This is a project phasing document for the Phoenix Sky Harbor International Airport (PHX) Base Building and TRACON (P50) Fire Sprinkler Upgrade project managed by the FAA's Terminal Engineering Services. The document includes detailed floor plans showing multiple phases of construction and a comprehensive project schedule.

The project is divided into multiple phases (Phase 0 through Phase 7) with specific work areas designated on each floor. Key components include fire sprinkler installations, ISO valve work, and fire pump replacements in various sections of the facility including the basement, ATCT areas, and technical operations areas. The schedule spans from early 2024 through late 2025, with Phase 0 dependent on fire pump delivery. Critical phases include basement and ATCT fire pump demolition and construction (Phase 0A), various fire sprinkler installations across different building sections (Phases 1-7), and final project testing and punchlist work scheduled for October 2025. The document includes specific timeframes for each phase's pre-construction, site work, completion, and occupancy milestones.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Phoenix Sky Harbor International Airport (PHX) Base Building and TRACON (P50) October 11, 2023 Fire Sprinkler Upgrade Final Design

PROJECT PHASING

UPGRADE FIRE LIFE SAFETY SYSTEM AND LEAK REPAIRS

PHOENIX SKY HARBOR INTERNATIONAL AIRPORT

3500 EAST SKY HARBOR BOULEVARD

PHOENIX, ARIZONA

FEDERAL AVATION ADMINISTRATION

10101 HILLWOOD PARKWAY

FORT WORTH, TEXAS 76177

TERMINAL ENGINEERING SERVICES

AJW-2C11C

FORT WORTH CENTRAL SERVICE AREA

FORT WORTH, TEXAS

Phoenix Sky Harbor International Airport (PHX) Base Building and TRACON (P50) October 11, 2023 Fire Sprinkler Upgrade Final Design

THIS PAGE INTENTIONALLY LEFT BLANK

File details come from the government source that posted it. Updated .