This document is an Addendum to Request for Proposal (RFP) #35663 issued by the Oregon Department of Transportation (ODOT) for the I-405 Fremont Bridge West Ramps Painting Project. The purpose of this Addendum is to correct the OregonBuys reference number and revise section 2.2.3 to expand the project sample period from 7 years to 10 years. The project involves painting work on the I-405 Fremont Bridge West Ramps in the jurisdictions of Multnomah County and the City of Portland. Proposers are required to submit key staff resumes and describe 3 relevant projects completed within the last 10 years, including information on whether the projects were completed within the original estimated budget and schedule.
The Addendum provides specific details on the evaluation criteria, including the maximum points allocated for each evaluation item. Proposers must be responsive to the requirements of this Addendum, and failure to do so may result in proposal rejection. The RFP documents, as modified by this Addendum, remain in full force and effect.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 35663_Attachment C_SSOW.docx | DOCX document | |
| 35663 Addendum_2.docx | DOCX document | |
| ATT A_Cover Sheet.doc | DOC document | |
| Project Description and Phasing~1.docx | DOCX document | |
| Master List Terms.docx | DOCX document | |
| Question 1.docx | DOCX document | |
| ATT B_Project Samples.doc | DOC document | |
| C2023226_GraphicsServices_RFP~2.pdf | ||
| 35663_ITA_Final.docx | DOCX document | |
| K22603 Project Summary.pdf | ||
| Section_B_List.docx | DOCX document | |
| 35663_Final.docx | DOCX document | |
| Freemont Bridge Painting AE Design Statement of Work.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Form S003-B080715
ODOT Procurement Office 355 Capitol St MS 51 Salem, OR 97301
Email: brian.r.nielsen@odot.oregon.gov
Date: August 24, 2023
From: Brian Nielsen, Procurement and Contracts Specialist
| Re: | RFP #35663 (ORBuys # S-73000-00007575) | |
| I-405 Fremont Bridge West Ramps Painting Project |
ADDENDUM #1 to RFP #35663
This Addendum modifies the Request for Proposal (RFP) document(s) only to the extent indicated herein. All other areas not changed or otherwise modified by this Addendum shall remain in full force and effect. This Addendum is hereby made an integral part of the RFP document. Proposer must be responsive to any requirements of this Addendum as if the requirements were set forth in the RFP. Failure to do so may result in Proposal rejection. See the RFP regarding requests for clarification or change and protests of this Addendum, and the deadlines for the foregoing.
The purpose of this Addendum is to:
· Correct the OregonBuys reference number
· Revise section 2.2.3 to expand the project sample period from 7 years to 10 years.
Added text is indicated by bold underlined font, deleted text is indicated by strikethrough font.
Page 1 – MINI-RFP/”Requestion Number”: REQ-73000-00034627 ORBuys Bid # S-73000-00007575
Page 11 - 2.2.3 EVALUATION ITEM 3 – General Qualifications MAX POINTS: 40
· (15 points) Describe your firm’s qualifications and proficiencies to complete the requested Services. Complete a “Key Staff Resumes” form available at http://www.oregon.gov/ODOT/Business/Procurement/Pages/PSK.aspx.
Provide information for the proposed key staff. Scoring will be based on relevance of the experience, qualifications, and technical competence of Project Manager and key staff proposed for use on this specific project.
Key Staff Resumes are not included in the Proposal page limit identified for this solicitation; however, a maximum of 3 Key Staff Resumes may be submitted. Any resumes submitted beyond this limit will be discarded by Agency and will not be included in the evaluation. The fields on the Key Staff Resumes form may be expanded, but may not exceed 1 page per resume and must use a minimum of 11-point font for substantive text. Each resume will be scored up to 5 points maximum.
· (15 points) Using Attachment B Project Samples & References form, describe 3 projects in the last 7 10 years that most closely represent the described Project. Include a brief description of project type, size, location, duration and objectives; a chronological timeline describing the tasks performed by the Proposer to fulfill the project objectives; and the actual project budget.
Each project sample may not exceed 1 page and must use a minimum of 11-point font for substantive text. Each sample project will be scored up to 5 points maximum.
· (10 points) For each of the 3 project samples, indicate in each project sample (in Attachment B) whether the services were accomplished within Proposers’ original estimated budget and schedule, or needed to be revised. Briefly explain the reason for any revisions.