This document is a Notice of Intent to Award from the Oregon Department of Transportation (ODOT) for the I-405: Fremont Bridge (Willamette River) West Ramps Painting Project. David Evans and Associates, Inc. has been selected as the top-ranked firm for negotiations of a Work Order Contract (WOC) to provide Personal Services for this project. The notice outlines the schedule for completing the statement of work, preparing a Breakdown of Costs, and securing approvals for both the Consultant and ODOT. It also states that no work is authorized until the WOC is executed and the Consultant receives a written Notice to Proceed from the ODOT Project Manager.
The notice includes a summary of the award submittal requirements, which include a Cost Disclosure Questionnaire, Breakdown of Costs, Responsibility Inquiry form, insurance certificates, Consultant Quality Plan, Committed DBE Breakdown and Certification Form-AE, and a W-9 Form. The notice also encourages the Consultant to authorize ACH direct deposit payments to expedite the transfer of payments to subcontractors, if applicable.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 35663_Attachment C_SSOW.docx | DOCX document | |
| 35663 Addendum_2.docx | DOCX document | |
| ATT A_Cover Sheet.doc | DOC document | |
| Project Description and Phasing~1.docx | DOCX document | |
| Master List Terms.docx | DOCX document | |
| 35663 Addendum_1.docx | DOCX document | |
| Question 1.docx | DOCX document | |
| ATT B_Project Samples.doc | DOC document | |
| C2023226_GraphicsServices_RFP~2.pdf | ||
| K22603 Project Summary.pdf | ||
| Section_B_List.docx | DOCX document | |
| 35663_Final.docx | DOCX document | |
| Freemont Bridge Painting AE Design Statement of Work.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of Transportation Procurement Office 355 Capitol St. NE, MS 51 Salem, OR 97301 Phone: (503) 986-2710 Fax: (503) 986-5790
OREGON DEPARTMENT OF TRANSPORTATION
Notice of Intent to Award
| DATE: | October 17, 2023 |
| TO: | David Evans and Associates, Inc. |
| SUBJECT: | 35663 - I-405: Fremont Bridge (Willamette River) West Ramps Painting Project |
The rankings of the Proposers are as follows:
1. David Evans and Associates, Inc.
2. DOWL
David Evans and Associates, Inc. is the top ranked firm selected for negotiations of a Work Order Contract (WOC) to provide Personal Services as specified in the above referenced Mini-Solicitation. The scores and rankings of all Proposers are shown in the score matrix accompanying this notice. The award submittal requirements stated in the Mini-Solicitation are summarized on Attachment 1 of this notice.
Nathan Potter will be the ODOT Project Manager (PM) for this Project. ODOT’s PM will initiate contact with Consultant and will be the primary contact for negotiation of the statement of work (SOW), schedule of performance and costs under the WOC. Following discussion and agreement on the SOW, a Breakdown of Costs (BOC) must be completed (using the BOC, BOC-CPFF or BOC-NBR as applicable) and submitted to ODOT’s PM. A BOC must demonstrate subcontractor utilization to meet the Disadvantaged Business Enterprise (DBE) goal set forth in the Mini-Solicitation. To set expectations for the contracting phase, listed below is a schedule for completing the SOW, preparing a BOC, completing negotiations, and securing approvals for both the Consultant and ODOT to follow:
| Activity |
| Responsible Party |
| Business Days |
| Negotiations |
| Establish initial work session to discuss the SOW with Consultant |
| ODOT PM |
| Within 1-2 days of this notice (days depend on size and complexity of the project) |
| Submission of Draft BOC & Draft SOW |
| Consultant |
| Within 15 days from the initial work session |
| Respond to BOC & SOW, Negotiate |
| ODOT PM |
| Within 5-10 days of Consultant submission of the BOC & SOW |
| Submission of Final BOC & Final SOW |
| Consultant |
| Within 30 days from the initial work session |
| WOC Preparation & CAU Review (If Required) |
| OPO |
| Within 15 days of Submission of Final BOC & Final SOW |
| Legal Sufficiency (If Required) |
| OPO, ODOT PM, and DOJ |
| Within 35 days of submission by ODOT PM |
| Signature routing and execution |
| OPO, Consultant, and ODOT Expenditure Authority (if required) |
| Within 6-8 days from initial routing |
| Issue Notice to Proceed (NTP) |
| ODOT PM |
| 1 day after execution |
Negotiations are anticipated to be completed (ready to submit to for legal sufficiency) within the schedule set forth in this notice.
If the schedule for negotiations cannot be met and the Consultant and ODOT are negotiating in good faith, additional time may be mutually agreed upon.
If agreement on costs, tasks, or other WOC requirements cannot be reached within this time frame, ODOT may terminate the negotiations and begin negotiations with the next highest ranked firm as provided in the solicitation and governing Oregon Administrative Rules (OARs).
Note that no work is authorized until the WOC is executed and Consultant has received a written NTP from the ODOT PM.
ODOT would like to thank each Proposer for your time and efforts in preparing a response to this solicitation.
Sincerely, Michael A. Day ODOT Procurement Specialist
Attachment 1 – Award Submittal Requirements Please email to me, the Contract Coordinator, the following items if marked as “REQUIRED” in the Mini-Solicitation (see detailed requirements and due date for each item in Section 2.3 of the Mini-Solicitation).
· Cost Disclosure Questionnaire
· Breakdown of Costs
· Responsibility Inquiry form
· Insurance certificates
· Consultant Quality Plan
· Committed DBE Breakdown and Certification Form-AE
· W-9 Form
Direct Deposit via Automated Clearing House (ACH). For Consultants that receive ongoing monthly payments from Agency on one or more contracts or work orders, Agency prefers making Consultant payments via ACH direct deposit. While not required, if Consultant has not previously authorized ACH direct deposit and would prefer ACH to expedite transfer of payments after invoices are approved, Consultant must complete a Vendor ACH Authorization form and submit to Agency per the instructions on the form. To expedite Consultant’s payments to its subcontractors, if applicable, Consultant should make reasonable efforts to offer ACH direct deposit payments.