J01b Specification.pdf

PDF 2 MB Posted

Attached to
Gallup Indian Medical Center (GIMC) Fire Alarm Upgrade – Construction (Gallup, NM)
Solicitation number
75H70126R00010
Issued by

About this file

This document is a detailed technical specification for a Fire Alarm System installation at the Gallup Indian Medical Center (GIMC) in Gallup, New Mexico. The specification provides comprehensive requirements for an advanced modular addressable fire alarm system, including a management station, control panel, notification appliances, and network communications infrastructure. Key technical specifications include support for up to 252 intelligent devices per loop, multi-criteria fire detectors with advanced signal analysis, digital voice evacuation capabilities, and integration with building automation systems. The system must meet UL 864 standards and NFPA 72 requirements, with features like remote connectivity, event logging, and multi-level user access rights.

The procurement is a 100% Indian Small Business Economic Enterprise (ISBEE) set-aside under NAICS code 236220, with a project magnitude between $1,000,000 and $5,000,000. The contract will be a Firm Fixed Price (FFP) with a 180-calendar day performance period. The solicitation (75H70126R00010) is issued by the Indian Health Service (IHS) and will be evaluated using Lowest Price Technically Acceptable (LPTA) criteria. Eligible businesses must have an average annual revenue under $45 million for the past five years. The project involves a complete redesign and construction installation of a fire alarm system at the Gallup Indian Medical Center located at 516 E Nizhoni Blvd, Gallup, NM 87301.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Final Construction Documents

12/6/2024

GIMC CAMPUS

FIRE ALARM SYSTEM

26 0000 - 1 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 1

SECTION 260000 - SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes supplementary general requirements for the following :

1. Codes and Standards

2. Conflicting Requirements

3. Specifications and Drawing Conventions

4. Work Restrictions

5. Fees, Permits, and Inspection

6. Submittals

7. Products

8. Warranties

9. Electrical License Requirement

10. Operation and Maintenance Manuals

11. Record Drawings

12. Owner Training

13. Demolition, Salvage, and Waste

14. General Coordination for Electrical Work

15. Cutting and Patching

16. Excavation and Trenching

17. Painting

18. Continuity Tests

1.3 DEFINITIONS

A. General: Basic Contract definitions are included in the Conditions of the Contract.

B. "Approved": When used to convey Engineer's action on Contractor's submittals, applications, and requests, "approved" is limited to Engineer's duties and responsibilities as stated in the

Conditions of the Contract.

C. "Directed": A command or instruction by Engineer. Other terms including "requested,"

"authorized," "selected," "required," and "permitted" have the same meaning as "directed."

D. "Indicated": Requirements expressed by graphic representations or in written form on

Drawings, in Specifications, and in other Contract Documents. Other terms including "shown,"

"noted," "scheduled," and "specified" have the same meaning as "indicated."

E. "Regulations": Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and rules, conventions, and agreements within the construction industry that control performance of the Work.

26 0000 - 2 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 2

F. "Furnish": Supply and deliver to Project site, ready for unloading, unpacking, assembly, installation, and similar operations.

G. "Install": Operations at Project site including unloading, temporarily storing, unpacking, assembling, erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations.

H. "Provide": Furnish and install, complete and ready for the intended use.

I. "Project Site": Space available for performing construction activities. The extent of Project site is shown on Drawings and may or may not be identical with the description of the land on which Project is to be built.

J. Products: Items obtained for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material,"

"equipment," "system," and terms of similar intent.

1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation shown or listed in manufacturer's published product literature, that is current as of date of the Contract Documents.

2. New Products: Items that have not previously been incorporated into another project or facility. Products salvaged or recycled from other projects are not considered new products.

3. Comparable Product: Product that is demonstrated and approved through submittal process to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.

K. Basis-of-Design Product: A product in which a specific manufacturer's product is named on the drawings or is accompanied by the words "basis-of-design product" in the specifications, including make or model number or other designation, to establish the significant qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics for purposes of evaluating comparable products of additional manufacturers named in the specification.

L. Action Submittals: Written and graphic information and physical samples that require

Engineer's responsive action. Action submittals are those submittals indicated in individual

Specification Sections as "action submittals."

M. Informational Submittals: Written and graphic information and physical samples that do not require Engineer's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual

Specification Sections as "informational submittals."

N. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another computer over a network and that serves as the basis for standard Internet protocols. An FTP site is a portion of a network located outside of network firewalls within which internal and external users are able to access files.

O. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.

26 0000 - 3 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 3

P. Construction Waste: Building and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.

Q. Demolition Waste: Building and site improvement materials resulting from demolition or selective demolition operations.

R. Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having jurisdiction.

S. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in another facility.

T. Salvage and Reuse: Recovery of demolition or construction waste and subsequent incorporation into the Work.

U. System: An organized collection of parts, equipment, or subsystems united by regular interaction.

V. Subsystem: A portion of a system with characteristics similar to a system.

W. Cutting: Removal of in-place construction necessary to permit installation or performance of other work.

X. Patching: Fitting and repair work required to restore construction to original conditions after installation of other work.

1.4 ABBREVIATIONS AND ACRONYMS

A. Industry Organizations: Where abbreviations and acronyms are used in Specifications or other

Contract Documents, they shall mean the recognized name of the entities in the following list.

Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.

AIA American Institute of Architects (The) (800) 242-3837 www.aia.org (202) 626-7300

ANSI American National Standards Institute (202) 293-8020 www.ansi.org

ASHRAE American Society of Heating, Refrigerating and Air-

Conditioning Engineers

(800) 527-4723 www.ashrae.org (404) 636-8400

ASME ASME International (800) 843-2763

(American Society of Mechanical Engineers International) (973) 882-1170 www.asme.org

ASTM ASTM International (610) 832-9500

(American Society for Testing and Materials International)

26 0000 - 4 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 4

www.astm.org

AWS American Welding Society (800) 443-9353 www.aws.org (305) 443-9353

CSI Construction Specifications Institute (The) (800) 689-2900 www.csinet.org (703) 684-0300

ISO International Organization for Standardization 41 22 749 01 11 www.iso.ch

NEMA National Electrical Manufacturers Association (703) 841-3200 www.nema.org

NFPA NFPA (800) 344-3555

(National Fire Protection Association) (617) 770-3000 www.nfpa.org

UL Underwriters Laboratories Inc. (877) 854-3577 www.ul.com (847) 272-8800

USGBC U.S. Green Building Council (800) 795-1747 www.usgbc.org

B. Code Agencies: Where abbreviations and acronyms are used in Specifications or other

Contract Documents, they shall mean the recognized name of the entities in the following list.

Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.

ICC International Code Council (888) 422-7233 www.iccsafe.org

C. Federal Government Agencies: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the entities in the following list. Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.

EPA Environmental Protection Agency (202) 272-0167 www.epa.gov

FCC Federal Communications Commission (888) 225-5322 www.fcc.gov

NIST National Institute of Standards and Technology (301) 975-6478 www.nist.gov

OSHA Occupational Safety & Health Administration (800) 321-6742 www.osha.gov (202) 693-1999

26 0000 - 5 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 5

D. Standards and Regulations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the standards and regulations in the following list. Names, telephone numbers, and Web sites are subject to change and are believed to be accurate and up-to-date as of the date of the Contract Documents.

ADAAG Americans with Disabilities Act (ADA) (800) 872-2253

UFAS Uniform Federal Accessibility Standards (800) 872-2253

Available from Access Board (202) 272-0080 www.access-board.gov http://www.arkansasbuildingauthority.com

1.5 CODES AND STANDARDS

A. All materials and workmanship shall comply with all applicable codes, specifications, local ordinances, industry standards and utility company regulations. Where specific code requirements apply, they shall be included in the job, whether or not specifically shown or elsewhere specified.

B. Applicable codes and standards shall include all state laws, local ordinances, utility company regulations, and the applicable requirements of the following adopted codes and standards.

1. Building Codes for New Mexico

a. New Mexico Commercial Building Code 2021 (International Building code (IBC

2021)

b. New Mexico Energy Conservation Code 2021 (International Energy Conservation

Code (IECC 2021)

c. New Mexico Existing Building Code 2021 (International Existing Building Code

(IEBC 2021)

d. New Mexico Boiler Code, Latest Edition

e. New Mexico Medical Gas and Certification Code, Latest Edition

f. New Mexico Electrical Code 2020 (National Electrical Code 2020)

g. New Mexico Electrical Safety Code 2017 (National Electrical Safety Code 2017)

h. New Mexico Plumbing Code 2021 (Uniform Plumbing Code (UPC 2021

i. New Mexico Mechanical Code 2021 (Uniform Mechanical Code (UMC 2021)

j. International Fire Code 2021

k. NFPA Life Safety Code 101, 2021

l. American National Standard: 2009 Accessible and Usable Building and Facilities, ICC/ANSI A117.1

m. Applicable Local Jurisdictive Requirements and Codes

1.6 CONFLICTING REQUIREMENTS

A. Conflicting requirements: If compliance with standards, codes, regulations, and specifications establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer conflicting requirements that are different, but apparently equal, to Engineer for a decision before proceeding.

B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits.

To comply with these requirements, indicated numeric values are minimum or maximum, as

26 0000 - 6 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 6

appropriate, for the context of requirements. Refer uncertainties to Engineer for a decision before proceeding.

1.7 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the

Work of all Sections in the Specifications.

1.8 COORDINATION

A. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.

3. Keynoting: Materials and products are identified by reference keynotes referencing

Specification Section numbers found in this Project Manual.

1.9 WORK RESTRICTIONS

A. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify Owner not less than 30 days in advance of proposed utility interruptions.

2. Obtain Owner's written permission before proceeding with utility interruptions.

3. Hours for Utility Shutdowns: after 10:00 p.m and before 6:00 a.m

1.10 FEES, PERMITS, AND INSPECTIONS

A. This Contractor shall be responsible for all costs incurred by any serving utility, municipal authority, and/or Owner for the relocation, removal, and installation of temporary or new services.

B. The Contractor shall be responsible for coordinating and providing the exact service equipment and installation methods with the serving utility, municipal authority, and/or Owner prior to bidding. Failure to do so will not constitute sufficient grounds for an authorized change order to the project.

26 0000 - 7 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 7

1.11 SUBMITTAL SCHEDULE

A. Submittal Schedule: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Engineer and additional time for handling and reviewing submittals required by those corrections.

1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and

Contractor's construction schedule.

2. Initial Submittal: Submit concurrently with startup construction schedule. Include submittals required during the first 60 days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.

3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's construction schedule.

a. Submit revised submittal schedule to reflect changes in current status and timing for submittals.

4. Format: Arrange the following information in a tabular format:

a. Scheduled date for first submittal.

b. Specification Section number and title.

c. Submittal category: Action; informational.

d. Name of subcontractor.

e. Description of the Work covered.

f. Scheduled date for Engineer's final release or approval.

1.12 SUBMITTAL ADMINISTRATIVE REQUIREMENTS

A. General Submittal Procedure Requirements: Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification

Sections.

1. Submit submittals to Engineer.

2. Engineer will return annotated file.

B. Digital Data Files:

1. Electronic digital data files of the Project drawings may be provided by Engineer for

Contractor's use in preparing submittals.

2. Electronic digital data files supplied for use in submittal preparation will be subject to terms and conditions of the Engineer’s Release Form. A signed release form and any payment required must be returned to the Engineer prior to the transmission of an electronic digital data files.

3. Electronic digital data file formats may include AutoCAD drawings, Revit converted to

AutoCAD drawings or Revit Model.

C. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.

3. Submit action submittals and informational submittals required by the same Specification

Section as separate packages under separate transmittals.

26 0000 - 8 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 8

4. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Engineer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

D. Processing Time: Allow time for submittal review, including time for resubmittals, as follows.

Time for review shall commence on Engineer's receipt of submittal. No extension of the

Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Engineer will advise

Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Resubmittal Review: Allow 14 days for review of each resubmittal.

E. Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:

1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.

2. Name file with submittal number or other unique identifier, including revision identifier.

a. File name shall use project identifier and Specification Section number followed by a decimal point and then a sequential number (e.g., LNHS-061000.01).

Resubmittals shall include an alphabetic suffix after another decimal point (e.g., LNHS-061000.01.A).

3. Provide means for insertion to permanently record Contractor's review and approval markings and action taken by Engineer.

4. Transmittal Form for Electronic Submittals: Use electronic form containing the following information:

a. Project name.

b. Date.

c. Name and address of Engineer.

d. Name of Construction Manager.

e. Name of Contractor.

f. Name of firm or entity that prepared submittal.

g. Names of subcontractor, manufacturer, and supplier.

h. Category and type of submittal.

i. Submittal purpose and description.

j. Specification Section number and title.

k. Specification paragraph number or drawing designation and generic name for each of multiple items.

l. Drawing number and detail references, as appropriate.

m. Location(s) where product is to be installed, as appropriate.

n. Related physical samples submitted directly.

o. Indication of full or partial submittal.

p. Transmittal number.

q. Submittal and transmittal distribution record.

r. Other necessary identification.

26 0000 - 9 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 9

s. Remarks.

5. Metadata: Include the following information as keywords in the electronic submittal file metadata:

a. Project name.

b. Number and title of appropriate Specification Section.

c. Manufacturer name.

d. Product name.

F. Options: Identify options requiring selection by Engineer.

G. Deviations and Additional Information: On an attached separate sheet, prepared on

Contractor's letterhead, record relevant information, requests for data, revisions other than those requested by Engineer on previous submittals, and deviations from requirements in the Contract

Documents, including minor variations and limitations. Include same identification information as related submittal.

H. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Note date and content of previous submittal.

2. Note date and content of revision in label or title block and clearly indicate extent of revision.

3. Resubmit submittals until they are marked with approval notation from Engineer's action stamp.

I. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

J. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Engineer's action stamp.

K. Comparable Product Requests: Submit request for consideration of each comparable product.

Identify product or fabrication or installation method to be replaced. Include Specification

Section number and title and Drawing numbers and titles.

1. Include data to indicate compliance with the requirements specified in "Comparable

Products" Article.

2. Engineer’s Action: If necessary, Engineer will request additional information or documentation for evaluation within one week of receipt of a comparable product request. Engineer will notify Contractor of approval or rejection of proposed comparable product request within 14 days of receipt of request, or 7 days of receipt of additional information or documentation, whichever is later.

a. Use product specified if Engineer does not issue a decision on use of a comparable product request within time allocated.

1.13 CLOSEOUT SUBMITTALS

A. Closeout submittals shall include, but not limited to, the following:

1. Operation and Maintenance Materials

2. Record Drawings

3. Demonstration and Training Materials

4. Final Approved Submittals

26 0000 - 10 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 10

1.14 MAINTENANCE MATERIAL SUBMITTALS

A. Manual Content: Operations and maintenance manual content is specified in individual

Specification Sections to be reviewed at the time of Section submittals. Submit reviewed manual content formatted and organized as required by this Section.

1. Engineer will comment on whether content of operations and maintenance submittals are acceptable.

2. Where applicable, clarify and update reviewed manual content to correspond to revisions and field conditions.

B. Format: Submit operations and maintenance manuals in the following format:

1. PDF electronic file. Assemble each manual into a composite electronically indexed file.

Submit on digital media acceptable to Engineer.

a. Name each indexed document file in composite electronic index with applicable item name. Include a complete electronically linked operation and maintenance directory.

b. Enable inserted reviewer comments on draft submittals.

2. In addition to the electronic submit provide two paper copies of the corrected final submittal as part of the “Closeout Documents”. Include a complete operation and maintenance directory. Enclose title pages and directories in clear plastic sleeves.

Engineer will return two copies. The two paper copies will be provided to the Owner as part of the “Closeout Documents”

C. Initial Manual Submittal: Submit draft copy of each manual at least 45 days before commencing demonstration and training. Engineer will comment on whether general scope and content of manual are acceptable.

D. Final Manual Submittal: Submit each manual in final form prior to requesting inspection for

Substantial Completion and at least 30 days before commencing demonstration and training.

Engineer will return copy with comments.

1. Correct or revise each manual to comply with Engineer's comments. Submit copies of each corrected manual within 15 days of receipt of Engineer's comments and prior to commencing demonstration and training.

1.15 TRAINING SUBMITTALS

A. Demonstration to the Owner personnel of the Electrical products and systems to be utilized on the project is required.

B. Training of Owner personnel in operation and maintenance is required for:

1. Electrical systems and equipment.

2. All software-operated systems.

3. Items specified in individual product Sections

1.16 QUALITY ASSURANCE

A. Products:

1. Compatibility of Options: If Contractor is given option of selecting between two or more products for use on Project, select product compatible with products previously selected, even if previously selected products were also options.

a. Each contractor is responsible for providing products and construction methods

26 0000 - 11 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 11

compatible with products and construction methods of other contractors.

b. If a dispute arises between contractors over concurrently selectable but incompatible products, Engineer will determine which products shall be used.

1.17 PRODUCT DELIVERY, STORAGE, AND HANDLING

A. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft and vandalism. Comply with manufacturer's written instructions.

B. Delivery and Handling:

1. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction spaces.

2. Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.

3. Deliver products to Project site in an undamaged condition in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.

4. Inspect products on delivery to determine compliance with the Contract Documents and to determine that products are undamaged and properly protected.

C. Storage:

1. Store products to allow for inspection and measurement of quantity or counting of units.

2. Store materials in a manner that will not endanger Project structure.

3. Store products that are subject to damage by the elements, under cover in a weathertight enclosure above ground, with ventilation adequate to prevent condensation or moisture damage.

4. Protect foam plastic from exposure to sunlight, except to extent necessary for period of installation and concealment.

5. Comply with product manufacturer's written instructions for temperature, humidity, ventilation, and weather-protection requirements for storage.

6. Protect stored products from damage and liquids from freezing.

7. Provide a secure location and enclosure at Project site for storage of materials and equipment by Owner's construction forces. Coordinate location with Owner.

1.18 PRODUCT WARRANTIES

A. Warranties specified in other Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract

Documents.

1. Manufacturer's Warranty: Written warranty furnished by individual manufacturer for a particular product and specifically endorsed by manufacturer to Owner.

2. Special Warranty: Written warranty required by the Contract Documents to provide specific rights for Owner.

B. Special Warranties: Prepare a written document that contains appropriate terms and identification, ready for execution.

1. Manufacturer's Standard Form: Modified to include Project-specific information and properly executed.

26 0000 - 12 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 12

2. Specified Form: When specified forms are included with the Specifications, prepare a written document using indicated form properly executed.

3. See other Sections for specific content requirements and particular requirements for submitting special warranties.

C. Submit warranties in accordance with “Closeout Procedures.”

1.19 FIELD CONDITIONS

A. The Contractor shall visit the site of the building before submitting a proposal on this work, and shall thoroughly familiarize himself with the existing conditions and operations. Failure on his part to do this will not be cause of extras after the contract is signed, by reason of unforeseen conditions.

1.20 WARRANTY

A. The Contractor shall, after completion of the original test of the installation, and acceptance by the Engineer, provide any service incidental to the proper performance of the electrical systems under guarantees outlined above for a period of 1 full year after acceptance by the Engineer and

Owner. Regardless of anything to the contrary in warranties by the equipment manufacturer involved, the Contractor's warranty shall run for 1 full year after final acceptance by the

Engineer.

1.21 ELECTRICAL LICENSE REQUIREMENT

A. No person shall perform electrical work on the contract without possessing a New Mexico State

Master or Journeyman License from the New Mexico State Electrical Examiners Board. All electrical work and apprentice electricians shall be supervised by a Master or Journeyman

Electrician on a one to one ratio.

B. All electricians shall have a copy of their license with them and shall be required to show it to an appropriate inspector upon request.

PART 2 - PRODUCTS

2.1 SUBMITTAL PROCEDURES

A. General Submittal Procedure Requirements: Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification

Sections.

1. Submit electronic submittals to Engineer.

a. Engineer will return annotated file. Annotate and retain one copy of file as an electronic Project record document file.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's catalog cuts.

26 0000 - 13 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 13

b. Manufacturer's product specifications.

c. Standard color charts.

d. Statement of compliance with specified referenced standards.

e. Testing by recognized testing agency.

f. Application of testing agency labels and seals.

g. Notation of coordination requirements.

h. Availability and delivery time information.

4. For equipment, include the following in addition to the above, as applicable:

a. Wiring diagrams showing factory-installed wiring.

b. Printed performance curves.

c. Operational range diagrams.

d. Clearances required to other construction, if not indicated on accompanying Shop

Drawings.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale and sufficiently large to show all pertinent features of the item, method of connections, and notations clearly legible. Do not base Shop Drawings on reproductions of the Contract

Documents or standard printed data, unless submittal based on Engineer's digital data drawing files is otherwise permitted.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products.

b. Schedules.

c. Compliance with specified standards.

d. Notation of coordination requirements.

e. Notation of dimensions established by field measurement.

f. Relationship and attachment to adjoining construction clearly indicated.

g. Seal and signature of professional engineer if specified.

D. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:

1. Type of product. Include unique identifier for each product indicated in the Contract

Documents or assigned by Contractor if none is indicated.

2. Manufacturer and product name, and model number if applicable.

3. Number and name of room or space.

4. Location within room or space.

E. Test and Inspection Reports and Schedule of Tests and Inspections Submittals: Comply with requirements specified in Division 01.

F. Closeout Submittals and Maintenance Material Submittals: Comply with requirements specified in Division 01.

G. Maintenance Data: Comply with requirements specified in Division 01.

H. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of Engineers and owners, and other information specified.

I. Welding Certificates: Prepare written certification that welding procedures and personnel

26 0000 - 14 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 14

comply with requirements in the Contract Documents. Submit record of Welding Procedure

Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified.

J. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that

Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

K. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.

L. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

M. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

N. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

O. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

P. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project.

Include the following information:

1. Name of evaluation organization.

2. Date of evaluation.

3. Time period when report is in effect.

4. Product and manufacturers' names.

5. Description of product.

6. Test procedures and results.

7. Limitations of use.

Q. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.

R. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

S. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

26 0000 - 15 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 15

2.2 PRODUCT SELECTION PROCEDURES

A. General Product Requirements: Provide products that comply with the Contract Documents, are undamaged and, unless otherwise indicated, are new at time of installation.

1. Provide products complete with accessories, trim, finish, fasteners, and other items needed for a complete installation and indicated use and effect.

2. Standard Products: If available, and unless custom products or nonstandard options are specified, provide standard products of types that have been produced and used successfully in similar situations on other projects.

3. Were two or more units of materials or equipment of the same type or class are required, these units shall be products of one manufacturer.

4. Owner reserves the right to limit selection to products with warranties not in conflict with requirements of the Contract Documents.

5. Where products are accompanied by the term "as selected," Engineer will make selection.

6. Descriptive, performance, and reference standard requirements in the Specifications establish salient characteristics of products.

7. Products containing asbestos shall not be used.

8. Or Equal: For products specified by name and accompanied by the term "or equal," or

"or approved equal," or "or approved," comply with requirements in "Comparable

Products" Article to obtain approval for use of an unnamed product.

B. Product Selection Procedures:

1. Product: Where Specifications name a single manufacturer and product, provide the named product that complies with requirements. Comparable products or substitutions for Contractor's convenience will not be considered.

2. Manufacturer/Source: Where Specifications name a single manufacturer or source, provide a product by the named manufacturer or source that complies with requirements.

Comparable products or substitutions for Contractor's convenience will not be considered.

3. Products:

a. Restricted List: Where Specifications include a list of names of both manufacturers and products, provide one of the products listed that complies with requirements. Comparable products or substitutions for Contractor's convenience shall be considered.

b. Nonrestricted List: Where Specifications include a list of names of both available manufacturers and products, provide one of the products listed, or an unnamed product, that complies with requirements. Comply with requirements in

"Comparable Products" Article for consideration of an unnamed product.

4. Manufacturers:

a. Restricted List: Where Specifications include a list of manufacturers' names, provide a product by one of the manufacturers listed that complies with requirements. Comparable products or substitutions for Contractor's convenience be considered.

b. Nonrestricted List: Where Specifications include a list of available manufacturers, provide a product by one of the manufacturers listed, or a product by an unnamed manufacturer, that complies with requirements. Comply with requirements in

"Comparable Products" Article for consideration of an unnamed manufacturer's product.

26 0000 - 16 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 16

5. Basis-of-Design Product: Where Specifications name a product, or refer to a product indicated on Drawings, and include a list of manufacturers, provide the specified or indicated product or a comparable product by one of the other named manufacturers.

Drawings and Specifications indicate sizes, profiles, dimensions, and other characteristics that are based on the product named. Comply with requirements in "Comparable

Products" Article for consideration of an unnamed product by one of the other named manufacturers.

C. Visual Selection Specification: Where Specifications include the phrase "as selected by

Engineer” or similar phrase, select a product that complies with requirements. Engineer will select color, gloss, pattern, density, or texture from manufacturer's product line that includes both standard and premium items.

2.3 COMPARABLE PRODUCTS

A. Conditions for Consideration: Engineer will consider Contractor's request for comparable product when the following conditions are satisfied. If the following conditions are not satisfied, Engineer may return requests without action, except to record noncompliance with these requirements:

1. Evidence that the proposed product does not require revisions to the Contract

Documents, that it is consistent with the Contract Documents and will produce the indicated results, and that it is compatible with other portions of the Work.

2. Detailed comparison of significant qualities of proposed product with those named in the

Specifications. Significant qualities include attributes such as performance, weight, size, durability, visual effect, and specific features and requirements indicated.

3. Evidence that proposed product provides specified warranty.

4. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners, if requested.

5. Contractor is responsible for any modification required by products other than the basis of design product at no additional cost to the owner including but not limited to modifications to supports and connections.

2.4 OPERATION AND MAINTENANCE DOCUMENTATION DIRECTORY

A. Directory: Prepare a single, comprehensive directory of emergency, operation, and maintenance data and materials, listing items and their location to facilitate ready access to desired information. Include a section in the directory for each of the following:

1. List of documents.

2. List of systems.

3. List of equipment.

4. Table of contents.

B. List of Systems and Subsystems: List systems alphabetically. Include references to operation and maintenance manuals that contain information about each system.

C. List of Equipment: List equipment for each system, organized alphabetically by system. For pieces of equipment not part of system, list alphabetically in separate list.

D. Tables of Contents: Include a table of contents for each emergency, operation, and maintenance manual.

26 0000 - 17 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 17

E. Identification: In the documentation directory and in each operation and maintenance manual, identify each system, subsystem, and piece of equipment with same designation used in the

Contract Documents. If no designation exists, assign a designation according to

ASHRAE Guideline 4, "Preparation of Operating and Maintenance Documentation for

Building Systems."

2.5 REQUIREMENTS FOR EMERGENCY, OPERATION, AND MAINTENANCE MANUALS

A. Organization: Unless otherwise indicated, organize each manual into a separate section for each system and subsystem, and a separate section for each piece of equipment not part of a system. Each manual shall contain the following materials, in the order listed:

1. Title page.

2. Table of contents.

3. Manual contents.

B. Title Page: Include the following information:

1. Subject matter included in manual.

2. Name and address of Project.

3. Name and address of Owner.

4. Date of submittal.

5. Name and contact information for Contractor.

6. Name and contact information for Construction Manager.

7. Name and contact information for Engineer.

8. Name and contact information for Commissioning Authority.

9. Names and contact information for major consultants to the Engineer that designed the systems contained in the manuals.

10. Cross-reference to related systems in other operation and maintenance manuals.

C. Table of Contents: List each product included in manual, identified by product name, indexed to the content of the volume, and cross-referenced to Specification Section number in Project

Manual.

1. If operation or maintenance documentation requires more than one volume to accommodate data, include comprehensive table of contents for all volumes in each volume of the set.

D. Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system, subsystem, and equipment. If possible, assemble instructions for subsystems, equipment, and components of one system into a single binder.

E. Manuals, Electronic Files: Submit manuals in the form of a multiple file composite electronic

PDF file for each manual type required.

1. Electronic Files: Use electronic files prepared by manufacturer where available. Where scanning of paper documents is required, configure scanned file for minimum readable file size.

2. File Names and Bookmarks: Enable bookmarking of individual documents based on file names. Name document files to correspond to system, subsystem, and equipment names used in manual directory and table of contents. Group documents for each system and subsystem into individual composite bookmarked files, then create composite manual, so that resulting bookmarks reflect the system, subsystem, and equipment names in a readily navigated file tree. Configure electronic manual to display bookmark panel on opening file.

26 0000 - 18 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 18

2.6 EMERGENCY MANUALS

A. Content: Organize manual into a separate section for each of the following:

1. Type of emergency.

2. Emergency instructions.

3. Emergency procedures.

B. Type of Emergency: Where applicable for each type of emergency indicated below, include instructions and procedures for each system, subsystem, piece of equipment, and component:

1. Fire.

2. Flood.

3. Gas leak.

4. Water leak.

5. Power failure.

6. Water outage.

7. System, subsystem, or equipment failure.

8. Chemical release or spill.

C. Emergency Instructions: Describe and explain warnings, trouble indications, error messages, and similar codes and signals. Include responsibilities of Owner's operating personnel for notification of Installer, supplier, and manufacturer to maintain warranties.

D. Emergency Procedures: Include the following, as applicable:

1. Instructions on stopping.

2. Shutdown instructions for each type of emergency.

3. Operating instructions for conditions outside normal operating limits.

4. Required sequences for electric or electronic systems.

5. Special operating instructions and procedures.

2.7 OPERATION MANUALS

A. Content: In addition to requirements in this Section, include operation data required in individual Specification Sections and the following information:

1. System, subsystem, and equipment descriptions. Use designations for systems and equipment indicated on Contract Documents.

2. Performance and design criteria if Contractor has delegated design responsibility.

3. Operating standards.

4. Operating procedures.

5. Operating logs.

6. Wiring diagrams.

7. Control diagrams.

8. Piped system diagrams.

9. Precautions against improper use.

10. License requirements including inspection and renewal dates.

B. Descriptions: Include the following:

1. Product name and model number. Use designations for products indicated on Contract

Documents.

2. Manufacturer's name.

3. Equipment identification with serial number of each component.

4. Equipment function.

26 0000 - 19 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 19

5. Operating characteristics.

6. Limiting conditions.

7. Performance curves.

8. Engineering data and tests.

9. Complete nomenclature and number of replacement parts.

C. Operating Procedures: Include the following, as applicable:

1. Startup procedures.

2. Equipment or system break-in procedures.

3. Routine and normal operating instructions.

4. Regulation and control procedures.

5. Instructions on stopping.

6. Normal shutdown instructions.

7. Seasonal and weekend operating instructions.

8. Required sequences for electric or electronic systems.

9. Special operating instructions and procedures.

D. Systems and Equipment Controls: Describe the sequence of operation, and diagram controls as installed.

E. Piped Systems: Diagram piping as installed, and identify color-coding where required for identification.

2.8 PRODUCT MAINTENANCE MANUALS

A. Content: Organize manual into a separate section for each product, material, and finish.

Include source information, product information, maintenance procedures, repair materials and sources, and warranties and bonds, as described below.

B. Source Information: List each product included in manual, identified by product name and arranged to match manual's table of contents. For each product, list name, address, and telephone number of Installer or supplier and maintenance service agent, and cross-reference

Specification Section number and title in Project Manual and drawing or schedule designation or identifier where applicable.

C. Product Information: Include the following, as applicable:

1. Product name and model number.

2. Manufacturer's name.

3. Color, pattern, and texture.

4. Material and chemical composition.

5. Reordering information for specially manufactured products.

D. Maintenance Procedures: Include manufacturer's written recommendations and the following:

1. Inspection procedures.

2. Types of cleaning agents to be used and methods of cleaning.

3. List of cleaning agents and methods of cleaning detrimental to product.

4. Schedule for routine cleaning and maintenance.

5. Repair instructions.

E. Repair Materials and Sources: Include lists of materials and local sources of materials and related services.

26 0000 - 20 SUPPLEMENTARY ELECTRICAL GENERAL CONDITIONS 26 0000 - 20

F. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and conditions that would affect validity of warranties or bonds.

1. Include procedures to follow and required notifications for warranty claims.

2.9 SYSTEMS AND EQUIPMENT MAINTENANCE MANUALS

A. Content: For each system, subsystem, and piece of equipment not part of a system, include source information, manufacturers' maintenance documentation, maintenance procedures, maintenance and service…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .