Attachment 6 ‐ SPECIAL INSTRUCTIONS
CONSTRUCTION STATUS (as of Dec 2021)
(This list is NOT all‐inclusive)
Interior Paint:
‐ Contractor shall perform misc. patchwork.
‐ Contractor shall complete the interior penetrations/exterior (to include misc. holes throughout interior of facility).
‐ Contractor shall complete misc. touch up paint throughout entire interior (to include doors).
Floor Epoxy:
‐ Contractor shall complete everything except demolition.
‐ Contractor shall complete floor repairs and actual installation of epoxy floor.
Exterior Paint and Repairs:
‐ Contractor shall readdress sealant in various locations. (Previous contractor installed It poorly/improperly).
‐ Contractor shall remove paint from door hinges.
‐ Sealant color used on exterior doors is incorrect. Contractor shall reinstall sealant using the correct color.
‐ Contractor shall repair exterior windows. (Previous contractors grinded various areas while removing old sealant and did not repair the paint they took off to the window frames).
‐ Contractor shall seal hose bib.
‐ Contractor shall repair/replace soffit.
VCT Flooring:
‐ Contractor shall install VCT flooring.
Resilient Wall Base:
‐ Contractor shall install resilient wall base.
Suspended Ceiling:
‐ Contractor shall install ceiling tiles.
‐ Contractor shall complete misc. ceiling grid work.
Electrical Upgrades:
‐ Contractor shall install new lights.
‐ Contractor shall install switches and OS (Occupancy Sensor)
‐ Contractor shall install Exit sign.
Crane:
‐ Contractor shall order and install crane and all electrical components.
‐ Contractor shall correct the depth of the footers.
Attachment 6 ‐ SPECIAL INSTRUCTIONS
‐ Contractor shall complete all remaining work related to the crane.
Bay Door Enlargement and Overhead Door:
‐ Contractor shall complete demolition of the opening.
‐ Contractor shall check the temporary structural bracing for the opening. The bracing does not work properly and poses a HUGE safety risk and a severe structural issue. Existing block and grout are also showing signs of failing. Contract shall repair block and grout and the contractor shall verify that it is properly bracing the structure.
‐ Contractor shall fix the temporary wall. Contractor shall ensure site is properly secured.
‐ Contractor shall install bay door and shall verify the status of the bay door order.
HVAC Modification:
‐ Contractor shall clean the duct.
‐ Contractor shall cover the duct opening until remaining duct is installed. (The duct is partially done and birds have been seen flying in and out).
‐ Contractor shall verify no animals/varmint have entered duct prior to continuing work.
‐ Contractor shall clean any animals, debris and dirt that has accumulated inside the duct.
‐ Contractor shall insulate the duct.
‐ Contractor shall install diffusers.
‐ Contractor shall complete the duct installation.
‐ Contractor shall install exhaust fan.
‐ Contractor shall complete HVAC testing, adjusting, and balancing (TAB).
Notable Mentions:
‐ Contractor shall submit remaining material submittals.