The document provided is a Project Summary from the Statewide Transportation Improvement Program (STIP) for the state of Oregon. It outlines a contract opportunity for the painting of the bridge approach ramps on the west end of the Fremont Bridge in Portland. The project is being administered by the Oregon Department of Transportation (ODOT) and has a total current estimate of $11,759,000. The work consists of painting the steel members of the bridge ramps and is scheduled to take place in the 2021-2024 STIP period. The project is federally funded, with $10,551,350.70 in federal funds and $1,207,649.30 in state funds, and is located in Multnomah County and the city of Portland.
The document provides details on the project's funding sources, work types, and timeline. The project is being advanced from the 2024-2027 STIP period to the 2021-2024 STIP period. The construction phase is currently estimated at $11,632,000, with an additional $127,000 budgeted for right-of-way acquisition. The project utilizes National Highway Performance Program (NHPP) funds, with a federal share of 89.73% and a state share of 10.27%.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 35663_Attachment C_SSOW.docx | DOCX document | |
| 35663 Addendum_2.docx | DOCX document | |
| ATT A_Cover Sheet.doc | DOC document | |
| Project Description and Phasing~1.docx | DOCX document | |
| Master List Terms.docx | DOCX document | |
| 35663 Addendum_1.docx | DOCX document | |
| Question 1.docx | DOCX document | |
| ATT B_Project Samples.doc | DOC document | |
| C2023226_GraphicsServices_RFP~2.pdf | ||
| 35663_ITA_Final.docx | DOCX document | |
| Section_B_List.docx | DOCX document | |
| 35663_Final.docx | DOCX document | |
| Freemont Bridge Painting AE Design Statement of Work.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statewide Transportation Improvement Program Generated on: 4/27/2023 4:21:31 PM Project Summary Page 1 of 3
Key Number: 22603 2021-2024 STIP Project Name: I-405 Fremont bridge (Willamette River) West ramps (Active STIP)
Project Overview
Total Current Estimate $11,759,000.00 Description Paint bridge approach ramps, steel members only, on the west end of the Fremont Bridge in Portland.
Responsible Region 1 Related Programs
Project Status Date 8/8/2022 STIP Name 2021-2024 STIP Project Status APPROVED Administrator ODOT
Monitor ROWACQ Applicant ODOT Bid Let Date MPO Portland Metro MPO Target Date Constructor CONTRACTOR PAYMENTS
Award Date Functional Class NO FUNCTIONAL CLASSIFICATION, URBAN INTERSTATE, URBAN PRINCIPAL
ARTERIAL-OTHER FWY/EXP
Air Quality Approval Req. Work Class STRUCTURES
Air Quality Approval Date. IGA #
Contract #
Created On 5/12/2022 Created By ADRIANA ANTELO Last Updated On 11/28/2022 Last Updated By COLLEEN HUNTER
Comment $10,551,350.70 in federal funds
Locations
Route Highway MP Begin
MP
End Length Street City County ACT Bridge Reg
State Repr Dist
State Sen Dist
US
Cngr Dist
RMP W TO
2W WB PORTLAND MULTNOMA
H R1ACT 09268W 1 33 17 1
092 LOWER
COLUMBIA RIVER
CONN TO
HWY 61 NB PORTLAND MULTNOMA
H R1ACT 09268E 1 33 17 1
I-405 061 STADIUM
FREEWAY 2.84 2.84 0.00 PORTLAND MULTNOMA
H R1ACT 09268S 1 33 17 1
I-405 061 STADIUM
FREEWAY 2.84 2.84 0.00 PORTLAND MULTNOMA
H R1ACT 09268N 1 33 17 1
I-405 061 STADIUM
FREEWAY 3.10 3.10 0.00 PORTLAND MULTNOMA
H R1ACT 09268 1 33 17 1
US-30 092 LOWER
COLUMBIA RIVER 1.26 1.26 0.00 PORTLAND MULTNOMA
H R1ACT 09268A 1 33 17 1
US-30 092 LOWER
COLUMBIA RIVER 1.24 1.24 0.00 PORTLAND MULTNOMA
H R1ACT 09268B 1 33 17 1
Phases
Ph Phase Total Est. Cost
Original Auth Amount
Original Auth Date
Current Auth Amount
Current Auth Date
Current STIP Amount
Curr
STIP
Year
Initial STIP Amount
Init
STIP
Year
EA Fed Aid ID Status
PE 11,632,000.00 11,632,000.00 11/22/22 11,632,000.00 11/22/22 11,632,000.00 2023 11,632,000.00 2023 PE003432 S061(014) APPROVED
RW 127,000.00 0.00 0.00 127,000.00 2024 127,000.00 2024 APPROVED
Tot 11,759,000.00 11,632,000.00 11,632,000.00 11,759,000.00 11,759,000.00
STIPFP_Project_Summary_Report_2017.06.2.v1.1
Project Summary Page 2 of 3
Key Number: 22603 2021-2024 STIP Project Name: I-405 Fremont bridge (Willamette River) West ramps (Active STIP)
Work Types
Phase Work Type Percent of Phase
Work Type Amount Opt Code Option Desc
PE
BRIDGE 100.00% 11,632,000.00 S STATE PROJECT
PE Totals 100.00% 11,632,000.00
RW
BRIDGE 100.00% 127,000.00 S STATE PROJECT
RW Totals 100.00% 127,000.00 Grand Totals 11,759,000.00
Financial Plan -- Estimate / Actual Amounts
Phase Funding Resp STIP Year Use Hist Savings Total Est/Act Amt Fed Est/Act
Amt State Est/Act
Amt Local Est/Act
Amt Comment
PE
FIX-IT SW
BRIDGE
2021-2024
STIP 2023 11,632,000.00 10,437,393.60 1,194,606.40 0.00
11/22/2022: Initial obligation per FMIS 8/8/2022: Add new project advanced from 24- 27 per 21-24-2100
PE Totals 11,632,000.00 10,437,393.60 1,194,606.40 0.00
RW
FIX-IT SW
BRIDGE
2021-2024
STIP 2024 127,000.00 113,957.10 13,042.90 0.00
Add new project advanced from 24-27 per 21-24-2100
RW Totals 127,000.00 113,957.10 13,042.90 0.00
Grand Totals 11,759,000.00 10,551,350.70 1,207,649.30 0.00
Financial Plan -- Target Amounts
Phase Funding Resp STIP Year Use Hist Savings Total Trgt Amt Fed Trgt Amt State Trgt Amt Local Trgt Amt Comment
PE FIX-IT SW BRIDGE 2021-2024
STIP
2023 0.00 0.00 0.00 0.00 11/22/2022: Initial obligation per FMIS 8/8/2022: Add new project advanced from 24-27 per 21- 24-2100
PE Totals 0.00 0.00 0.00 0.00
RW FIX-IT SW BRIDGE 2021-2024
STIP
2024 0.00 0.00 0.00 0.00 Add new project advanced from 24- 27 per 21-24-2100
RW Totals 0.00 0.00 0.00 0.00 Grand Totals 0.00 0.00 0.00 0.00
Project Summary Page 3 of 3
Key Number: 22603 2021-2024 STIP Project Name: I-405 Fremont bridge (Willamette River) West ramps (Active STIP)
Fund Codes Phase Fund
Code Description ICA P
Percent of Phase Total Amount Federal
Percent Federal Amount State Percent State Amount Local
Percent Local Amount
PE
Y001 National Highway Perf
IIJA Y 100.00% 11,632,000.00 89.73% 10,437,393.60 10.27% 1,194,606.40 0.00% 0.00
PE Totals 100.00% 11,632,000.00 10,437,393.60 1,194,606.40 0.00
RW
Z001 NATIONAL HIGHWAY
PERF FAST 100.00% 127,000.00 89.73% 113,957.10 10.27% 13,042.90 0.00% 0.00
RW Totals 100.00% 127,000.00 113,957.10 13,042.90 0.00 Grand Totals 11,759,000.00 10,551,350.70 1,207,649.30 0.00
Amendments Status Date Amendment Num. Status Project Change Type S/C Key
Number Change Reason
8/8/22 21-24-2100 APPROVED ADD PROJECT 22603 Add new project.
Selection Criteria: STIP 2021-2024 STIP Key Number 22603 Project ID 45763