Freemont Bridge Painting AE Design Statement of Work.docx

DOCX document 459 KB Posted

Attached to
I-405: Fremont Bridge (Willamette River) West Ramps painting project
Solicitation number
S-73000-00007575
Issued by
Multnomah County, Oregon

About this file

This document is a Statement of Work (SOW) for an architectural and engineering (A&E) design contract related to the I-405: Fremont Bridge (Willamette River) West Ramps painting project. The project is located in Multnomah County and the City of Portland, Oregon. The SOW details the scope of services to be provided by the consultant, including project management, meetings, risk management, value engineering, environmental services, public involvement, utilities coordination, bridge and structures design, traffic engineering, right-of-way services, and quality assurance/quality control. Key deliverables include progress reports, schedules, design packages, review meetings, and risk management plans. The contract term is not specified.

The SOW does not provide specific pricing terms, set-asides, or funding sources. However, it notes that the project is likely over $25 million in value, which may trigger certain requirements such as a cost risk assessment and value engineering study. The document also references the use of ProjectWise for document management and coordination with the agency.

View the file

Other files

File Type Posted
35663_Attachment C_SSOW.docx DOCX document
35663 Addendum_2.docx DOCX document
ATT A_Cover Sheet.doc DOC document
Project Description and Phasing~1.docx DOCX document
Master List Terms.docx DOCX document
35663 Addendum_1.docx DOCX document
Question 1.docx DOCX document
ATT B_Project Samples.doc DOC document
C2023226_GraphicsServices_RFP~2.pdf PDF
35663_ITA_Final.docx DOCX document
K22603 Project Summary.pdf PDF
Section_B_List.docx DOCX document
35663_Final.docx DOCX document
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A&E Statement of Work - I-405 Fremont Bridge (Willamette River) West Ramps

Contents

Task 1 – Project Management [11010]12
Task 1.1 – Project Management and Coordination [11020]12
Task 1.2 – Progress Reports and Invoices [11030]13
Task 1.3 – Project Schedule and Schedule Updates [11040]13
Task 1.4 – Meetings [11050]14
Task 1.4.1 – Kick-off Meeting [11060]15
Task 1.4.2 – Project Development Team (“PDT”) Meetings [11070]15
Task 1.4.3 – Project Coordination Meetings [11080]16
Task 1.4.4 – Project Subteam Meetings [11090]16
Task 1.4.5 – Project Site Visit Meetings [11100]18
Task 1.4.6A – Mobility Advisory Committee Meetings ("MAC”) [11110] [RESERVED]18
Task 1.4.6B – Mobility Advisory Committee Meetings (“MAC”) [11110]18
Task 1.4.7 – Design Verification Workshop (“DVW”) [11120]19
Task 1.4.8 – Cost Risk Assessment (“CRA”) [11130]20
Task 1.4.9 – Design Acceptance Workshop (“DAW”) [11180]23
Task 1.4.10 – Preliminary Plans Review Meeting [11190]24
Task 1.4.11 – Advance Plans Review Meeting [11200]25
Task 1.4.12 – Final Plans Review Meeting [11210]25
Task 1.4.13 – Pre-PS&E Package Submittal Meeting [11220]26
Task 1.4.14 –PS&E Review Meetings [11230]27
Task 1.5 – Construction Support [11250]28
Task 1.6 – Risk Management [11260]28
Task 1.6.1 – Risk Management Plan [11270]29
Task 1.6.2 – Monitoring and Controlling Project Risks [11280]29
Task 1.7 – VE Study [11290]31
Task 1.7.1 – Pre-VE Workshop [11300]32
Task 1.7.2 – VE Workshop [11310]33
Task 1.7.3 – VE Report [11320]33
Task 1.7.4 – VE Implementation Meeting [11330]34
Task 1.7.5 – VE Study Findings Analysis [11340]34
Task 1.7.6 – Additional SME(s) for VE workshop [11350] [Contingency Task]35
Task 1.8 – Construction Risk Management Transition [11360]35
Task 1.9 – Quality Assurance/Quality Control [11370]36
Task 1.9.1 – Quality Assurance [RESERVED]36
Task 1.9.2 – QA/QC Quality Reviews [11390]36
Task 2 – Project Initiation [12010]37
Task 2.1 – Consultant SOW Development and Review [RESERVED]38
Task 2.2 – Intergovernmental Agreements [RESERVED]38
Task 2.3 – Project Charter [RESERVED]38
Task 2.4 – Draft Change Management Request (Zero-CMR) [RESERVED]38
Task 2.5 – Project Initiation Package [12060] RESERVED]38
Task 2.6 – Project Initiation Quality Reviews [12070] RESERVED]38
Task 2.7 – Project Initiation Region Phase Gate [RESERVED]38
Task 2.8 – Phase Gate Quality Assurance [RESERVED]38
Task 3 – Planning Services [13010] [RESERVED]38
Task 4 – Scoping [14010] RESERVED]38
Task 4.1 – Scoping [14020] RESERVED]38
Task 4.1.1 – Scoping Team Coordination [14030] RESERVED]38
Task 4.1.2 – Scoping Packet [14040] RESERVED]38
Task 4.1.3 – Project Scoping [14050] RESERVED]38
Task 4.1.4 – Project Re-scoping [14080] RESERVED]38
Task 4.2 – Project Selection [RESERVED]38
Task 4.3 – STIP Adoption [RESERVED]38
Task 4.4 – Scoping Quality Reviews [14130] RESERVED]38
Task 5 – Survey [15010] [Contingency Task]38
Task 5.1 – Project Control [15020] [Contingency Task]39
Task 5.2 – Control, Recovery, and Retracement (“CRR”) [15030] [Contingency Task]40
Task 5.2.1– Survey Filing Map (“SFM”) [15040] [Contingency Task]41
Task 5.3 – Topographic Data and Basemap [15050] [Contingency Task]42
Task 5.3.1 – Survey Project Initiation [15060] [Contingency Task]43
Task 5.4 – [RESERVED]43
Task 5.5 – Monumentation Surveys [15080] [Contingency Task]43
Task 5.6 – Right of Way (“ROW”) Engineering (Mapping and Descriptions) [15090] [Contingency Task]44
Task 5.6.1 – Proposed ROW Design and Layout [15100] [Contingency Task]44
Task 5.6.2 – Active ROW Acquisition Map [15110] [Contingency Task]44
Task 5.6.3 – ROW Addendum, Descriptions, and Sketch Maps [15120] [Contingency Task]45
Task 5.6.4 – ROW Descriptions Revisions due to Project Scope Changes [15125][RESERVED]46
Task 5.6.5 – Railroad Exhibit Maps [15130] [Contingency Task]46
Task 5.6.6 – Forest Service Plat Maps [15140] [RESERVED]47
Task 5.6.7 – Bureau of Land Management (“BLM”) Plat Maps [15150] [RESERVED]47
Task 5.7 – Staking [15160] [Contingency Task]47
Task 5.8 – Pre-Construction Survey [15170] [Contingency Task]47
Task 5.9 – Survey Design Coordination [15180]47
Task 5.10 – Survey Quality Reviews [15190]48
Task 6 – Environmental Services [15310]48
Task 6.1 – Pre-National Environmental Policy Act (“NEPA”) and Planning and Environment Linkages (“PEL”) Activities [15320] ] [RESERVED]48
Task 6.2 – NEPA - Categorical Exclusion (“CE”) or Programmatic CE (“PCE”) Documentation [15360] ] [RESERVED]48
Task 6.5 – Land Use (includes Coastal Zone, Farmland, and Wild and Scenic Rivers) [15730] [RESERVED]48
Task 6.6 – Environmental Justice (“EJ”) [15800] [RESERVED]49
Task 6.7 – Socioeconomic Analysis [15850] [RESERVED]49
Task 6.8 – Parks and Recreation Resources [15890] [RESERVED]49
Task 6.9 – Historic Resources [16100] [RESERVED]49
Task 6.10 – Cultural Resources – Archaeology [16210] [RESERVED]49
Task 6.11 – Visual/Aesthetics [16440] [RESERVED]49
Task 6.12 – Wetlands and Waters Delineation, and Permitting Services [16510] [RESERVED]49
Task 6.13 – Biological Services [16680] [RESERVED]49
Task 6.14 – Air Quality [16920]49
Task 6.14.1 – Air Quality Assessments for Categorical Exclusion Project [16930]49
Task 6.14.2 – Air Quality for Environmental Impact Statements (“EIS’s”) or Environmental Assessments (“EA’s”) [17050] [RESERVED]62
Task 6.14.3 – Energy Analysis [17210] [RESERVED]63
Task 6.14.4 – Air Quality Coordination [17230]63
Task 6.14.5 – Air-Quality Quality Reviews [17240]64
Task 6.15 – Noise Studies and Variances [17250] [RESERVED]65
Task 6.15.1 – Screening Analysis for Traffic Noise Impacts [17260] [RESERVED]65
Task 6.15.2 – Field Investigation and Data Gathering for NTR [17270] [RESERVED]65
Task 6.15.3 – Noise Model Verification: Compare Measured-to-Predicted (Modeled) Noise Values [17280] [RESERVED]65
Task 6.15.4 – Traffic Noise Impact Analysis and Mitigation Consideration [17290] [RESERVED]65
Task 6.15.5 – Noise Technical Report (“NTR”) [17300] [RESERVED]65
Task 6.15.6 – Final Noise Wall Height and Location Analysis [17350] [RESERVED]66
Task 6.15.7 – Noise Variances [17360]66
Task 6.15.8 – Noise Studies and Variances Coordination [17420]71
Task 6.15.9 – Noise Studies and Variances Quality Reviews [17430]71
Task 7 – Public Involvement – Public Information – Public Engagement [18510] [Contingency Task]72
Task 7.1 –Public Hearing [18520] [RESERVED]72
Task 7.2 – Public Involvement and Communications Plan [18530]72
Task 7.2.1 – Public Involvement Kickoff Strategy Meeting [18540]74
Task 7.2.2 – Stakeholder Database and Communications Log [18550]74
Task 7.3 – Communications Materials75
Task 7.3.1 – Graphics [18570]75
Task 7.3.1.2 – Display Boards [18650]76
Task 7.3.2 – Outreach Materials: Project Fact Sheets, Newsletters, Fliers, and Stakeholder Emails [18580]77
Task 7.3.3 – Translation of Outreach Materials and Content [18630]79
Task 7.3.4 – Interpretation Services [18640]80
Task 7.3.5 – Small Group Briefings, One-on-One Briefings, and Stakeholder Interviews [18730]80
18730.10 – Due to APM at least 15 business days before the first briefing or interview82
18730.20 – Due to APM within 5 business days after receipt of Agency comments82
18730.30 – Due to APM at least 5 business days before the first briefing or interview as defined in Task 7.2 – Public Involvement and Communications Plan82
18730.40 – Due to APM within 5 business days after the last briefing or interview as defined in Task 7.2 – Public Involvement and Communications Plan82
18730.50 – Due to APM within 5 business days after receipt of Agency comments82
Task 7.3.6 – Website [18660]82
Task 7.3.7 – Social Media Content [18670]83
Task 7.3.8 – Advertising and Advertising Plan [18780]83
Task 7.3.8.1 – Radio Advertisements [18790] [Contingency Task]85
Task 7.3.8.2 – Radio Advertisements [18790] [RESERVED]85
Task 7.4 – Media Releases [18680]85
Task 7.4.1 – Open House and Public Event [18690]86
Task 7.4.2 – Online Open House [18700]87
Task 7.4.3 – Project Area Canvassing [18720]89
Task 7.5 – Soundwall, Noise Study and Noise Variance Outreach [18740]90
Task 7.6 – Access Management Outreach [18750] [RESERVED]91
Task 7.7 – Public Involvement Summary Report [18760]91
Task 7.8 – Public Comment Response [18770]91
Task 7.9 – Community Advisory Committee (“CAC”) [18810] [RESERVED]92
Task 7.10 – Community Engagement Liaison Services [18820] [RESERVED]92
Task 7.11 – Public Involvement Design Coordination [18830]92
Task 7.12 – Public Involvement – Public Information – Public Engagement Quality Reviews [18840]92
Task 8 – Utilities Coordination [19010]92
Task 8.1 – Utility Location and Coordination [19020]93
Task 8.2 – Utility Report [19030]94
Task 8.2.1 – National Environmental Policy Act (“NEPA”) Utilities Technical Memorandum or Report for EA and EIS Projects [19040] [RESERVED]94
Task 8.3 – Utility Coordination Meetings [19050]94
Task 8.4 – Utility Relocations [19060]95
Task 8.4.1 – Utility Notices [19070]95
Task 8.4.2 – Utility Constraints Notice [19080]96
Task 8.4.3 – Review Utility Relocation Plans and Relocation Time Requirement Letters [19090]96
Task 8.4.4 – Master Relocation Plan [19095] [RESERVED]97
Task 8.5 – Utility Reimbursement [19100] RESERVED]97
Task 8.5.2 – Contract with Utility for Reimbursement [RESERVED]97
Task 8.5.3 – Reimbursable Utility Agreement [RESERVED]97
Task 8.5.4 – Utility Billing Review, Approval, and Payment Recommendation [19150]97
Task 8.6 – Add Work Agreements [19130]98
Task 8.7 – Utility Special Provisions [19160]98
Task 8.8 – Utility Certification [19170]99
Task 8.9 – Utilities Design Coordination [19180]99
Task 8.10 – Utilities Coordination Quality Reviews [19190]100
Task 9 – Geotechnical, Geologic, and Hazardous Materials Services [20010] [RESERVED]100
Task 10 – Pavement Design Services [21010] [RESERVED]100
Task 11 – Hydraulics and Stormwater [22010] [RESERVED]100
Task 12 – Roadway Design [23010][RESERVED]100
Task 13 - Railroad Coordination and Support [24010]100
Task 13.1 – Railroad Coordination and Correspondence [24020]101
Task 13.1.1 - On-site Field Diagnostic Review [24030] [RESERVED]101
Task 13.2 – Railroad Notice to Proceed [RESERVED]101
Task 13.3 – Railroad Design [24050]101
Task 13.3.1 – Railroad Design Quality Review [24060]103
Task 13.4 – ODOT Railroad Crossing Order Application [24070] [Contingency Task]104
Task 13.5 – Construction and Maintenance Agreement (“C&M”) [24080] [RESERVED]104
Task 13.6 – Railroad Design Coordination [24090]104
Task 13.7 – Railroad Design Quality Reviews [24100]104
Task 14 – Bridges and Structures Design [24210]105
Task 14.1 – Bridge Design [24220] [RESERVED]105
Task 14.1.1 – Bridge Design Verification Package [24230]105
Task 14.1.2 – Bridge Design Acceptance Package (“DAP”) Design Phase [24260]107
Task 14.1.3 – Bridge Plans, Specifications, and Estimate (“PS&E”) Design [24330]110
Task 14.2 – Retaining Wall Design [24420] [RESERVED]116
Task 14.2.1 – Retaining Wall DVP Design [24430] [RESERVED]116
Task 14.2.2 – Retaining Wall DAP Design Phase [24460] [RESERVED]116
Task 14.2.3 – Retaining Wall PS&E Design [24510] [RESERVED]116
Task 14.3 – Sound Wall Design [24590] [RESERVED]116
Task 14.3.1 – Sound Wall DVP Design [24600] [RESERVED]116
Task 14.3.2 – Sound Wall DAP Design Phase [24630] [RESERVED]116
Task 14.3.3 – Sound Wall PS&E Design [24680] [RESERVED]116
Task 14.3.3.3 – Sound Wall Final Design [24710] [RESERVED]116
Task 14.4 – Traffic Structures Design [24760] [RESERVED]117
Task 14.4.1 – Traffic Structures DVP Design [24770] [RESERVED]117
Task 14.4.2 – Traffic Structures DAP Design Phase [24800] [RESERVED]117
Task 14.4.3 – Traffic Structures PS&E Design [24850] [RESERVED]117
Task 14.5 – Culvert Structure Design [24930] [RESERVED]117
Task 14.5.1 – Culvert DVP Design [24940] [RESERVED]117
Task 14.5.2 – Culvert DAP Design Phase [24970] [RESERVED]118
Task 14.5.3 – Culvert PS&E Design [25020] [RESERVED]118
Task 14.6 – [RESERVED]118
Task 14.7 – [RESERVED]118
Task 14.8 – Major Bridge Inspections [25100]118
Task 14.8.1 – Inspection Coordination and Closeout [25110]118
Task 14.8.2 – Access Plan and Traffic Control [25140]119
Task 14.8.3 – Inspections [25150] [Contingency Task]121
Task 14.8.4 – Inspection Reports [25200] [Contingency Task]125
Task 14.8.5 – Additional Bridge Inspection Services [25280]129
Task 14.8.6 – Major Bridge Inspections Quality Reviews [25330]130
Task 15 – Intelligent Transportation Systems (“ITS”) [RESERVED]132
Task 16 – Traffic Engineering and Management [26010]132
Task 16.1 – Transportation Analysis [26020]132
Task 16.1.1 – Plans and Policies Review [26030]132
Task 16.1.2 – Methodology and Assumptions Technical Memorandum [26040]133
Task 16.1.3 – Evaluation of Existing Conditions [26050]133
Task 16.1.4 – Future Year Background Traffic Analysis [26090]137
Task 16.1.5 – Concept Development and Evaluation [26100]138
Task 16.1.6 – Traffic Analysis Report [26140]141
Task 16.1.7 – Transportation Analysis Coordination [26150]142
Task 16.1.8 – Transportation Analysis Quality Reviews [26160]142
Task 16.2 – Code Refinement and Adoption [26170] [RESERVED]143
Task 16.2.1 – Code Refinement and Adoption Coordination [26180] [RESERVED]143
Task 16.2.2 – Code Refinement and Adoption Quality Reviews [26190][RESERVED]143
Task 16.3 – State and Region Traffic Engineer Approval Requests [26200]143
Task 16.3.1 – State Traffic-Roadway Engineer (“STRE”) Approvals [26210]143
Task 16.3.2 – Region Traffic Engineer (“RTE”) Approvals [26220]144
Task 16.3.3 – State and Region Traffic Engineer Approval Requests Coordination [26230]145
Task 16.3.4 – State and Region Traffic Engineer Approval Requests Quality Reviews [26240]146
Task 16.4 – Access Management [26250]146
Task 16.4.1 – Official Project Access List (“OPAL”) [26260]146
Task 16.4.2A – Access Management Methodology [26270]146
Task 16.4.2B – Access Management Methodology [26270]147
Task 16.4.3 – Access Management Methodology Letters [26280]147
Task 16.4.4 – Access Approach Decisions [26290]148
Task 16.4.5 – [RESERVED] [26300]148
Task 16.4.6 – Access Management Meetings with Affected Property Owners [26310]148
Task 16.4.7 – Access Management Strategy (“AMStrat”) [26320]149
Task 16.4.8 – Final Access Approach Modification, Relocation, and Closure Letters [26330]149
Task 16.4.9 – Access Management Strategy Exemption [RESERVED] [26340]150
Task 16.4.10 – Access Management Coordination [26350] [RESERVED]150
Task 16.4.11 – Access Management Quality Reviews [26360] [RESERVED]150
Task 16.5 – Transportation Management Plan (“TMP”) [26370]150
Task 16.5.1 – Work Zone Traffic Analysis and Documentation [26380]151
Task 16.5.2 – Work Zone Decision Tree [26390] [RESERVED]151
Task 16.5.3 – Mobility Considerations Checklist [26400]151
Task 16.5.4 – TMP Coordination [26410]152
Task 16.5.5 – TMP Quality Reviews [26420]152
Task 16.6 –Work Zone Traffic Control Plans (“TCP”) [26430]153
Task 16.6.1 –TCP DAP Design [26440]153
Task 16.6.2 – TCP PS&E Design [26450]154
Task 16.6.2.3 – TCP Final Design [26480]154
Task 16.6.2.4 – TCP Final PS&E Design [26490]155
Task 16.6.3 – Work Zone TCP Coordination [26500]155
Task 16.6.4 – Work Zone TCP Design Quality Review [26510]155
Task 16.7 – [RESERVED]157
Task 16.8 – Traffic Signal Design [26610] [RESERVED]157
Task 16.8.1 – Traffic Signal DAP Design [26620] [RESERVED]157
Task 16.8.2 – Traffic Signal PS&E Design [26630] [RESERVED]157
Task 16.8.3 – Traffic Signal Design Coordination [26680] [RESERVED]157
Task 16.8.4 – Traffic Signal Design Quality Review [26690] [RESERVED]157
Task 16.9 – Traffic Signal Interconnect Design [26700] [RESERVED]157
Task 16.9.1 – Traffic Signal Interconnect DAP Design [26710] [RESERVED]157
Task 16.9.2 – Traffic Signal Interconnect PS&E Design [26720] [RESERVED]157
Task 16.9.3 – Traffic Signal Interconnect Design Coordination [26770] [RESERVED]157
Task 16.9.4 – Traffic Signal Interconnect Design Quality Review [26780] [RESERVED]157
Task 16.10 – Sign Design [26790] [RESERVED]157
Task 16.10.1 – Sign DAP Design [26800] [RESERVED]157
Task 16.10.2 – Sign PS&E Design [26810] [RESERVED]157
Task 16.10.3 – Sign Design Coordination [26860] [RESERVED]157
Task 16.10.4 – Sign Design Quality Review [26870] [RESERVED]157
Task 16.11 – Pavement Marking Design [26880] [RESERVED]157
Task 16.11.1 – Pavement Marking DAP Design [26890] [RESERVED]157
Task 16.11.2 – Pavement Marking PS&E Design [26900] [RESERVED]158
Task 16.11.3 – Pavement Marking Design Coordination [26950] [RESERVED]158
Task 16.11.4 – Pavement Marking Design Quality Review [26960] [RESERVED]158
Task 16.12 – Illumination Design [26970] [RESERVED]158
Task 16.12.1 – Illumination DAP Design [26980] [RESERVED]158
Task 16.12.2 – Illumination PS&E Design [26990] [RESERVED]158
Task 16.12.3 – Illumination Design Coordination [27040] [RESERVED]158
Task 16.12.4 – Illumination Design Quality Review [27050] [RESERVED]158
Task 16.13 – National Environmental Policy Act (“NEPA”) Traffic and Transportation Technical Memorandum or Report for EA or EIS Projects [27060] [RESERVED]158
Task 16.13.1 – NEPA Traffic and Transportation Technical Memorandum or Report Coordination [27070] [RESERVED]158
Task 16.13.2 – NEP Traffic and Transportation Technical Memorandum or Report for EA or EIS Projects Quality Reviews [27080] [RESERVED]158
Task 17 – Erosion and Sediment Control [28010] [RESERVED]158
Task 18 – Roadside Development [28510] [RESERVED]158
Task 19 – Right of Way (“ROW”)158
Task 19.1 – NEPA ROW Technical Memorandum or Report for EA and EIS Projects [29020] [RESERVED]158
19.2 – ROW Services Administration [29030]158
Task 19.2.1 – ROW Existing Information [RESERVED]159
Task 19.2.2 - ROW Process Coordination [29050]159
Task 19.2.3 - ROW Information Tracking System (“RITS”) Management [29060]160
Task 19.2.4 - ROW Schedule [29070]160
Task 19.2.5 - ROW Meetings [29080]161
Task 19.3 – ROW Cost Estimating, Programming Estimate, Access Management, Title Reports, and ROW Setting [29090]161
Task 19.4 – Rights of Entry [29100]163
Task 19.5 – ROW Authorization [RESERVED]163
Task 19.6 – General Information Notice (“GIN”) [29120]163
Task 19.7 – Real Estate Appraisals [29130]164
Task 19.8 – Document Requests and Subject To Requests [29140]165
Task 19.9 – Offer and Negotiation [29150]166
Task 19.10 – Relocation [29160] [RESERVED]168
Task 19.11 – ROW Condemnation Support [29170]168
Task 19.12 – Closings [29180]168
Task 19.13 – Certification [29190]169
Task 19.14 – Project-Related Property Management [29200] [RESERVED]170
Task 19.15 – ROW Coordination During Construction [29210]170
Task 19.16 – ROW Design Coordination [29220]171
Task 19.17 – ROW Design Quality Reviews [29230]171
Task 20 – Design Acceptance Package (“DAP”) [30010]171
Task 20.1 – Design Verification Package (“DVP”) [30020]172
Task 20.2 – Draft DAP [30030]172
Task 20.2.1 – DAP Narrative [30040]172
Task 20.2.2 – Design Exception Requests [30070]173
Task 20.3 – Final DAP [30080]174
Task 20.4 – Certification of Design Acceptance with DAP checklist [RESERVED]175
Task 20.5 – DAP Exception Letter [30100] [Contingency Task]175
Task 20.6 – DAP Quality Reviews [30110]175
Task 20.7 – Phase Gate Quality Assurance [RESERVED]176
Task 21 – Plans, Specifications and Estimate (“PS&E”) [31010]176
Task 21.1 – Preliminary Plans package [31020]177
Task 21.2 – Advance Plans package [31030]178
Task 21.2.1 – Letters of Public Interest Finding [31040] [Contingency Task]179
Task 21.3 – Final Design package [31050]179
Task 21.3.1 – Final PS&E Package Provided by ODOT [RESERVED]180
Task 21.4 – Phase Gate Quality Assurance [RESERVED]180
Task 21.5 – PS&E Submittal Package [31090]180
Task 21.6 –eBIDS Handoff Package [31100]180
Task 21.7 –Construction Survey handoff [31110]181
Task 21.8 – PS&E Quality Reviews [31120]181
Task 22 - Bid and Award assistance [32010]182
Task 22.1 – Pre-bid Meeting [RESERVED]182
Task 22.2 – Questions During Bidding [32030]182
Schedule183
Task 22.3 – Addenda to the Bid Documents [32050] [Contingency Task] ,183
Task 22.4 – Bid and Award Assistance Quality Reviews [32060]184
Task 1 – Project Management [11010]1
Task 1.1 – Project Management and Coordination [11020]1
Task 1.2 – Progress Reports and Invoices [11030]2
Task 1.3 – Project Schedule and Schedule Updates [11040]2
Task 1.4 – Meetings [11050]3
Task 1.4.1 – Kick-off Meeting [11060]4
Task 1.4.2 – Project Development Team (“PDT”) Meetings [11070]4
Task 1.4.3 – Project Coordination Meetings [11080]5
Task 1.4.4 – Project Subteam Meetings [11090]5
Task 1.4.5 – Project Site Visit Meetings [11100]7
Task 1.4.6A – Mobility Advisory Committee Meetings ("MAC”) [11110] [RESERVED]8
Task 1.4.6B – Mobility Advisory Committee Meetings (“MAC”) [11110]8
Task 1.4.7 – Design Verification Workshop (“DVW”) [11120]9
Task 1.4.8 – Cost Risk Assessment (“CRA”) [11130]10
Task 1.4.9 – Design Acceptance Workshop (“DAW”) [11180]13
Task 1.4.10 – Preliminary Plans Review Meeting [11190]14
Task 1.4.11 – Advance Plans Review Meeting [11200]14
Task 1.4.12 – Final Plans Review Meeting [11210]15
Task 1.4.13 – Pre-PS&E Package Submittal Meeting [11220]16
Task 1.4.14 –PS&E Review Meetings [11230]16
Task 1.5 – Construction Support [11250]17
Task 1.6 – Risk Management [11260]18
Task 1.6.1 – Risk Management Plan [11270]18
Task 1.6.2 – Monitoring and Controlling Project Risks [11280]19
Task 1.7 – VE Study [11290]21
Task 1.7.1 – Pre-VE Workshop [11300]22
Task 1.7.2 – VE Workshop [11310]22
Task 1.7.3 – VE Report [11320]23
Task 1.7.4 – VE Implementation Meeting [11330]23
Task 1.7.5 – VE Study Findings Analysis [11340]24
Task 1.7.6 – Additional SME(s) for VE workshop [11350] [Contingency Task, see Section F] mark as [RESERVED] and delete the paragraph text if not needed24
Task 1.8 – Construction Risk Management Transition [11360]25
Task 1.9 – Quality Assurance/Quality Control [11370]26
Task 1.9.1 – Quality Assurance [RESERVED]26
Task 1.9.2 – QA/QC Quality Reviews [11390]26
Task 2 – Project Initiation [12010]27
Task 2.1 – Consultant SOW Development and Review [RESERVED]27
Task 2.2 – Intergovernmental Agreements [RESERVED]27
Task 2.3 – Project Charter [RESERVED]27
Task 2.4 – Draft Change Management Request (Zero-CMR) [RESERVED]27
Task 2.5 – Project Initiation Package [12060] RESERVED]27
Task 2.6 – Project Initiation Quality Reviews [12070] RESERVED]27
Task 2.7 – Project Initiation Region Phase Gate [RESERVED][RESERVED]28
Task 2.8 – Phase Gate Quality Assurance [RESERVED][RESERVED]28
Task 3 – Planning Services [13010] [RESERVED][RESERVED]28
Task 4 – Scoping [14010] RESERVED]28
Task 4.1 – Scoping [14020] RESERVED]28
Task 4.1.1 – Scoping Team Coordination [14030] RESERVED]28
Task 4.1.2 – Scoping Packet [14040] RESERVED]28
Task 4.1.3 – Project Scoping [14050] RESERVED]29
Task 4.1.4 – Project Re-scoping [14080] RESERVED]30
Task 4.2 – Project Selection [RESERVED]31
Task 4.3 – STIP Adoption [RESERVED]31
Task 4.4 – Scoping Quality Reviews [14130] RESERVED]31
Task 5 – Survey [15010] [Contingency Task]32
Task 5.1 – Project Control [15020] [Contingency Task]33
Task 5.2 – Control, Recovery, and Retracement (“CRR”) [15030] [Contingency Task]34
Task 5.2.1– Survey Filing Map (“SFM”) [15040] [Contingency Task]35
Task 5.3 – Topographic Data and Basemap [15050] [Contingency Task]35
Task 5.3.1 – Survey Project Initiation [15060] [Contingency Task]37
Task 5.4 – [RESERVED]37
Task 5.5 – Monumentation Surveys [15080] [Contingency Task]37
Task 5.6 – Right of Way (“ROW”) Engineering (Mapping and Descriptions) [15090] [Contingency Task]38
Task 5.6.1 – Proposed ROW Design and Layout [15100] [Contingency Task]38
Task 5.6.2 – Active ROW Acquisition Map [15110] [Contingency Task]38
Task 5.6.3 – ROW Addendum, Descriptions, and Sketch Maps [15120] [Contingency Task]39
Task 5.6.4 – ROW Descriptions Revisions due to Project Scope Changes [15125][RESERVED]40
Task 5.6.5 – Railroad Exhibit Maps [15130] [Contingency Task]40
Task 5.6.6 – Forest Service Plat Maps [15140] [RESERVED]41
Task 5.6.7 – Bureau of Land Management (“BLM”) Plat Maps [15150] [RESERVED]42
Task 5.7 – Staking [15160] [Contingency Task]42
Task 5.8 – Pre-Construction Survey [15170] [Contingency Task]43
Task 5.9 – Survey Design Coordination [15180]43
Task 5.10 – Survey Quality Reviews [15190]44
Task 6 – Environmental Services [15310]44
Task 6.1 – Pre-National Environmental Policy Act (“NEPA”) and Planning and Environment Linkages (“PEL”) Activities [15320] ] [RESERVED]44
Task 6.2 – NEPA - Categorical Exclusion (“CE”) or Programmatic CE (“PCE”) Documentation [15360] ] [RESERVED]44
Task 6.5 – Land Use (includes Coastal Zone, Farmland, and Wild and Scenic Rivers) [15730] [RESERVED]44
Task 6.6 – Environmental Justice (“EJ”) [15800] [RESERVED]45
Task 6.7 – Socioeconomic Analysis [15850] [RESERVED]45
Task 6.8 – Parks and Recreation Resources [15890] [RESERVED]45
Task 6.9 – Historic Resources [16100] [RESERVED]45
Task 6.10 – Cultural Resources – Archaeology [16210] [RESERVED]45
Task 6.11 – Visual/Aesthetics [16440] [RESERVED]45
Task 6.12 – Wetlands and Waters Delineation, and Permitting Services [16510] [RESERVED]45
Task 6.13 – Biological Services [16680] [RESERVED]45
Task 6.14 – Air Quality [16920]45
Task 6.14.1 – Air Quality Assessments for Categorical Exclusion Project [16930]45
Task 6.14.2 – Air Quality for Environmental Impact Statements (“EIS’s”) or Environmental Assessments (“EA’s”) [17050] [RESERVED]58
Task 6.14.3 – Energy Analysis [17210] [RESERVED]82
Task 6.14.4 – Air Quality Coordination [17230]83
Task 6.14.5 – Air-Quality Quality Reviews [17240]83
Task 6.15 – Noise Studies and Variances [17250] [RESERVED]84
Task 6.15.1 – Screening Analysis for Traffic Noise Impacts [17260] [RESERVED]84
Task 6.15.2 – Field Investigation and Data Gathering for NTR [17270] [RESERVED]85
Task 6.15.3 – Noise Model Verification: Compare Measured-to-Predicted (Modeled) Noise Values [17280] [RESERVED]86
Task 6.15.4 – Traffic Noise Impact Analysis and Mitigation Consideration [17290] [RESERVED]87
Task 6.15.5 – Noise Technical Report (“NTR”) [17300] [RESERVED]88
Task 6.15.6 – Final Noise Wall Height and Location Analysis [17350] [RESERVED]93
Task 6.15.7 – Noise Variances [17360]96
Task 6.15.8 – Noise Studies and Variances Coordination [17420]100
Task 6.15.9 – Noise Studies and Variances Quality Reviews [17430]101
Task 7 – Public Involvement – Public Information – Public Engagement [18510] [Contingency Task]101
Task 7.1 –Public Hearing [18520] [RESERVED]102
Task 7.2 – Public Involvement and Communications Plan [18530]103
Task 7.2.1 – Public Involvement Kickoff Strategy Meeting [18540]104
Task 7.2.2 – Stakeholder Database and Communications Log [18550]105
Task 7.3 – Communications Materials106
Task 7.3.1 – Graphics [18570]106
Task 7.3.1.2 – Display Boards [18650]106
Task 7.3.2 – Outreach Materials: Project Fact Sheets, Newsletters, Fliers, and Stakeholder Emails [18580]107
Task 7.3.3 – Translation of Outreach Materials and Content [18630]110
Task 7.3.4 – Interpretation Services [18640]110
Task 7.3.5 – Small Group Briefings, One-on-One Briefings, and Stakeholder Interviews [18730]111
18730.10 – Due to APM at least 15 business days before the first briefing or interview112
18730.20 – Due to APM within 5 business days after receipt of Agency comments112
18730.30 – Due to APM at least 5 business days before the first briefing or interview as defined in Task 7.2 – Public Involvement and Communications Plan112
18730.40 – Due to APM within 5 business days after the last briefing or interview as defined in Task 7.2 – Public Involvement and Communications Plan112
18730.50 – Due to APM within 5 business days after receipt of Agency comments112
Task 7.3.6 – Website [18660]112
Task 7.3.7 – Social Media Content [18670]113
Task 7.3.8 – Advertising and Advertising Plan [18780]113
Task 7.3.8.1 – Radio Advertisements [18790] [Contingency Task, see Section F] mark as [RESERVED] and delete the paragraph text if not needed115
Task 7.3.8.2 – Radio Advertisements [18790] [Contingency Task, see Section F] mark as [RESERVED] and delete the paragraph text if not needed115
Task 7.4 – Media Releases [18680]116
Task 7.4.1 – Open House and Public Event [18690]117
Task 7.4.2 – Online Open House [18700]118
Task 7.4.3 – Project Area Canvassing [18720]119
Task 7.5 – Soundwall, Noise Study and Noise Variance Outreach [18740]120
Task 7.6 – Access Management Outreach [18750] [RESERVED]121
Task 7.7 – Public Involvement Summary Report [18760]122
Task 7.8 – Public Comment Response [18770]122
Task 7.9 – Community Advisory Committee (“CAC”) [18810] [RESERVED]122
Task 7.10 – Community Engagement Liaison Services [18820] [RESERVED]124
Task 7.11 – Public Involvement Design Coordination [18830]124
Task 7.12 – Public Involvement – Public Information – Public Engagement Quality Reviews [18840]125
Task 8 – Utilities Coordination [19010]125
Task 8.1 – Utility Location and Coordination [19020]125
Task 8.2 – Utility Report [19030]126
Task 8.2.1 – National Environmental Policy Act (“NEPA”) Utilities Technical Memorandum or Report for EA and EIS Projects [19040] [RESERVED]127
Task 8.3 – Utility Coordination Meetings [19050]128
Task 8.4 – Utility Relocations [19060]129
Task 8.4.1 – Utility Notices [19070]129
Task 8.4.2 – Utility Constraints Notice [19080]129
Task 8.4.3 – Review Utility Relocation Plans and Relocation Time Requirement Letters [19090]130
Task 8.4.4 – Master Relocation Plan [19095] [Contingency Task, see Section F] mark as [RESERVED] and delete the paragraph text if not needed131
Task 8.5 – Utility Reimbursement [19100] [Contingency Task, see Section F] mark as [RESERVED] and delete the sub-paragraph text if not needed131
Task 8.5.1 – Reimbursement Review and Package [19110]131
Task 8.5.2 – Contract with Utility for Reimbursement [RESERVED]132
Task 8.5.3 – Reimbursable Utility Agreement [RESERVED]132
Task 8.5.4 – Utility Billing Review, Approval, and Payment Recommendation [19150]132
Task 8.6 – Add Work Agreements [19130]133
Task 8.7 – Utility Special Provisions [19160]133
Task 8.8 – Utility Certification [19170]134
Task 8.9 – Utilities Design Coordination [19180]134
Task 8.10 – Utilities Coordination Quality Reviews [19190]135
Task 9 – Geotechnical, Geologic, and Hazardous Materials Services [20010] [RESERVED]135
Task 10 – Pavement Design Services [21010] [RESERVED]135
Task 11 – Hydraulics and Stormwater [22010] [RESERVED]135
Task 12 – Roadway Design [23010][RESERVED]135
Task 13 - Railroad Coordination and Support [24010]135
Task 13.1 – Railroad Coordination and Correspondence [24020]136
Task 13.1.1 - On-site Field Diagnostic Review [24030] [Contingency Task, see Section F] mark as [RESERVED] and delete the paragraph text if not needed136
Task 13.2 – Railroad Notice to Proceed [RESERVED]137
Task 13.3 – Railroad Design [24050]137
Task 13.3.1 – Railroad Design Quality Review [24060]139
Task 13.4 – ODOT Railroad Crossing Order Application [24070] [Contingency Task, see Section F] mark as [RESERVED] and delete the paragraph text if not needed139
Task 13.5 – Construction and Maintenance Agreement (“C&M”) [24080] [RESERVED]141
Task 13.6 – Railroad Design Coordination [24090]141
Task 13.7 – Railroad Design Quality Reviews [24100]141
Task 14 – Bridges and Structures Design [24210]141
Task 14.1 – Bridge Design [24220] [RESERVED]141
Task 14.1.1 – Bridge Design Verification Package [24230]143
Task 14.1.2 – Bridge Design Acceptance Package (“DAP”) Design Phase [24260]145
Task 14.1.3 – Bridge Plans, Specifications, and Estimate (“PS&E”) Design [24330]150
Task 14.2 – Retaining Wall Design [24420] [RESERVED]155
Task 14.2.1 – Retaining Wall DVP Design [24430] [RESERVED]155
Task 14.2.2 – Retaining Wall DAP Design Phase [24460] [RESERVED]156
Task 14.2.3 – Retaining Wall PS&E Design [24510] [RESERVED]159
Task 14.3 – Sound Wall Design [24590] [RESERVED]162
Task 14.3.1 – Sound Wall DVP Design [24600] [RESERVED]162
Task 14.3.2 – Sound Wall DAP Design Phase [24630] [RESERVED]163
Task 14.3.3 – Sound Wall PS&E Design [24680] [RESERVED]165
Task 14.3.3.3 – Sound Wall Final Design [24710] [RESERVED]166
Task 14.4 – Traffic Structures Design [24760] [RESERVED]168
Task 14.4.1 – Traffic Structures DVP Design [24770] [RESERVED]169
Task 14.4.2 – Traffic Structures DAP Design Phase [24800] [RESERVED]170
Task 14.4.3 – Traffic Structures PS&E Design [24850] [RESERVED]172
Task 14.5 – Culvert Structure Design [24930] [RESERVED]175
Task 14.5.1 – Culvert DVP Design [24940] [RESERVED]175
Task 14.5.2 – Culvert DAP Design Phase [24970] [RESERVED]177
Task 14.5.3 – Culvert PS&E Design [25020] [RESERVED]179
Task 14.6 – [RESERVED]182
Task 14.7 – [RESERVED]182
Task 14.8 – Major Bridge Inspections [25100]182
Task 14.8.1 – Inspection Coordination and Closeout [25110]182
Task 14.8.2 – Access Plan and Traffic Control [25140]183
Task 14.8.3 – Inspections [25150] [Contingency Task]185
Task 14.8.4 – Inspection Reports [25200] [Contingency Task]189
Task 14.8.5 – Additional Bridge Inspection Services [25280]194
Task 14.8.6 – Major Bridge Inspections Quality Reviews [25330]195
Task 15 – Intelligent Transportation Systems (“ITS”) [RESERVED]197
Task 16 – Traffic Engineering and Management [26010]197
Task 16.1 – Transportation Analysis [26020]197
Task 16.1.1 – Plans and Policies Review [26030]197
Task 16.1.2 – Methodology and Assumptions Technical Memorandum [26040]198
Task 16.1.3 – Evaluation of Existing Conditions [26050]199
Task 16.1.4 – Future Year Background Traffic Analysis [26090]202
Task 16.1.5 – Concept Development and Evaluation [26100]203
Task 16.1.6 – Traffic Analysis Report [26140]206
Task 16.1.7 – Transportation Analysis Coordination [26150]207
Task 16.1.8 – Transportation Analysis Quality Reviews [26160]207
Task 16.2 – Code Refinement and Adoption [26170] [Contingency Task, see Section F] mark as [RESERVED] and delete the paragraph text (and all subparagraphs) if not needed208
Task 16.2.1 – Code Refinement and Adoption Coordination [26180]209
Task 16.2.2 – Code Refinement and Adoption Quality Reviews [26190] [Contingency Task, see Section F] mark as [RESERVED] and delete the paragraph text (and all subparagraphs) if not needed209
Task 16.3 – State and Region Traffic Engineer Approval Requests [26200]210
Task 16.3.1 – State Traffic-Roadway Engineer (“STRE”) Approvals [26210]210
Task 16.3.2 – Region Traffic Engineer (“RTE”) Approvals [26220]211
Task 16.3.3 – State and Region Traffic Engineer Approval Requests Coordination [26230]212
Task 16.3.4 – State and Region Traffic Engineer Approval Requests Quality Reviews [26240]212
Task 16.4 – Access Management [26250]213
Task 16.4.1 – Official Project Access List (“OPAL”) [26260]213
Task 16.4.2A – Access Management Methodology [26270]213
Task 16.4.2B – Access Management Methodology [26270]213
Task 16.4.3 – Access Management Methodology Letters [26280]214
Task 16.4.4 – Access Approach Decisions [26290]214
Task 16.4.5 – [RESERVED] [26300]215
Task 16.4.6 – Access Management Meetings with Affected Property Owners [26310]215
Task 16.4.7 – Access Management Strategy (“AMStrat”) [26320]215
Task 16.4.8 – Final Access Approach Modification, Relocation, and Closure Letters [26330]216
Task 16.4.9 – Access Management Strategy Exemption [RESERVED] [26340]216
Task 16.4.10 – Access Management Coordination [26350] [RESERVED]216
Task 16.4.11 – Access Management Quality Reviews [26360] [RESERVED]217
Task 16.5 – Transportation Management Plan (“TMP”) [26370]217
Task 16.5.1 – Work Zone Traffic Analysis and Documentation [26380]218
Task 16.5.2 – Work Zone Decision Tree [26390] [RESERVED]219
Task 16.5.3 – Mobility Considerations Checklist [26400]219
Task 16.5.4 – TMP Coordination [26410]220
Task 16.5.5 – TMP Quality Reviews [26420]220
Task 16.6 –Work Zone Traffic Control Plans (“TCP”) [26430]221
Task 16.6.1 –TCP DAP Design [26440]221
Task 16.6.2 – TCP PS&E Design [26450]222
Task 16.6.2.3 – TCP Final Design [26480]222
Task 16.6.2.4 – TCP Final PS&E Design [26490]223
Task 16.6.3 – Work Zone TCP Coordination [26500]223
Task 16.6.4 – Work Zone TCP Design Quality Review [26510]223
Task 16.7 – [RESERVED]224
Task 16.8 – Traffic Signal Design [26610] [RESERVED]224
Task 16.8.1 – Traffic Signal DAP Design [26620] [RESERVED]224
Task 16.8.2 – Traffic Signal PS&E Design [26630] [RESERVED]225
Task 16.8.3 – Traffic Signal Design Coordination [26680] [RESERVED]227
Task 16.8.4 – Traffic Signal Design Quality Review [26690] [RESERVED]227
Task 16.9 – Traffic Signal Interconnect Design [26700] [RESERVED]228
Task 16.9.1 – Traffic Signal Interconnect DAP Design [26710] [RESERVED]228
Task 16.9.2 – Traffic Signal Interconnect PS&E Design [26720] [RESERVED]229
Task 16.9.3 – Traffic Signal Interconnect Design Coordination [26770] [RESERVED]231
Task 16.9.4 – Traffic Signal Interconnect Design Quality Review [26780] [RESERVED]231
Task 16.10 – Sign Design [26790] [RESERVED]232
Task 16.10.1 – Sign DAP Design [26800] [RESERVED]232
Task 16.10.2 – Sign PS&E Design [26810] [RESERVED]233
Task 16.10.3 – Sign Design Coordination [26860] [RESERVED]234
Task 16.10.4 – Sign Design Quality Review [26870] [RESERVED]234
Task 16.11 – Pavement Marking Design [26880] [RESERVED]235
Task 16.11.1 – Pavement Marking DAP Design [26890] [RESERVED]235
Task 16.11.2 – Pavement Marking PS&E Design [26900] [RESERVED]236
Task 16.11.3 – Pavement Marking Design Coordination [26950] [RESERVED]237
Task 16.11.4 – Pavement Marking Design Quality Review [26960] [RESERVED]238
Task 16.12 – Illumination Design [26970] [RESERVED]238
Task 16.12.1 – Illumination DAP Design [26980] [RESERVED]238
Task 16.12.2 – Illumination PS&E Design [26990] [RESERVED]239
Task 16.12.3 – Illumination Design Coordination [27040] [RESERVED]240
Task 16.12.4 – Illumination Design Quality Review [27050] [RESERVED]241
Task 16.13 – National Environmental Policy Act (“NEPA”) Traffic and Transportation Technical Memorandum or Report for EA or EIS Projects [27060] [RESERVED]242
Task 16.13.1 – NEPA Traffic and Transportation Technical Memorandum or Report Coordination [27070] [RESERVED]243
Task 16.13.2 – NEP Traffic and Transportation Technical Memorandum or Report for EA or EIS Projects Quality Reviews [27080] [RESERVED]243
Task 17 – Erosion and Sediment Control [28010] [RESERVED]243
Task 18 – Roadside Development [28510] [RESERVED]243
Task 19 – Right of Way (“ROW”)243
Task 19.1 – NEPA ROW Technical Memorandum or Report for EA and EIS Projects [29020] [RESERVED]244
19.2 – ROW Services Administration [29030]245
Task 19.2.1 – ROW Existing Information [RESERVED]245
Task 19.2.2 - ROW Process Coordination [29050]245
Task 19.2.3 - ROW Information Tracking System (“RITS”) Management [29060]246
Task 19.2.4 - ROW Schedule [29070]246
Task 19.2.5 - ROW Meetings [29080]247
Task 19.3 – ROW Cost Estimating, Programming Estimate, Access Management, Title Reports, and ROW Setting [29090]248
Task 19.4 – Rights of Entry [29100]249
Task 19.5 – ROW Authorization [RESERVED]249
Task 19.6 – General Information Notice (“GIN”) [29120]249
Task 19.7 – Real Estate Appraisals [29130]250
Task 19.8 – Document Requests and Subject To Requests [29140]252
Task 19.9 – Offer and Negotiation [29150]252
Task 19.10 – Relocation [29160] [RESERVED]255
Task 19.11 – ROW Condemnation Support [29170]256
Task 19.12 – Closings [29180]256
Task 19.13 – Certification [29190]257
Task 19.14 – Project-Related Property Management [29200] [RESERVED]259
Task 19.15 – ROW Coordination During Construction [29210]259
Task 19.16 – ROW Design Coordination [29220]260
Task 19.17 – ROW Design Quality Reviews [29230]260
Task 20 – Design Acceptance Package (“DAP”) [30010]261
Task 20.1 – Design Verification Package (“DVP”) [30020]261
Task 20.2 – Draft DAP [30030]262
Task 20.2.1 – DAP Narrative [30040]262
Task 20.2.2 – Design Exception Requests [30070]262
Task 20.3 – Final DAP [30080]263
Task 20.4 – Certification of Design Acceptance with DAP checklist [RESERVED]264
Task 20.5 – DAP Exception Letter [30100] [Contingency Task]264
Task 20.6 – DAP Quality Reviews [30110]265
Task 20.7 – Phase Gate Quality Assurance [RESERVED]265
Task 21 – Plans, Specifications and Estimate (“PS&E”) [31010]265
Task 21.1 – Preliminary Plans package [31020]267
Task 21.2 – Advance Plans package [31030]267
Task 21.2.1 – Letters of Public Interest Finding [31040] [Contingency Task]268
Task 21.3 – Final Design package [31050]269
Task 21.3.1 – Final PS&E Package Provided by ODOT [RESERVED]269
Task 21.4 – Phase Gate Quality Assurance [RESERVED]269
Task 21.5 – PS&E Submittal Package [31090]270
Task 21.6 –eBIDS Handoff Package [31100]270
Task 21.7 –Construction Survey handoff [31110]271
Task 21.8 – PS&E Quality Reviews [31120]271
Task 22 - Bid and Award assistance [32010]272
Task 22.1 – Pre-bid Meeting [RESERVED]272
Task 22.2 – Questions During Bidding [32030]272
Schedule273
Task 22.3 – Addenda to the Bid Documents [32050] [Contingency Task, see Section F] mark as [RESERVED] and delete the paragraph text if not needed273
Task 22.4 – Bid and Award Assistance Quality Reviews [32060]274

Task 1 – Project Management [11010] [Project manager to determine what meetings are required, what additional or added coordination efforts are needed to fit the needs of the project.

Project Manager to determine schedule for all milestone deliverables and when associated deliverables are due through coordination with the regional tech center prior to negotiations] This task is to implement a project management strategy through meetings, schedules, coordination, and project management related deliverables to properly manage the project between Agency and Consultant.

Task 1.1 – Project Management and Coordination [11020] Consultant shall provide on-going coordination and communication as needed to appropriately manage the Services under this Contract.

Consultant shall guide and direct the Services and Consultant’s team in conformance with all applicable requirements of the Contract, Statement of Work (“SOW”) and the Project’s goals and objectives. Consultant’s Project Manager (“PM”) shall be Consultant’s primary point of contact and shall communicate with Agency regarding the status of Services being performed and to discuss issues or concerns that may impact the Project, to include weekly check-in phone calls between Agency Project Manager (“APM”) and the PM.

Consultant shall provide leadership, direction and control of these Services and maintain liaison, communication and coordination between Consultant’s staff, APM, and Agency staff to facilitate timely, efficient operations for all involved.

Consultant shall monitor progress of the Project and Services to include, but not limited to budget and expenditures.

Consultant shall maintain Project files including, but not limited to: engineering computations, assumptions, estimated quantities with unit costs, meeting agendas and minutes, business drawings, progress reports, correspondence and memoranda. Compiling the Project files must be an ongoing task, commencing upon receipt of the notice to proceed (“NTP”), and incorporating documents as they are generated throughout the Services for this Project. Unless otherwise indicated, Project files must be saved in an appropriate ODOT assigned ProjectWise folder. All documents must conform to standardized naming conventions from the ProjectWise Naming Tool or the ProjectWise Document Naming Tool Search document in the PW standards folder. Refer to the ODOT Partners PW External User Manual found within the ProjectWise document management system, and ODOT Partners PW Exhibit L for additional information.

Deliverables

11020.10 – Project files as requested by Agency Schedule

11020.10 – Due to APM within XX business days of request Task 1.2 – Progress Reports and Invoices [11030] [Invoice Preparation - may be listed as a task or deliverable (and may include costs in BOC) only if ODOT has on a file a signed Certification of Invoicing and ODC Billing Practices from Consultant that indicates invoice preparation is charged to each project and is not included in the Consultant’s overhead. Consultants approved for invoice prep charges are identified in the Billing Rate Share Drive maintained by OPO. The invoice limitation does not apply to project status reports, which are a required deliverable to be submitted with monthly invoices. Some regions may have required templates for invoicing or progress reports, use of these templates must be negotiated prior to execution of the contract. Format must be negotiated prior to execution of the contract.] Consultant shall prepare monthly progress reports and invoices in a format approved by Agency. Consultant’s progress report must summarize the activities completed and deliverables submitted by task for the reporting period and who the deliverables were provided to. Consultant’s progress report must identify schedule and budget issues, if there are pending issues that need resolution, and describe the planned activities for the next month. Progress report must also identify percentage completed of each task and associated deliverables. Consultant shall include its progress report with Consultant’s monthly invoice.

Consultant’s invoice must identify the reporting period and provide a breakdown of labor and expense costs incurred and must include copies (if required) of expense receipts. The invoice must be in a format acceptable to Agency.

Consultant shall prepare up to XX progress reports for the Services performed under this Contract.

Consultant shall submit monthly billing invoices (electronic copy) in accordance with Section H of the WOC / Exhibit B Compensation Part 1.

Deliverables

11030.10 – Electronic monthly progress reports and invoices Schedule

11030.10 – Due to APM once per month on [identify day – e.g., last business day] Task 1.3 – Project Schedule and Schedule Updates [11040] Consultant shall prepare a detailed work element schedule using MS Project for Consultant’s tasks. Consultant’s work element schedule must have, as a minimum, the following milestones with associated submittal dates:

· NTP

· Meetings (PS&E review, etc.)

· Workshops (Design Acceptance, Design Verification, etc.) Package review milestone completion dates (Preliminary, Advance, Final, PS&E, and Region PS&E)

· Right of Way (“ROW”) phase (if authorized) (i.e. begin prep for obligation, and conclusion of negotiations)

· Project Controls Office (“PCO”) PS&E delivery date

· PCO advertisement date

· PCO bid opening date Consultant shall submit the draft baseline MS Project schedule for Agency review and comment. Agency will consolidate all comments and submit to Consultant. Consultant shall address and incorporate Agency comments and suggested revisions, then deliver the final baseline MS Project schedule to Agency for approval. Consultant shall provide up to XX schedule updates throughout the Project as requested by Agency. If the Project schedule would change any of the due dates or timeframes required for Services or deliverables, an amendment to this contract will be required to make those changes.

Deliverables

11040.10 – Draft baseline MS Project schedule

11040.20 – Final baseline MS Project schedule

11040.30 – Project schedule updates submitted as requested Schedule

11040.10 – Due to APM within 10 business days after NTP

11040.20 – Due to APM 5 business days from receipt of Agency comments

11040.30 – Due to APM within XX business days of Agency request Task 1.4 – Meetings [11050] Consultant shall prepare for, lead, and facilitate meetings as identified in the subtasks below. Meeting locations will be collaboratively scheduled between Consultant and APM. Unless specifically stated otherwise, Consultant shall host meetings with screen and voice sharing software capable of running concurrently for use by Agency, Consultant staff, and sub-Consultant staff, at the discretion of the APM.

For each meeting, Consultant shall prepare a meeting agenda and provide draft meeting summary notes, which must include draft action items and record of any decisions from the meetings. Unless otherwise stated, Consultant shall submit the draft meeting summary for Agency review and comment. Agency will consolidate all comments and submit to Consultant. Consultant shall address and incorporate Agency comments and suggested revisions, then deliver the final meeting summary notes to Agency for approval.

Consultant shall prepare and maintain a Project action item and decision log (as part of meeting summary notes) to track action items and decisions discussed at Project meetings. The action item and decision log must include a description of the item or decision and who is assigned the action. Consultant shall provide the draft meeting summary notes to Agency for review and distribution.

Task 1.4.1 – Kick-off Meeting [11060] Consultant shall facilitate 1 Project kick-off meeting within X business days of contract NTP. Up to XX Consultant staff shall attend the meeting, which is estimated to be 2 hours in length. Consultant shall prepare meeting agenda and draft and final meeting summary notes for the meeting.

Deliverables

11060.10 – Meeting agenda

11060.20 – Draft meeting summary notes (including action item and decision log)

11060.30 – Final meeting summary notes

11060.40 – Meeting attendance - Consultant to verify attendance with Agency. No tangible deliverable may be required for this deliverable.

Schedule

11060.10 – Due to APM at least 5 business days prior to the meeting

11060.20 – Due to APM within 5 business days after the meeting

11060.30 – Due to APM within 5 business days after receipt of Agency comments

11060.40 – Within X business days from Agency issuance of contract NTP Task 1.4.2 – Project Development Team (“PDT”) Meetings [11070] PDT meetings are meant to address issues, design alternatives, technical discussions between Agency and Consultant, and provide an opportunity for the consultant to engage with their peers within the Agency. For ADA Curb Ramp or smaller scaled Projects, other meeting or workshops may be consolidated and addressed during this meeting. Examples: Design Exception and Crossing Closure Workshop, Monitoring and Controlling Project Risks, Construction Risk Management Transition Pre-PS&E Package Submittal Meeting, PS&E Review Meeting.] Consultant shall facilitate XX Agency PDT meetings during performance of the work. Agency PDT meetings will be scheduled at the APM discretion.