L2 - Price Proposal.xlsx

XLSX spreadsheet 24 KB Posted

Attached to
MFE Fire and Safety Upgrade Federal contract opportunity
Solicitation number
697DCK-22-R-00483
Issued by
Department of Transportation Federal Aviation Administration Southwestern Region

About this file

This document contains a price proposal spreadsheet and related federal contract opportunity notice. The price proposal spreadsheet is for an HVAC upgrade project for the McAllen International Airport air traffic control tower in McAllen, Texas. It includes line items for general site conditions, structural work, roofing, electrical, plumbing, safety and security, and miscellaneous work, with allocated costs for materials, labor, equipment, and total costs.

The related federal contract opportunity is a solicitation notice from the Federal Aviation Administration for the required HVAC and fire safety upgrade project at the McAllen airport air traffic control tower. Interested offerors must register in the System for Award Management, attend an optional site visit on August 23rd, and submit proposals in response to the solicitation by the due date provided. The notice also includes details on asking questions and the agencies involved.

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HVAC

COST PROPOSALDATESHEET 1 OF 1
PROJECTBASIS FOR ESTIMATE
MFE Fire and Safety UpgradeSTANDARD DESIGN
LOCATIONDRAWING REF. NO.PROJECT DESIGN
McAllen, TXOTHER (SPECIFY)
PREPARING ORGANIZATIONSPEC. REF. NO.

CLASS OF WORK ESTIMATOR CHECKED BY

ITEMQUANTITYMATERIAL COST ($)LABOR COST ($)EQUIPMENT COST ($)TOTAL
UNITNO.PERPERPERITEM
MEAS.UNITSUNITTOTALUNITTOTALUNITTOTALCOST ($)
General / Site Conditions
Mobilization / Demobilization$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Site Cleanup$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Misc. Utility Relocations$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Site Supervision/PM$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Structural
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Roofing
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Lightning Protection
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Electrical
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Plumbing
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Safety & Security
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Miscellaneous
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00
SUBTOTAL$0.00$0.00$0.00$0.00
Overhead0%$0.00$0.00$0.00$0.00
Profit0%$0.00$0.00$0.00$0.00
Bond$0.00$0.00$0.00$0.00

TOTAL COSTS $0.00 $0.00 $0.00 $0.00

File details come from the government source that posted it. Updated .