This document summarizes a federal solicitation for rolling fire door and shutters services. The U.S. Army Mission Installation Contracting Command at Fort Eustis is seeking these services for various buildings at West Point from April 2024 through April 2029, consisting of one base year and four option years. The requirement is set aside entirely for small businesses under NAICS code 811310 for commercial and industrial machinery repair and maintenance. Offerors must be registered in SAM and have a valid DUNS and CAGE code. A mandatory site visit will take place on February 15, 2024 and responses are due by February 14. Requests for information are due by February 21. Offers for the solicitation and required documents must be submitted by March 11 to the contact via email.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TABLE 1 Building Names and Numbers
Building Number Building Name Number of
Rolling
Fire Doors
Number of
Accordion
Doors
Number of Fire
Shutters
Number of
Elevator
Curtains
Location
500 Youth Center 3 Rooms 101, 105 and 115
601 Thayer Hall 5 2 Vertical Doors at Bookstore and 3
Vertical Doors across the hall at Gift Shop
667 DPW 9 2 Horizontal Rolling Door on second floor at Paper Clips (fusible links are painted);
2 Vertical Rolling Doors on first floor at
IMES; 2 Vertical Rolling Doors on first floor in Carpenter Shop; and 2 Horizontal
Rolling Doors on the second floor at the old paint shop (one single door and one double door - fusible links are painted and both have rope instead of cable) 1
Horizontal @ DFMWR
Warehouse/Loading Dock
693 Arts & Crafts 1 In Kitchen
700 Randal/Kimsey 2 2 Vertical Doors in 3rd Floor Atrium
Area
714 Holleder • 1 1 Vertical Door on 2nd Floor at Class of
56 Walkway
727 Arvin Gym 3 2 Vertical Rolling Doors in Hayes Gym (1 on first floor north; 1 on second floor north; and 1 on first floor south):
Shutters (I in DPE Equipment Room and
1 in DIA Equipment Room)
745D MacArthur 4 Basement/5th/4th/3rd
753N Science Center 5 8 Vertical Curtains attached to Elevator
755 Davis Barracks 1 Vertical Door for Electric Vault
758 Library 22 3 1 2nd Floor has 1 Vert Door, 1 Horizontal
Accordion Door, and 1 Vert Shutter at
Circulation Desk; 3rd and 5th Floors each have 7 Vert Doors and 1 Horizontal
Accordion Door; and 4th Floor has 7 Vert
Doors
845 Laundry Plant 6 6 Horizontal Rolling Doors on first floor
(Some have rope instead of steel cable)
950 USMAPS 2 Horizontal Accordion Doors (1 on first floor of Athletic Bldg. and 1 on second floor of Athletic Bldg.)
1946 TMP Admin 1
628 BOSS I 1 Vert Shutter on First Floor in Kitchen
Area
1534 Barth Hall 2 2 Vertical Shutters in Boodlers Cafe
51 9 9 5 74