Amendment 04--RFP LBNF-367397-JEE.pdf

PDF 143 KB Posted

Attached to
Thin Sprayed on Liner (TSL) Application IDIQ
Solicitation number
LBNF-RFP-367397-JEE
Issued by

About this file

This document is an Amendment (No. 04) to a Request for Proposal (RFP) for the Long-Baseline Neutrino Facility/Deep Underground Neutrino Experiment, specifically for a Thin Spray on Liner project. The amendment, issued on May 23, 2025, addresses two bidder questions regarding electrical work and certification requirements. The first response clarifies that electrical work must be coordinated with the BSI Construction Manager KAJV supervision, with contact information provided for Josh Schurger for electrical coordination. The second response indicates that CIP/NANCE Certification is not required for field testing.

The solicitation (LBNF-367397-JEE) has a proposal due date of May 30, 2025, and is associated with the Department of Energy's Fermi National Accelerator Laboratory. The project involves a competitive Indefinite Delivery/Indefinite Quantity (IDIQ) contract under NAICS 23832 for applying Thin Spray Liner (TSL) to shotcrete liner at the 4850 Level. Up to three IDIQ subcontracts may be awarded, with the first task order focusing on lab testing, field trials, and test reporting, with an expected start date of July 2025. The work will be performed at the Sanford Underground Research Facility (SURF) in Lead, SD, with specific access and logistical constraints outlined in the original solicitation.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT TO SOLICITATION

AMENDMENT NO.

DATE OF AMENDMENT:

May 23,2025

SOLICITATION NO.

RFP LBNF-367397-JEE

DATE ISSUED:

May 23, 2025

PROJECT NO.

N/A

PROPOSAL DUE DATE:

May 30, 2025

TITLE OF PROJECT:

Long-Baseline Neutrino Facility/Deep Underground Neutrino Experiment Thin Spray on Liner

Additional Bidder questions dated 05/23/2025; (1) If we provide a stepdown transformer to convert 480 3 ph. to 220 1 ph., do we need to supply the electrician? If so, who do we contact for a quote that is approved onsite? (2) For all the field testing, does FFDG require a Certified Coating Inspector (CIP) or NANCE certification.

Please find FFDG reply to the above questions 1 and 2 as follows:

1) Electrical work to be coordinated with the BSI Construction Manager KAJV supervision. For electrical coordination please contact Josh Schurger, Joshua.scherger@kiewit.com, Ph # 619-520-4948. For electrical connections refer to RFP 367397- JEE Amendment 02, Question and answer #17.

2) CIP/NANCE Certification is not required.

Fermi Forward Discovery Group, LLC.

168 Ross Street Lead, SD 57754

Joe Eagleston LBNF Procurement Specialist (713)-449-7515 mailto:Joshua.scherger@kiewit.com