these have been changed to the Dusted Crystal type film as indicated on the updated spreadsheet.
Question 3.) Lift plan requirements?
Answer 3.) MBW will not specify; it is advised the follow manufacturer recommendations at a minimum and recommend compliance with EM-385-1-1 (Safety and Health Requirements Manual).
Question 4.) Period of performance?
Answer 4.) Based on industry standard procedures, MBW is amenable to extending the delivery date to 25 April 2025. This should provide enough time to complete installations in the appropriate temperature ranges (above 55F) when spring arrives, but prior to the 2025 parade season with the first parade expected to occur on 02 May 2025. Preference will be for the contractors to complete the west/parade deck side work first, but MBW understands weather impacts may require the contractors to shift installation efforts to the interior applications on poor weather days and then resuming work on the exterior applications when weather is appropriate for installation.
Question 5.) Is the street and parking directly outside of Marine Barracks Washington considered base or public? If a cherry picker is needed will we need to get permits from Department of Public Works and Transportation?
Answer 5.) The outside streets and parking are public spaces and will require arrangements with the Department of Public Works and Transportation to block off streets.
Question 6.) Will restrooms be available for contractors or will there need to be a procurement of portable restrooms.
Amswer 6.) Restrooms within MBW will be available for employees.