- Fresno County, Inyo County, Kern County, Kings County, Madera County, Mariposa County, Merced County, Mono County, San Benito County, San Luis Obispo County, Tulare County, Fresno City, Kingsburg City, Inyokern CDP, Kernville CDP, Madera City, Madera Acres CDP, Madera Ranchos CDP, Corte Madera Town, Mariposa CDP, Merced City, University of California-Merced CDP, Mono City CDP, Kings Beach CDP, San Luis Obispo City, East Tulare Villa CDP, Tulare City, Mono Vista CDP, California
About this file
This is a Job Order Contract (JOC) project manual for the California Department of General Services (DGS), Real Estate Services Division, Project Management and Development Branch, establishing a sample restroom remodel project in the Central Region. The project involves the renovation of two multi-stall restrooms (women's and men's) located at the Library & Courts building at 914 Capitol Mall in Sacramento, California. The scope of work includes complete demolition to studs with no salvage, installation of new plumbing fixtures (sinks, water closets, urinals, and drinking fountains), electrical systems including LED lighting and exhaust fans, ceramic tile flooring and wall coverings, toilet partitions with ADA-compliant stalls, and comprehensive toilet accessories including dispensers, grab bars, and sharps disposal containers. The project manual documents sample documentation including a detailed scope of work, job order price proposal, proposed duration schedule, subcontractor list, and unit price catalog. The proposed construction duration is approximately 90 calendar days from notice to proceed, with a proposed timeline spanning from February through May 2026 for submittals, demolition, rough utilities, drywall and tile work, carpentry, and final finishes.
The proposed lump sum contract total is $196,601.85, with a construction subtotal of $159,317.33, comprised of five primary buckets: Demo—After Hours ($29,316.98), Carpentry/Gypsum Board/Tile ($67,346.40), Plumbing and Fixtures ($36,737.87), Electrical ($19,749.51), and Toilet Accessories ($43,451.09). DVBE (Disabled Veteran Business Enterprise) participation totals $80,000.00, representing 40.69% of the contract value, with certified subcontractors including Byte Electrical, CBCANDO Painting, Joe's Demo, and Sally's Specialties. The prime contractor, CannonDesign, is performing 59.31% of the work ($116,601.85), with SB (Small Business) participation totaling $22,000.00 or 11.19% of the bid price. The pricing proposal was valid for ninety days from January 26, 2026, and includes adjustment factors ranging from 1.2201 for normal working hours to 1.3200 for after-hours demolition work. No hazardous materials are present on the site, and the project reflects holistic unit pricing with quantities calculated for two identical restroom spaces measuring approximately 21.17 feet wide by 31.75 feet long with nine-foot-tall walls.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| JOC_Central_Region_Book_1.pdf | ||
| JOC_Central_Bid_Package.pdf | ||
| JOC_Central_Region_Book_3.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF CALIFORNIA DEPARTMENT OF GENERAL SERVICES
REAL ESTATE SERVICES DIVISION
PROJECT MANAGEMENT AND DEVELOPMENT BRANCH
PROJECT MANUAL – Book 2 of 3
BOOK 1
DIVISION 00 & 01 SPECIFICATIONS
BOOK 2
JOB ORDER PRICE PROPOSAL SAMPLE
JOB ORDER SAMPLE DOCUMENTS
UNIT PRICE CATALOG (UPC)
BOOK 3
TECHNICAL SPECIFICATIONS
FOR:
JOB ORDER CONTRACT – CENTRAL REGION
DEPARTMENT OF GENERAL SERVICES
CALIFORNIA
Juli Kawahata, Capital Outlay Program Manager West Sacramento, California
Consultants: Facility Optimization Solutions, LLC (FOS)
AUGUST 2026
#000000000014572
000000000014572
STATE OF CALIFORNIA DEPARTMENT OF GENERAL SERVICES
TABLE OF CONTENTS
BOOK 2
JOB ORDER PRICE PROPOSAL (JOPP) SAMPLE
Page Detailed Scope of Work Proposed Price Summary and Detail Proposed Duration Schedule Subcontractor List DVBE Participation Summary
JOB ORDER SAMPLE DOCUMENTS
Project Request Joint Scope Meeting Invitation Joint Scope Meeting Minutes Question List Request for Proposal Authorization for Extension of Time
UNIT PRICE CATALOG (UPC)
Job Order Contract Detailed Scope of Work
Job Order Number 99999A-NOR-01-JUS-055522-01
Project Information
Job Order Title Project Location
Sample for Pre Bid Demonstration - Restroom Remodel Library & Courts 914 Capitol Mall Sacramento, CA
Contractor Contact DGS Project Director Contact
Mike Swarm
(814) 602-2239 mswarm@cannondesign.com
Julia Lewis
(916) 233-6516 julia.lewis@dgs.ca.gov
Contractor Address FOS AM Contact
CannonDesign 50 Fountain Plaza, Suite 200
STE 200
Buffalo, NY 14202 814-897-3685
Paul Burns
(805) 423-4062 pburns@cannondesign.com
Detailed Scope of Work
Final DSOW as of 1.13.26 DGS PD
Restroom Remodel - Renovate (2) Restrooms. Women's and Men's multi stall restrooms.
1. Gut to the studs.No Salvage to State. No Hazmat Present
2. Plan on existing plumbing good up to stub out of wall.
3. Provide all new fixtures, sinks, water closets, 1 ADA compatible toilet each M/W.(2 total).
3.1. Provide 2 ADA sinks (2 total) each M/W RR.
4. Install at each stall (1) Seat Protector Holder, Wall Mount Lockable each toilet (6 total).
5. Install at each stall (1) 2 roll Toilet Paper Holder, Wall Mount Lockable (6 total).
6. Install at each stall (1) Standard Sharps Disposal Container Wall Mount lockable (2 total).
7. Install at each sink (1) electronic function cold water faucet, (1) soap dispenser (4 total).
8. Install at each sink (1) 18"x24" commercial grade frame less mirror.(4 total).
9. Provide all Stainless Steel (2 total) ADA Stalls (4 total) non ADA Stalls, (1 Total) Urinal Screen. All toilet accessories Brushed Stainless steel.
10. New 2' x 4' LED Ceiling Mount Lights (8 total), switches (2 total), outlets (4 total).
10.1 Assume 10' of 3/4' EMT for each device.
10.2 Assume 3 wires at 30' each for each device (to get back to panel).
11. Remove 2 12"x12" bathroom electric exhaust fans (2) remove. Replace with (2) new.
12. New flooring and full wall height premium grade tile.
13. Prep, Patch and Paint NEW drywall ceilings.
14. New entry door hardware on both.
15. New solid blocking for all ADA grab bars and all toilet stall standoff/brackets.
15.1. Note: FIre Stop caulk at all piping, electrical penetrations.
15.2. Note: Solid Blocking at all wall mounted toilet partitions.
15.3. Solid blocking at Urinals, sinks and grab bars behind wall board/tile. (4 grab bars ADA
Page 1 of 3 01/13/2026
Project Information
Job Order Title Project Location
Sample for Pre Bid Demonstration - Restroom Remodel Library & Courts 914 Capitol Mall Sacramento, CA
Contractor Contact DGS Project Director Contact
Mike Swarm
(814) 602-2239 mswarm@cannondesign.com
Julia Lewis
(916) 233-6516 julia.lewis@dgs.ca.gov
Contractor Address FOS AM Contact
CannonDesign 50 Fountain Plaza, Suite 200
STE 200
Buffalo, NY 14202 814-897-3685
Paul Burns
(805) 423-4062 pburns@cannondesign.com stalls, 2 urinals, 4 sinks, 2 water fountains, 7 full vertical behind toiled partitions@wall connection, 1 vertical behind urinal screen, 2 at width of baby changing tables)
16. See Sample floor plan, DSOW and photos.
17. General Dimensions Restroom Rectangle is 21.17' wide by 31.75' long
18. General Dimensions Restroom Walls are 9' Tall
19. Toilet Partitions are to be floor to ceiling, with 12" clearance top / bottom.
20. Remove total of 4 each 12" x 12" ceiling registers and replace with new. Painted White
21. Assume there is a Chase wall behind all toilets and urinals for access.
22. Ceramic Wall Tile Full height on wall surfaces in restroom and the wall behind the drinking fountains at the entry doors. Estimated (1410 S.F.). Will allow 10% for over stock for maintenance overstock.
Use Mold/Moisture resistant drywall for tile backer at all walls.
23. Ceramic Floor Tile all floor areas inside restrooms, none outside restroom. Estimated (516 S.F.) for estimating purposes. Will allow 10% for over stock for maintenance overstock.
24. Ceiling prep/paint is (516 S.F.) for estimating purposes.
25. Replace existing (2) water fountains with 2 new, 1 set to ADA required height.
26. Replace existing (2) elect hand dryer with (2) new.
27. Install (2 new) plastic baby changing wall hung station.
In Progress by Paul Burns for Training and Pre bid Documentation
Page 2 of 3 01/13/2026
Project Information
Job Order Title Project Location
Sample for Pre Bid Demonstration - Restroom Remodel Library & Courts 914 Capitol Mall Sacramento, CA
Contractor Contact DGS Project Director Contact
Mike Swarm
(814) 602-2239 mswarm@cannondesign.com
Julia Lewis
(916) 233-6516 julia.lewis@dgs.ca.gov
Contractor Address FOS AM Contact
CannonDesign 50 Fountain Plaza, Suite 200
STE 200
Buffalo, NY 14202 814-897-3685
Paul Burns
(805) 423-4062 pburns@cannondesign.com
Detailed Scope of Work Approval
All information contained in this Detailed Scope of Work (DSOW) is assumed to be true and accurate. Please submit a written notice and suggested corrections so that the submittal of the Job Order Pricing Package is not delayed.
By signing, you agree that the Detailed Scope of Work is considered to be correct and will become part of the project record.
Paul Burns Paul Burns FOS Account Manager
Date
Julia Lewis Project Director
Date
Mike Swarm Contractor
Date
Page 3 of 3 01/13/2026
Job Order Price ProposalJob Order Contract
Project Information
Job Order Title Project Location
Sample for Pre Bid Demonstration - Restroom Remodel Library & Courts 914 Capitol Mall Sacramento, CA
DGS Project Director ContactContractor Contact
Mike Swarm
(814) 602-2239 mswarm@cannondesign.com
Julia Lewis
(916) 233-6516 julia.lewis@dgs.ca.gov
FOS AM ContactContractor Address
CannonDesign 50 Fountain Plaza, Suite 200
STE 200
Buffalo, NY 14202 814-897-3685
Paul Burns
(805) 423-4062 pburns@cannondesign.com
Job Order Price Proposal
Julia Lewis, Please find attached the following documentation for the Job Order Price Proposal (JOPP) for the project 99999A-NOR-01- JUS-055522-01, Sample for Pre Bid Demonstration - Restroom Remodel.
1) Price Proposal Summary & Detail
2) Proposed Duration Schedule
3) Schedule of Values
4) Bond & Insurance (If required)
5) Subcontractor List
6) SB Participation Validation (If applicable)
7) DVBE Participation Validation
8) Certificate of Reported Compliance (CRC)
9) Other Requested Documentation
The Proposed Pricing Summary is valid for ninety (90) days and will then go into HOLD Status. FOS Account Manager, Paul Burns, has reviewed the JOPP. If you would like to proceed with the project, please sign and return the included Job Order Pricing Package Acceptance.
Proposed Pricing Summary
Proposed Sub-total Proposed Lump Sum Total Proposed Construction Duration
$159,317.33 $196,601.85 0 Calendar Day(s)
Page 1 of 33 01/26/2026
Job Order Price Proposal
Paul Burns 01/14/2026
Paul Burns - FOS Account Manager Date
Julia Lewis - Project Director Date
Mike Swarm - Contractor Date
Page 2 of 33 01/26/2026
Project Information
Job Order Title Project Location
Sample for Pre Bid Demonstration - Restroom Remodel Library & Courts 914 Capitol Mall Sacramento, CA
DGS Project Director ContactContractor Contact
Mike Swarm
(814) 602-2239 mswarm@cannondesign.com
Julia Lewis
(916) 233-6516 julia.lewis@dgs.ca.gov
Contractor Address DGS Address
707 3rd St, West Sacramento, CA 95605
(916) 233-6516
CannonDesign 50 Fountain Plaza, Suite 200
STE 200
Buffalo, NY 14202 814-897-3685
FOS AM Phone Number
Paul Burns
(805) 423-4062
TotalFactorBucket Name
01 Demo - After Hours $29,316.98
Main Bucket Area 1 Other Than Normal Working Hours ( x 1.320 $29,316.98
02 Carpentry, Gypsum Board, Tile $67,346.40
Main Bucket Area 1 Normal Working Hours ( x 1.2201 ) $67,346.40
03 Plumbing and Fixtures $36,737.87
Main Bucket Area 1 Normal Working Hours ( x 1.2201 ) $36,737.87
04 Electrical $19,749.51
Main Bucket Area 1 Normal Working Hours ( x 1.2201 ) $19,749.51
05 Toilet Accessories $43,451.09
Main Bucket Area 1 Normal Working Hours ( x 1.2201 ) $43,451.09
Total Proposal $196,601.85
Page 3 of 33 01/26/2026
Bucket Total $29,316.9801 Demo - After Hours
$29,316.98Sub-Bucket Total
1 20 CY Dumpster Rental100250 EA
Includes delivery, pick-up and dump fees01-54-00
Hover Notes:
LV3: Cost excludes fuel and operator unless noted otherwise. If the rental equipment use is for a trades specific scope of work, an operator cannot be added
LV4:
Quantity Book Price Book Total Factor Bid Price
2.00 x $882.46 = $1,764.92 x 1.3200 = $2,329.69
Contractor's Note:
Needed onsite for 2 months of work.
2 Remove Joint Sealant - Partition101103 LF
02-41-22
Hover Notes:
LV1: Removals for MasterFormat divisions three through fourteen and thirty-two are included in 02-00- 00 Existing Conditions. Mechanical, Electrical, and Site Utility removals are located within their applicable divisions
LV2: Unit pricing includes all labor and equipment to safely remove the item and transport it into an approved rubbish container, such as a dumpster, trailer, truck, etc. Hauling of demolished materials which are not disposed of in a dumpster can be selected at the end of each section.
LV3:
LV4:
Quantity Book Price Book Total Factor Bid Price
20.00 x $7.12 = $142.40 x 1.3200 = $187.97
Contractor's Note:
To cover small amounts at each (2) restrooms. Around any pipe/conduit penetrations. Figure 10 LF per restroom.
This is separate from overall demo. 20 LF total
Page 4 of 33 01/26/2026
3 Remove Partition - Plaster Only101109 SF
Includes removal of lath and plaster02-41-22
Hover Notes:
LV1: Removals for MasterFormat divisions three through fourteen and thirty-two are included in 02-00- 00 Existing Conditions. Mechanical, Electrical, and Site Utility removals are located within their applicable divisions
LV2: Unit pricing includes all labor and equipment to safely remove the item and transport it into an approved rubbish container, such as a dumpster, trailer, truck, etc. Hauling of demolished materials which are not disposed of in a dumpster can be selected at the end of each section.
LV3:
LV4:
Quantity Book Price Book Total Factor Bid Price
1410.00 x $1.90 = $2,679.00 x 1.3200 = $3,536.28
Contractor's Note:
This covers demo of existing wall tile and cement board on existing studs.Math calculated with (New Cememt Board and New Wall Tile).
4 Remove Insulation – Batt or Rolls101118 SF
Fiberglass or Mineral Wool02-41-22
Hover Notes:
LV1: Removals for MasterFormat divisions three through fourteen and thirty-two are included in 02-00- 00 Existing Conditions. Mechanical, Electrical, and Site Utility removals are located within their applicable divisions
LV2: Unit pricing includes all labor and equipment to safely remove the item and transport it into an approved rubbish container, such as a dumpster, trailer, truck, etc. Hauling of demolished materials which are not disposed of in a dumpster can be selected at the end of each section.
LV3:
LV4:
Quantity Book Price Book Total Factor Bid Price
1410.00 x $0.83 = $1,170.30 x 1.3200 = $1,544.80
Contractor's Note:
Math calculated with (New Cememt Board and New Wall Tile).
Page 5 of 33 01/26/2026
5 Remove Mirror101149 SF
02-41-22
Hover Notes:
LV1: Removals for MasterFormat divisions three through fourteen and thirty-two are included in 02-00- 00 Existing Conditions. Mechanical, Electrical, and Site Utility removals are located within their applicable divisions
LV2: Unit pricing includes all labor and equipment to safely remove the item and transport it into an approved rubbish container, such as a dumpster, trailer, truck, etc. Hauling of demolished materials which are not disposed of in a dumpster can be selected at the end of each section.
LV3:
LV4:
Quantity Book Price Book Total Factor Bid Price
4.00 x $6.78 = $27.12 x 1.3200 = $35.80
Contractor's Note:
2 per restroom, 4 total.
6 Remove Toilet Compartment - Floor Mounted101157 EA
Includes removal of one door panel, one side panel, pilasters and all associated hardware02-41-22
Hover Notes:
LV1: Removals for MasterFormat divisions three through fourteen and thirty-two are included in 02-00- 00 Existing Conditions. Mechanical, Electrical, and Site Utility removals are located within their applicable divisions
LV2: Unit pricing includes all labor and equipment to safely remove the item and transport it into an approved rubbish container, such as a dumpster, trailer, truck, etc. Hauling of demolished materials which are not disposed of in a dumpster can be selected at the end of each section.
LV3:
LV4:
Quantity Book Price Book Total Factor Bid Price
4.00 x $161.74 = $646.96 x 1.3200 = $853.99
Contractor's Note:
2 existing compartments per restroom (4 total)
Page 6 of 33 01/26/2026
7 Remove Urinal Screen101158 EA
02-41-22
Hover Notes:
LV1: Removals for MasterFormat divisions three through fourteen and thirty-two are included in 02-00- 00 Existing Conditions. Mechanical, Electrical, and Site Utility removals are located within their applicable divisions
LV2: Unit pricing includes all labor and equipment to safely remove the item and transport it into an approved rubbish container, such as a dumpster, trailer, truck, etc. Hauling of demolished materials which are not disposed of in a dumpster can be selected at the end of each section.
LV3:
LV4:
Quantity Book Price Book Total Factor Bid Price
4.00 x $71.25 = $285.00 x 1.3200 = $376.20
Contractor's Note:
2 existing in each restroom (4 total)
8 Remove Toilet Accessory - Medicine Cabinet101168 EA
02-41-22
Hover Notes:
LV1: Removals for MasterFormat divisions three through fourteen and thirty-two are included in 02-00- 00 Existing Conditions. Mechanical, Electrical, and Site Utility removals are located within their applicable divisions
LV2: Unit pricing includes all labor and equipment to safely remove the item and transport it into an approved rubbish container, such as a dumpster, trailer, truck, etc. Hauling of demolished materials which are not disposed of in a dumpster can be selected at the end of each section.
LV3:
LV4:
Quantity Book Price Book Total Factor Bid Price
2.00 x $88.58 = $177.16 x 1.3200 = $233.85
Contractor's Note:
1 per restroom to be removed. (2 total)
Page 7 of 33 01/26/2026
9 Remove Toilet Accessory - Grab Bar101170 EA
Excludes grab bar removal attached to toilet partitions unless required to be saved by the contract02-41-22
Hover Notes:
LV1: Removals for MasterFormat divisions three through fourteen and thirty-two are included in 02-00- 00 Existing Conditions. Mechanical, Electrical, and Site Utility removals are located within their applicable divisions
LV2: Unit pricing includes all labor and equipment to safely remove the item and transport it into an approved rubbish container, such as a dumpster, trailer, truck, etc. Hauling of demolished materials which are not disposed of in a dumpster can be selected at the end of each section.
LV3:
LV4:
Quantity Book Price Book Total Factor Bid Price
4.00 x $20.22 = $80.88 x 1.3200 = $106.76
Contractor's Note:
Remove 2 per restroom (4 total)
10 Remove Coat Rack101184 EA
02-41-22
Hover Notes:
LV1: Removals for MasterFormat divisions three through fourteen and thirty-two are included in 02-00- 00 Existing Conditions. Mechanical, Electrical, and Site Utility removals are located within their applicable divisions
LV2: Unit pricing includes all labor and equipment to safely remove the item and transport it into an approved rubbish container, such as a dumpster, trailer, truck, etc. Hauling of demolished materials which are not disposed of in a dumpster can be selected at the end of each section.
LV3:
LV4:
Quantity Book Price Book Total Factor Bid Price
4.00 x $44.54 = $178.16 x 1.3200 = $235.17
Contractor's Note:
2 Per restroom
Page 8 of 33 01/26/2026
11 Remove Flooring - Hard Tile101189 SF
Includes ceramic, porcelain, quarry or other similar tiles02-41-22
Hover Notes:
LV1: Removals for MasterFormat divisions three through fourteen and thirty-two are included in 02-00- 00 Existing Conditions. Mechanical, Electrical, and Site Utility removals are located within their applicable divisions
LV2: Unit pricing includes all labor and equipment to safely remove the item and transport it into an approved rubbish container, such as a dumpster, trailer, truck, etc. Hauling of demolished materials which are not disposed of in a dumpster can be selected at the end of each section.
LV3:
LV4:
Quantity Book Price Book Total Factor Bid Price
516.00 x $6.47 = $3,338.52 x 1.3200 = $4,406.85
Contractor's Note:
2 restrooms 258 per plan
12 Remove Shelving101243 LF
02-41-22
Hover Notes:
LV1: Removals for MasterFormat divisions three through fourteen and thirty-two are included in 02-00- 00 Existing Conditions. Mechanical, Electrical, and Site Utility removals are located within their applicable divisions
LV2: Unit pricing includes all labor and equipment to safely remove the item and transport it into an approved rubbish container, such as a dumpster, trailer, truck, etc. Hauling of demolished materials which are not disposed of in a dumpster can be selected at the end of each section.
LV3:
LV4:
Quantity Book Price Book Total Factor Bid Price
6.00 x $17.81 = $106.86 x 1.3200 = $141.06
Contractor's Note:
3' shelf on wall on each restroom (6 LF Total)
Page 9 of 33 01/26/2026
13 Remove Door Assembly - Interior Solid Door, Single101126 EA
Includes door, frame and hardware02-41-22
Hover Notes:
LV1: Removals for MasterFormat divisions three through fourteen and thirty-two are included in 02-00- 00 Existing Conditions. Mechanical, Electrical, and Site Utility removals are located within their applicable divisions
LV2: Unit pricing includes all labor and equipment to safely remove the item and transport it into an approved rubbish container, such as a dumpster, trailer, truck, etc. Hauling of demolished materials which are not disposed of in a dumpster can be selected at the end of each section.
LV3:
LV4:
Quantity Book Price Book Total Factor Bid Price
2.00 x $89.07 = $178.14 x 1.3200 = $235.14
Contractor's Note:
2 doors (1 door per restroom)
14 Specialty Cleaning & Damage Restoration - Floor Protection Paperboard, 48 Mil, 38" Wide, In100076 SF
01-35-29
Hover Notes:
LV3:
LV4: All items in Division 01-35-29 Health, Safety and Emergency Response Procedures apply to emergency work only and must be authorized by Agency and Account Manager prior to usage.
Quantity Book Price Book Total Factor Bid Price
600.00 x $0.48 = $288.00 x 1.3200 = $380.16
Contractor's Note:
Sticky mats/paperboard. Path from restroom to side door. Replace every other week. Onsite 8 weeks. (one-month submittals)3' x 50 feet = 150 SF. x 4 changes = 600 SF.
15 Temporary Construction Fence - 8' Tall100227 LF
Includes delivery, set-up and removal; Rental rate is LF per month01-53-00
Hover Notes:
LV4:
Quantity Book Price Book Total Factor Bid Price
240.00 x $4.10 = $984.00 x 1.3200 = $1,298.88
Contractor's Note:
Laydown area given by DGS and requirement to secure materials, equip, tools.20' wide by 40' long. total is 120 LF2 months on site needed. 240 LF
Page 10 of 33 01/26/2026
16 Temp Fence Single Gate – Up To 6' Wide – Includes Removal100229 EA
01-53-00
Hover Notes:
LV4:
Quantity Book Price Book Total Factor Bid Price
2.00 x $285.86 = $571.72 x 1.3200 = $754.67
Contractor's Note:
1 gate needed for 2 months
17 Temporary Construction Fence Windscreen - 8' High100235 LF
Includes delivery, set-up and removal01-53-00
Hover Notes:
LV4:
Quantity Book Price Book Total Factor Bid Price
240.00 x $3.09 = $741.60 x 1.3200 = $978.91
Contractor's Note:
Per DGS direction during JSM meeting.120 LF x 2 months = 240 LF
18 [Modifier] Temporary Fence Ballast Rental Over 1 Month - Sand / Gravel Bag100239 MO
Rental rate is per EA for 1 month01-53-00
Hover Notes:
LV4:
Quantity Book Price Book Total Factor Bid Price
48.00 x $3.00 = $144.00 x 1.3200 = $190.08
Contractor's Note:
10' Panels, 240 lf = 24 panels x 2 bags = 48 bags.
Page 11 of 33 01/26/2026
19 Remove Plumbing Fixture & Rough-In108001 EA
Includes Faucet or Flush Valve and Carrier.22-05-05
Hover Notes:
LV1: • Item costs include all labor, material (including gaskets, bolts, etc.), small equipment (welders, etc.), small tools and consumables (solder, flux, etc.) to install the item.
• Item costs exclude rigging equipment. Refer to (CSI) - MasterFormat® Division 01 - General Requirements for Assembly Items: Construction Aids.
• Cutting and patching work required for the installation or demolition/removal of plumbing systems or components shall be included under the General Trades Division 1 through 14.
• Installation and Demolition/Removal costs assume accessible locations. Removals and/or relocations of adjacent items required for access such as ceilings, walls, MEP systems, etc. to be priced separately.
LV2:
LV4: • Demolition/Removal costs exclude any salvage value.
• Plumbing Equipment and Fixture Demolition/Removal costs exclude piping, hook-ups, rough-ins, and electrical connections.
Quantity Book Price Book Total Factor Bid Price
14.00 x $244.59 = $3,424.26 x 1.3200 = $4,520.02
Contractor's Note:
4 fixtures each restroom (14 total)W = 2 sinks and 4 WC's, 1 Drinking FountainM = 2 sinks and 2 WC and 2 Urinals, 1 Drinking Fountain
20 Temp Plastic Poly Sheeting – Includes Removal100221 SF
01-53-00
Hover Notes:
LV4:
Quantity Book Price Book Total Factor Bid Price
400.00 x $0.59 = $236.00 x 1.3200 = $311.52
Contractor's Note:
200 sf. per restroom area changed 2 times. 400 sf total.
21 Traffic Control Mesh/Vinyl Roll Up Construction Signs (MO), Set and Remove by Hand Daily100699 EA
Includes sign and stand01-55-26
Hover Notes:
Quantity Book Price Book Total Factor Bid Price
2.00 x $492.65 = $985.30 x 1.3200 = $1,300.60
Contractor's Note:
Per DGS for pedestrian notifications. Needed in parking lot for 2 months
Page 12 of 33 01/26/2026
22 Remove Light Fixture - Fluorescent112585 EA
Includes Lamp, Ballast, and Recycle Costs26-05-05
Hover Notes:
LV2:
Quantity Book Price Book Total Factor Bid Price
8.00 x $276.60 = $2,212.80 x 1.3200 = $2,920.90
Contractor's Note:
Per JSM site walk, revised DSOW existing lights inside restrooms to be removed. QTY: 4 per bathroom - total 8.
23 Remove Wiring Device - Outlets & Switches112589 EA
26-05-05
Hover Notes:
LV2:
Quantity Book Price Book Total Factor Bid Price
8.00 x $174.19 = $1,393.52 x 1.3200 = $1,839.45
Contractor's Note:
Remove devices per JSM site walk and drawings - 2 switches and 6 outlets.
24 Remove Electrical Connection - HVAC Fan112625 EA
26-05-05
Hover Notes:
LV2:
Quantity Book Price Book Total Factor Bid Price
2.00 x $87.09 = $174.18 x 1.3200 = $229.92
Contractor's Note:
QTY:2 Per note 19 of DSOW.
Page 13 of 33 01/26/2026
25 Remove Fan - Residential109700 EA
Bathroom or Attic23-05-05
Hover Notes:
LV1: • Item costs include all labor, material (including gaskets, bolts, etc.), small equipment (welders, etc.), small tools and consumables (solder, flux, etc.) to install the item.
• Item costs exclude rigging equipment. Refer to (CSI) - MasterFormat® Division 01 - General Requirements for Assembly Items: Construction Aids.
• Cutting and patching work required for the installation or demolition/removal of HVAC systems or components shall be included under the General Trades Division 1 through 14.
• Installation and Demolition/Removal costs assume accessible locations. Removals and/or relocations of adjacent items required for access such as ceilings, walls, MEP systems, etc. to be priced separately.
LV2:
LV4: • Demolition/Removal costs exclude any salvage value.
• HVAC Equipment and Terminal Unit Demolition/Removal costs exclude piping, ductwork, hook-ups, and electrical connections.
Quantity Book Price Book Total Factor Bid Price
2.00 x $69.75 = $139.50 x 1.3200 = $184.14
Contractor's Note:
QTY:2 Per note 19 of DSOW. Removed restroom exhaust fan.
26 Remove Register, Grille or Diffuser - Up to 24" x 24"109731 EA
23-05-05
Hover Notes:
LV1: • Item costs include all labor, material (including gaskets, bolts, etc.), small equipment (welders, etc.), small tools and consumables (solder, flux, etc.) to install the item.
• Item costs exclude rigging equipment. Refer to (CSI) - MasterFormat® Division 01 - General Requirements for Assembly Items: Construction Aids.
• Cutting and patching work required for the installation or demolition/removal of HVAC systems or components shall be included under the General Trades Division 1 through 14.
• Installation and Demolition/Removal costs assume accessible locations. Removals and/or relocations of adjacent items required for access such as ceilings, walls, MEP systems, etc. to be priced separately.
LV2:
LV4: • Demolition/Removal costs exclude any salvage value.
• HVAC Equipment and Terminal Unit Demolition/Removal costs exclude piping, ductwork, hook-ups, and electrical connections.
Quantity Book Price Book Total Factor Bid Price
4.00 x $34.88 = $139.52 x 1.3200 = $184.17
Contractor's Note:
QTY:4 Per note 20 of DSOW.
Page 14 of 33 01/26/2026
Bucket Total $67,346.4002 Carpentry, Gypsum Board, Tile
$67,346.40Sub-Bucket Total
27 2X6 Wood Blocking or Bridging – Pressure Treated102149 LF
Structural Support Bracing, Fastening, or Anchor06-10-53
Hover Notes:
LV1: Items in this category include all connections, fasteners, and anchors
LV3:
LV4: Structural framing lumber includes but not limited to, regionally available, Kiln dried, PS DOC 2 graded dimensional solid wood in Pine, Spruce, Douglas-Fir or Hem-Fir, No. 2 or better. Costs are per LF of member unless noted otherwise
Quantity Book Price Book Total Factor Bid Price
160.00 x $4.86 = $777.60 x 1.2201 = $948.75
Contractor's Note:
80 lf. per restroom for horizontal blocking. Est for all anchor points on stalls, hangers, grab bars, accessories. 80 lf. x 2 restrooms = 160 lf.
28 2X4 Partitions Studs and Plates – 12" O.C. (> 500 SF) – Pressure Treated102164 SF
Wood Framing, #1 Grade or Better, Southern Yellow Pine (SYP) Dimensional Lumber06-11-16
Hover Notes:
LV1: Items in this category include all connections, fasteners, and anchors
LV4: Structural framing lumber includes but not limited to, regionally available, Kiln dried, PS DOC 2 graded dimensional solid wood in Pine, Spruce, Douglas-Fir or Hem-Fir, No. 2 or better. Pricing includes all plates, clips, fasteners, connections, curves, bracing, straps, and bridging
Quantity Book Price Book Total Factor Bid Price
200.00 x $4.90 = $980.00 x 1.2201 = $1,195.70
Contractor's Note:
Misc. Infill of studs with blocking for new stalls, and hanger supports for toilet fixtures.Estimate 100 SF per restroom x 2 = 200 sf.
Page 15 of 33 01/26/2026
29 Ceramic Tile Wall – Class 3 Up To 1/4" Thick105355 SF
Class 2: up To 1/2" thick09-30-13
Hover Notes:
LV1: Includes fasteners and clips to substrate, casing, and corner beads. Division Nine quantities are based on greater than 500 square feet unless otherwise noted.
LV2: Tile work includes glazed and unglazed tile materials, cement or modified setting, profiling floors to drain, mortars, grouts, sealers, spacers, trim pieces, marble thresholds or equal unless noted otherwise, termination strips, expansion strips, and reveals for a complete flooring installation
LV3:
Quantity Book Price Book Total Factor Bid Price
1500.00 x $19.41 = $29,115.00 x 1.2201 = $35,523.21
Contractor's Note:
157.126 LF (wall length) - 6LF Door Openings = 151.126LF x 9 LF (wall height) = 1360.134 SF + 10% = 1496.147 / 25 SF per case = 59.845 cases = 60 cases x 25sf = 1500 SF Total. Due to ordering tiles in full boxes/cases. Will order tile in closed case/box and give remaining to CADGS for repair stock.
30 Paint Interior Ceiling - GWB, Drywall, or Plaster105856 SF
Includes One Coat Primer and Two Coats Acrylic Latex Paint09-91-23
Hover Notes:
LV1: Includes fasteners and clips to substrate, casing, and corner beads. Division Nine quantities are based on greater than 500 square feet unless otherwise noted.
LV3: All painting costs are complete systems with one primer coat and two finish coats unless noted otherwise. Includes surface preparation to comply with manufacturer’s requirements, and application of primer (over unpainted) or barrier coats (over previously painted surfaces). Follow project documents as well as manufacturers requirements for number of required coats and DFT thicknesses. Includes all protection, including but not limited to plastic sheeting, tarps, tape, etc.
Excludes stripping existing paint.
Quantity Book Price Book Total Factor Bid Price
517.00 x $2.40 = $1,240.80 x 1.2201 = $1,513.90
Contractor's Note:
517 S.F. per overall floor plan.Paint color/type finish will be provided by Owner, per JSM.
Page 16 of 33 01/26/2026
31 Solid Core Wood Door Up To 3' X 7' – Prehung103978 EA
Paint grade. Includes frame and hinges08-14-16
Hover Notes:
LV2: All Doors are prepped for hinges, locksets and closer. All Frames are prepped for hinges, strike and closer, with rabbeted profile
LV4: All doors are flat sawn, Buy America Compliant, with an STC rating of 35. Includes prep for hinges, lockset and closer
Quantity Book Price Book Total Factor Bid Price
2.00 x $443.55 = $887.10 x 1.2201 = $1,082.35
Contractor's Note:
1 per restroom
32 Hollow Metal Door Frame (Knock Down) - 3' X 7' : 4" Throat103543 EA
08-12-13
Hover Notes:
LV2: All Doors are prepped for hinges, locksets and closer. All Frames are prepped for hinges, strike and closer, with rabbeted profile
LV4: Hollow metal frames for doors and lites, prepped for hinges, strike and closer, with rabbeted profile. All frames are welded unless noted otherwise and fire rated up to 90 minutes.
Quantity Book Price Book Total Factor Bid Price
2.00 x $487.50 = $975.00 x 1.2201 = $1,189.60
Contractor's Note:
1 per restroom
33 Protection Plate / Kick Plate – Stainless Steel, .050" Thick104763 SF
08-71-00
Hover Notes:
LV3: All hardware is ANSI/BHMA Grade 1, 626 Satin chrome finish unless otherwise noted.
LV4:
Quantity Book Price Book Total Factor Bid Price
10.00 x $34.95 = $349.50 x 1.2201 = $426.42
Contractor's Note:
Page 17 of 33 01/26/2026
34 Push Plate – Stainless Steel, .050” Thick, 3 X 12104799 EA
08-71-00
Hover Notes:
LV3: All hardware is ANSI/BHMA Grade 1, 626 Satin chrome finish unless otherwise noted.
LV4:
Quantity Book Price Book Total Factor Bid Price
2.00 x $119.50 = $239.00 x 1.2201 = $291.60
Contractor's Note:
1 per restroom
35 Closer Full Profile- Surface, Operating Size 2-6, Regular Arm Or Top Jamb Regular104728 EA
08-71-00
Hover Notes:
LV3: All hardware is ANSI/BHMA Grade 1, 626 Satin chrome finish unless otherwise noted.
LV4:
Quantity Book Price Book Total Factor Bid Price
2.00 x $448.48 = $896.96 x 1.2201 = $1,094.38
Contractor's Note:
1 per restroom
36 Door Pull – Aluminum, ¾” Dia., 12” Length104782 PR
08-71-00
Hover Notes:
LV3: All hardware is ANSI/BHMA Grade 1, 626 Satin chrome finish unless otherwise noted.
LV4:
Quantity Book Price Book Total Factor Bid Price
1.00 x $251.60 = $251.60 x 1.2201 = $306.98
Contractor's Note:
Items is a pair, o per restroom equals 1 pr.
Page 18 of 33 01/26/2026
37 R-19 Fiberglass Batt Insulation - Faced102890 SF
07-21-16
Hover Notes:
LV1: Includes fasteners and clips to substrate and standard prefinished trim pieces in manufacturers standard color selection. Division Seven quantities are based on greater than 500 square feet unless otherwise noted. Utilize applicable modifiers
LV4: Insulation includes facing in either paper or foil where applicable
Quantity Book Price Book Total Factor Bid Price
1410.00 x $2.72 = $3,835.20 x 1.2201 = $4,679.33
Contractor's Note:
1410 SF, same as demo. equals wall area.
38 GWB Taped and Finished – 5/8" Thick (Water Resistant)105289 SF
Includes single layer of GWB taped and finished. Partition systems already include this item09-21-16
Hover Notes:
LV1: Includes fasteners and clips to substrate, casing, and corner beads. Division Nine quantities are based on greater than 500 square feet unless otherwise noted.
LV4: All assemblies are assumed Level 4 finish or equal, ready for paint, covering or other specified wall treatments
Quantity Book Price Book Total Factor Bid Price
1422.00 x $3.27 = $4,649.94 x 1.2201 = $5,673.39
Contractor's Note:
158 LF (wall length) x 9 LF (wall height) = 1422 SF of new GWB
39 Ceramic Tile Floor – Class 3 Up To 1/4" Thick – Large Format > 1'-0" x 2'-0"105350 SF
Class 2: up To 1/2" thick09-30-13
Hover Notes:
LV1: Includes fasteners and clips to substrate, casing, and corner beads. Division Nine quantities are based on greater than 500 square feet unless otherwise noted.
LV2: Tile work includes glazed and unglazed tile materials, cement or modified setting, profiling floors to drain, mortars, grouts, sealers, spacers, trim pieces, marble thresholds or equal unless noted otherwise, termination strips, expansion strips, and reveals for a complete flooring installation
LV3:
Quantity Book Price Book Total Factor Bid Price
575.00 x $19.13 = $10,999.75 x 1.2201 = $13,420.79
Contractor's Note:
258.56 x 2 = 517.2Sf + 10% = 568.832SF / 25SF per case = 22.753 cases = 23 cases x 25sf = 575sf total.
Page 19 of 33 01/26/2026
Bucket Total $36,737.8703 Plumbing and Fixtures
$36,737.87Sub-Bucket Total
40 2X8 Wood Blocking or Bridging – Pressure Treated102151 LF
Structural Support Bracing, Fastening, or Anchor06-10-53
Hover Notes:
LV1: Items in this category include all connections, fasteners, and anchors
LV3:
LV4: Structural framing lumber includes but not limited to, regionally available, Kiln dried, PS DOC 2 graded dimensional solid wood in Pine, Spruce, Douglas-Fir or Hem-Fir, No. 2 or better. Costs are per LF of member unless noted otherwise
Quantity Book Price Book Total Factor Bid Price
60.00 x $4.92 = $295.20 x 1.2201 = $360.17
Contractor's Note:
10LF per plumbing fixture (2 urinals and 4 sinks)
41 Lavatory- Wall Hung, Vitreous China, W/Faucet, Carrier & Trim- Wheelchair109150 EA
Kohler K12634 Lavatory W/Chicago Faucet 2200 Combination Faucet Or Equal. Includes Carrier, Drain, Tailpiece, Supply Pipes W/Loose Key Control Stops, Escutcheons, Cast Adjustable P-Trap W/Cleanout Plug And Ada Insulator Kit For Water Supply And Drainage Assemblies.
22-42-16
Hover Notes:
LV1: • Item costs include all labor, material (including gaskets, bolts, etc.), small equipment (welders, etc.), small tools and consumables (solder, flux, etc.) to install the item.
• Item costs exclude rigging equipment. Refer to (CSI) - MasterFormat® Division 01 - General Requirements for Assembly Items: Construction Aids.
• Cutting and patching work required for the installation or demolition/removal of plumbing systems or components shall be included under the General Trades Division 1 through 14.
• Installation and Demolition/Removal costs assume accessible locations. Removals and/or relocations of adjacent items required for access such as ceilings, walls, MEP systems, etc. to be priced separately.
LV2: • Plumbing Fixture Rough-Ins (connections) include all required pipe, fittings, valves, and specialties within 5 LF of the point of connection for proper operation. Reference contract documents and applicable codes and standards for details.
Quantity Book Price Book Total Factor Bid Price
4.00 x $2,190.62 = $8,762.48 x 1.2201 = $10,691.10
Contractor's Note:
QTY: 4 - 2 per each bathroom per DSOWBoth sinks at ADA height per JSM meeting.
Page 20 of 33 01/26/2026
42 [Modifier] Thermostatic Temperature Actuated Mixing Valve - Chrome Finish108450 EA
Watts Powers HydroGuard XP Series LFMM430 or Equal.22-11-19
Hover Notes:
LV1: • Item costs include all labor, material (including gaskets, bolts, etc.), small equipment (welders, etc.), small tools and consumables (solder, flux, etc.) to install the item.
• Item costs exclude rigging equipment. Refer to (CSI) - MasterFormat® Division 01 - General Requirements for Assembly Items: Construction Aids.
• Cutting and patching work required for the installation or demolition/removal of plumbing systems or components shall be included under the General Trades Division 1 through 14.
• Installation and Demolition/Removal costs assume accessible locations. Removals and/or relocations of adjacent items required for access such as ceilings, walls, MEP systems, etc. to be priced separately.
LV2: • Piping items include hangers and couplings (as required) unless stated otherwise.
• Pipe fitting items reflect the average cost of all fitting types and should be quantified as such.
Fittings exclude couplings, valves, and specialties.
• Cast iron no hub pipe and fittings including heavy-duty shielded couplings.
LV3: • Plumbing Equipment costs exclude temperature controls, electrical connections, and piping hook-ups (connections) unless stated otherwise. The contractor is responsible for adding these additional items as required.
• Plumbing Equipment Hook-Ups (connections) include all required pipe, fittings, valves, and specialties within 10 LF of the point of connection for proper operation. Reference contract documents and applicable codes and standards for details.
• Plumbing Equipment costs exclude housekeeping pads and dunnage.
LV4: • 2" and down valves include threaded or soldered connections unless stated otherwise.
• 2-1/2" and up valves include flanged, grooved, lug, or wafer connections unless stated otherwise.
Quantity Book Price Book Total Factor Bid Price
4.00 x $729.54 = $2,918.16 x 1.2201 = $3,560.45
Contractor's Note:
Per Note 7 on DSOW
43 Grille w/o Damper - 1 To 6 SF111492 EA
Steel Or Aluminum, Perforated Or Louvered, Ceiling Or Sidewall23-37-13
Hover Notes:
LV1: • Item costs include all labor, material (including gaskets, bolts, etc.), small equipment (welders, etc.), small tools and consumables (solder, flux, etc.) to install the item.
• Item costs exclude rigging equipment. Refer to (CSI) - MasterFormat® Division 01 - General Requirements for Assembly Items: Construction Aids.
• Cutting and patching work required for the installation or demolition/removal of HVAC systems or components shall be included under the General Trades Division 1 through 14.
• Installation and Demolition/Removal costs assume accessible locations. Removals and/or relocations of adjacent items required for access such as ceilings, walls, MEP systems, etc. to be priced separately.
Quantity Book Price Book Total Factor Bid Price
4.00 x $280.85 = $1,123.40 x 1.2201 = $1,370.66
Contractor's Note:
QTY:4 Per note 20 of DSOW.
Page 21 of 33 01/26/2026
44 Air Testing, Adjusting & Balancing (TAB) - Register, Grille or Diffuser110076 EA
23-05-93
Hover Notes:
LV1: • Item costs include all labor, material (including gaskets, bolts, etc.), small equipment (welders, etc.), small tools and consumables (solder, flux, etc.) to install the item.
• Item costs exclude rigging equipment. Refer to (CSI) - MasterFormat® Division 01 - General Requirements for Assembly Items: Construction Aids.
• Cutting and patching work required for the installation or demolition/removal of HVAC systems or components shall be included under the General Trades Division 1 through 14.
• Installation and Demolition/Removal costs assume accessible locations. Removals and/or relocations of adjacent items required for access such as ceilings, walls, MEP systems, etc. to be priced separately.
LV2:
LV4: Includes TAB plan, test reports, schematic diagrams, systems & device readiness checks, test probe installation & removal, device marking, and recording measurements.
Quantity Book Price Book Total Factor Bid Price
4.00 x $174.19 = $696.76 x 1.2201 = $850.12
Contractor's Note:
QTY:4 Per note 20 of DSOW.
45 Urinal- Wall Mount, Vitreous China, w/ Carrier- Waterless109121 EA
Sloan Wes-1000 Or Equal.22-42-13
Hover Notes:
LV1: • Item costs include all labor, material (including gaskets, bolts, etc.), small equipment (welders, etc.), small tools and consumables (solder, flux, etc.) to install the item.
• Item costs exclude rigging equipment. Refer to (CSI) - MasterFormat® Division 01 - General Requirements for Assembly Items: Construction Aids.
• Cutting and patching work required for the installation or demolition/removal of plumbing systems or components shall be included under the General Trades Division 1 through 14.
• Installation and Demolition/Removal costs assume accessible locations. Removals and/or relocations of adjacent items required for access such as ceilings, walls, MEP systems, etc. to be priced separately.
LV2: • Plumbing Fixture Rough-Ins (connections) include all required pipe, fittings, valves, and specialties within 5 LF of the point of connection for proper operation. Reference contract documents and applicable codes and standards for details.
Quantity Book Price Book Total Factor Bid Price
2.00 x $1,475.51 = $2,951.02 x 1.2201 = $3,600.54
Contractor's Note:
QTY:2 - per agency provided drawings. ADA compliant
Page 22 of 33 01/26/2026
46 Water Closet- Floor Mount, Siphon Jet, Vitreous China, w/ Flush Valve109124 EA
Kohler K-4405, K-4368 Water Closet W/Sloan Royal 115 Flush Valve Or Equal. Includes Seat.22-42-13
Hover Notes:
LV1: • Item costs include all labor, material (including gaskets, bolts, etc.), small equipment (welders, etc.), small tools and consumables (solder, flux, etc.) to install the item.
• Item costs exclude rigging equipment. Refer to (CSI) - MasterFormat® Division 01 - General Requirements for Assembly Items: Construction Aids.
• Cutting and patching work required for the installation or demolition/removal of plumbing systems or components shall be included under the General Trades Division 1 through 14.
• Installation and Demolition/Removal costs assume accessible locations. Removals and/or relocations of adjacent items required for access such as ceilings, walls, MEP systems, etc. to be priced separately.
LV2: • Plumbing Fixture Rough-Ins (connections) include all required pipe, fittings, valves, and specialties within 5 LF of the point of connection for proper operation. Reference contract documents and applicable codes and standards for details.
Quantity Book Price Book Total Factor Bid Price
6.00 x $1,059.07 = $6,354.42 x 1.2201 = $7,753.03
Contractor's Note:
QTY: 6 - 4 per womens bathroom and 2 per mens bathroom per agency provided drawing. Will be using K-4405 for ADA requirements.
47 Drinking Fountain - Wall Mounted Dual Height109275 EA
Elkay EMABFTLDDSC or Equal.22-47-13
Hover Notes:
LV1: • Item costs include all labor, material (including gaskets, bolts, etc.), small equipment (welders, etc.), small tools and consumables (solder, flux, etc.) to install the item.
• Item costs exclude rigging equipment. Refer to (CSI) - MasterFormat® Division 01 - General Requirements for Assembly Items: Construction Aids.
• Cutting and patching work required for the installation or demolition/removal of plumbing systems or components shall be included under the General Trades Division 1 through 14.
• Installation and Demolition/Removal costs assume accessible locations. Removals and/or relocations of adjacent items required for access such as ceilings, walls, MEP systems, etc. to be priced separately.
LV2: • Plumbing Fixture Rough-Ins (connections) include all required pipe, fittings, valves, and specialties within 5 LF of the point of connection for proper operation. Reference contract documents and applicable codes and standards for details.
Quantity Book Price Book Total Factor Bid Price
2.00 x $2,394.01 = $4,788.02 x 1.2201 = $5,841.86
Contractor's Note:
QTY: 2 per drawing provided by agency and conversation during JSM.
Page 23 of 33 01/26/2026
48 Drinking Fountain Rough-In109282 EA
22-47-13
Hover Notes:
LV1: • Item costs include all labor, material (including gaskets, bolts, etc.), small equipment (welders, etc.), small tools and consumables (solder, flux, etc.) to install the item.
• Item costs exclude rigging equipment. Refer to (CSI) - MasterFormat® Division 01 - General Requirements for Assembly Items: Construction Aids.
• Cutting and patching work required for the installation or demolition/removal of plumbing systems or components shall be included under the General Trades Division 1 through 14.
• Installation and Demolition/Removal costs assume accessible locations. Removals and/or relocations of adjacent items required for access such as ceilings, walls, MEP systems, etc. to be priced separately.
LV2: • Plumbing Fixture Rough-Ins (connections) include all required pipe, fittings, valves, and specialties within 5 LF of the point of connection for proper operation. Reference contract documents and applicable codes and standards for details.
Quantity Book Price Book Total Factor Bid Price
2.00 x $1,110.54 = $2,221.08 x 1.2201 = $2,709.94
Contractor's Note:
QTY: 2 per drawing provided by agency.
Bucket Total $19,749.5104 Electrical
$19,749.51Sub-Bucket Total
49 3/4" Galvanized Steel Electric Metallic Tubing (EMT) Conduit - Connector112986 EA
Adapter - IP Thread x Set Screw or Comp, Insulated or Non-Insulated26-05-33
Hover Notes:
LV2:
Quantity Book Price Book Total Factor Bid Price
44.00 x $15.30 = $673.20 x 1.2201 = $821.37
Contractor's Note:
2 connectors per device and home run. 18 devices x 2 connectors = 36 connectors + 4 homeruns x 2 connectors = 8 connectors = 44 connectors total.
50 3/4" Galvanized Steel Electric Metallic Tubing (EMT) Conduit - Coupling112997 EA
Compression or Set Screw26-05-33
Hover Notes:
LV2:
Quantity Book Price Book Total Factor Bid Price
18.00 x $20.00 = $360.00 x 1.2201 = $439.24
Contractor's Note:
Per IBC code, 1 support per 10'. 180'/10' = 18 couplings.
Page 24 of 33 01/26/2026
51 3/4" Galvanized Steel Electric Metallic Tubing (EMT) Conduit - Support113018 EA
Hanger w/Nut and Bolt26-05-33
Hover Notes:
LV2:
Quantity Book Price Book Total Factor Bid Price
23.00 x $13.97 = $321.31 x 1.2201 = $392.03
Contractor's Note:
Per IBC code, 1 support per 8'. 180'/8' = 23 supports.
52 3/4" Galvanized Steel Electric Metallic Tubing (EMT) Conduit112975 LF
Thin-Wall EMT - ANSI C80.326-05-33
Hover Notes:
LV2:
Quantity Book Price Book Total Factor Bid Price
180.00 x $12.35 = $2,223.00 x 1.2201 = $2,712.28
Contractor's Note:
Per note #10.1 DSOW - an allowance of 10' per device was agreed upon, 9 devices in total per bathroom. 9 x 10 = 90' x 2 bathrooms = 180'
53 #12 AWG Copper THHN/THWN 600V Single Conductor Wire or Cable112680 LF
Solid or Stranded26-05-12
Hover Notes:
LV2:
Quantity Book Price Book Total Factor Bid Price
300.00 x $1.50 = $450.00 x 1.2201 = $549.05
Contractor's Note:
Per note 10.2 - all devices need 10' of wire with 3 wires. 30' x 10 devices = 300'
54 Duplex Receptacle - GFCI, Tamper Resistant113768 EA
125 V, 15 or 20 A26-27-26
Hover Notes:
Quantity Book Price Book Total Factor Bid Price
6.00 x $373.27 = $2,239.62 x 1.2201 = $2,732.56
Contractor's Note:
QTY 6 GFCI Duplexes per note 10 on DSOW. 3 in each bathroom including the hand dryer.
Page 25 of 33 01/26/2026
55 Firestopping Intumescent Sealant - Pipe Penetration Up to 2"108018 EA
Fireproofing size based on pipe outer diameter including insulation.22-05-17
Hover Notes:
LV1: • Item costs include all labor, material (including gaskets, bolts, etc.), small equipment (welders, etc.), small tools and consumables (solder, flux, etc.) to install the item.
• Item costs exclude rigging equipment. Refer to (CSI) - MasterFormat® Division 01 - General Requirements for Assembly Items: Construction Aids.
• Cutting and patching work required for the installation or demolition/removal of plumbing systems or components shall be included under the General Trades Division 1 through 14.
• Installation and Demolition/Removal costs assume accessible locations. Removals and/or relocations of adjacent items required for access such as ceilings, walls, MEP systems, etc. to be priced separately.
LV2:
Quantity Book Price Book Total Factor Bid Price
10.00 x $96.12 = $961.20 x 1.2201 = $1,172.76
Contractor's Note:
EST to go through 4 walls per drawings provided and 3x through ceilings
56 4" Steel Square Box - 2-1/8" Deep113249 EA
Knockout Type26-05-46
Hover Notes:
LV2:
LV4: Boxes and covers are priced independently.
Quantity Book Price Book Total Factor Bid Price
10.00 x $97.71 = $977.10 x 1.2201 = $1,192.16
Contractor's Note:
QTY 10 for lights, outlets and switches
57 4" Steel Square Box Plaster or Mud Ring113250 EA
1-Gang or 2-Gang26-05-46
Hover Notes:
LV2:
LV4: Boxes and covers are priced independently.
Quantity Book Price Book Total Factor Bid Price
10.00 x $20.78 = $207.80 x 1.2201 = $253.54
Contractor's Note:
QTY 10 for lights, outlets and switches
Page 26 of 33 01/26/2026
58 Bathroom Exhaust Fan - Commercial111435 EA
Speed Controllable23-34-16
Hover Notes:
LV1: • Item costs include all labor, material (including gaskets, bolts, etc.), small equipment (welders, etc.), small tools and consumables (solder, flux, etc.) to install the item.
• Item costs exclude rigging equipment. Refer to (CSI) - MasterFormat® Division 01 - General Requirements for Assembly Items: Construction Aids.
• Cutting and patching work required for the installation or demolition/removal of HVAC systems or components shall be included under the General Trades Division 1 through 14.
• Installation and Demolition/Removal costs assume accessible locations. Removals and/or relocations of adjacent items required for access such as ceilings, walls, MEP systems, etc. to be priced separately.
LV3: • HVAC Equipment costs exclude balancing, temperature controls, electrical, ductwork, and piping hook-ups (connections) unless stated otherwise. The contractor is responsible for adding these additional items as required.
• Exhaust Fan costs include roof curbs as required.
Quantity Book Price Book Total Factor Bid Price
2.00 x $1,089.95 = $2,179.90 x 1.2201 = $2,659.70
Contractor's Note:
QTY: 2 - per note 19 on DSOW
59 2' X 4' LED Acrylic (TYPE 19) Panel Surface Mount114618 EA
LED Troffers Surface26-51-14
Hover Notes:
Quantity Book Price Book Total Factor Bid Price
8.00 x $600.23 = $4,801.84 x 1.2201 = $5,858.72
Contractor's Note:
QTY of (8) per note #10 on DSOW. (4) per bathroom. Ceiling is GYP board, that's why surface was selected.
60 Duel Technology Wall Mounted Occupancy…