J01e Infection Control Risk Assessment Permit.pdf

PDF 222 KB Posted

Attached to
PIMC Pharmacy, ATS & Standpipe Federal contract opportunity
Solicitation number
75H701-25-R-00029
Issued by
Department of Health and Human Services Indian Health Service

About this file

The document is an Infection Control Risk Assessment (ICRA) Permit template used to assess and mitigate infection risks during construction or renovation projects in healthcare settings. The template provides a comprehensive matrix categorizing risk levels (Low, Medium, High, Highest) and project types (Type A, B, C, D) with corresponding infection control requirements and mitigation strategies across four risk classes (Class I-IV).

The form details specific protocols for each risk class, including dust control, HVAC system isolation, critical barrier implementation, negative air pressure maintenance, personnel protective measures, and post-construction cleaning procedures. Key requirements include minimizing dust generation, using HEPA-filtered equipment, sealing work areas, requiring shoe covers and protective clothing, maintaining negative air pressure, and ensuring thorough environmental cleaning before removing construction barriers. The matrix helps healthcare facilities systematically manage infection risks during construction and renovation activities by providing a structured approach to infection control based on the specific type and risk level of the project.

View the file

Other files for this federal contract opportunity

Other files attached to PIMC Pharmacy, ATS & Standpipe, newest first.
File Type Posted
J02 WD AZ20250039 Mod 8 2025.08.29.pdf PDF
B05 Amendment A00006 to 75H701-25-R-00029 2025.09.08.pdf PDF
B01 RFP 75H701-25-R-00029 (Conformed thru A00006).pdf PDF
J01b Drawings - PIMC Pharmacy ATS Standpipe w-Addendum 1 2025.09.04.pdf PDF
J01a Specifications - PIMC Pharmacy ATS Standpipe w-Addendum 1 2025.09.04.pdf PDF
J01g Addendum 01.pdf PDF
B05 Amendment A00005 to 75H701-25-R-00029 2025.08.28.pdf PDF
B01 RFP 75H701-25-R-00029 (Conformed thru A00005).pdf PDF
B05 Amendment A00004 to 75H701-25-R-00029 2025.08.20.pdf PDF
B05 Amendment A00003 to 75H701-25-R-00029 2025.08.19.pdf PDF
B05 Amendment A00002 to 75H701-25-R-00029 2025.08.11.pdf PDF
B05 Amendment A00001 to 75H701-25-R-00029 2025.07.31.pdf PDF
J02 WD AZ20250039 Mod 6 2025.07.25.pdf PDF
J01c Location Map.pdf PDF
J01d Preliminary Commissioning Plan - PIMC Inpatient Pharmacy.pdf PDF
J01f Above Ceiling Work Permit.pdf PDF
J04 2025 Exemption Letter for a Qualifying Hospital.pdf PDF
J01a Specifications - PIMC Pharmacy ATS Standpipe 2025-04-25.pdf PDF
J01b Drawings - PIMC Pharmacy ATS Standpipe 2025-04-25.pdf PDF
J04a FORMS_TPT_5000HC_11228.pdf PDF
J06 PPQ.pdf PDF
J07 IHS IEE Representation Form.pdf PDF
J08 OF 306 Declaration for Federal Employment.pdf PDF
J05 Company Specialized Experience Form Construction.pdf PDF
J09 Addendum to OF-306 (Childcare Form).pdf PDF
B01 RFP 75H701-25-R-00029 PIMC Pharmacy ATS Standpipe.pdf PDF
J02 WD AZ20250039 Mod 5 2025.07.04.pdf PDF
J03 Self Performed Calculation Sheet.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Infection Control Risk Assessment

(ICRA)

Infection Control Risk Assessment Permit

Work Location/Description:

Start Date End Date:

Project Manager Name / Phone Number :

TYPE A:

TYPE B:

TYPE C:

TYPE D:

Low Risk Identify Any Adjacent High Risk Areas:

Above Below Front Behind

Lateral

NA

Medium Risk

High Risk Highest Risk

CLASS 1 1 Minimize raising dust from construction operations 2 Immediately replace any ceiling tile displaced for visual inspection.

1 Minor demolition for remodeling.

CLASS II 1 Minimize raising dust by water misting work surfaces to control dust while cutting.

2 Seal unused doors with duct tape.

3 Block off and seal air vents with plastic or impervious material.

4 Wipe surfaces with cleaner/disinfectant.

5 Isolate HVAC system in areas where work is being performed

1 Contain construction waste prior to transport in tightly covered containers.

2 Wet mop and/or vacuum with HEPA-filtered vacuum prior to leaving area.

3 Remove critical barrier(s) carefully to minimize spread of dirt/debris.

4 Use hospital-approved disinfectant 5 Place dust mat at entrance and exit of work area.

7 Restore HVAC when work completed.

CLASS III 1 Infection control permit prior to construction.

2 Isolate HVAC system in area of work to prevent contamination of the duct system.

3 Complete all critical barriers or implement control cube or other method prior to work.

4 Maintain negative air pressure within work environment with HEPA-equipment.

5 Do not remove barriers from site until completed project is checked by infection Control.

6 Environmental Services thoroughly cleans.

1 Vacuum work with HEPA-filtered vacuum.

2 Wet mop with hospital approved cleaner/disinfectant.

3 Remove barrier materials carefully to minimize spread of dirt/debris.

4 Contain construction waste prior to transport in tightly covered containers.

5 Cover transport receptacles or carts.

6 Tape coverings.

7 When complete, restore HVAC system where work was performed.

CLASS IV 1 Obtain Infection Control permit prior to start of construction.

2 Isolate HVAC system in work area to prevent contamination of duct system.

3 Complete all critical barriers or use control cube method prior to start of construction.

4 Maintain negative air pressure within work site – utilizing HEPA-equipped air filtration units.

5 Seal holes, pipes, conduits, and punctures.

6 Construct anteroom and require all personnel to pass through this room so they can be vacuumed off using a HEPA vacuum cleaner before leaving work site, or wear protective paper coveralls (bunny suit) that is removed each time leaving the work site.

7 Require all personnel entering work site to wear shoe covers.

1 Do not remove barriers from work site until project is checked by Infection Control; and is thoroughly cleaned by environmental services.

2 Vacuum work area with HEPA-filtered vacuums.

3 Wet mop with hospital–approved disinfectant.

4 Remove barrier(s) carefully to minimize spread of dirt/debris associated with construction.

5 Contain construction waste prior to transport in tightly covered containers.

6 Cover transport receptacles or cart.

7 Tape coverings.

8 At completion, restore HVAC system where work was performed.

Permit Requested By Signature / Date Infection Control Signature / Date

1 | P a g e

Class Determination

RISK GROUP TYPE A TYPE B TYPE C TYPE D

LOW Risk Class 1 Class II Class II Class III/IV MEDIUM Risk Class 1 Class II Class III Class IV HIGH Risk Class 1 Class II Class III/IV Class IV HIGHEST Risk Class II Class III/IV Class III/IV Class IV

Risk Groups Low Risk Office areas, Maintenance, Housekeeping, Storage Areas, Stairwells, Storage buildings, Warehouse, Library, Meeting Rooms, Staff Lounges, Empty Patient Rooms

Medium Risk Clinical areas, Physical Therapy, Radiology, Dental, Behavioral Health, Same Day Surgery, Outpatient Services, Cafeteria, Snack Bar

High Risk Emergency Room, Laboratories, Pharmacy, Occupied Patient Rooms, Inpatient Departments, Food Preparation Areas, Nursery, PACU, Above Ceiling Work in Open Interstitial Space within 100 Linear Feet of Group III/IV, Labor and Delivery, Medication Rooms.

Highest Risk Sterile Areas, Segregated Compound Area (IV Room), Containment Segregated Compounding Area (Chemo), Airborne Isolation, Positive Pressure Rooms, Sterile Supply, Operating Rooms, C-Section Operating Rooms, Endoscopy, Intensive Care, Oncology Infusion.

Project Type TYPE A Inspection and non-invasive activities

• Removal of ceiling tiles for visual inspection only ( limited to one tile per 50 square feet)

• Painting, not sanding

• Wallcovering, electrical trim work, minor plumbing, and activities that do not general dust or require cutting of walls or access to ceiling other than for visual inspection

• Do not work in occupied patient rooms

TYPE B Small-scale, short duration activities that create minimal dust

• Installation of telephone and computer cabling

• Access to chase spaces

• Cutting of walls or ceiling where dust migration can be controlled

TYPE C Work that generates moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies

• Sanding of walls for painting or wall coverings

• Removal of floor covering, ceiling tiles, and case work

• New wall construction

• Minor duct work or electrical work above ceiling

• Major cabling activities

• Activities that cannot be completed in a single work shift

TYPE D Major demolition and construction projects

• Activities that require consecutive work shifts

• Required heavy demolition or removal of a complete cabling system

• New Construction

2 | P a g e