This document is Amendment A00005 to Solicitation 75H70126R00010 for the Gallup Indian Medical Center (GIMC) Fire Alarm Upgrade construction project. The amendment extends the proposal due date from February 17, 2026, at 2:00 PM PST to March 5, 2026, at 2:00 PM PST. It revises Attachment J01a Drawings (page G101 only) with an updated Site Plan (G101r1 - GIMC Fire Alarm) and updates Attachment J02 from WD NM20250024 to J02 WD NM20260024. The amendment also includes 48 pre-proposal inquiries with IHS-approved responses addressing technical clarifications on system requirements, installation procedures, and project logistics.
The solicitation is issued by the Indian Health Service, Division of Engineering Services (DES) in Seattle for a 100% Indian Small Business Economic Enterprise (ISBEE) set-aside under NAICS code 236220. The project is located at 516 E Nizhoni Boulevard, Gallup, New Mexico 87301, with an estimated construction magnitude between $1,000,000 and $5,000,000. The contractor must begin performance within 10 calendar days and complete the work within 180 calendar days of notice to proceed. An offer guarantee is required, and the contractor must furnish performance and payment bonds within 10 days after award. Key technical requirements include installation of a new Siemens Cerberus PRO Modular Fire Alarm Control Panel (or approved equal) with networking to existing systems, all new fire alarm cabling installed in conduit (red-colored), complete removal of existing fire alarm systems after new system acceptance by the Fire Marshal and Authority Having Jurisdiction, and phased implementation beginning with the Main Hospital Building. The project involves multiple buildings across the GIMC campus with coordination to existing Siemens, Edwards EST4, and third-party monitoring systems.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
A00005
JOSHUA T. VANSKIKE
See the following SF30 continuation page.
Indian Health Service Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1600 Seattle, WA 98104
Indian Health Service Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1600 Seattle, WA 98104
75H70126R00010
NA19GA009H8
1 13
02/13/2026
11/13/2025
SF30 CONTINUATION OF BOX 14.
Solicitation 75H70126R00010 Amendment A00005 Gallup Indian Medical Center (GIMC) Fire Alarm Upgrade Project No. NA19GA009H8
SUMMARY OF CHANGES:
Amendment A00005 to solicitation 75H70126R00010 hereby addresses the following:
1. Revises SF-1442, extending the proposal due date from February 17, 2026, at 2:00 PM PST to March 5, 2026, at 2:00 PM PST.
2. Section J List of Attachments:
a. Revises Attachment J01a Drawings, page G101 only, with attachment G101r1 - Site Plan
(GIMC Fire Alarm);
b. Updates attachment J02 WD NM20250024 with J02 WD NM20260024.
3. Provides Pre-Proposal Inquiries and responses 1 through 48; 9 pages.
NOTICE TO OFFERORS: Offerors must acknowledge receipt of all amendments by number and date on their cover letter in their offer or by submitting a signed copy of the SF30. All other terms and conditions remain unchanged.
END SUMMARY OF CHANGES
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR
INFORMATION CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF PAGES
75H70126R00010
Indian Health Service Division of Engineering Services (DES) - Seattle 701 5th Ave, Suite 1600 Seattle, WA 98104
Project: Gallup Indian Medical Center (GIMC) Fire Alarm Upgrade
Location: 516 E Nizhoni Blvd, Gallup, NM 87301
See Section L for Proposal Submittal Instructions and Site Visit Information.
This project will be procured as a 100% Indian Small Business Economic Enterprise (ISBEE) set-aside under North American Industry Classification System (NAICS) code 236220 - Commercial and Institutional Building Construction. The associated size standard for this procurement is $45 million.
CONSTRUCTION MAGNITUDE: The magnitude of this construction project is anticipated to be between $1,000,000 and $5,000,000.
Indian Health Service Division of Engineering Services (DES) - Seattle Attn: Joshua VanSkike 701 5th Ave, Suite 1600 Seattle, WA 98104
Joshua VanSkike (240) 485-7526 or joshua.vanskike@ihs.gov
NA19GA009H8
1 5411/13/2025
3/5/2026
2:00PM
10 Days after award
F.2. Period of Performance
AWARD (To be completed by Government)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES
CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
B.3
Indian Health Service, DES - Seattle 701 5th Ave, Suite 1600 Seattle, WA 98104
IHS Navajo Area P.O. Box 9020 Window Rock, AZ 86515
Joshua T. VanSkike
LUMP SUM TOTAL $______________________
A00005 under Solicitation 75H70126R00010 SFIHC Roof Replacement and Fall Protection
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H70126R00010
GIMC Fire Alarm Upgrade – Construction
Item No. COMMENTS IHS Approved Response
1. Can you please clarify if Notifier by Honeywell is acceptable. The following listed below are the manufacturers you approved for the project. The spec reads as if Honeywell direct is the basis of design, not Notifier by Honeywell.
Siemens Edwards Honeywell
See RFP Section C SOW, item 3. WORK COVERED BY CONTRACT DOCUMENTS: “Note: No brand names are required per the specification, drawings, or elsewhere throughout the requirement. Equivalent products meeting the quality and characteristics required will be accepted.”
2. Per specifications it state that FACP system needs to have the ability to be networked to, and interface with existing Siemens system. (see snippet below)
However, in the SOW it Notes: No brand names are required per the specification, drawings, or elsewhere throughout the requirement. Equivalent products meeting the quality and characteristics required will be accepted. (see snippet below)
Please clarify if this a a total complete upgrade of the system including the existing Siemens system which would open this up to all brand names meeting the characteristics and requirements, or is it required to network and interface with existing Siemens System?
We are open to all systems, but we need it to be able to communicate with the existing siemens system. The existing East Annex fire alarm control panel, initiating devices and annunciation devices shall remain and communicate with the new fire alarm system. The existing Edwards EST4 fire alarm system within the Tohatchi Health Center roughly (40) miles from the GIMC main campus shall also communicate with the Siemens Cerberus PRO Modular Fire Control Panel at the main campus. The Edwards EST4 system shall transit the CMS (point list) to the central station.
Also, reconfirming RFP Section C SOW, item 3. WORK COVERED BY CONTRACT DOCUMENTS: “Note: No brand names are required per the specification, drawings, or elsewhere throughout the requirement. Equivalent products meeting the quality and characteristics required will be accepted.”
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H70126R00010
GIMC Fire Alarm Upgrade – Construction
3. Will all work need to be performed after hours? See RFP H.1. WORK HOURS. After-hour work may needed for certain areas. Currently, OR area will be the only area that shall require after-hour work. The service unit is flexible with having contractor work after hours. Coordination is required.
4. Site Plan- Electrical Per Sheet E101, the contract documents indicate the installation of new fiber lines, new raceways, and innerduct to connect each building to the main building’s Fire Alarm Control Panel (FACP).
During the site visit, the IT Manager advised that the existing fiber and associated pathways were recently installed and currently have sufficient capacity to accommodate additional lines.
Please confirm the intended scope:
1. Should the contractor proceed with installing new fiber, raceways, and innerduct as shown on E101, or will this portion of the site-work scope be removed given available pathway capacity?
2. If the site-work fiber scope is removed, will an independent, standalone fire alarm system be acceptable for each building?
Please provide direction so that we may accurately coordinate the design intent, pricing, and installation requirements.
1. Proceed with the installation of new fiber, raceways and innerduct as shown on E101.
2. See immediately preceding response re installation of new fiber, raceways and innerduct as shown on E101.
5. Level 0 – Level 4 Fire Alarm Demolition Demolition Plans general note A state that the new fire alarm system is to be fully installed, operational, tested, and approved by the local Fire Marshal and AHJ prior to demolition of the existing system.
Please clarify the following:
Will the new FACP units, notification devices (strobes and horns), and manual pull stations be installed in locations different from the existing devices, or should the contractor assume that device locations will remain generally consistent with the current layout?
Confirmation is needed to ensure accurate installation planning, coordination with other trades, and to prevent rework during system transition.
Contractor shall assume that the new devices will remain generally consistent with the current layout.
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H70126R00010
GIMC Fire Alarm Upgrade – Construction
6. Pathway Requirements Please provide clarification on the required pathway methods for low-voltage cabling:
1. In-wall locations:
Should the contractor install EMT conduit for all in-wall cable pathways, or is plenum-rated cabling without conduit acceptable per project requirements and code compliance?
2. Above-ceiling locations:
Should EMT conduit be provided for all above-ceiling routing, or is plenum-rated cabling supported by J-hooks acceptable?
1. All new fire alarm system cabling shall be installed in conduit.
2. See immediately preceding response re new fire alarm system cabling shall be installed in conduit.
7. Existing Siemens Panels The RFP Document states “Note: No brand names are required per the specification, drawings, or elsewhere throughout the requirement. Equivalent products meeting the quality and characteristics required will be accepted.”
Please clarify the following:
1. Does the new fire alarm system need to be capable of networking with the existing Siemens panel?
We are open to all systems, but we need it to be able to communicate with the existing siemens system. The existing East Annex fire alarm control panel, initiating devices and annunciation devices shall remain and communicate with the new fire alarm system. The existing Edwards EST4 fire alarm system within the Tohatchi Health Center roughly (40) miles from the GIMC main campus shall also communicate with the Siemens Cerberus PRO Modular Fire Control Panel at the main campus. The Edwards EST4 system shall transit the CMS (point list) to the central station.
Also, reconfirming RFP Section C SOW, item 3. WORK COVERED BY CONTRACT DOCUMENTS: “Note: No brand names are required per the specification, drawings, or elsewhere throughout the requirement. Equivalent products meeting the quality and characteristics required will be accepted.”
8. Is the Potter IPA-4000V integrated voice fire alarm control panel an acceptable substitution? See RFP H.17. APPROVED EQUIVALENTS (OR EQUALS) Contractor proposed equivalents shall be submitted for review after award as a Request for Information (RFI). Proposed equivalents will not be reviewed during the solicitation period.
9. Is there a Project schedule that you share that has more details of the project time frame? Project to begin as soon as practicable starting with the Main Building. See also RFP F.2 PERIOD OF PERFORMANCE
10 Is this Project going to be phased? Project to be Phased by building starting with the Main Hospital Building. Remaining building shall be sequential scheduled on building at a time from start to finish prior to starting the next scheduled building. Subsequent scheduling building after the main building completion shall be as prioritized by GIMC Facilities.
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H70126R00010
GIMC Fire Alarm Upgrade – Construction
11 The ‘General Overview of Sequence of Construction’ on the Final CD plans references installing a Siemens panel (Note: A) and revising programing to communicate CMS data with Est-4 panel in TOHATCHI Health Clinic (note: K)
• Where is the TOHATCHI health clinic located on the site plans?
• In document ‘Division 28 Electronic Safety and Security_4, section D & C calls for the new FACP to be networked/ interfaced with existing Siemens Panel. The documents state that all existing fire systems should be decommissioned after the new system is successfully accepted by AHJ, please clarify as these contradicts each other.
• Section C (FACP networked to Management Station) – Please confirm that the system is to have the ability to be networked to a PC based management Station, ability to be integrated with BMS and Security but NOT include a PC based management station with integration of BMS and security system in this quote.
1. Tohatchi is roughly 25 miles north of Gallup.
2. New fire alarm system shall be complete with a new
Siemens Cerberus Pro Modular Fire Alarm Control Panel or approved equal manufacturer, and management station complete with server monitor, keyboard and printer in the existing boiler control room. System shall be integrated to the BMS and Security Access Control Systems.
12 Document: Gallup Indian Medical Center (GIMC) Fire Alarm Upgrade – Construction, Final CD shows multiple FACPs installed in building 2000. (Please confirm if this is accurate.)
• page E141.0 shows 3 locations for installation of an FACP
• page E141.1 shows 1 location for installation of an FACP
• page E141.3 shows 1 location for installation of an FACP
• page E141.5 shows 1 location for installation of an FACP
• Page E141.4 shows 0 locations for installation of an FACP
The single FACP shall be located within the existing Building 2000 boiler control room. The remaining panes indicated are Cerberus PRO Modular networked panels.
13 Per Final Construction Documents 12/6/2024 GIMC CAMPUS FIRE ALARM SYSTEM contractor to provide; Furnish 10% extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. The parts should include, but are not limited to, main system equipment (motherboards, processors, cards, etc.) and peripheral components (field devices such as initiating devices and notification appliances).
• Please provide an exact list of all material types that need to be part of this 10%, because this request is wide ranging and can be interpreted to include ALL materials in the BOM.
Provide (1) of each type of peripheral field device.
14 Drawing E141.0, keynote 1 instructs: "Where fire alarm devices have been removed, install all new fire alarm devices with their associated wiring and conduit in existing wall which was abandoned for reinstallation".
• Is this keynote referring to the wall being abandoned or the conduit?
• If it is instructing the conduit is to be re-used, how would this apply if the new fire alarm system needs to be completely installed before demolition.
New fire alarm system shall be installed in new conduits and boxes.
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H70126R00010
GIMC Fire Alarm Upgrade – Construction
15 Drawing E101, keynote 3 shows a concrete encased feeding going across college drive.
• Is there a current traffic plan in place to re-route the large amount of traffic that uses this road daily or will this be the contractors responsibility?
• How many days will the contractor be allowed to have this area shut down and will it need to be re-opened during non-construction hours?
• Is a concrete encased conduit required for this portion or could we directional bore the conduit under the road instead? This would help reduce the delay of traffic for emergency vehicles, patients and people who reside in the area. Especially with the current construction and road closure at Nizhoni Blvd and 2nd street, this could pose potential delays that could have impacts on emergency vehicles getting to the hospital.
• Will Government Circle still be used during this constuction period as well? If so, will we need a traffic plan for employees or patients using this road?
Directional boring under the roadways would be acceptable. If trenching is provided contractor to provide traffic control and steel plate trenching when work is not in progress to open roadway to traffic.
16 Is the 180 day period of performance listed in F.2 of the RFP a mandatory requirement? This project will absolutely take longer than 180 days to complete in its entirety, including removal of the old system, conduit, wiring, patch, paint, etc.
Yes. Note: consideration of long lead items will be discussed at the pre-construction conference and if needed, we will allow administrative time prior to issuance of NTP to accommodate within Period of Performance.
17 Will the site provide the awarded contractor with a secure location to store materials and equipment or is the awarded contractor to provide their own storage container.
Awardee must provide their own secured storage container on site.
Location to be determined by GIMC Facilities. See also RFP H.32.
OPERATIONS AND STORAGE AREAS.
18 Is it a requirement of the project that the existing fire alarm system remain fully operational until after the new system has been fully installed, tested, inspected and approved by the State Fire Marshall and
AHJ?
Yes.
19 Is it a requirement to remove existing conduit and wiring from old system, or just devices and panels? All existing accessible fire alarm system conduit, boxes and cabling shall be removed and disposed of properly off site.
20 Is it a requirement to patch and match paint for removed devices from the old fire alarm system? Yes.
21 Is GIMC able to provide us with drawings showing existing fiber pathway as discussed during site walk on November 18th.
For Informational Purposes Only, see attachment provided: GIMC - Fiber Copper Cable Reroutes (2025).
22 Is GIMC able to confirm that there is an existing pathway with available space to pull new fiber to all the GIMC buildings that need to be networked together for this project?
For Informational Purposes Only, see attachment provided: GIMC - Fiber Copper Cable Reroutes (2025).
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H70126R00010
GIMC Fire Alarm Upgrade – Construction
23 J01a drawings General Demolition Notes (page 6) states: THE NEW FIRE ALARM SYSTEM
MUST BE COMPLETELY INSTALLED, COMMUNICATING WITH THE FIRE CONTROL
PANEL, REMOTE DISPLAYS AND THIRD PARTY MONITORING COMPANY TESTED,
ACCEPTED AND SIGNED OFF BY THE AHJ (IHS) AND THE LOCAL STATE FIRE
MARSHALL PRIOR TO THE START OF ANY DEMOLITION WITHIN ANY BUILDING.” this requirement will significantly impact installation timeline and device placement as this would require the new system to be fully installed, (along side the existing system) tested and approved, prior to removal of the existing fire alarm system.
Correct.
24 Is there a smoke control system at any of the GIMC buildings within this project? No.
25 May the QCM assume the responsibilities of the SSHO on this project? Yes, provided the individual is qualified. A résumé demonstrating the individual’s qualifications must be submitted.
If the individual is proposed to serve in multiple roles (“triple-hatted”), experience must be clearly demonstrated separately for each position, and the résumé must reflect the required qualifications for all applicable roles.
26 May the QCM assume the responsibilities of the Superintendent on this project? Yes, provided the individual is qualified. A résumé demonstrating the individual’s qualifications must be submitted.
If the individual is proposed to serve in multiple roles (“triple-hatted”), experience must be clearly demonstrated separately for each position, and the résumé must reflect the required qualifications for all applicable roles.
27 May the SSHO assume the responsibilities of the Superintendent on this project? Yes, provided the individual is qualified. A résumé demonstrating the individual’s qualifications must be submitted.
If the individual is proposed to serve in multiple roles (“triple-hatted”), experience must be clearly demonstrated separately for each position, and the résumé must reflect the required qualifications for all applicable roles.
28 Can conduit be surfaced mounted? Only within utility rooms i.e. mechanical and electrical rooms, central plant and facilities.
29 Will conduit need to be red, or will conduit need to be painted to match existing and red banded? Red conduit.
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H70126R00010
GIMC Fire Alarm Upgrade – Construction
30 Can existing conduit be reused? No, as the new system must be tested and online prior to the existing system being removed.
31 Will the building be occupied during fire sprinkler installation? This project has no sprinkler system piping modifications.
32 Will off-hour work be required? See RFP H.1. WORK HOURS. After hours work may need to be required for certain areas. Currently, OR area will be the only area that shall require after-hour work. The service unit is flexible with having contractor work after hours. Coordination is required.
33 For the RFP what is the order of precedence, code or scope of work? Code, however will need to be discussed if arises.
34 In the event of conflict between scope of work and code what will be preferred? Code, however will need to be discussed if arises.
35 Is there any asbestos or lead that the Contractor will encounter during construction? For Informational Purposes Only, see (2) attachments provided:
GIMC Asbestos Sampling Report Feb 2012 GIMC Campus Lead Report 2-2012
36 Is the Siemens Cerberus PRO fire alarm system mandatory for this project, or will truly equivalent systems from other manufacturers (Notifier, EST, Fike, etc.) be accepted?
See RFP SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK at 3.
WORK COVERED BY CONTRACT DOCUMENTS: “The General Contractor (GC) shall furnish all personnel, material, services, and facilities to perform all work necessary described in construction drawings and specifications. Note: No brand names are required per the specification, drawings, or elsewhere throughout the requirement.
Equivalent products meeting the quality and characteristics required will be accepted.”
37 If equivalents are acceptable, please confirm whether any compatibility, integration, or existing infrastructure considerations within Main Hospital Building 2000 or the broader GIMC campus require matching the existing Siemens system.
The existing East Annex fire alarm devices are to remain and must communicate with the new fire alarm system manufacturer.
38 If Siemens is required, please confirm whether this is due to facility standardization, existing proprietary programming, or other operational/maintenance considerations.
See above Item 7 response.
39 Please provide the name and contact information for GIMC’s third-party monitoring company and confirm any special programming requirements they may require.
Bldg.2000 & Bldg.2018 - Alarmco Inc (208)376-9731, ACCT 6470
Bldg.3003 Behavioral health - Vets fire (888)746-7539, ACCT 212-
Bldg.3000 New Modular Bldg. Advance Solutions (Siemens) (602)
4331271, ACCT 7064
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H70126R00010
GIMC Fire Alarm Upgrade – Construction
40 Please confirm whether a Potter Panel Network would be considered an acceptable substitution for the fire alarm control panel and associated equipment.
See RFP H.17. APPROVED EQUIVALENTS (OR EQUALS) Contractor proposed equivalents shall be submitted for review after award as a Request for Information (RFI). Proposed equivalents will not be reviewed during the solicitation period.
41 Is the Potter IPA-4000V integrated voice fire alarm control panel an acceptable substitution? See RFP H.17. APPROVED EQUIVALENTS (OR EQUALS) Contractor proposed equivalents shall be submitted for review after award as a Request for Information (RFI). Proposed equivalents will not be reviewed during the solicitation period.
42 Please indicate what building the East Annex is. As we cannot find a mention of it in the RFP, Specs, or drawings.
The East Annex is the single-story addition to building 2000, on the eastern side of the main hospital. See RFP Amendment A0005, updated attachment G101r1 SITE PLAN.
43 RFI #12 Response states that the Edwards EST4 Fire Alarm System Shall Communicate with the Siemens Cerberus Pro Modular Fire Control Panel at the main campus. The two different manufacturers Siemens and Edwards are not able to communicate signals to each other.
The existing Edwards EST4 fire alarm system within the Tohatchi Health Center roughly (40) miles from the GIMC main campus shall also communicate with the Siemens Cerberus PRO Modular Fire Control Panel at the main campus. The Edwards EST4 system shall transit the CMS (point list) to the central station.
44 Although the spec lists EST and Honeywell the drawings themselves are very specific to the Siemens solution. Due to the specificity of the drawings, I would hate to move forward with building the full proposal without a notice from the end user that they are okay with the Notifier system.
See above Item 7 response.
45 Can you confirm that GIMC has all dedicated primary power 120V circuits for the new proposed fire alarm system, as we are upgrading the older system to a new system. (fire alarm control panels, power-supply units, will need to have their own dedicated 120V power). NFPA 72, Sec. 10.6.5.1
a. Should GIMC not have the information to share for our electrical contractors to finalize their bid numbers, can we request allowed additional extended time to retrieve the Dedicated Primary Power information?
Provide dedicated life safety branch circuits from existing life safety branch circuit panelboards if the existing fire alarm system panels are not sourced from the life safety branch.
46 Can you confirm that GIMC has clear Underground Pathway, for the new Fiber Optic Cable crossing between College Drive? To connect Buildings 2018, 2016 & 3003 (which will connect back to the rest of the buildings off Nizhoni Blvd, and no need to dig or trench & repair pathway(s) for the additional new fire alarm fiber optic cable).
There is an existing 4" conduit pathway that will allow the contractor to connect buildings without digging or trenching. For Informational Purposes Only, see attachment provided: GIMC – Fiber Copper Cable Reroutes (2025).
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H70126R00010
GIMC Fire Alarm Upgrade – Construction
47 1. Can you confirm that GIMC has all dedicated primary power 120V circuits for the new proposed fire alarm system, as we are upgrading the older system to a new system. (fire alarm control panels, power-supply units, will need to have their own dedicated 120V power. NFPA 72, Sec. 10.6.5.1
The existing fire alarm control panels and power supplies should be presently sourced from the Life Safety branch. Contractor shall field verify and provide Life Safety 20A, 120V as required to comply with
NFPA 72.
48 Can you confirm that GIMC has clear Underground Pathway, for the new Fiber Optic Cable crossing between College Drive? To connect Buildings 2018, 2016 & 3003 (which will connect back to the rest of the buildings off Nizhoni Blvd, and no need to dig or trench & repair pathway(s) for the additional new fire alarm fiber optic cable).
• Will there be a laydown yard or designated storage area for this project.?
• There is a new portion of the hospital that was just updated on the east part of the building 2000. Will there be able to tie into that existing fire alarm system to the new system you are installing or replacing entirely? It currently doesn't show that it is a part of the current scope of work.
Provide new underground conduits and fiber optic cable as noted on Sheet E101 providing trenching, backfilling and patching surfaces to match existing.
Refer to the RFP scope of work within the East Annex.