Addendum 6 for KEYS Bid 12-25 is a document issued by Keys Energy Services (KEYS), a municipal electric utility in Key West, Florida, modifying the bid specifications for the purchase of a power transformer. The addendum extends the bid opening to Friday, June 6, 2025, at 10:00 AM, with electronic bid submissions to be made via a GoToMeeting link. The project involves procuring a power transformer for the Big Coppitt Substation, with a detailed project schedule spanning from project advertisement on March 21, 2025, to final project close-out on May 24, 2027. Key milestones include the contract award by the Utility Board on July 16, 2025, notice to proceed on July 28, 2025, transformer removal and new pad construction in January 2027, and delivery and field testing by April 30, 2027.
The addendum provides a comprehensive tentative schedule outlining responsibilities for both KEYS and the contractor, including quality control plan submission, transformer delivery, assembly, field testing, and project acceptance. While specific pricing details are not included in this document, the project involves significant infrastructure investment with multiple stages of implementation. The bid process allows for electronic submission and virtual bid opening, reflecting a modern procurement approach. The project timeline suggests a complex, multi-phase transformer replacement process with clear delineation of tasks and responsibilities between KEYS and the selected contractor.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KEYS BID 12-25 SPECIFICATIONS FOR PURCHASE OF POWER TRANSFORMER
Addendum 6
The bid opening is hereby extended to Friday, June 6, 2025, at 10:00 AM. It shall be the sole responsibility of each bidder to have their bid electronically delivered on or before the time for opening proposals last announced to bidders.
KEYS Bid Opening Jun 6, 2025, 10:00 – 10:30 AM (America/New_York) Please join my meeting from your computer, tablet or smartphone.
https://meet.goto.com/171619581 You can also dial in using your phone.
Access Code:
171-619-581 United States:
+1 (571) 317-3112 Get the app now and be ready when your first meeting starts:
https://meet.goto.com/install
In the event of any conflict between the terms of this Addendum and the original bid and previous Addendums, the terms of this Addendum shall control.
The tentative schedule is listed below.
KEYS Transformer Tentative Schedule
Task By Description Start Date Completion Date
1 KEYS Project Advertised 3/21/2025 06/06/2025 2 KEYS Question Period 3/21/2025 04/18/2025 3 KEYS Bid Opening 06/06/2025 4 KEYS Contract Award by Utility Board 7/16/2025
5 KEYS Notice To Proceed 07/28/2025
6 CONTRACTOR Quality Control Plan/IFC Drawings 07/17/2025
NLT 11/24/2026
KEYS
Remove/Dispose of Existing
Transformer and Construct New Pad 01/04/2027 01/29/2027
8 CONTRACTOR Delivery Assembly/Field Testing
02/01/2027 NLT 04/30/2027
9 KEYS Project Acceptance and Sign‐Off 05/03/2027 10 CONTRACTOR Final Payment and Project Close‐Out 05/24/2027 https://meet.goto.com/171619581 tel:+15713173112,,171619581 https://meet.goto.com/install