Site Preparation Requirements and Installation Plan DI-MGMT-80033.pdf
Data Item Description PDF 159 KB Posted
- Attached to
- Air Compressor Dryer & Piping Replacement
- Solicitation number
- M00146-08-T-9020
- Issued by
-
United States Marine Corps
About this file
Data Item Description - Attachment 10
View the file
Other versions and copies of DI-MGMT-80033
| File | Revision | Posted | Attached to |
|---|---|---|---|
| DI-MGMT-80033A.pdf | Rev. A | Makerspace | |
| A037_DID_DI-MGMT-80033A_Site_Preparation_Requirements_and_Installation_Plan.pdf | Rev. A | Bidders Library for Open Skies OC-135 DVIS | |
| Site_Prep_and_Install_Plan_DI-MGMT-80033A.pdf | Rev. A | Abrasive Blast System | |
| A002 DIMGMT80033a Carousel.pdf | Rev. A | C-130 Carousels | |
| A002 DIMGMT80033a Carousel.pdf | Rev. A | C-130 Carousels | |
| Site Preparation Requirements and Installation Plan DI-MGMT-80033.pdf Same revision and size as this file | Revision not stated | UPGRADE OF ROTARY SCREW COMPRESSOR (RSC) | |
| Site Preparation Requirements and Installation Plan DI-MGMT-80033.pdf Same revision and size as this file | Revision not stated | Upgrade of Rotary Screw Compressor (RSC) |
Who attaches DI-MGMT-80033
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATA ITEM DESCRIPTION
-4Pm.d OM# NO. 07olOlU &D. &te.' Jun30. 1986
. TITLE 2. IDENTlFKATtON NUMBER
. SITE PREPARATION REQUIREMENTS AND INSTALLATION PLAN DI-MGMT-80033
. DESCXPTION/PURPOSE
3.1 The Site Preparation REquirements and Installation Plan defines require-ments and responsibilities for the coordinated, integrated Governinent and contractor site preparation and installation efforts of the deliverable end product (s) .
. APPROVAL DATE
(WMMDD)
5. OFFICE OF PRIMARY RESPONSIBILITY (OPR) h. OTIC REQUIRED 60. GiDE? AEQUIRED
8506 17 I C/T21 I I . APPLICATION I INTERRELATlONSHlP
7.1 This data item description contains the format and content preparation instructions for the data product generated by.the specific and discrete task requirement for this data included in the contract.
7.2 This data item may be applied in any program phase and contract which contains Site Preparation Requirements.
7.3 This data item supersedes DI-L-5083A and U-L-5083B.
. APPROVAL LIMITATION h . A P P U W L E FORMS Pb. AMSC NUMBER
G3626
O. PREPARATION INSTRUCTIONS
10.1 Contract. This data item is generated by the contract which contains a specific and discrete work task to develop this data product.
10.2 General. The following general instructions shall apply to the Site Preparation Requirements and Installation Plan:
a. Text - Typewritten or by such other office composition machine(s) as may be available, provided no additional cost is incurred'by the Government for such method of preparation and the delivered plan can be reproduced by standard office copying equipment.
b. DiagramsfDrawings - Be in accordance with the Contractor's standard engineering drawing practices.
C. Illustration/Graphs - Illustrative material, e.g., charts, graphs, photographs, sketches, etc., shall be in accordance with the contractor's normal methods for such data.
d. Legibility - The complete plan, including appendices, attachments, illustrations, graphics, etc., shall be clear, legible and reproducible.
10.3 Format. Contractor 'format.
Licensed by Information Handling Services
Document provided by IHS Licensee=NADEP/5918326100, User=, 02/11/2003 06:32:34 MST Questions or comments about this message: please call the Document Policy Management Group at 1-800-451-1584.
DI-MGMT-B0033 M G 7777787 0008487 8
DI-MGMT-80033
10. PREPARATION INSTRUCTIONS (Cont'd)
10.4 Content. Contents of the plan shall include the following as applicable:
a. A detailed description, by major subheadings, of a l l installation work to be done by the contractor at the sit te, to include schedulink and de-pendency of the various tasks.
b. A site layout plan including detailed layouts (placement) of all equipment, racks, cabinets and consoles.
C. General equipment specifications to include:
1. Physical specifications - height, length, width, and weight (floor loading) of each equipment rack, cabinet and console.
2. Equipment rack, cabinet and console templates.
3. Manufacturer's specific machine configuration and space requirements.
4. Maintenance access requirements for each equipment, rack cabinet and console.
5 . Special operational line-of-sight requirements between various equipments.
d. A lighting plan to include general and special lighting requirements.
e. A site and/or facility construction section detailing al1 required structural modifications or additions plans.
f. An electrical power utilization section to include requirements plans for:
1. Input voltages, frequency, and tolerances
2. Grounding
3. KVA required for each rack, cabinet and console. and the type of termination to Government's power supply, cable connections, terminal strip, etc.
4. Phasing number and color code of conductors per cabinet.
5. Location of power and signal entry points and their respective hole sizes.
6. Generator and control cabinet dimensions and specifications, con-trol wiring, and emergency off requirements.
Page 2 of 3 Pages
Management Group at 1-800-451-1584.
10. PREPARATION INSTRUCTIONS (Cont 'd)
g. A section containing the plans for an equipment inter-unit cabling, wave guide and wiring, and lists.
h. A cooling section containing plans which show facility and equipment air conditioning requirements, water requirements, and any special co6ling re-quirements, to include:
1. Operating area environmental conditions:
(a ) Temperature range
(b) Relative humidity range
(c) Atmospheric pressure
2. Equipment air conditioning requirements which shall specify:
(a) Type of air conditioning required, i.e., ambient or forced air. If forced air is indicated, required static air pressure shall be specified.
(b) Type of air carrier, i.e., subfloor or overhead duct.
(c) Location for each equipment rack, cabinet and console of the required overhead ducts or subfloor opening and their respective sizes.
(d) Equipment operating and non-operating environmental condi-tions, e.g., temperature, atmospheric pressure and relative humidity.
3 . . Operating requirements and capabilities of air conditioning equipment to include:
(a) Temperature range
(b) KVA
(c) BTUs (dl C.F.M./each, temperature, relative humidity range
i. Shipping requirements and related information to include:
1. Names of time span of contractor personnel to be used at the in-stallation site to ascertain delivery routes, dock facilities and to perform equipment installation.
2. Special requirements for on-site movement of equipment/systems.
*U.S. GOVERNMENT PRINTING OFFICE 1985 - 505-037130178