J04-SOW Enoree RD Road Maintenance 2024.pdf

PDF 97 KB Posted

Attached to
Francis Marion & Sumter National Forests Roads Maintenance, Repairs & Construction IDIQ
Solicitation number
12445224B0007
Issued by

About this file

This document is a Statement of Work (SOW) for the Enoree Ranger District 2024 Road Maintenance and Repair contract. The SOW outlines the scope of work, which includes road grading and mowing on the Enoree Ranger District of the Sumter National Forest. The contractor is required to provide all necessary personnel, equipment, and supplies to perform the work. Key requirements include public safety and traffic control measures, coordination of work activities with the Contracting Officer's Representative, and documentation of work through daily accomplishment reports and a quality control plan.

The SOW is related to a federal contract opportunity for a Multiple Award Task Order Contract (IDIQ) for maintenance, repair, and construction of roads within the Francis Marion and Sumter National Forests in South Carolina. The IDIQ has a ceiling of $10,000,000 and the majority of task orders are expected to be valued under $150,000. This is a 100% Small Business Set-Aside with a primary NAICS code of 237310 Highway, Street, and Bridge Construction. The Request for Proposal is due on Friday, June 7, 2024, and site visits are scheduled for May 14-16, 2024.

View the file

Other files

File Type Posted
J19-Enoree Work List Revised (05292024).pdf PDF
J18-Enoree Schedule of Items (SOI) Revised (05292024).pdf PDF
Amd 0002 - 12445224B0007 (05292024).pdf PDF
J18-Enoree Schedule of Items (SOI) Revised (05172024).pdf PDF
J20-MATOC FMS Roads Past Performance Questionnaire Revised (05172024).pdf PDF
Amd 0001 - 12445224B0007 (05172024).pdf PDF
J19-Enoree Work List Revised (05172024).pdf PDF
J11-Schedule of Items (SOI) Francis Marion RD.pdf PDF
J06-Work List Enoree RD.pdf PDF
J13-Wage Determination SC20240034_01052024 (Berkeley County).pdf PDF
SF1442 - Solicitation 12445224B0007 (w_clauses).pdf PDF
J01-MATOC FM and S Roads Maintenance SOW.pdf PDF
J02-MATOC FM and S Roads Maintenance Specifications.pdf PDF
J09-Work List Andrew Pickens RD.pdf PDF
J17-MATOC FM and S Roads Past Performance Questionnaire.pdf PDF
J12-Work List Francis Marion RD.pdf PDF
J08-Schedule of Items (SOI) Andrew Pickens RD.pdf PDF
J05-Schedule of Items (SOI) Enoree RD.pdf PDF
J10-SOW Francis Marion RD Road Maintenance 2024.pdf PDF
J16-MATOC FM and S Roads Experience Questionnaire.pdf PDF
J14-Wage Determination SC20240039_01052024 (Oconee County).pdf PDF
J15-Wage Determination SC20240040_01052024 (Newberrie County).pdf PDF
J07-SOW Andrew Pickens Road Maintenance 2024.pdf PDF
J03-MATOC FM and S Roads Potential Supplemental Specs.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Enoree Ranger District 2024 Road Maintenance and Repair

STATEMENT OF WORK

C.1 Scope of Contract

A. This solicitation and resulting contract is for maintenance and repair of Forest Service roads on the Enoree Ranger District of the Sumter National Forest. Work includes road grading and mowing.

B. The Contractor shall furnish the necessary personnel, material, equipment, facilities, supervision, transportation, operating supplies, and incidentals to perform contract work.

C. District maps are available at the Enoree Ranger District Office, 20 Work Center Road Whitmire, SC 29178. The Government will supply the contractor with 2 copies of the administrative district map.

A PDF copy of the map can be supplied for the contractor to print additional copies at their own expense.

C.2 Public Safety and Traffic Control

A. The Contractor shall exercise caution and care while pursuing the work to prevent unnecessary conflict with, or potential hazards to, road users or others within the work area.

B. The Contractor is to pursue all work on site in accordance with all Federal, State and Local laws governing the transportation and work being performed.

C. The Contractor will post warning signs on each end of the section of road being worked. Signs are to be of the size, quantity, and colors as required in the current edition of the 11 Manual on Uniform

Traffic Control Devises", (MUTCD). A copy of MUTCD is located at the District Rangers Office and may be made available to the Contractor for in office reference on request. These signs shall be moved as needed to properly delineate and identify the section of the road being maintained. At no time shall these signs be more than two miles from operating equipment and shall be in place only when road equipment or persons are performing operations. All slow-moving equipment is to have a reflectorized

"slow moving" vehicle emblem properly attached.

D. All work is to be scheduled so that at the end of a working day, the road is passable for the type of traffic normally using the road. If for any reason traffic hazards (segments of unfinished work which may present a hazard to road users, such as rolls of surface material, berms on the shoulder, etc.) are left in or adjacent to the road after normal working hours, the work is to be properly signed as hazardous and visibly illuminated at night.

C.3 Coordination of Work

A. The Contractor shall inform the Contracting Officer's Representative (COR) of their proposed operating schedule on a weekly basis to facilitate timely inspections.

Enoree Ranger District 2024 Road Maintenance and Repair

B. The Contractor shall complete all maintenance required for one road before starting another road. Contractor shall inform the COR of each road completed.

C. At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly supervise the work or assign and have on the work site a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the

Contractor. The superintendent shall be designated in writing to the Contracting Officer prior to the commencement of work.

D. The Contractor's proposed equipment shall be made available for inspection prior to award of the contract. If at any time during this contract the equipment is deemed unsatisfactory, the Contracting

Officer may order removal and may require a satisfactory replacement, at Contractor's expense.

Replacement equipment, if ordered, is to be onsite and working within 48 hours.

E. Any movement or transportation of equipment to or from work areas required to pursue the work on designated roads, to repair or replace equipment, or for the Contractor's convenience shall be at the Contractor's expense.

C.4 Documentation of Work

A. Accomplishment Reports

The Contractor shall maintain records of accomplishments using the Daily Accomplishment Report

(Exhibit C). These records are to be delivered to the COR monthly with an invoice for the services rendered that month and shall become the property of the Government. No payment will be made prior to receipt of these records and acceptance of the work performed.

B. Quality Control Plan

The Contractor shall submit to the CO, a Quality Control Plan (QCP) as part of their technical proposal that will detail the methods the Contractor will use to perform self-inspection to ensure the requirements of this contract are performed in accordance with the contract documents. The QCP shall at a minimum record the reference pay item, location, frequency, type of test and resulting outcome.

QCPs shall be submitted with the Accomplishment Report and no payment will be made prior to receipt of these records and acceptance of the work performed.

C. Quality Assurance Surveillance Plan:

This Quality Assurance Surveillance Plan (QASP) has been developed pursuant to the requirements of the Performance Work Statement (PWS) for this contract. This plan sets forth procedures and guidelines that will be used in evaluating the technical performance of the Contractor.