J2_ Specification Volume I.pdf
PDF 10 MB Posted
- Attached to
- B2424 Dorm Construction Renovations Federal contract opportunity
- Solicitation number
- FA448425R0004
About this file
The provided file appears to be titled "J2_ Specification Volume I.pdf" but no actual content from this file was shared to analyze. The associated federal contract opportunity describes a dorm renovation construction project at Building 2424 at Joint Base McGuire-Dix-Lakehurst (JB MDL) in New Jersey for the Department of the Air Force Air Mobility Command, but without access to the specification document itself, I cannot provide details about its specific contents.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Airside Office Park 100 Airside Drive Moon Township, PA 15108
100% Final Design Submission Specifications
Vol. I: Div. 01 – 12
B2424 Dorm Renovations Title I A&E Services Joint Base McGuire-Dix-Lakehurst, NJ
100 Airside Drive Moon Township, PA 15108
02 July 2024
This Page Intentionally Left Blank
Joint Base McGuire-Dix-Lakehurst, NJ B2424 Dorm Renovations
Joint Base McGuire-Dix-Lakehurst, NJ B2424 Dorm Renovations
B2424 Dorm Renovations Joint Base McGuire-Dix-Lakehurst, NJ
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 JBMDL STATEMENT OF WORK
01 14 00 WORK RESTRICTIONS
01 20 00 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 33 00 SUBMITTAL PROCEDURES
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 26 11/20, CHG 4: 08/23 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19, CHG 1: 08/23 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23 QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 05/23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION AND DECONSTRUCTION
02 42 51 11/19 CARPET REMOVAL AND RECLAMATION
02 81 00 11/18 TRANSPORTATION AND DISPOSAL OF
HAZARDOUS MATERIALS
02 83 00 11/18 LEAD REMEDIATION
02 84 16 11/22 HANDLING OF LIGHTING BALLASTS AND
LAMPS CONTAINING PCBs AND MERCURY
02 84 33 11/22 REMOVAL AND DISPOSAL OF
POLYCHLORINATED BIPHENYLS (PCBs)
02 85 00 11/18, CHG 1: 05/22 MOLD REMEDIATION
DIVISION 03 - CONCRETE
03 01 00 02/18 REHABILITATION OF CONCRETE
03 30 53 05/14 MISCELLANEOUS CAST-IN-PLACE CONCRETE
03 45 33 05/16, CHG 1: 11/21 PRECAST STRUCTURAL CONCRETE
DIVISION 04 - MASONRY
04 03 00 11/17 CONSERVATION TREATMENT FOR PERIOD
MASONRY
04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY
DIVISION 05 - METALS
05 05 20 05/22 POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING
05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS
05 52 00 08/23 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY
DOCUMENT PROJECT Page 1
06 41 16.00 10 08/10, CHG 1: 11/18 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABINETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 60 00 08/23 FLASHING AND SHEET METAL
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/23 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
DIVISION 09 - FINISHES
09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 24 23 08/17, CHG 2: 11/18 CEMENT STUCCO
09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD
09 30 10 08/20 CERAMIC TILING
09 62 38 08/17, CHG 1: 08/18 STATIC-CONTROL FLOORING
09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING
09 90 00 02/21 PAINTS AND COATINGS
09 96 00 11/14 HIGH-PERFORMANCE COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.20 08/20 INTERIOR SIGNAGE
10 26 00 08/20 WALL PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
DIVISION 12 - FURNISHINGS
12 21 00 08/17, CHG 2: 11/18 WINDOW BLINDS
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
DIVISION 22 - PLUMBING
22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE
22 07 19.00 40 02/23 PLUMBING PIPING INSULATION
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 15 05/22 COMMON PIPING FOR HVAC
23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
23 11 20 05/20 FACILITY GAS PIPING
23 23 00 08/21 REFRIGERANT PIPING
DOCUMENT PROJECT Page 2
23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION
23 31 13.00 40 08/22 METAL DUCTS
23 37 13.00 40 08/22 DIFFUSERS, REGISTERS, AND GRILLES
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.01 05/21, CHG 1: 08/23 CYBERSECURITY FOR HVAC
FACILITY-RELATED CONTROL SYSTEMS
25 05 11.03 05/21, CHG 1: 08/23 CYBERSECURITY FOR ELECTRICAL
FACILITY-RELATED CONTROL SYSTEMS
25 08 10 05/21 UTILITY MONITORING AND CONTROL SYSTEM
TESTING
25 10 10 02/19, CHG 1: 05/21 UTILITY MONITORING AND CONTROL SYSTEM
(UMCS) FRONT END AND INTEGRATION
DIVISION 26 - ELECTRICAL
26 05 00.00 40 11/20 COMMON WORK RESULTS FOR ELECTRICAL
26 05 26.00 40 08/19 GROUNDING AND BONDING FOR ELECTRICAL
SYSTEMS
26 20 00 08/23 INTERIOR DISTRIBUTION SYSTEM
26 24 16.00 40 08/19 PANELBOARDS
26 27 14.00 20 02/21, CHG 1: 05/21 ELECTRICITY METERING
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
26 56 00 08/21 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 70 08/20 INTERIOR FIRE ALARM SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 08/23 EARTHWORK
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 92 19 08/17, CHG 1: 08/21 SEEDING
DIVISION 33 - UTILITIES
33 11 00 02/18, CHG 2: 11/23 WATER UTILITY DISTRIBUTION PIPING
33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
DOCUMENT PROJECT Page 3
01 00 00 - 1
DIVISION 1
GENERAL REQUIREMENTS
SECTION 01 00 00
STATEMENT OF WORK
PART I - GENERAL
1.01 DESCRIPTION OF WORK:
A. The contractor shall provide all plant, supervision, management, quality control, labor, tools, equipment, appliances and materials and perform all work necessary to...
This project is to address repairs and upgrades to the facilities at B2424, including interior renovations, and exterior repairs and upgrades.
B. This project shall be performed in strict accordance with the specifications and drawings forming parts thereof, subject to the terms and conditions of the contract.
1.02 LOCATION:
Building 2424 is located on Joint Base McGuire-Dix-Lakehurst (JB MDL), NJ.
1.03 PRINCIPAL FEATURES:
A. The work to be performed includes the principal features listed below. This general outline of principal features does not in any way limit the responsibility of the contractor to perform all work and furnish all plant, labor, and material required by the specifications and drawings to perform a complete and permanent job to adequately fulfill the intent of these specifications and to deliver a work product(s) that is fit for its intended purpose. The inspection clause of any resultant contract for this work shall not in any way be interpreted as waiving the Government’s requirement that the work product(s) be fit for its intended purpose. Government inspections do not in any way constitute acceptance of work quality or fitness until the final acceptance inspection is made.
Alterations to the existing facilities include the following:
1. Interior
i. Interior surfaces will be repaired and repainted. The “popcorn” ceilings will be replaced with new gypsum board in all locations. All flooring and bases including vinyl, rubber, carpet, and ceramic tiles will be replaced.
ii. New LED lighting throughout will meet the current UFC lighting levels. See electrical for more information.
iii. Openings:
01 00 00 - 2
Doors including hardware (and frames as needed) will be replaced with new. Keyed locks with dead bolts and lever handles will be installed, no electrified hardware. Door hardware replacement will comply with ADA/ABA standards. Window blinds will be replaced.
iv. Restrooms and Bathrooms:
The Scope of Work (SOW) includes refinished single and shared bathrooms (in dorm rooms) in both the dormitory and common buildings. Wall tiles and substrate will be replaced with new mold-resistant substrate and new tiles. Floor tiles will be replaced with new. Bathroom ceilings will be replaced with new mold-resistant gypsum board. All plumbing fixtures and accessories will be replaced with new. Tubs will be replaced with acrylic shower stalls with tempered glass doors. All plumbing fixtures will be replaced with fixtures that are WaterSense labeled. New exhaust grilles will be in the shower not next to the shower.
v. Common Kitchen:
All cabinetry, countertops, medicine cabinets, accessories and sinks will be replaced with new.
Cabinetry will be plastic laminate-clad and topped with solid surface countertops.
Finishes will only be replaced in the listed spaces. The kitchen layout will be expanded. A gas line will be installed, electric range will be replaced with gas range. A second range/oven will be added.
vi. Second-floor Mailroom:
To be converted into two rooms by removing the existing partition wall and mail slots/boxes. One shall be a telecom room and one shall be a study/lounge room suitable for activities such as yoga.
vii. Laundry Rooms:
Renovated to add a partition behind the machines to shield the utilities, creating a chase. A door will be added to access this chase for maintenance. The opposite walls will be bumped out to compensate for the loss of floor space.
viii. Day Room:
Renovations will include the main space, TV room, kitchen, and restrooms. All finishes, casework, lighting, and accessories will be updated in the kitchen only.
2. Exterior
i. Roof:
Roof gutters and downspouts will be replaced entirely. New Eave detail includes baker plywood construction and metal facia.
ii. Soffits:
Exterior hallway soffits will be replaced to match existing at locations of water damage.
iii. Masonry Repairs:
Capstones at walkways throughout the building will be replaced as well as all flashing and weeps on windows, fenestration headers, and locations where there is water infiltration and/or deterioration. All closed cell backer rod in exterior walls and concrete hallways are to be replaced including all expansion and control joints. Sealants in the windows, doors, exterior walls and concrete hallways will be replaced. Water infiltration problems discovered or observed during the
01 00 00 - 3 site visit will be repaired. Brick masonry will be replaced and repointed where needed. Stains and efflorescence will be cleaned from surfaces.
iv. Existing Stairs to Remain:
Spalling and staining present on the staircases at the ends of each wing are likely due to moisture penetration at the guardrail bracket mounting locations.
Concrete repairs will be done at each column, beam, landing, and stair deficiency and guardrails will be removed and refurbished, brackets will be refurbished and reinstalled using a high-grade anchors and sealers at each connection.
v. Central Stair:
The central exterior precast concrete stair connecting both wings is to be replaced in its entirety.
The central stair has significant cracking and spalling. Cracking is primarily occurring at the horizontal beams and occasionally along the face of the stair runs. Significant cracking is present at the beam-to-column connection supporting the second-floor landing. Cracks are likely due to moisture penetration and possible foundation settlement. Spalling and staining is present primarily at the beam-to-column connection and at each guardrail bracket connection most likely due to water penetration. New stair will be precast concrete replace in kind. Structural requirements for precast delegated design are defined in stair drawings.
vi. New Water Supply:
A new water service connection will be installed along with a vault to provide separate fire and domestic water lines to the existing mechanical room.
3. Utility:
i. Service Meters:
Water, natural gas, and electric meters are to be replaced with “smart meters” and interconnected to provide connection to the base-wide system.
B. Contract Period of Performance is: 360 days.
PART II – NOT USED
PART III – NOT USED
END OF SECTION 01 00 00
AMRS Meter Specifications v.01.23.20 Appendix 3
1.1 AMRS Electric Meter Specifications
The AMRS Compliant Electric Meter shall meet Department of Defense cybersecurity in addition to the following requirements:
• Current Inputs:
• Nominal 5A (Class 0.2s)
• Measured Current: 50mA to 10A
• Withstand: 20A Continuous
• Poly Phase (3 voltages and 3 currents)
• Voltages are verified by testing Line to Neutral Voltages (LN) and Line to Line (LL) or
Phase to Phase (PP) Voltages
• Internal storage for recording 2 values or channels for 90 days, configurable using manufacturer supplied configuration software. Must support interval consumption (15 minute) and demand (15 minute block average)
• Clear and concise manufacturer’s published procedure or method for extracting the internally recorded values, register sets (buffer) or channel data via Modbus and Ethernet
• Shall support time of use recording
• Onboard Ethernet communications, base 10/100 with RJ45 connector or pigtail with receptacle connector
• Modbus/TCP communication protocol is required.
• Front display with ability to display all measured values
• Minimum of two external dry contact inputs that shall count pulses from other devices
• Minimum of one (1) external RS485 serial port
1.2 AMRS Compliant Meter List
The following list of meters were evaluated, meet the AMRS meter specification and shall function within the AMRS platform. All networked devices, their integrated firmware and software will be approved by the PMO for use in the AMRS. PMO approval is contingent upon the device, in its fielded configuration, passing USAF cyber and AMRS compatibility testing.
• Schneider Electric ION 8650
• Schneider Electric ION8600
* (ION8600s currently connected to AMRS only, no new installs due to End-of-Life)
• Schneider Electric PM8000
• Electro Industries Nexus 1272
• Electro Industries Nexus 1262
• Schneider Electric PM5560 series
• Schneider Electric PM800 with PM8ECC network card
* (PM800s currently connected to AMRS only, no new installs due to End-of-Life)
1.3 Meter Installation Guidelines
• Contractor shall assume all existing equipment is working properly. If during the post award survey portion of the SOW an existing piece of equipment is found to be malfunctioning, then the contractor shall bring it to the government's attention to
AMRS Meter Specifications Appendix 3 determine how to proceed. An RFI shall be submitted. This may require a contract change to delete this meter from the scope or to add a new meter.
• All due diligence to survey the existing site conditions is the responsibility of the contractor.
• New and relocated meters shall be installed adjacent to the main distribution panel in a separate enclosure unless otherwise noted
• All new and relocated meter assemblies be located approximately 5 feet above the ground (4 feet minimum -- 6 feet maximum).
• All new meter installations, including relocated existing meters, shall include the installation of new properly sized split or solid core current transformers (CTs). Accurate sizing of new CTs is the responsibility of the contractor.
• If CT installation method includes disturbing the bonds of existing cables or wiring within the gear, before and after IR scans shall be performed before removing and after torqueing the connections to ensure the integrity of the conductor bonds.
• All new meter installations, including relocated existing meters, three phase voltage will be supplied from a three phase breaker/disconnect or fused voltage source which shall be labeled and marked in electrical meters and electrical panels.
• All meter safety disconnect switches shall be marked as follows “Meter Disconnect NOT Service Equipment” per the NEC. In addition, instructions to safely engage the safety disconnect switches and short the CT conductors shall be included inside each meter assembly
• Meter assemblies shall be provided with voltage and current safety disconnect devices or equivalent so that the meter assembly can be worked on safely over the life of the meter installation and not require utility outages for servicing. Additionally, meters shall have control power regardless of breaker position when installed in a split buss switchgear
• In the event communications equipment and/or a metering device has to be located in an exterior location, the NEMA enclosure must be a lockable NEMA 4 enclosure. All new install interior meters are required to be enclosed in a NEMA 3 enclosure unless otherwise noted.
• All new meter installations, including relocated existing meters, shall be connected from the meter, to a RJ45 wall outlet in the mechanical room, to a patch panel in the communications room, and then to the Air Force switch in the communications room.
• Preferred technical approach to network communication cabling in excess of 328 feet is:
Fiber optic cable and fiber media converters with dedicated power supplies. Fiber media converter shall be installed in the communications room within 6 feet of the network switch and within 6 feet of the electric meter enclosure.
• Surge protection is required on all communication cabling extending from the exterior to the interior of a facility. This includes gas meter communication cables from the exterior to the interior of the building. Surge suppression devices shall be installed w/in 3 feet of the building entrance inside the facility unless otherwise noted. Devices shall be easily accessable and labled to aide in location during future troubleshooting efforts.
• Meter assemblies and communication receptacles accessible to the public must be installed in a locked enclosure.
• Electric meters with gas or water meters connected shall have two internal registers configured - one for a raw pulse count and one for a weighted pulse count based on the scaling of the connected gas or water meter.
AMRS Meter Specifications Appendix 3
2.0 AMRS Compatible Gas Meter Specifications
AMRS compatible gas metering solutions consist of a componential system to achieve the goal of delivering gas consumption data into the AMRS. To accurately scale output pulses the contractor shall obtain building gas usage from base personnel, taking into account peak demand when sizing the components that are necessary as well as determining peak pulse rate as to not saturate the receiving device and risk losing captured pulse data. The various components that may be necessary include but are not limited to the following: Gas Meter, Pulse Kit, High Speed Dividing Pulse Relay, Surge Suppression Device, Accumulator, Electric Meter with digital input availability.
• Pulse kit must be able to produce a two-wire (Form A) pulse output via RS485
• Gas meter or attached pulse kit must include a visual register or dial
• Pulse output shall be delivered to a high speed dividing pulse relay that has the capability of producing a wetting voltage if necessary
• High speed dividing pulse relay shall provide isolated pulse outputs (Form A) that shall be delivered to an AMRS compatible electric meter
• Gas meters that can communicate to AMRS via the Modbus/TCP protocol may be acceptable if they can pass technical and cybersecurity evaluations directed by the AMRS PMO. At this time there are no tested or approved Modbus /TCP gas meters
3.0 AMRS Compatible Water Meter Specifications
AMRS compatible water metering solutions consist of a componential system to achieve the goal of delivering water consumption data into the AMRS. To accurately scale output pulses the contractor shall obtain building water usage from base personnel, taking into account peak demand when sizing the components that are necessary as well as determining peak pulse rate as to not saturate the receiving device and risk losing captured pulse data. The various components that may be necessary include but are not limited to the following: Water Meter, Pulse Kit, High Speed Dividing Pulse Relay, Surge Suppression Device, Accumulator, Electric Meter with digital input availability.
• Pulse kit must be able to produce a two-wire (Form A) pulse output via RS485
• Water meter or attached pulse kit must include a visual register or dial
• Pulse output shall be delivered to a high speed dividing pulse relay that has the capability of producing a wetting voltage if necessary
• High speed dividing pulse relay shall provide isolated pulse outputs (Form A) that shall be delivered to an AMRS compatible electric meter
• Water meters that can communicate to AMRS via the Modbus/TCP protocol may be acceptable if they can pass technical and cybersecurity evaluations directed by the AMRS PMO. At this time there are no tested or approved Modbus /TCP water meters
4.0 AMRS Compatible Translation Devices and Accumulators
The following device is compatible with the AMRS platform, is consistent with the need of the existing site conditions, and has been tested and passed cybersecurity requirements:
Schneider Electric EGX150 Ethernet Gateway
JBMDL - STATEMENT OF WORK
Page. 1 of 56
SECTION 01000
GENERAL CONTRACT REQUIREMENTS
1.0 DEFINITIONS:
1.1 Contracting Officer (CO): The Contracting Officer refers to a person with the authority to enter into, administer, change and/or terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the Contracting Officer acting within the limits of their authority as delegated by the Contracting Officer.
1.2 Contracting Officer’s Technical Representative (COTR): The Base Civil Engineer or his authorized representative is designated as the COTR (Construction Manager), for the purpose of technical surveillance and evaluation of the work performed under this contract. This designation in no way authorizes anyone other than the CO to commit the Government to changes in the terms of the contract. The COTR functions include, but is not limited to:
1. Technical administration and review of work in process.
2. Recommending approval/disapproval of shop drawings, samples, and materials.
3. Reviewing and recommending approval/disapproval by the CO all applications for progress payments.
4. Reporting to the CO any work stoppage or discovered non-conforming work items.
5. Recommending destructive testing of work by the Contractor to the CO. Testing materials not otherwise specified to be performed by the Contractor or others.
6. Conducting Pre-Final and Final Acceptance Inspections to develop a recommendation for accepting/not-accepting the work.
1.3 Contract Clauses: Where Special Clauses or General Provisions are referred to in the specifications, reference should be to Contract Clauses.
1.4 Statement of Work (SOW): Written descriptions documenting work required by each Government TO. May be provided by the Government or prepared by the Contractor, depending on the individual TO. Included in the SOW are the specific technical requirements for the project.
1.5 Professional Certification: The process of affixing a seal or statement to a drawing or design document to indicate that the work to which it is affixed has been performed by a person licensed as a professional, in that area of expertise, in the state of New Jersey.
1.6 Color Board: A visual presentation consisting of samples of the various finishes, grouped together based on location within the project. Samples shall be of adequate size to show the full pattern, texture, and color of each item.
1.7 Designer of Record (DOR): The individual accountable for specific portions of the design documents. Where professional certification is required for the design, the DOR would be the individual providing certification for that portion of the design. Where professional certification is not required, the DOR would typically be the individual who provided the design or specifications for a particular aspect of the project (i.e.: architectural, civil, structural, mechanical, or electrical).
Page. 2 of 56
1.8 Direct Design Cost: This cost includes direct engineering design time used to create drawings and specifications for the project.
1.9 Indirect Design Cost: This cost includes site visits and site investigations, administrative support, project manager during design, surveying on site, reproduction of drawings and prints, test soil borings, water flow testing of existing fire hydrants, and meetings with base personnel during design.
2.0 CONTRACT REQUIREMENTS: The Contractor shall furnish all personnel, labor, equipment, tools, materials, supervision, and other items and services necessary to design, manage, and accomplish a broad range of repair, alteration, renovation, upgrade, maintenance, demolition and/or new construction work on various real property facilities. The projects may include tasks in a variety of trades such as earth work, excavation, infrastructure, water distribution system, sanitary sewer, storm drain, electrical, telecommunications, cast-in-place concrete, masonry, structural steel, framing, roofing, carpentry, millwork, painting, plumbing, mechanical (including HVAC), lead and lead based paint abatement/removal, asbestos abatement/removal, site work, road and parking lot paving, airfield pavement, HAZMAT surveys and other specialty and general contracting work.
3.0 CONTRACTOR ORGANIZATION:
3.1 DESIGN AND CONSTRUCTION STAFF: The Contractor shall have available a design and construction staff to respond to the requirements of this type contract. The Contractor’s organizational approach shall integrate with this staff to provide project management, project design/engineering, on-site superintendence, quality control and administration.
3.2 SUBCONTRACTOR: The Contractor shall be responsible for the management and performance of all subcontractors. The Contractor shall ensure construction is completed within the stated requirements.
4.0 PROJECT LOCATION: The primary location of work performed under this contract shall be at Joint Base McGuire-Dix-Lakehurst (JBMDL), New Jersey. JBMDL encompasses approximately 42,030 acres spread out over Burlington County and Ocean County. JBMDL is made up of the McGuire Air Force Base area, the Fort Dix area, and the Naval Air Engineering Station Lakehurst area.
4.1 The Contractor shall conform to all JBMDL regulations and directives, as identified specifically at the pre-construction conference, that pertain to security, safety, traffic, fire, and personnel clearances insofar as they apply to the Contractor’s activities or as directed by the CO. The Contractor shall be responsible for providing and placing barricades, lighting, and safety devices during construction activities.
4.2 The work to be performed under this contract is on an active military base. The Contractor shall coordinate work operations with the COTR prior to starting work under this contract. The Contractor shall have a superintendent who speaks, reads, writes, and understands the English language; has authority to act for the Contractor and to be available on the job site throughout each workday. The Contractor shall be responsible for his quality control at all times. A specific individual shall be designated as the Contractor’s quality control inspector and identified to the COTR at the pre-construction conference.
5.0 WORKING HOURS:
5.1 STANDARD WORKING HOURS: for the Contractor are for the period from 7:30 a.m. to 4:30 p.m., Monday through Friday, excluding Saturdays, Sundays, and Federal Holidays. If the Contractor desires to work during non-standard working hours, on a Standard Working Hours construction order, Page. 3 of 56 additional Government inspection forces may be required. The Contractor shall notify the CO in writing by email, five working days in advance of his/her intention to work during periods other than Standard Working Hours. This notification shall allow the inquiry into the availability of additional Government Inspectors. If the CO confirms that additional Government Inspectors are reasonably available, the CO may authorize the Contractor to perform work during periods other than Standard Working Hours; however, if the Government Inspectors are required to perform in excess of their normal duty days solely for the benefit of the Contractor, the actual cost of inspection at overtime rates may be charged to the Contractor.
5.2 NON-STANDARD WORKING HOURS: shall be outside the definition of the standard working hours and not in controlled areas.
5.3 STANDARD AND NON-STANDARD WORK IN CONTROLLED AREAS: All work in restricted areas is assumed to be within standard working hours. All work inside of controlled areas may be subject to brief delays due to security processing (30 minutes time each process on and off per visit to the controlled area) or interruption to the normal work schedule to permit the completion of mission essential operations. Such interruptions, if required, will be given on short notice and expeditious action will be required. Each interruption may last up to sixty (60) minutes. The Contractor shall not be compensated for said delays.
5.4 BASE ACCESS: JBMDL 87th Security Forces Squadron (SFS) Installation Entry Control procedures will be provided to the Contractor. The Contractor shall abide by all JBMDL requirements for entering and conducting business on JBMDL.
1. The Contractor shall obtain the necessary passes and/or identification for entry into JBMDL for himself, all employees, and subcontractors prior to commencement of work. Procedures and limitations for entry control are addressed in depth in the Installation Entry Control Procedures at the end of this section. The Government reserves the right to refuse to issue a pass to any and all employees of the Contractor for any reason deemed appropriate by the Government and, in doing so, Contractor shall not be entitled to equitable adjustment or relief under the Contract Disputes Act. The Entry Screening Facility may be contacted at (609) 754- 3938/3628/2200 for McGuire or Dix and (732) 323-4000 for Lakehurst. The Government will issue passes depending on the type of work to be completed and the length of the contract.
The maximum length of these passes is 30 days. The Contractor shall be responsible for obtaining additional passes upon the expiration of each pass issued. The Government may inspect, at its discretion, all vehicles, including those with vehicle passes.
2. Prior to entering JBMDL, commercial/over-sized vehicles shall be inspected at Checkpoint 9 located on Saylors Pond Road at the Dix Area of JBMDL for the Dix and the McGuire Areas and from Rt. 547 for the Lakehurst area. The Contractor shall anticipate delays during the inspection process as well as delays due to vehicle queues.
3. Conditions caused by Force Majeure (acts of war, terrorism, nature, etc.) shall be addressed via contract time extension, where warranted, at no cost only. The Contractor shall anticipate that in the event of heightened alert, access to JBMDL may be denied for approximately three to five days. The Contractor shall also anticipate that during periods of heightened alert, time required to access JBMDL may increase.
6.0 SUBMITTALS:
6.1 SUBMITTAL SCHEDULE: For some projects, a material submittal schedule will not be provided by the Government. Solicitation instructions will specify if offerors will be provided a material submittal schedule or if they are to include in their proposal a material submittal schedule. If the requirement for a material submittal schedule is absent from the individual solicitation documents, the following guidelines apply. After award, the Contractor awarded the contract shall complete and submit a material submittal schedule for approval by the Government. The Contractor shall identify all
Page. 4 of 56 planned submittals dates on the schedule. Submit the schedule to the CO within 30 calendar days after contract award or within another agreed to timeframe as directed by the CO.
6.2 SUBMITTAL PROCEDURE: The CO may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal shall include an original AF Form 3000, Material Approval Submittal, and three (3) copies of supporting documentation. When available, the Government may request electronic copies of submittals via email, in lieu of hard copies. The availability and practicality of submitting electronically versus hardcopy will be discussed and agreed to during the initial pre-construction conference after contract award. In general, submittals shall be provided a minimum of 21 calendar days in advance of scheduled purchase to allow satisfactory time for government review. Additionally, unless stated otherwise, submissions on test results and other submissions of that nature shall be made within 14 days, after the work or test is performed. Each submittal shall be complete and in sufficient detail for ready determination of compliance with the contract requirements. Submittal items that are disapproved will be promptly corrected and resubmitted within 10 calendar days by the Contractor. No materials or equipment shall be ordered or installed until submittals are approved by the CO or his/her representative. The approved submittals shall be always available at the job site for inspection by the CO. All submittals involving color selections, patterns and other decorative architectural features shall be submitted at the same time for both interior and exterior materials.
6.3 SUBMITTAL REQUIREMENTS: Units of weights and measures used on all submittals shall be the same as those used in the contract drawings. Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Submittals shall include items such as: Contractor’s work plans / schedules, material submittal register, samples, brochures, manufacturers data, product data sheets, shop drawings and/or certificates of materials (relative to the construction execution), Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; installation procedures and recommendations; templates and other descriptive literature; test reports; test cylinders; samples;
O&M manuals (including parts list); certifications; warranties; and other such required submittals.
Catalog cuts and other descriptive data which may have more than one model or type shall be clearly marked to show the model, type, size, and all optional accessory equipment the Contractor proposes to install. Submittals on component items forming a system or interrelated items shall be submitted at one time as a single submittal in order to demonstrate that the items have been properly coordinated and will function as a unit. For example, for an air conditioning system, the submittals shall be made at the same time for piping, insulation, condensing units, air-handlers, pumps, valves, shop drawings, controls, and other components that make-up the required work feature. Contractor shall plan for and submit all submittals requiring Government approval prior to the acquisition of the material or equipment covered thereby, in accordance with design criteria, specifications and Construction Requirements. If the material submittals provided are in variance from the design criteria and/or contract specifications, the Contractor shall describe such variations in writing at the time of submission and request a variance from the design criteria and/or contract specifications in accordance with the terms and conditions of the contract. Failure to provide such notification will not relieve the Contractor from his responsibility of meeting the design criteria and/or contract specifications regardless of whether or not the submittal is approved by the Government. Material submittals shall be as specified under each specification section. All the material submittals as indicated in the applicable specification section shall be submitted at the same time. If the submittal requirement is listed on the drawings, all material submittals of like work shall be submitted simultaneously along with all corresponding specification sections. A system of standard submittals for each Contractor will be used to minimize the submittal requirement. Failure to submit all material submittals associated with an individual specification section at the same time may be cause for rejection.
6.4 APPROVED EQUAL: The Statement of Work (SOW), drawings and the Technical Provisions of the specifications may, in some instances, refer to certain items of equipment, material, or article by trade name. References of this type shall not be construed as limiting competition but shall be regarded as establishing a standard of quality.
Page. 5 of 56
6.5 SUBMITTAL CLASSIFICATIONS: Submittals are classified as follows:
a) GOVERNMENT APPROVED: Governmental approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as indicated on the Submittal Register or as designated by the CO.
Within the terms of the Contract Clause entitled “Specifications and Drawings for Construction,” they are considered to be “shop drawings”.
b) RE-CERTIFICATION: Contractor shall provide the requested submittals unless otherwise specifically approved by the CO for the submittal in question. If approved and the Contractor intends to use previously approved materials or equipment, a letter certifying the specific material or equipment in lieu of a submittal is acceptable. Certification letter will contain the contract number and approved electronic copies of AF Form 3000 submittal.
c) APPROVED SUBMITTALS: The CO’s approval of submittals shall not be construed as a complete check but will indicate only that the general method of construction, materials, detailed and other information are satisfactory. Approval will not relieve the Contractor of the responsibility for any error that may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work. After submittals have been approved by the CO, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
d) DISAPPROVED SUBMITTALS: The Contractor shall make all corrections required by the CO and furnish a corrected submittal. Corrected submittals shall be submitted within five (5) working days, or as required by the disapproved submittal, after receipt of disapproval, in the form and number of copies specified for the initial submittal. If the Contractor considers any correction indicated on the submittals to constitute a change to the contract, a notice in accordance with the Contract Clause “Changes” shall be given promptly to the CO.
6.6 MATERIAL APPROVAL SUBMITTAL FORM: (AF Form 3000) shall be used. The Contractor shall fill out and submit an electronic Material Approval Submittal (AF Form 3000) for all the equipment and materials that are required to be submitted. Submit the required material submittals and shop drawings to the CO for approval.
6.6.1 Submittal Scheduling: Submittals covering component items forming a system or items that are interrelated shall be scheduled to be coordinated and submitted concurrently. Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of fourteen
(14) calendar days) shall be allowed for review and approval.
6.7 SUBMITTAL REGISTERS (AF FORM 66): Submittal Registers shall be submitted by the Contractor at the time the 90 percent design is submitted or within fourteen (14) calendar days after issuance of the Notice to Proceed and prior to any material processing.
6.8 CONTROL OF SUBMITTALS: The Contractor shall carefully control his procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date.
6.9 GOVERNMENT APPROVED SUBMITTALS: Upon completion of review of submittals and approval by the Government, the submittals will be identified as having received Government approval and dated. One copy of the submittal will be returned to the Contractor.
Page. 6 of 56
7.0 PROJECT COORDINATION:
7.1 WORK SCHEDULE: The Contractor shall coordinate all work schedules with the CO or designated representative and COTR prior to the start of work.
7.2 TEMPORARY CONSTRUCTION: Any Contractor installed temporary construction intended to prevent interruption of normal work activity or loss of utility services is subject to coordination and approval by the 787th CES through the CO.
8.0 PROJECT SCHEDULES AND REPORTS:
8.1 PROJECT SCHEDULE AND PROGRESS REPORT: The progress schedules and reports for this contract shall be prepared using AF Form 3065 (Progress Report) in electronic format. Progress reports shall be prepared for all projects with performance times over 60 days. The submitted schedule must breakdown the project into distinct tasks, show which tasks will be accomplished simultaneously, and indicate the critical path. The purpose of the submitted project schedule is to aid in the determination of the construction period.
9.0 MEETINGS AND CONFERENCES:
9.1 PRE-CONSTRUCTION CONFERENCE: The CO or designated representative will schedule a meeting attended by designated representatives of the Government, the Contractor and customer after project award but before the start of work to discuss all aspects of the required work.
9.2 COORDINATION MEETING: After the Pre-construction Conference, before start of construction, and prior to acceptance by the Government of the Quality Control Plan, the Contractor shall meet with the CO or his/her authorized representative to discuss the Contractor's quality control system. During the meeting, a mutual understanding of the quality control system details shall be developed, including the forms for recording the CQC operations, control activities, testing, administration of the system for both on-site and off-site work, and the interrelationship of Contractor's management and control with the Government's quality assurance. Minutes of the meeting shall be prepared by the Contractor, approved, and signed by both the CO and 787th CES representative. The minutes shall become a part of the contract file. There may be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the CQC system or procedures that may require corrective action by the Contractor.
9.3 SAFETY ASSURANCE:
9.3.1 Safety Meeting: The Contractor shall keep a Safety Meeting log of weekly meetings held with his /her employees on Safety and the government has the right to inspect it at any time.
Representatives of the Contractor shall meet with the CO and his/her representative(s) prior to the start of repair, alteration, or construction activities for the purpose of reviewing the Contractor's safety and health programs and discussing implementation of all safety and health provisions pertinent to the work to be performed under the contract. The Contractor shall be prepared to discuss, in detail, the measures he/she intends to take in order to control any unsafe or unhealthy conditions associated with the work to be performed under the contract. This meeting may be held in conjunction with the pre-construction conference, if so directed by the CO. The conduct of this meeting is not contingent upon a general pre-construction meeting. The level of detail for the safety meeting is dependent upon the nature of the work and the potential inherent hazards. The Contractor's principal on site representative(s), the general superintendent, and his/her safety representative(s) shall attend this meeting.
9.3.2 Requirement for Safety Coordination: The 787th CES shall be the determining office for each
Page. 7 of 56 design requiring coordination with other safety offices, such as JBMDL Safety Office, Environmental, etc.
9.3.3 Contractor shall provide an accident prevention plan for the contract wide effort within 10 days of award of this contract. Project requires specific activity hazard analysis be submitted within 10 days of NTP and a hard copy provided at the kick-off meeting.
10.0 AUTHORITY: the term “CO” as used in this specification includes the authorized representative of the CO acting within the limits of his/her authority. With respect to all paragraphs of the specifications citing “approval by the CO” and all paragraphs cited in Material Approval Submittals, of the solicitation, the term “CO” means only those individuals properly appointed as a CO within the Contracting Squadron; no other Government personnel has the authority to grant such approval. The COTR has authority to review Material Submittal packages and recommend approval by the CO. At the Final Acceptance Inspection, the COTR will perform the inspection and recommend acceptance or conditional acceptance to the CO.
END OF SECTION
Page. 8 of 56
SECTION 01100 GENERAL
SITE REQUIREMENTS
1.0 REGULATIONS:
1.1 The Contractor shall comply with all applicable Federal, State, Local, Air Force, Army, and DOD regulations, including supplements pertaining to safety, traffic control, and fire prevention.
2.0 STANDARD PRODUCTS:
2.1 Materials and equipment shall be standard products of a manufacturer regularly engaged in the manufacture of-such products, which are of a similar material, design, and workmanship. The standard products shall have been in satisfactory commercial and/or industrial use for 2 years prior to use. The 2-year use shall include applications of equipment and materials under similar circumstances and of similar size. The 2-year experience must be satisfactorily completed by a product that has been sold or is offered for sale on the commercial market through advertisements, manufacturers' catalogs, or brochures. Products having less than a 2-year field service record will be acceptable, if a certified record of satisfactory field operation, for not less than 6,000 hours exclusive of the manufacturer's factory or laboratory tests, can be shown and approved by the Government. The Contractor shall not purchase "close-out" products that are being discontinued by the manufacturer.
2.2 Recovered Materials Procurement: In accordance with Executive Order 13514 the Contractor shall use sustainable environmental materials, including acquisition of bio-based, environmentally preferable, energy- efficient, water-efficient, and recycled-content products. The materials shall be non-ozone depleting and non- toxic odorless products, where such products and services meet project performance requirements. The applicable materials are given by the U.S. EPA Comprehensive Procurement Guidelines and the USDA Bio Preferred Catalog. Determination of feasibility of using these materials shall be in accordance with FAR 23.405(c).
2.3 The Contractor shall provide the Government with a list of locally available sustainable environmental materials as listed by the U.S. EPA Comprehensive Procurement Guidelines in the Construction Products and Landscaping Products categories as well as the USDA Bio Preferred Catalog for the life of the contract. The list shall be furnished to the CO no later than 30 days of contract award. Additionally, it shall be updated as requested by the CO.
3.0 SAFETY:
3.1 All work shall be accomplished in accordance with the current U.S. Army Corps of Engineers "Safety and Health Requirements Manual", (USACE EM 385-1-1); Occupational Safety and Health Act (OSHA 29 CFR 1910, OSHA 29 CFR 1926)) standards; applicable Air Force Occupational Safety and Health (AFOSH) Standards; National Safety Council, Accident Prevention Manual for Industrial Operations; applicable federal, state, and local safety operating procedures; and current JBMDL safety regulations. The prime Contractor shall be held responsible to ensure that his/her workforce and any subcontractor or supplier workforce comply with the above safety requirements.
Page. 9 of 56
3.2 Load Handling: Load Handling Equipment (LHE):
1. Equip cranes and derricks as specified in EM 385-1-1, Section 16.
2. Submit to the Government Project manager / QAR/ COR 60 working days in advance of any LHE entering the activity, in accordance with EM 385-1-1, Section 16.A.02, so that necessary quality assurance spot checks, and Airfield Crane Waiver can be coordinated. Include in the submission all crane and operator certificates and details, as well as the expected height of the boom and the GPS coordinates of the expected crane position during use. Contractor's operator must remain with the crane during the spot check. Rigging gear must comply with OSHA, ASME B30.9 Standards safety standards.
3. Comply with the LHE manufacturer's specifications and limitations for erection and operation of cranes and hoists used in support of the work. Perform erection under the supervision of a designated person (as defined in ASME B30.5). Perform all testing in accordance with the manufacturer's recommended procedures.
4. Comply with ASME B30.5 for mobile and locomotive cranes, ASME B30.22 for articulating boom cranes, ASME B30.3 for construction tower cranes, ASME B30.8 for floating cranes and floating derricks, ASME B30.9 for slings, ASME B30.20 for below the hook lifting devices and ASME B30.26 for rigging hardware.
5. Under no circumstance must a Contractor make a lift at or above 90 percent of the cranes rated capacity in any configuration.
6. When operating in the vicinity of overhead transmission lines, operators and riggers must be alert to this special hazard and follow the requirements of EM 385-1-1 Section 11, and ASME B30.5 or ASME B30.22 as applicable.
7. Do not use crane suspended personnel work platforms (baskets) unless the Contractor proves that using any other access to the work location would provide a greater hazard to the workers or is impossible. Do not lift personnel with a line hoist or friction crane. Additionally, submit a specific AHA for this work to the Contracting Officer. Ensure the activity and AHA are thoroughly reviewed by all involved personnel.
8. Inspect, maintain, and recharge portable fire extinguishers as specified in NFPA 10, Standard for Portable Fire Extinguishers.
9. All employees must keep clear of loads about to…