J - LBP-B Street East - H and I East.pdf

PDF 338 KB Posted

Attached to
100% WOSB-Design Build Construction, Repave C St East Full Depth Repair-JBSA Randolph
Solicitation number
FA301621R0056
Issued by

About this file

This document contains details regarding a federal contract opportunity for design-build construction services to repave C Street East on Joint Base San Antonio Randolph. The Woman Owned Small Business-set aside solicitation seeks a contractor to provide design and full depth road reconstruction for approximately 1,380 linear feet of C Street East. The scope of work includes roadway, curb and gutter, pavement marking, and associated roadway repairs. The solicitation also indicates potential lead-based paint on existing roadway markings, requiring adherence to OSHA regulations. The contracting agency is the Department of the Air Force Air Education and Training Command.

View the file

Other files

File Type Posted
Amendment 06.pdf PDF
Amendment 5.pdf PDF
Amendment 4.pdf PDF
SOW-08272021-Revised.pdf PDF
Amendment 3.pdf PDF
Atch 1 - SOW-07142021.pdf PDF
Amendment 02-Attachment C St Pre-Pre-Proposal.pdf PDF
Amendment 02-Attachment CStreetSiteVisit.pdf PDF
Solicitation Amendment 02 FA301621R00560002 SF 30-.pdf PDF
Solicitation Amendment-01 FA301621R00560001 SF 30.pdf PDF
Atch 9-Financial Information Questionnaire.docx DOCX document
C - Demo Locations.pdf PDF
Atch 6-Base Access_Request Form.pdf PDF
F - Utilities Maps.pdf PDF
B - Project Boundary.pdf PDF
Atch 5-RFI Template.xlsx XLSX spreadsheet
Atch 3-Ozone Depletion Control Compliance.pdf PDF
H - DD1354 - Project Closeout.pdf PDF
APPENDIX COVER.pdf PDF
A - LOCATION MAP.pdf PDF
I- AW TRENCH PICTURE.pdf PDF
L- C St WEST Trench Photos June 2021.pdf PDF
E- American Water Design Plans - C St East.pdf PDF
K- AW ROAD CLOSURES.pdf PDF
Solicitation - FA301621R0056.pdf PDF
Atch 2-AETC Form 47.pdf PDF
G - Dig Perm (AF 103).pdf PDF
Atch 10-Contractor Responsibility Questionnaire.docx DOCX document
Atch 1 - SOW-07142021.pdf PDF
Atch 8-Sample Progress Schedule.xlsx XLSX spreadsheet
Atch 4-HAZMAT Letter.pdf PDF
Atch 7-Sample - Cost Estimate Breakdown.xls XLS spreadsheet
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JBSA LBP Inventory Print Report

Lead Based Paint Detected:

Unknown

Square Footage: 0

Number of Floors: 0

None.tif

Drawing File Name:

Facility Status: Manned

C Street East.jpg

Photo File Name

Date Constructed: 0

Facility Number: Facility Name:Roadwa Basewide

Facility Owner: Unknown

Facility Type

Facility Address: BASE

Facility Summary Report:

08/18/2012 - Workorder 11024 - Repair pavement new B Street West - The yellow hydrant markings are Positive for LBP. Do not disturb any areas that are POS for LBP by any abrasive means such as sanding, scraping blasting, drilling or any brazing/welding operations.etc. OSHA 29 CFR 1926.62 rules will apply for this project. The OSHA requirement for these rules apply for any amount of LBP .1 mg/cm2 or greater. A negative determination will be required for this project by a certified Lead Firm

07/12/2012 - Workorder 11023, Repair pavement I Street - Do not disturb yellow lines. All yellow lines are Positive for LBP. Do not disturb any areas that are POS for LBP by any abrasive means such as sanding, scraping blasting, drilling or any brazing/welding operations.etc. OSHA 29 CFR 1926.62 rules will apply for this project. The OSHA requirement for these rules apply for any amount of LBP .1 mg/cm2 or greater. A negative determination will be required for this project by a certified Lead Firm

Facility Site: JBSA Randolph

ViewFacility Comments:

Facility Comments:

Date User Comment

7/6/2021 elv Assess centerline of roadway, B Street East to New B Street East. H Street East to I Street east. All yellow centerlines are Positive for Lead Based Paint. An OSHA Negative Exposure Assessment is required in accordance with 29 CFR 1926.62 Lead in Construction Rules for any disturbance of Lead Based Paint. A TCLP is required to determine proper disposal of the waste. All waste will be profiled manifested and signed through the JBSA Environmental Office based on the resultts of the TCLP. All TCLPs will be reviewed by the JBSA Hazardous Waste Manager.

A Lead Plan is required. All associated costs for waste disposal, or any costs associated with abatement fees are the responsibility of the contractor.

4/22/2021 ELV RND First Street East Section 06, (Between H St West and J St East) Mill & Overlay. All markings on 1st Street East are Positive for Lead Based paint. Thermal Strips placed over Lead Based Paint markings 2.RND J Street West Section 03, (Between Third Dr West and First St West) Mill & Overlay The marking on J Street west Centerline is Negative up to building 52, The Parking

1 6/17/2021 1.93 0.12Centerline N/A Lower B street east Asphalt yellow Deteriorate Positiv

2 6/17/2021 1.17 0.14Centerline N/A Lower B street east Asphalt yellow Deteriorate Positiv

3 6/17/2021 0 0Centerline N/A Lower B street east Asphalt yellow Deteriorate Negativ

4 6/17/2021 1.09 0.28Centerline N/A Lower B street east Asphalt yellow Deteriorate Positiv

5 6/17/2021 2.98 0.33Centerline N/A Lower B street east Asphalt yellow Deteriorate Positiv

6 6/17/2021 0 0Centerline N/A Lower B street east Asphalt yellow Deteriorate Negativ

7 6/17/2021 0.01 0Centerline N/A Lower B street east Asphalt yellow Deteriorate Negativ

8 6/17/2021 0 0Centerline N/A Lower B street east Asphalt yellow Deteriorate Negativ

9 6/17/2021 0 0Centerline N/A Lower B street east Asphalt yellow Deteriorate Negativ

10 6/17/2021 4.34 0.19Centerline N/A Lower B street east Asphalt yellow Deteriorate Positiv

11 6/17/2021 2.15 0.13Centerline N/A Lower B street east Asphalt yellow Deteriorate Positiv

12 6/17/2021 0 0Centerline N/A Lower H/ I Asphalt yellow Deteriorate Negativ

13 6/17/2021 0 0Centerline N/A Lower H/ I Asphalt yellow Deteriorate Negativ

14 6/17/2021 0 0Centerline N/A Lower H/ I Asphalt yellow Deteriorate Negativ

15 6/17/2021 5 0.81Centerline N/A Lower H/ I Asphalt yellow Deteriorate Positiv

16 6/17/2021 5 0.41Centerline N/A Lower H/ I Asphalt yellow Deteriorate Positiv

17 6/17/2021 3.93 0.12Centerline N/A Lower H/ I Asphalt yellow Deteriorate Positiv

18 6/17/2021 0 0Centerline N/A Lower H/ I Asphalt yellow Deteriorate Negativ

19 6/17/2021 4.64 0.33Centerline N/A Lower H/ I Asphalt yellow Deteriorate Positiv

Markings in front of building 863 and the no parking markings near building 52 are positive for Lead Based Paint. 3.RND Fifth Street West Section 02, (In the intersection of NorthWest Thruway and fifth St West) Mill & Overlay The North west thru way is Positive for Lead Based. Paint. All Lead work must be done by a Lead Team. A negative Exposure assessment would be required in accordance with OSHA 29 CFR 1926.62.

2/1/2021 elv 8531848- Assess paving of C Street east. Lead Based Paint is still existing on this roadway. Te existing LBP lines remain after the installation of the thermal yellow tape. An OSHA Negative Exposure Assessment is required in accordance with 29 CFR

1926.62 Lead In Construction rules. This applies for any

disturbance of Lead Based Paint by any mechanical or physical means this includes grinding, scraping, blasting, etc

12/12/2018 elv Work Order 13770 - Repair F Street - The majority of the yellow markings are taped markings, the only marking that are painted are in front of building 693. All painted markings are Negative for Lead Based Paint. See 13770_Fstreet_LBPreport.

Recommend recycling of the concrete. Report all weights to the JBSA area specific Environmental Office

Sample Date Room Side Quadrant Component Substrate Color Condition Pb+ Pb- Results

1401561150C Highlight

File details come from the government source that posted it. Updated .