Instructions
| Instructions for Prime Contractor: |
| 1 | In the Cost Summary Spreadsheet, enter the Prime offeror's name into cell A3. |
| 2 | Enter all prime employee names in Column A (starting at row 9) If necessary, insert additional rows--but ensure integrity of formulas. |
| 3 | Enter all prime labor categories in Column C (starting at row 9) If necessary, insert additional rows--but ensure integrity of formulas. In column C, the Offeror should insert the title of the labor category it will be utilizing. Please note, in evaluation, the Offeror's proposal will be compared to the Government Estimate in terms of hours and labor categories. Also, labor categories with more than one person providing service shall be listed multiple times for each person performing work. For example, if the offeror proposes four Senior Analysts, then the labor category Senior Analyst shall be listed four times along with their applicable rates and information. |
| 4 | In column D, use Orlando as the work location that the contractor will be working at in accordance with the T11. Note, the Location-Labor Cat Spreadsheet can be referenced to show how the T11 locality lines up with the SOW. |
| 5 | Only one worksheet shall be prepared for the entire period of performance (for each Prime and Subcontractor or JV Team Member) |
| 6 | The worksheets of the workbook should all be formatted for printing on letter-size paper, without requiring "adjustments." It may be formatted for either landscape or portrait. DO NOT FORMAT FOR LEGAL SIZE PAPER. |
| 7 | All cells shall be unprotected and unlocked, with formulae intact to show mathematical operations. |
| 8 | All dollar figures shall be carried out no further than two decimal places. |
| 9 | In column E, f identify for the specific labor category individual whether they are full-time on this acquisition or part-time. Enter "F" for full-time or "P" for part-time. |
| 10 | In column F, the Offeror shall insert a "K" if the worker will be performing at the Contractor's facility or a "G" if it will be performing in the Government Spaces. |
| 11 | Insert applicable indirect rates and apply accordingly. For example, if there are multiple fringe rates, insert separately and apply accordingly. |
| 12 | For each subcontractor, enter the subcontractor name, total hours, and total amount for each period of performance. |
| 13 | Please note if more subcontractors or JV Team Members are needed, the contractor may add additional rows to accommodate them, but ensure integrity of formulas. |
| 14 | The prime should insert the subcontractor handling charge, if any. |
| 15 | The prime should insert the fixed fee rate applied to its cost excluding subcontractor labor. |
| 16 | The prime should insert the fixed fee rate it is applying to the subcontractor and JV Team Member labor, if any. |
| 17 | Under Other Direct Costs, the prime contractor should separate by Travel, Material and NMCI as applicable. |
| 18 | Apply indirects to the Other Direct Costs if applicable and if in compliance with the RFP instructions. |
| 19 | On the Summary tab, break out all costs by CLIN. Ensure that the total costs of the CLINs match Section B and the total on the Cost Summary Spreadsheet. Add rows and columns as needed to match section B. All cell formulas are contractor inputs. |
| 20 | When submitting this file, the instructions may be deleted. |
Instructions for Subcontractors and JV Team Members:
tc={B4BF191E-6810-43A8-AF81-529A65191D2E}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
can the JV team members mirror these instructions or would they need to be different.
| 1 | Enter Prime offeror name into cell A3. |
| Replace Prime Contractor with Subcontractor or JV Team Member in A7, A8, A13, and A20. |
| 2 | Enter all subcontractor or JV Team Member employee names in Column A (starting at row 9) If necessary, insert additional rows--but ensure integrity of formulas. |
| 3 | Enter all subcontractor or JV Team Member labor categories in Column C (starting at row 9) If necessary, insert additional rows--but ensure integrity of formulas. In column C, the Offeror should insert the title of the labor category it will be utilizing. Please note, in evaluation, the Offeror's proposal will be compared to the Government Estimate in terms of hours and labor categories. Also, labor categories with more than one person providing service shall be listed multiple times for each person performing work. For example, if the offeror proposes four Senior Analysts, then the labor category Senior Analyst shall be listed four times along with their applicable rates and information. |
| 4 | In column D, use Orlando as the work location that the contractor will be working at in accordance with the T11. Note, the Location-Labor Cat Spreadsheet can be referenced to show how the T11 locality lines up with the SOW. |
| 5 | Only one worksheet shall be prepared for the entire period of performance (for each Prime and Subcontractor or JV Team Member) |
| 6 | The worksheets of the workbook should all be formatted for printing on letter-size paper, without requiring "adjustments." It may be formatted for either landscape or portrait. DO NOT FORMAT FOR LEGAL SIZE PAPER. |
| 7 | All cells shall be unprotected and unlocked, with formulae intact to show mathematical operations. |
| 8 | All dollar figures shall be carried out no further than two decimal places. |
| 9 | In column D, f identify for the specific labor category individual whether they are full-time on this acquisition or part-time. Enter "F" for full-time or "P" for part-time. |
| 10 | In column E, the Offeror shall insert a "K" if the worker will be performing at the Contractor's facility or a "G" if it will be performing in the Government Spaces. |
| 11 | Insert applicable indirect rates and apply accordingly. For example, if there are multiple fringe rates, insert separately and apply accordinly. |
| 12 | For subcontractor and JV Team Members cost summary sheets, delete Rows 22-35, 44-48. |
| 13 | For JV Team Members, Rows 28, 32 and 33 do not apply. |
Location-Labor Cat Spreadsheet
| ORLANDO, FL | | |
| Labor Category | Level | 2023 BLS SOC Code |
tc={1FBF90B3-5A49-4174-AA42-0C735CB461F6}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
MOCK up a tab for each location and then place the wage rate
| General and Operations Managers | Senior | 11-1021 |
| General and Operations Managers | Journeyman | 11-1021 |
Public Relations Specialist Journeyman 27-3031
Administrative Services Managers Journeyman 11-3012
Facilities Managers Journeyman 11-3013
| Training and Development Managers | Senior | 11-3131 |
| Training and Development Managers | Journeyman | 11-3131 |
| Logisticians | Senior | 13-1081 |
| Logisticians | Journeyman | 13-1081 |
| Project Management Specialists | Senior | 13-1082 |
| Project Management Specialists | Journeyman | 13-1082 |
Management Analysts Journeyman 13-1111
| Training and Development Specialists | Senior | 13-1151 |
| Training and Development Specialists | Journeyman | 13-1151 |
| Training and Development Specialists | Junior | 13-1151 |
| Financial Specialists, All Other | Senior | 13-2099 |
| Financial Specialists, All Other | Journeyman | 13-2099 |
| Financial Specialists, All Other | Junior | 13-2099 |
| Operations Research Analysts | Senior | 15-2031 |
| Operations Research Analysts | Journeyman | 15-2031 |
| Operations Research Analysts | Junior | 15-2031 |
| Drafter, All Others | SCA 30060 Drafter/CAD Operator II [Journeyman] | 17-3019 |
| Drafter, All Others | SCA 30060 Drafter/CAD Operator I [Junior] | 17-3019 |
| Psychologists, All Other | Senior | 19-3039 |
| Psychologists, All Other | Journeyman | 19-3039 |
| Psychologists, All Other | Junior | 19-3039 |
| Instructional Coordinators | Senior | 25-9031 |
| Instructional Coordinators | Journeyman | 25-9031 |
| Instructional Coordinators | Junior | 25-9031 |
| Technical Writer | II | 27-3042 |
| Technical Writer | I | 27-3042 |
Executive Secretaries and Executive Administrative Assistants Journeyman 43-6011
Legal Secretaries and Administrative Assistants Journeyman 43-6012
Secretaries and Administrative Assistants, Except Legal, Medical and Executive Journeyman 43-6014
| Computer Systems Analysts | Senior | 15-1211 |
| Computer Systems Analysts | Journeyman | 15-1211 |
| Computer Network Architects | Senior | 15-1241 |
| Computer Network Architects | Journeyman | 15-1241 |
| Computer Network Architects | Junior | 15-1241 |
| Data Scientists | Senior | 15-2051 |
| Data Scientists | Journeyman | 15-2051 |
| Data Scientists | Junior | 15-2051 |
| Software Developer | Senior | 15-1252 |
| Software Developer | Journeyman | 15-1252 |
| Software Developer | Junior | 15-1252 |
| Software Quality Assurance Analysts and Testers | Senior | 15-1253 |
| Software Quality Assurance Analysts and Testers | Journeyman | 15-1253 |
| Aerospace Engineers | Senior | 17-2011 |
| Aerospace Engineers | Journeyman | 17-2011 |
| Electronics Engineers | Senior | 17-2072 |
| Electronics Engineers | Journeyman | 17-2072 |
| Electronics Engineers | Junior | 17-2072 |
| Mechanical Engineers | Senior | 17-2141 |
| Mechanical Engineers | Journeyman | 17-2141 |
| Engineers, All Other | Senior | 17-2199 |
| Engineers, All Other | Journeyman | 17-2199 |
| Engineers, All Other | Junior | 17-2199 |
| Electrical and Electronic Engineering Technologists and Technicians | Senior | 17-3023 |
| Electrical and Electronic Engineering Technologists and Technicians | Journeyman | 17-3023 |
| Electrical and Electronic Engineering Technologists and Technicians | Junior | 17-3023 |
| Engineering Technologist & Technician, Except Drafters, All Other | Senior | 17-3029 |
| Engineering Technologist & Technician, Except Drafters, All Other | Journeyman | 17-3029 |
| Engineering Technologist & Technician, Except Drafters, All Other | Junior | 17-3029 |
| Industrial-Organizational Psychologists | Senior | 19-3032 |
| Industrial-Organizational Psychologists | Journeyman | 19-3032 |
| Industrial-Organizational Psychologists | Junior | 19-3032 |
Special Effects Artists and Animators Journeyman 27-1014
Cost Summary Spreadsheet
COST SUMMARY SPREADSHEET
| Prime Offeror Name: | | | | | | | | | | | | | | | | | | | | | | | | | |
| Subcontractor Name (if applicable): | | | | | | | | | | | | | | | | | | | | | | | | | |
| Solicitation Number # N6134025R0004 | | | | | | Year 1 | | | Year 2 | | | Year 3 | | | Year 4 | | | Year 5 | | | FAR 52.217-8 | | | Total for All Years | |
| Cost Elements | Government Labor Category | Proposed Labor Category | Location - Orlando | F/P | Site | Rate | Hours | Amount | Rate | Hours | Amount | Rate | Hours | Amount | Rate | Hours | Amount | Rate | Hours | Amount | Rate | Hours | Amount | Hours | Amount |
| Prime Contractor Labor Cost | | | | | | | | | | | | | | | | | | | | | | | | | |
| Prime Contractor Direct Labor | | | | | | | | | | | | | | | | | | | | | | | | | |
| Labor Category 1 | | | | | | | | 0 | | | 0 | | | 0 | | | 0 | | | 0 | | | 0 | 0 | 0 |
| Labor Category 2 | | | | | | | | 0 | | | 0 | | | 0 | | | 0 | | | 0 | | | 0 | 0 | 0 |
| Etc. | | | | | | | | 0 | | | 0 | | | 0 | | | 0 | | | 0 | | | 0 | 0 | 0 |
| Total Direct Labor Cost | | | | | | | | 0 | | | 0 | | | 0 | | | 0 | | | 0 | | | 0 | 0 | 0 |
| Prime Contractor Indirect Labor Cost | | | | | | | | | | | | | | | | | | | | | | | | | |
| Overhead | | | | | | | | | | | | | | | | | | | | | | | | | |
| Fringe Benefits | | | | | | | | | | | | | | | | | | | | | | | | | |
| G&A | | | | | | | | | | | | | | | | | | | | | | | | | |
| Total Indirect Labor Cost | | | | | | | | | | | | | | | | | | | | | | | | | |
| Total Direct and Indirect Labor cost | | | | | | | | 0 | | | 0 | | | 0 | | | 0 | | | 0 | | | 0 | | 0 |
| COM (if applicable) | | | | | | | | | | | | | | | | | | | | | | | | | |
| Total Prime Contractor Labor Cost | | | | | | | | 0 | | | 0 | | | 0 | | | 0 | | | 0 | | | 0 | | 0 |
| Subcontractor or JV Team Member Labor Cost | | | | | | | |
| Subcontractor or JV Team Member proposed cost and fee | | | | | | | |
| Subcontractor or JV Team Member 1 | | | | | | | |
| Subcontractor 2 or JV Team Member 2 | | | | | | | |
| Etc. | | | | | | | |
| Total proposed subcontractor or JV Team Member labor cost and fee | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Prime contractor pass through (not including fee) | | | | | | | |
| Handling | | | | | | | |
| G&A | | | | | | | |
| Other (if any) | | | | | | | |
| Total pass through (not including fee) | | | | | | | |
| Total Subcontractor Cost including pass through | | | | | | | 0 |
Total Labor Cost (Prime and Subcontractor or JV Team Member Labor)
| Fixed Fee |
| Prime Contractor Fee for Prime Contractor Labor |
| Prime Contractor Fee for Subcontractor or JV Team Member Labor * |
| Total Fee (for Prime and Subcontractor or JV Team Member Labor) |
Total Labor Cost Plus Fixed Fee (CPFF) 0
| Increased Capacity for Labor |
| Subtotal Labor Increased Capacity |
| Subtotal Profit/Fee Increased Capacity |
| Total Labor Increased Capacity |
| Grand Subtotal Labor Cost |
| Grand Subtotal Labor Profit/Fee |
| Grand Total Labor |
| Other Direct Costs - Travel |
| Other Direct Costs (ODCs) - Travel |
| Any adders to ODCs such as G&A (cost only - no fee) |
| Sub total of ODCs |
| Increased Capacity for ODCs |
| Base for Increased Capacity ODCs |
| Total Increased Capacity for ODCs |
| Grand Total ODCs |
Total CPFF all CLINs (Labor and ODCs) $ - 0
Grand Total of CPFF all CLINs
| Pass Through Analysis - Total for All Years | Amount | Percent |
| Subcontractor proposed cost and fee | $0 | |
| Pass Through Amount (not including fee) | $0 | |
| Prime Contractor Fee for Subcontractor Labor * | $0 | |
| Total Pass Through Amount (including fee) | $0 | ERROR:#DIV/0! |
| Fee Analysis - Total for All Years | Amount | Percent |
| Prime Contractor Labor Cost | $0 | |
| Fixed Fee for Labor Performed by Prime Contractor | $0 | ERROR:#DIV/0! |
| *In Section B, the prime offeror fee on subcontractor price is a fee element rather than a cost element. Prime offeror fee on subcontractor price should be included in the fee column (rather than the cost column) of Section B. | | |
Page &P &F
KTR: (name) Source Selection Information - See: FAR 2.101 and 3.104 RFP:
Fully Burdened Labor Rates
| Composite Fully Burdened Rates (Exclusive of fee and regardless of provided by prime, sub or JV entity) | | | |
| May 2023 BLS / OMB / SOC / NAVAIR Title | Level | 2023 SOC Code | Base (FY26) |
1 Nov 2025 - 31 Oct 2026 Year 2 (FY27) 1 Nov 2026 - 31 Oct 2027 Year 3 (FY28) 1 Nov 2027 - 31 Oct 2028 Year 4 (FY29) 1 Nov 2028 - 31 Oct 2029 Year 5 (FY30) 1 Nov 2029 - 31 Oct 2030 Option 1 (FY31) 1 Nov 2030 - 30 Apr 2031
| General and Operations Managers | Senior | 11-1021 |
| General and Operations Managers | Journeyman | 11-1021 |
Public Relations Specialist Journeyman 27-3031
Administrative Services Managers Journeyman 11-3012
Facilities Managers Journeyman 11-3013
| Training and Development Managers | Senior | 11-3131 |
| Training and Development Managers | Journeyman | 11-3131 |
| Logisticians | Senior | 13-1081 |
| Logisticians | Journeyman | 13-1081 |
| Project Management Specialists | Senior | 13-1082 |
| Project Management Specialists | Journeyman | 13-1082 |
Management Analysts Journeyman 13-1111
| Training and Development Specialists | Senior | 13-1151 |
| Training and Development Specialists | Journeyman | 13-1151 |
| Training and Development Specialists | Junior | 13-1151 |
| Financial Specialists, All Other | Senior | 13-2099 |
| Financial Specialists, All Other | Journeyman | 13-2099 |
| Financial Specialists, All Other | Junior | 13-2099 |
| Operations Research Analysts | Senior | 15-2031 |
| Operations Research Analysts | Journeyman | 15-2031 |
| Operations Research Analysts | Junior | 15-2031 |
| Drafter, All Others | SCA 30060 Drafter/CAD Operator II [Journeyman] | 17-3019 |
| Drafter, All Others | SCA 30060 Drafter/CAD Operator I [Junior] | 17-3019 |
| Psychologists, All Other | Senior | 19-3039 |
| Psychologists, All Other | Journeyman | 19-3039 |
| Psychologists, All Other | Junior | 19-3039 |
| Instructional Coordinators | Senior | 25-9031 |
| Instructional Coordinators | Journeyman | 25-9031 |
| Instructional Coordinators | Junior | 25-9031 |
| Technical Writer | II | 27-3042 |
| Technical Writer | I | 27-3042 |
Executive Secretaries and Executive Administrative Assistants Journeyman 43-6011
Legal Secretaries and Administrative Assistants Journeyman 43-6012
Secretaries and Administrative Assistants, Except Legal, Medical and Executive Journeyman 43-6014
| Computer Systems Analysts | Senior | 15-1211 |
| Computer Systems Analysts | Journeyman | 15-1211 |
| Computer Network Architects | Senior | 15-1241 |
| Computer Network Architects | Journeyman | 15-1241 |
| Computer Network Architects | Junior | 15-1241 |
| Data Scientists | Senior | 15-2051 |
| Data Scientists | Journeyman | 15-2051 |
| Data Scientists | Junior | 15-2051 |
| Software Developer | Senior | 15-1252 |
| Software Developer | Journeyman | 15-1252 |
| Software Developer | Junior | 15-1252 |
| Software Quality Assurance Analysts and Testers | Senior | 15-1253 |
| Software Quality Assurance Analysts and Testers | Journeyman | 15-1253 |
| Aerospace Engineers | Senior | 17-2011 |
| Aerospace Engineers | Journeyman | 17-2011 |
| Electronics Engineers | Senior | 17-2072 |
| Electronics Engineers | Journeyman | 17-2072 |
| Electronics Engineers | Junior | 17-2072 |
| Mechanical Engineers | Senior | 17-2141 |
| Mechanical Engineers | Journeyman | 17-2141 |
| Engineers, All Other | Senior | 17-2199 |
| Engineers, All Other | Journeyman | 17-2199 |
| Engineers, All Other | Junior | 17-2199 |
| Electrical and Electronic Engineering Technologists and Technicians | Senior | 17-3023 |
| Electrical and Electronic Engineering Technologists and Technicians | Journeyman | 17-3023 |
| Electrical and Electronic Engineering Technologists and Technicians | Junior | 17-3023 |
| Engineering Technologist & Technician, Except Drafters, All Other | Senior | 17-3029 |
| Engineering Technologist & Technician, Except Drafters, All Other | Journeyman | 17-3029 |
| Engineering Technologist & Technician, Except Drafters, All Other | Junior | 17-3029 |
| Industrial-Organizational Psychologists | Senior | 19-3032 |
| Industrial-Organizational Psychologists | Journeyman | 19-3032 |
| Industrial-Organizational Psychologists | Junior | 19-3032 |
Special Effects Artists and Animators Journeyman 27-1014
CLIN Summary
| Base Year | Description | Total Hours | Total Cost | Total Profit/Fixed Fee | Total Value $ |
| CLIN 0001 | Mobilization | | | | |
| CLIN 0002 | Labor | 418564 | | | |
| CLIN 0003 | Travel | | | | |
| CLIN 0004 | Technical Data | | | | |
| CLIN 1002 | Labor | 418564 | | | |
| CLIN 1003 | Travel | | | | |
| CLIN 1004 | Technical Data | | | | |
| CLIN 2002 | Labor | 421952 | | | |
| CLIN 2003 | Travel | | | | |
| CLIN 2004 | Technical Data | | | | |
| CLIN 3002 | Labor | 416120 | | | |
| CLIN 3003 | Travel | | | | |
| CLIN 3004 | Technical Data | | | | |
| CLIN 4002 | Labor | 407957 | | | |
| CLIN 4003 | Travel | | | | |
| CLIN 4004 | Technical Data | | | | |
Total 2083157
Option Year Summary Sheet
| Option Year (FAR 52.217-8) | Option Year Description | Total Hours | Total Cost | Total Fixed Fee | Total Value $ |
| CLIN 8010 | Labor | 204938 | | | |
| CLIN 8011 | Travel | | | | |
| CLIN 8012 | Technical Data | | | | |
| Option Total | 204938 | |