Lake_Tarpon_MAR_106487_0385705-001-UC_5R_-Notice_of_Permit_Package.pdf
PDF 363 KB Posted
- Attached to
- CHESNUT ASR & MAR SURFACE FACILITIES - ENGINEERING DESIGN, PERMTTING AND CONSTRUCTION OVERSIGHT
- Solicitation number
- 26-0282-RFQ-CCNA
- Issued by
- Pinellas County, Clewiston City, Florida
About this file
Summary
This is a Notice of Permit Package issued by the Florida Department of Environmental Protection (FDEP) to Pinellas County Utilities for a Class V Underground Injection Control (UIC) permit authorizing the construction and testing of a Managed Aquifer Recharge (MAR) system at Lake Tarpon Chesnut Park in Pinellas County, Florida. The permit (0385705-001-UC/5R, WACS Facility ID 106487) was issued on September 29, 2025, and is valid through September 29, 2030. The project involves constructing one non-hazardous Class V injection well (MAR-1) with a 24-inch diameter final steel casing set to 600 feet below surface level and a total depth of 1,250 feet, along with two pre-existing monitor wells (SZMW-1 and SZMW-2). The MAR-1 well will accept partially treated surface water from Lake Tarpon with a maximum injection rate of 6,944 gallons per minute and a maximum injection volume of 10 million gallons per day. The permit requires comprehensive hydrogeologic testing through the confining layer, including packer testing and geophysical logging, with Department approval required at multiple construction stages including intermediate casing installation, final casing installation, monitor zone selection, short-term injection testing, and operational cycle testing.
The permit conditions establish extensive monitoring and reporting requirements, including continuous monitoring of injection well pressure and flow rates with daily and monthly reporting, monthly operating reports containing water quality analyses, and sampling of monitor zones at specified frequencies (monthly, quarterly, and annually depending on the parameter). The permittee must employ a professional engineer registered in Florida throughout the construction period and maintain continuous on-site supervision by qualified personnel during testing and logging operations. Financial responsibility provisions require the permittee to maintain adequate resources to properly close, plug, and abandon all injection and monitor wells. Weekly progress reports must be submitted throughout construction, and all records must be retained for at least three years from the date of sampling or measurement, with monitoring records retained for five years after plugging and abandonment. The permit includes strict requirements for mechanical integrity demonstration, operational testing approval, water quality standards compliance, and emergency notification procedures, with any noncompliance potentially endangering groundwater requiring 24-hour reporting to FDEP's Southwest District and Aquifer Protection Program offices.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jay Collins Lt. Governor
Alexis A. Lambert Secretary
Sent Via Electronic Mail September 29, 2025
In the Matter of an Application for Permit by:
Pinellas County Utilities UIC Permit: 0385705-001-UC/5R Jeremy Waugh, P.E. WACS Facility ID: 106487 Director Utilities Department County: Pinellas 14 South Fort Harrison Avenue Class V Injection Well System, MAR-1 Clearwater, Florida 33765 Construction Permit JWaugh@Pinellas.gov Lake Tarpon Chesnut Park Managed Aquifer
Recharge System
Notice of Permit
Enclosed is permit number 0385705-001-UC/5R for a Class V injection well system.
Any party to this Order (permit) has the right to seek judicial review of the permit pursuant to Section 120.68, Florida Statutes, (F.S.), by the filing of a Notice of Appeal pursuant to Rules 9.110 and 9.190, Florida Rules of Appellate Procedure, with the Clerk of the Department in the Office of General Counsel, 3900 Commonwealth Boulevard, Mail Station 35, Tallahassee, Florida 32399-3000, Agency_Clerk@FloridaDEP.gov; and by filing a copy of the Notice of appeal accompanied by the applicable filing fees with the appropriate District Court of Appeal. The Notice of Appeal must be filed within 30 days from the date this Notice is filed with the Clerk of the Department.
Permittee: Pinellas County Utilities UIC Permit: 0385705-001-UC/5R Jeremy Waugh, P.E., Director Utilities Department WACS Facility ID: 106487 Lake Tarpon Chesnut Park Managed Aquifer Recharge System
Date: September 29, 2025
Executing and Clerking:
Executed in Tallahassee, Florida.
State of Florida Department of Environmental Protection
Certificate of Service The undersigned duly designated clerk hereby certifies that this Notice of Permit and all copies were sent on the filing date September 29, 2025, to the following listed persons:
Richard Lobinske, DEP/TLH, Richard.Lobinske@FloridaDEP.gov Dan Warmke, DEP/TLH, Daniel.Warmke@FloridaDEP.gov Edith Chuy, DEP/TLH, Edith.Chuy@FloridaDEP.gov Cheryl Greenwell, DEP/TLH, Cheryl.Greenwell@FloridaDEP.gov Emily Larson, DEP/SWD, Emily.Larson@FloridaDEP.gov Sean P. Menard, PE, Jones Edmunds & Associates, SMenard@JonesEdmunds.com Pete Larkin, PG, ASRus, PLarkin@ASRus.net David S. Adams, P.G. Pinellas County Utilities, DAdams@Pinellas.gov Jason Meadows, USEPA/ATL, Meadows.JasonB@EPA.gov
Filing and Acknowledgment Filed, on this date, pursuant to Section 120.52, Florida Statutes, (F.S.), with the designated Department Clerk, receipt of which is hereby acknowledged.
Clerk Date
Richard Lobinske, Ph.D.
Environmental Administrator Aquifer Protection Program
Division of Water Resource Management
9/29/2025
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Alexis A. Lambert Secretary
Underground Injection Control
Class V, Group 2 Aquifer Recharge Injection Well System Construction and Testing Permit
Permittee Permit/Certification Pinellas County UIC Permit: 0385705-001-UC/5R Jeremy Waugh, P.E. WACS Facility ID: 106487 Director Utilities Department Date of Issuance: September 29, 2025 14 South Fort Harrison Avenue Date of Expiration: September 29, 2030 Clearwater, Florida 33756 Permit Processor: Dan Warmke JWaugh@Pinellas.gov
Facility Location
Lake Tarpon Chesnut Park Managed Aquifer Recharge System
County:
Latitude:
Pinellas 28˚ 04' 56.5" N
2200 East Lake Road South Longitude: 82˚ 42' 10.2" W Palm Harbor, Florida 34685
Project: Class V Managed Aquifer Recharge Injection Well System, MAR-1 This permit is issued under the authority of Chapter 403, Florida Statutes (F.S.), and the rules adopted thereunder, particularly Chapters 62-4, 62-520, and 62-528, Florida Administrative Code (F.A.C.).
The permittee is required to comply with the provisions outlined in 40 Code of Federal Regulations (C.F.R.) 144, 145, 146, and 147. [62-528.601(2) F.A.C., 40 C.F.R § 144.82] Pursuant to Section 403.088(2)(c)4., F.S., the Department of Environmental Protection (Department or DEP) has the authority to impose conditions necessary to protect and preserve water quality.
The above-named permittee is hereby authorized to perform the work or operate the facility shown on the application and approved drawing(s), plans, and other documents attached hereto or on file with the Department and made a part hereof and specifically described below. [62- 528.307(1)(b), F.A.C.] Subject To: The following Specific Conditions and General Conditions.
I. Specific Conditions A. Project Description
1. To construct one non-hazardous Class V Managed Aquifer recharge injection well MAR-1 and associated pre-existing monitor wells SZMW-1, and SZMW-2. MAR-1 will be constructed with a 24-inch diameter final steel casing set to 600 feet below surface level (bls) with a total depth of 1250 feet bls. MAR-1 will accept partially treated surface water from Lake Tarpon to provide aquifer recharge. The maximum injection rate for MAR-1 shall be 6,944 gallons per minute (gpm) and the maximum injection volume shall be 10 million gallons per day (mgd). Monitor well SZMW-1 is completed in the Upper
Permittee: Pinellas County UIC Permit: 0385705-001-UC/5R
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025
Floridan aquifer from 235 to 335 feet bls. Monitor well SZMW-2 is completed in the Upper Floridan aquifer from 190 to 240 feet bls.
2. Hydrogeologic testing shall be conducted through the confining layer overlying the proposed recharge interval. Based on an evaluation of hydrogeologic conditions encountered, if a continuous permeable interval of 30 feet or greater exists between the depth of 370 feet (35 feet below the existing SLMW-1 monitoring interval)and depth at which groundwater has a TDS concentration of greater than 10,000 mg/L,which is estimated to be approximately 460 feet, the Department may require the addition of a monitoring well within this permeable interval to be located at a horizontal distance of 150 feet from the MAR well.
The characterization of the confining properties will be based primarily on estimated hydraulic conductivity (k) established from analysis of pumping test data collected during packer testing of the confining interval. Inflatable packer elements used to isolate tested intervals in the pilot hole are limited in their ability to provide a perfect “seal” against the borehole wall nor does it prevent movement of water within the formation above and below the packer into the tested interval, resulting in a higher than actual calculated hydraulic conductivity. This is observed in the order(s) of magnitude differences in hydraulic conductivity observed between packer test results and laboratory results of core permeability over the same interval. Therefore, packer test analysis should be viewed as a qualitative measurement used to compare relative differences in hydraulic characteristics between different portions of the borehole. The packer test intervals will be determined upon evaluation of the video and caliper log data to select suitable portions of the borehole for successful packer seating. The packer testing plan will be provided to the Department for approval with justification of the selected intervals.
Pursuant to the definitions in Chapter 62-528, FAC, a “confining zone” means a geological formation, group of formations, or part of a formation that is capable of limiting fluid movement from an injection zone. As this is purposely a subjective criterion to account for the wide variabilities in hydrogeologic conditions encountered in Florida, the determination of confining properties will be based on the relative differences in hydraulic conductivity of the proposed confining interval compared to the overlying permeable interval represented by SZMW-1. From previous packer testing conducted during construction of SLMW-1, the hydraulic conductivity of the SLMW-1 “permeable” interval (packer test 210 to 335 feet) was estimated at 10 feet per day (ft/d) which is moderately low and projected to be an order of magnitude lower than the targeted recharge zone in the Avon Park high permeability zone (APHPZ). For this site, the interval separating the recharge zone from the overlying permeable unit represented by SZMW-1 shall be considered distinctly less permeable if the hydraulic conductivity is 3 ft/d or less (estimated from packer testing analysis) which is approximately 3 times lower than the overlying permeable unit.
In the event conditions of the borehole are incompatible for effective packer sealing and discrete interval isolation, other methods will be used to evaluate the confining properties including geophysical logging sonic porosity data, and core laboratory analysis. If sonic porosity responses from the interval separating the recharge zone and SZMW-1 is distinctly lower than the overlying interval represented by SZMW-1, it will be considered confining. Laboratory core permeability testing that indicates a vertical hydraulic conductivity of 10-1 ft/d will be considered confining.
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025
3. Documents
a. This permit is issued in accordance with the information received in the following documents:
1) The ASRus, LLC/HydroGeo Consulting, LLC/Jones Edmunds, Inc.: “Lake Tarpon, Chestnut Park Managed Aquifer Recharge System Class V Construction Permit Application”, Dated March 9, 2020.
2) Jones Edmunds response to the Department’s request for additional information dated October 8, 2021.
3) Supporting information submitted to the Aquifer Protection Program (APP) Tallahassee office.
4. Location
a. The project will be located at the Lake Tarpon Chesnut Park Managed Aquifer
Recharge System, 2200 East Lake Road South, Palm Harbor, Florida 34685, in Pinellas County.
B. Injection and Monitor Wells
1. The injection and monitor wells, as designated below by well name and Water
Assurance Compliance System (WACS) testsite identification (ID), and construction details at this facility, are as follows:
Table 1 Recharge Well
Well Name
WACS
Testsite
ID
Well Depth
(Feet bls)
Casing Size
(Inches)
Casing Thickness (Inches)
Casing or Tubing Type
Casing Depth or Interval (Feet bls)
MAR-1 14287 1,250
42 0.375 Steel 160 32 0.375 Steel 470 24 0.39 Steel 600
Open Hole 600 – 1,250 Notes:
2. Monitor Wells
a. Location
1) Monitor wells are required above the injection zone, near the injection well. [62- 528.425(1)(g), F.A.C.]
2) The permittee shall monitor a zone below the base of the underground source of drinking water, if a zone is available, and at least one zone within, and near the base of, the underground source of drinking water. [62-528.425(1)(g)4., F.A.C.]
b. The permittee shall be able to monitor the following:
1) The absence of fluid movement adjacent to the well bore, and
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025
2) The long-term effectiveness of the confining zone.
[62-528.425(1)(g)1., F.A.C.]
Table 2 Monitor Wells
Well Name
WACS
Testsite ID
Monitor Zone
Casing Size
(Inches) Casing Type
Casing Thickness
Casing Depth
(Feet bls)
Monitoring Depth
(Feet bls)
SZMW-2 23153A
14 Steel 0.375 21
6 PVC 0.39 190
Upper Zone 190 - 240
SZMW-1 23152A
18 Steel 0.375 59 12 Steel 0.375 210
6 PVC 0.28 235
Lower Zone 235 - 335 Notes: SZMW-1 and SZMW-2 are pre-existing wells permitted under 0231277-005-UC/5SR
C. Authorized Activities
1. This permit is for the Pinellas County Utilities to construct and operationally test injection well MAR-1 and it will be constructed with a 24-inch diameter final steel casing set to 600 feet bls with a total depth of 1250 feet bls. Monitor well SZMW-1 is completed in the Upper Floridan aquifer from 235 to 335 feet bls. Monitor well SZMW-2 is completed in the Upper Floridan aquifer from 190 to 240 feet bls. This permit authorizes the construction of one additional monitor well if site geologic conditions warrant (Condition I.A.2 above).
[62-528.307(1)(b), 62-528.625(1), F.A.C.]
D. Evaluation and Department Approvals
1. The construction, geophysical logging, and packer testing programs shall be implemented in accordance with this permit and as proposed in the following submittals:
a. ASRus, LLC/HydroGeo Consulting, LLC/Jones Edmunds, Inc., “Lake Tarpon, Chestnut
Park Managed Aquifer Recharge System Class V Construction Permit Application
b. DEP, Request for Additional Information (RAI)
c. Jones Edmunds, Response to RAI
d. Other approved submittals received by the Department [62.528.307(1)(b), F.A.C.]
2. Department Approvals
a. Department approval is required prior to the following stages of construction and testing:
1) Intermediate (32-inch) casing seat in the injection well
2) Final (24-inch) casing seat in the injection well
3) Final seat for tubing and packer in the injection well
4) Intermediate casing seat of any monitor well that may be constructed
5) Final casing seat of any monitor well that may be constructed
6) Monitor zone selection of any monitor well that may be constructed
7) Short-term injection test
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025
8) Operational (cycle) testing [62-528.605(2), F.A.C.]
E. Water Quality Standards
1. The wells shall be constructed so that their intended use does not violate the water quality standards of Chapter 62-520, F.A.C. Migration or mixing of fluids from aquifers of substantively different water quality through the construction or use of a Class V well shall be prevented by preserving the integrity of confining beds between these aquifers through cementing or other equally protective method acceptable to the Department.
[62-528.605(3), F.A.C.]
2. Partially treated surface water accepted by the well shall meet the criteria established in Rule 62-520.440, F.A.C.
F. Monitoring Requirements
1. The MAR system shall be monitored in accordance with Rules 62-528.425(1)(g) and 62-
528.430(2), F.A.C. [62-528.307(2)(c), F.A.C.]
2. Monitor wells shall be sampled periodically. The frequency of sampling and constituents to be analyzed are specified in the permit and shall be representative of the monitored activity. [62-528.425(1)(g)2., F.A.C.]
3. The Department shall determine the frequency of monitoring based on the location of the well, the nature of the injected fluid and, where applicable, the requirements of Chapters 62-600 and 62-601, F.A.C. [62-528.615(2), F.A.C.]
4. Additional requirements are outlined in the General Conditions section of this permit.
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025
Table 3 Monitoring Schedule
Parameters Unit Recording
Frequency or Sampling Method
Frequency of Analyses
MAR-1
14287
SZMW-2
Upper Zone
23153A
SZMW-1
Lower Zone
23152A
ASR Well Pressure, Max. psi Continuous D/M a ASR Well Pressure, Min. psi Continuous D/M a ASR Well Pressure, Avg. psi Continuous D/M a Flow Rate, Max. gpm Continuous D/M a Flow Rate, Min. gpm Continuous D/M a Flow Rate, Avg. gpm Continuous D/M a Volume Injected per Well MG Daily/Monthly D/M Pressure or Water Level Max. psi or ft NAVD Continuous D/M a D/M a Pressure or Water Level Min. psi or ft NAVD Continuous D/M a D/M a Pressure or Water Level Avg. psi or ft NAVD Continuous D/M a D/M a pHb standard units Grab/Purge M M M Specific Conductanceb µmhos/cm Grab/Purge M M M Temperatureb °C Grab/Purge M M M Dissolved Oxygenb mg/L Grab/Purge M M M Oxidation-Reduction Potentialb mV Grab/Purge M M M Turbidityb NTU Grab/Purge M M Arsenic mg/L Grab/Purge M M M Total Organic Carbon (TOC) mg/L Grab/Purge M M M Color color units Grab/Purge M M M Odor TON Grab/Purge M M M Chloride mg/L Grab/Purge M M M Sulfate mg/L Grab/Purge M M M Total Dissolved Solids mg/L Grab/Purge M M M Nitrate + Nitrite as N mg/L Grab/Purge M M M Ammonia as N mg/L Grab/Purge M M M Total Kjeldahl Nitrogen mg/L Grab/Purge M M M Bicarbonate mg/L Grab/Purge M M M Calcium mg/L Grab/Purge M M M Total Iron mg/L Grab/Purge M M M Magnesium mg/L Grab/Purge M M M Potassium mg/L Grab/Purge M M M Sodium mg/L Grab/Purge M M M Total Suspended Solids mg/L Grab/Purge M M M Total Coliform cfu/100 mL Grab/Purge Mc M M Fecal Coliform cfu/100 mL Grab/Purge Mc Mc Mc Escherichia coli cfu/100 mL Grab/Purge Mc Mc Mc Primary & Secondary Drinking Water Standards, Source Water Grab A
D – Daily; W – Weekly; B/W – Biweekly (twice per month); M – Monthly; Q – Quarterly; A – Annually a – Operational data reporting for flows, pressures and water levels: daily maximum, minimum and average from continuous reporting; monthly maximum, minimum and average (calculated from daily averages).
b – Field samples C - Upon a result of Total Coliform above 4 CFU per 100 mL in a monitor well, permittee shall sample immediately all wells for Total Coliform, Fecal Coliform, and E. coli, then monthly until results demonstrate a concentration of Total Coliform below 4 CFU per 100 mL in monitor wells.
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025
II. General Conditions A. Permit
1. All “ground water recharge by injection” projects (Aquifer Recharge) shall comply with the technical and permitting requirements in Chapter 62-528, F.A.C., and shall obtain an underground injection control construction and operation permit..
2. The terms, conditions, requirements, limitations and restrictions set forth in this permit are “permit conditions” and are binding and enforceable pursuant to Section 403.141, F.S. [62-528.307(1)(a), 62-4.160 (1), F.A.C.]
3. This permit is valid only for the specific processes and operations applied for and indicated in the approved drawings or exhibits. Any unauthorized deviation from the approved drawings, exhibits, specifications, or conditions of this permit may constitute grounds for revocation and enforcement action. [62-528.307(1)(b), F.A.C.]
4. This permit or a copy thereof shall be kept at the work site of the permitted activity. [62 528.307(1)(l), F.A.C.]
5. Modification
a. Any proposed modifications to the permit, construction procedures, testing procedures, completion procedures, operation procedures, or any additional work not described in the application or supporting documents shall be submitted in writing to the APP Tallahassee office for review and clearance prior to implementation. Changes of negligible impact to the environment and staff time will be reviewed and approved when appropriate and incorporated into this permit. Other changes or modifications will require submission of a completed application and applicable processing fee as per Rule 62-4.050, F.A.C. [62-4.050, F.A.C.]
6. Permit Transfer
a. This permit is transferable only upon Department approval in accordance with rules
62-4.120 and 62-528.350, F.A.C. The permittee shall be liable for any non-compliance of the permitted activity until the transfer is approved by the Department. [62-528.307(1)(k), F.A.C.]
7. Expiration and Extension
a. If the injection is to continue beyond the expiration date of this permit the permittee shall apply for and obtain an operation permit. If necessary to complete the operational (cycle) testing period, the permittee shall apply for renewal of the construction permit at least 60 days prior to the expiration date of this permit. [62- 528.307(2)(a), F.A.C.]
8. Renewal
a. For renewal of this permit, the permittee shall submit a separate laboratory analysis for each permitted injectate source. [62-528.425(1)(g), 62-528.430(2)(b)a, F.A.C.]
b. When the application for renewal is timely and sufficient, the existing permit shall remain in effect until the renewal application has been finally acted upon by the Department or, if there is court review of the Department’s final agency action, until a later date is required by Section 120.60, F.S. [62-4.090, F.A.C.]
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025
9. Corrections
a. If the permittee becomes aware that relevant facts were not submitted or were incorrect in the permit application or in any report to the Department, such facts or information shall be corrected promptly. [62-528.307(1)(m), F.A.C.]
B. No Rights, Privileges, or Waivers
1. As provided in subsection 403.087(7), F.S., the issuance of this permit does not convey any vested rights or exclusive privileges. Neither does it authorize any injury to public or private property or any invasion of personal rights, nor infringement of federal, state, or local laws or regulations. This permit is not a waiver of or approval of any other Department permit that may be required for other aspects of the total project which are not addressed in this permit. [62-528.307(1)(c), F.A.C.]
2. This permit conveys no title to land, water, does not constitute State recognition or acknowledgment of title, and does not constitute authority for the use of submerged lands unless herein provided and the necessary title or leasehold interests have been obtained from the State. Only the Trustees of the Internal Improvement Trust Fund may express State opinion as to title. [62-528.307(1)(d), F.A.C.]
C. Liability for Harm
1. This permit does not relieve the permittee from liability for harm to human health or welfare, animal, or plant life, or property caused by the construction or operation of this permitted source, or from penalties there from; nor does it allow the permittee to cause pollution in contravention of Florida Statutes and Department rules, unless specifically authorized by an order from the Department. [62-528.307(1)(e), F.A.C.]
D. Rule Changes
1. The permittee agrees to comply with changes in Department rules and Florida Statutes after a reasonable time for compliance; provided, however, the permittee does not waive any other rights granted by Florida Statutes or Department rules. [62- 528.307(1)(j), F.A.C.]
E. Quality Assurance/Quality Control
1. The permittee shall ensure that the construction and operational testing of this MAR well system shall be as described in the application and supporting documents.
F. Hazardous Waste
1. The injection of hazardous waste through any well or septic system is prohibited. [62- 528.400(1), F.A.C.]
G. Fluid Movement and Confinement
1. No owner or operator shall construct, operate, maintain, convert, plug, abandon, or conduct any other injection activity in a manner that allows the movement of fluid containing any contaminant into underground sources of drinking water, if the presence of that contaminant may cause a violation of any primary drinking water regulation under 40 CFR part 142 or may otherwise adversely affect the health of persons. If operation of the well results in a potential violation of a secondary drinking water standard in the overlying USDW, the applicant shall seek a Water Quality Criteria Exemption under Rule 62-520.510, F.A.C. The applicant for a permit shall have the burden of showing that the requirements of this paragraph are met. [62-528.601(2), 62- 528.625(1), F.A.C., 40 C.F.R §144.12(a)]
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025
2. Migration or mixing of fluids from aquifers of substantively different water quality through the construction or use of a Class V well shall be prevented by preserving the integrity of confining beds between these aquifers through cementing or other equally protective method acceptable to the Department. [62-528.605(3), F.A.C.]
3. If site conditions are warranted as per numbers 1 and 2 above during the construction of injection well MAR-1, a deeper monitor will be installed to help monitor the new recharge well MAR-1.
H. Engineer of Record
1. A professional engineer registered pursuant to Chapter 471, F.S., shall be retained throughout the construction period to be responsible for the construction operation and to certify the application, specifications, completion report, and other related documents.
The permittee shall immediately notify the Department of any change of engineer. [62- 4.050(3), F.A.C.]
2. Continuous on-site supervision by qualified personnel (engineer and/or geologist, as applicable) is required during all testing and geophysical logging operations. [62- 4.050(3), F.A.C.]
I. Facility
1. Operation and Maintenance
a. The permittee shall properly operate and maintain the facility and systems of treatment and control (and related appurtenances) that are installed and used by the permittee to achieve compliance with the conditions of this permit, or are required by Department rules. Proper operation and maintenance includes:
1) Adequate operator staffing and training
2) Adequate laboratory and process controls, including appropriate quality assurance procedures
3) Effective performance
4) Adequate funding
5) This provision requires the operation of back-up or auxiliary facilities or similar systems only when necessary to achieve compliance with the conditions of the permit.
[62-528.307(2)(b), F.A.C., 40 CFR 144.51(e)]
b. This provision requires the operation of backup or auxiliary facilities or similar systems only when necessary to achieve compliance with the conditions of the permit and when required by Department rules. [62-528.307(1)(f), 62-4.160 (6), F.A.C., 40 CFR 144.51(e)]
c. All indicating, recording and totalizing devices associated with the MAR well system shall be maintained in good operating condition and calibrated annually at a minimum. The pressure gauges, flow meter, and chart records shall be calibrated using standard engineering methods. [62-528.307(1)(f) and 62-528.307(3)(b), F.A.C.]
2. Surface Equipment
a. The integrity of the monitor zone sampling systems shall be maintained at all times.
Sampling lines shall be clearly and unambiguously identified by monitor zone at the point at which samples are drawn. All reasonable and prudent precautions shall be taken to ensure that samples are properly identified by monitor well name or zone and that samples obtained are representative of those zones. Sampling lines and
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025 equipment shall be kept free of contamination with independent discharges and no interconnections with any other lines. [62-528.307(1)(f) and 62-528.307(2)(b), F.A.C.]
b. The surface equipment for each MAR well disposing of domestic (municipal) effluent shall maintain compliance with Rule 62-600.540(5), F.A.C., for water hammer control, screening, access for logging and testing, and reliability and flexibility in the event of damage to the well and effluent piping. [62-600.540(5), 62-528.307(1)(f), and 62-528.307(2)(b), F.A.C.]
c. MAR wells not disposing of domestic (municipal) effluent shall maintain compliance with Rule 62-528.450(2)(j), F.A.C. for water hammer control, as well as access for logging and testing, and reliability and flexibility in the event of damage to the well and effluent piping. [62-528.450(2)(j), 62-528.307(1)(f), and 62-528.307(2)(b), F.A.C.]
d. The surface equipment and piping for the MAR and monitor wells shall be kept free of corrosion at all times. [62-528.307(1)(f) and 62-528.307(2)(b), F.A.C.]
e. Spillage onto the MAR well pad(s) during construction activities, and any waters spilled during mechanical integrity testing, maintenance, testing, or repairs to the system(s) shall be contained on the pad(s) and directed to a sump which in turn discharges to the pumping station wet well, or via other approved means to the MAR well system, or by another method approved by the Department. [62-528.307(1)(f) and 62-528.307(2)(b), F.A.C.]
f. After well construction activities are complete, the MAR well pads are not, unless specific approval is obtained from the Department, to be used for storage of any material or equipment at any time. [62-528.307(1)(f) and 62-528.307(2)(b), F.A.C.]
3. Site Requirements
a. The permittee shall provide a containment structure during drilling operations to collect any spillage of contaminants and to support the heaviest load encountered during drilling, in accordance with Rule 62-528.630, F.A.C. The permittee shall provide specific containment structure dimensions and design drawings to the Department prior to commencing construction and shortly after the selection of the drilling contractor.
b. Waters spilled during construction or testing of the MAR well system shall be contained and properly disposed. [62-528.307(1)(e) and (f), F.A.C.]
c. No drilling operations shall begin without an approved disposal site for drilling fluids, cuttings, or waste. The permittee shall obtain the necessary approval(s) for disposal prior to the start of construction. A detailed disposal plan shall be submitted to the APP Tallahassee office prior to the commencement of drilling activities for the MAR and monitor wells. [62-528.630, F.A.C.]
4. Pad Wells
a. Surficial aquifer monitor wells, identified as pad monitor wells (pad wells), as approved in the well construction specifications shall be located near the corners of the pads to be constructed for the injection and monitor wells, and shall be identified by number or pad location, i.e. NW, NE, SW, and SE. If located in a traffic area the well head(s) must be protected by traffic bearing enclosure(s) and cover(s). Each cover must lock and be specifically marked to identify the well and its purpose. The pad wells shall be sampled as follows:
b. The pad wells shall be sampled and analyzed prior to drilling the test injection or monitor wells and then weekly thereafter during the construction and associated
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025 testing phases. Sampling shall include specific conductance (micromhos/centimeter [µmhos/cm]), pH (standard units), chloride (milligram per liter [mg/L]), field temperature (°Celsius [C]), and water level (pound per square inch [psi] or feet [ft] North American Vertical Datum [NAVD] of 1988). Chloride and specific conductance may be from field or lab samples.
c. Initial PMW analyses shall be submitted prior to the onset of drilling activities.
d. The pad wells shall also be sampled for total dissolved solids (mg/L, laboratory samples) during the first four weeks of PMW sampling and at all times when specifically requested by the Department.
e. The results of the PMW analyses shall be submitted to the Department in the weekly progress report. The pad wells shall be retained in service throughout the construction phase of the project. Upon completion of construction, the permittee may submit a request to the Department for cessation of sampling followed by capping, or plugging and abandonment of these wells.
[62-160, 62-528.630(3),(4), F.A.C.]
5. Hurricane Preparedness
a. Upon the issuance of a “Hurricane Watch” by the National Weather Service, the preparations to be made include but are not necessarily limited to the following:
1) Secure all on-site salt and stockpiled additive materials to prevent surface and/or groundwater contamination.
2) Properly secure drilling equipment and rig(s) to prevent damage to well(s) and on-site treatment process equipment.
[62-528.307(1)(f), F.A.C.]
J. Construction
1. Pre-Drilling Submittal Requirements
a. Submit the following to the APP Tallahassee office during site preparation but prior to drilling operation commencement for the MAR well system:
1) The drilling and construction schedule
2) Site layout of drilling pad
3) Proposed pad monitor well locations [62-528.307(1)(v), F.A.C.]
2. Notifications
a. The permittee shall notify the APP Tallahassee office seven (7) days prior to the mobilization of drilling operations to the site. [62-528.635(1), F.A.C.]
b. The permittee shall notify the Department as soon as possible of any planned physical alterations or additions to the permitted facility. In addition, prior approval is required for activities described in rule 62-528.410(1)(h). [62-528.307(1)(v), F.A.C.]
c. The permittee shall give advance notice to the Department of any planned changes in the permitted facility or injection activity which may result in noncompliance with permit requirements. [62-528.307(1)(w), F.A.C.]
3. Construction Standards
a. Any construction, modification, repair, or abandonment of a well shall be performed by a Florida licensed water well contractor, licensed under Chapter 62-532, F.A.C., to engage in the business of construction, modification, repair, or abandonment of a well. [62-532.200, 62-528.605(4), F.A.C.]
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025
b. Well construction shall comply with Rule 62-532.500, F.A.C., Water Well Construction Standards. [62-528.605(4), 62-532.500, F.A.C.]
c. The measurement points for drilling and logging operations shall be surveyed and referenced to the NAVD of 1988 (NAVD 88) prior to the onset of drilling activities for the injection and monitor wells. [62-160.240(3)(b)3., F.A.C.]
d. Blow-out preventers or comparable flow control devices shall be installed on the MAR and monitor wells prior to penetration of the Floridan aquifer system. [62- 528.605(2),(3), F.A.C.]
e. If additives that were not approved in the permit application are to be used during grouting, for lost circulation, or for any other reason, information on their properties shall be submitted to the APP Tallahassee office prior to their use for review and approval. [62-528.605(2),(3), F.A.C.]
f. No more than 6% bentonite gel shall be used to cement any casing or tubing unless advance approval is received from the Department due to conditions found during the drilling and logging of the well.
[62-528.605(2),(3), F.A.C.]
4. Casing Seats and Monitoring Intervals
a. Exact depths of casing seats and monitoring intervals shall be determined based on field conditions and the results obtained during the construction and testing program, and are subject to the conditions of this permit.
b. At least one MAR well or storage zone monitor well will be constructed prior to overlying zone monitor wells. [62-528.425(1)(g), F.A.C.]
c. Data and Analysis
1) The data and analysis supporting the selection of the monitoring intervals shall be submitted to the APP Tallahassee office after the collection, interpretation, and analysis of all pertinent cores, geophysical logs, packer tests and analysis of fluid samples. The Department shall approve the final selection of the specific monitoring intervals prior to monitor well completion. [62-528.425(1)(g), F.A.C.]
d. Department Approval
1) The final selection of specific MAR and monitoring intervals must be approved by the Department. In order to obtain an approval, the permittee shall submit a written request to the Department’s Tallahassee office.
2) All casing seat requests for the MAR and monitor wells shall be accompanied by technical justification.
3) Each casing seat request shall address the following items:
a) Lithologic and geophysical logs with interpretations, as the interpretations relate to the casing seat.
b) Water quality data (including but not necessarily limited to TDS concentrations).
c) Identification of confining units, including hydrogeologic data and interpretations.
d) Identification of monitor zones.
e) Casing depth evaluation (mechanically secure formation, potential for grout seal).
f) Lithologic drilling rate and weight on bit data, with interpretations (related to the casing seat).
g) Identification of the base of the USDW using water quality and geophysical log interpretations, if applicable.
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025
h) A certified (PE or PG) evaluation of all logging and test results submitted with test data.
i) Transmissivity or specific capacity of proposed monitor zone for new monitor well if required.
j) Packer test drawdown curves and interpretation.
4) If site geologic conditions warrants an additional monitor well (as specified in condition I.A.2 above), a well construction plan for the new well must be submitted by the engineer of record and approved by the Department prior to installation.
[62-528.410(4)(c), 62-528.420(4)(c), and 62-528.605(2), F.A.C.]
5. Weekly Progress Reports
a. Weekly progress reports shall be submitted to the APP Tallahassee and Southwest
District offices throughout the construction period for each well. These reports, which may be submitted via electronic mail, shall be submitted within 48 hours of the end of the period of record and shall include at a minimum the following information:
1) A cover letter summary of the daily engineer report, driller’s log, and a projection for activities in the next reporting period.
2) Daily engineer’s reports and driller’s/work logs with detailed descriptions of all drilling progress, cementing, testing, logging, and casing installation activities.
3) Description of daily footage drilled by diameter of bit, size of hole opener, or reamer being used.
4) Collection of drilling cuttings every 10 feet and at every formation change.
5) Description of work during installation and cementing of casing, including amounts of casing and cement used. Details of cementing operations shall include the number of cementing stages, and the following information for each stage of cementing: the volume and type of cement pumped, the theoretical fill depth, and the actual tag depth. From both the physical tag and the geophysical logs, a percent fill shall be calculated. An explanation of any deviation between actual versus theoretical fill shall be provided.
6) Details of the additions of salt or other materials to suppress well flow, including the date, depth, and amount of material used.
7) Description of testing accomplished including (but not limited to) pumping and packer tests.
8) Lithologic logs and core descriptions with cuttings description, formation and depth encountered.
9) Geophysical logs, video logs, and deviation survey results.
10) Water quality analyses, including but not limited to the weekly water quality analysis and water levels for the pad wells.
11) Well development records.
12) Description of any construction problems that developed during the reporting period and current status.
13) Interpretations included with all test results and logs submitted.
14) Documentation of disposal of drilling fluids, cuttings, formation water, and waste.
[62-528.410(9)(a), 62-528.430(1), 62-528.605(2), F.A.C.]
6. The short-term injection test request shall contain the following justifications:
a. Cement bond logs and interpretation.
b. Final downhole television survey with interpretation.
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025
c. Demonstration of mechanical integrity, which shall include radioactive tracer test results, pressure testing results, and temperature logging results (if the injection test is to be after any of these mechanical integrity tests).
d. Reasonable assurance that adequate confinement exists.
e. Planned injection testing procedures.
f. Proposed source water to be used. Per Rule 62-528.405(3)(b), F.A.C., if an adequate potable water supply for the injection test does not exist, and the data collected during drilling provide assurance of the presence of confining bed(s), the applicant shall, after demonstrating mechanical integrity pursuant to Rules 62-528.300(6)(b)2.
and (c), F.A.C., be allowed to use an alternate source for testing only with specific prior written authorization from the Department. An analysis of the alternate water source is required prior to Department approval, according to the table below:
Water Source Required Analyses Potable Water No analysis needed.
Domestic Wastewater A copy of the latest comprehensive analysis submitted to the Department’s domestic wastewater program.
Desalination Concentrate or Other Industrial Wastewater
A copy of the latest comprehensive analysis submitted to the Department’s industrial wastewater program. If more than one year old, sample the water for the parameters required for monthly monitoring of the wastewater in Specific Condition VI.
Groundwater Sample the water for:
· total dissolved solids (mg/L)
· chloride (mg/L)
· specific conductance (temperature compensated, µmhos/cm or mS/cm)
· total suspended solids (TSS) (mg/L)
· nitrogen, ammonia, total as N (mg/L)
· nitrogen, total Kjeldahl as N (TKN, mg/L)
· nitrogen, nitrate, total as N (mg/L)
· sodium (mg/L)
· potassium (mg/L)
· calcium (mg/L)
· magnesium (mg/L)
· total iron (mg/L)
· bicarbonate (mg/L)
· phosphorous, total as P (mg/L)
· pH (standard units, s.u.)
· sulfate, total as SO4 (mg/L)
· field temperature (°C)
· gross alpha (pCi/L)
· combined radium-226 and radium-228 (pCi/L)
Surface Water As above for groundwater, with the additional constituents:
· total and fecal coliform (cfs/100mL)
· Escherichia coli (cfu/100mL)
· Enterococci (cfu/100mL)
· Turbidity [Nephelometric Turbidity Units (NTU)]
[62-528.405(3)(b), F.A.C.]
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025
7. Cores and Cuttings
a. Upon completion of analysis of cores and sample cuttings recovered during the construction of wells covered by this permit (when no longer needed by the well owner), the permittee shall contact the Geological Sample Acquisition & Management Section of the Florida Geological Survey (FGS) to arrange for the transfer of the cores and cuttings. [62-528.605(6), F.A.C.]
b. All cores and cuttings for FGS shall be shipped to the Florida Geological Survey, Geological Sample Acquisition & Management Section, 3915 Commonwealth Boulevard, Tallahassee, Florida 32399. All cores and samples shall clearly identify the site name, well name/number, depths of samples/cores, and the latitude/longitude location of the well(s) using the form attached to this permit. [62-528.605(6), F.A.C.]
K. Monitoring – See also Specific Conditions, Monitoring Requirements
1. Annual Sampling
a. A laboratory analysis of the injectant for the Primary and Secondary Drinking Water Standards shall be submitted annually. [62-528.605(3), F.A.C.]
2. Monthly Operating Report (MOR)
a. The permittee shall report monthly on the following [62-528.430(2)(b), F.A.C.]:
1) The physical, chemical, and other relevant characteristics of the injection fluids, including the required monitoring listed in Table 3. [62-528.425(1)(g)5., 62- 528.430(2)(b)a.,d., F.A.C.]
2) Daily readings of the pressure and flow for each well. [62-528.430(2)(b)b., F.A.C.]
3) Monthly average, maximum and minimum values for injection pressure, flow rate and volume, and annular pressure. [62-528.430(2)(b)c., F.A.C.]
4) The results of required monitoring listed in Table 3. [62-528.425(1)(g)5., 62- 528.430(2)(b)d., F.A.C.]
b. MAR Sampling Schedule
1) The injection system shall be monitored in accordance with Rules 62-528.425 and
62-528.430, F.A.C. The following injection well performance data and monitor zone data shall be recorded and reported in the Monthly Operation Report (MOR) as indicated below. Samples and measurements taken for the purpose of monitoring shall be representative of the monitored activity. [62- 528.307(2)(c),(d), 62-528.425, 62-528.430, and 62-528.450(3), F.A.C.]
a) Biweekly (B/W) samples (twice per month) shall be taken as close to 15 days apart as possible.
b) Monthly (M) samples and measurements shall be taken as close to 30 days apart as possible.
c) Quarterly (Q) samples and measurements shall be taken during the following quarters:
¨ January 1 – March 31 ¨ April 1 – June 30 ¨ July 1 – September 30 ¨ October 1 – December 31
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025
Samples and measurements collected during consecutive quarters shall be taken at least 30 days apart. A MOR including quarterly results shall be noted as such on the title page of the report
d) Annual (A) samples and measurements
i. The period for reports of annual samples and measurements shall be for the calendar year ending December 31.
ii. Annual samples and measurements taken in consecutive years shall be taken at least 6 months apart and as close to a year apart as possible. If a MOR includes annual results, it shall be noted as such on the title page of the report.
[62-528.307(1)(m) F.A.C.]
2) The permittee shall submit the results of all injection well and monitor well data required by this permit to the Department no later than the last day of the month immediately following the month of record. [62-528.307(2)(d)]
3) Technical malfunctions and emergencies that interfere with the sampling schedule can be explained in the comment section of the MOR. The explanation shall include what issues occurred, how long it will take to address the issues, and an estimated time when the samples and measurements will be completed and submitted.
c. Deadlines and Format
1) The permittee shall submit monthly to the Department the results of all AR well and monitor well data required by this permit no later than the last day of the month immediately following the month of record. The report shall include:
2) A cover page summarizing the current status of all monthly activities, including the certification and signature required by 62-528.340, F.A.C.
3) Operational and water quality data in a tabular format. The following identifying information must be included on each data sheet:
Facility Name Well Name UIC Permit Number WACS Facility ID WACS Testsite ID (on appropriate data sheet) as provided in Table 1 and Table 2 of this permit.
Laboratory pages and supporting documentation including DEP form FD 9000-24, Groundwater Sampling Log, for the purging of each monitor well.
4) A site-specific template for the MOR will be provided upon permit execution. The template ensures consistency and streamlines the review process. [62- 528.307(2), F.A.C.]
5) Addresses for submission of MOR Send the report, in portable document format (.pdf), to the following e-mail addresses:
Southwest District SWD_UIC@FloridaDEP.gov Tallahassee - APP Program TAL_UIC@FloridaDEP.gov
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025
Send paper copies of the report to:
Southwest District 13051 N. Telecom Parkway, Suite 101
Temple Terrace, Florida 33637-0926 Tallahassee - APP Program 2600 Blair Stone Road, MS 3530
Tallahassee, Florida 32399-2400 [62-528.307(2)(d), F.A.C.]
3. Additional Reporting
a. The permittee shall report the results, within three months after the completion of:
1) Periodic tests of mechanical integrity
2) Any other test of the injection well conducted by the permittee if required by the
Department
4. Monitoring Records
a. In accepting this permit, the permittee understands and agrees that all records, notes, monitoring data and other information relating to the construction or operation of this permitted source which are submitted to the APP Tallahassee office may be used by the Department as evidence in any enforcement case involving the permitted source arising under the Florida Statutes or Department rules, except where such use is proscribed by sections 403.111 and 403.73, F.S. Such evidence shall only be used to the extent it is consistent with the Florida Rules of Civil Procedure and appropriate evidentiary rules. [62-528.307(1)(i), F.A.C.]
b. During enforcement actions, the retention period for all records shall be extended automatically unless the Department determines that the records are no longer required.
c. The permittee shall hold at the facility or other location designated by this permit records of all monitoring information, including the following:
d. Calibration and maintenance records and all original strip chart recordings for continuous monitoring instrumentation, copies of all reports required by this permit, and records of all data used to complete the application for this permit, for a period of at least 3 years from the date of the sample, measurement, report, or application.
This period may be extended at any time. [62-528.307(1)(m), F.A.C.]
e. The permittee shall retain all records of all monitoring information concerning the nature and composition of injected fluid until five years after completion of any plugging and abandonment procedures specified under rule 62-528.435, F.A.C. The permittee shall deliver the records to the Department office that issued the permit at the conclusion of the retention period unless the permittee elects to continue retention of the records. [62-528.307(1)(t), F.A.C.]
f. Records of monitoring information shall include:
1) The date, exact place, and time of sampling or measurements.
2) The person responsible for performing the sampling or measurements.
3) The dates analyses were performed.
4) The person responsible for performing the analyses.
5) The analytical techniques or methods used.
6) The results of such analyses.
g. The permittee shall retain all records of all monitoring information concerning the nature and composition of injected fluid until five years after completion of any plugging and abandonment procedures specified under Rule 62-528.435, F.A.C. The permittee shall deliver the records to the Department office that issued the permit at
Lake Tarpon Chestnut Park Managed Aquifer Recharge System Date: September 29, 2025 the conclusion of the retention period unless the permittee elects to continue retention of the records. [62-528.307(1)(t), F.A.C.]
L. Department Standard Operation Procedures
1. All water quality samples required by this permit shall be collected in accordance with the appropriate Department Standard Operation Procedures (SOP), pursuant to Rule 62- 160.210, F.A.C., Approved Field Procedures.
2. A certified laboratory shall conduct the analytical work, as provided by Rule 62-160.300, F.A.C., Laboratory Certification.
3. Department approved test methods shall be utilized, unless otherwise stated in this permit.
4. All calibration procedures for field testing and laboratory equipment shall follow manufacturer’s instrumentation manuals and satisfy the requirements of the Department SOPs.
5. A listing of the SOPs pertaining to field and laboratory activities is available at the DEP website at: https://floridadep.gov/dear/quality-assurance/content/dep-sops. [62-4.246, 62-160, F.A.C.]
6. Analyses shall be conducted on unfiltered samples, unless filtered samples have been approved by the Department as being more representative of ground water…
This is the start of the file's text. The full file is on GovTribe.