(J) ECMS.pdf
PDF 80 KB Posted
- Attached to
- M2M &M12N Feeder Repairs
- Solicitation number
- 6012068
About this file
This document is a section from an Electronic Construction and Facility Support Contract Management System (eCMS) specification. It outlines the requirements for using the eCMS system to manage the transfer, sharing, and documentation of electronic construction documents and submittals for a federal contract.
The key details are:
- The eCMS is the designated means of transferring technical documents between the contractor and the government. Paper or email submissions are not permitted except when eCMS is unavailable.
- Contractors must provide a list of personnel who will have access to eCMS and the associated roles (e.g. project manager, QC manager).
- A tablet computer with CAC reader must be provided on-site for government use to facilitate data input.
- Specific document types are identified as either "Unclassified" (U) or "For Official Use Only" (FOUO), with required markings and eCMS application usage.
- Requirements are provided for usage, security classification, and marking of documents in the eCMS throughout the contract duration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI 2 Responses.pdf | ||
| Amendment 0001.pdf | ||
| RFI Responses.pdf | ||
| Site Visit Log.pdf | ||
| (A) RFP Information Rev1.pdf | ||
| (P) CERT-141.pdf | ||
| (M) Map to B135.pdf | ||
| (K) RFI Form.pdf | ||
| (H) FAR 52.204-24.pdf | ||
| (F) CT20240024 03 MAY 2024.pdf | ||
| (I) General Requirements.pdf | ||
| (E) LESSA.pdf | ||
| (D) NEPA.pdf | ||
| (O) 2016-R-0149.pdf | ||
| (L) Base Map.pdf | ||
| (G) Price Proposal Form.pdf | ||
| (C) Drawings.pdf | ||
| (N) Building Contractors Guide to Taxes.pdf | ||
| (B) Specifications.pdf | ||
| (A) RFP Information.pdf |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01 31 23.13 20 Page 1
SECTION TABLE OF CONTENTS DIVISION
01 - GENERAL REQUIREMENTS SECTION
01 31 23.13 20
ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM
05/17
PART 1 GENERAL
1.1 CONTRACT ADMINISTRATION
1.2 USER PRIVILEGES
1.3 SUBMITTALS
1.4 SYSTEM REQUIREMENTS AND CONNECTIVITY
1.4.1 General
1.4.2 Contractor Personnel List
1.4.3 Field Administration
1.5 SECURITY CLASSIFICATION
1.6 ECMS UTILIZATION
1.6.1 Information Security Classification/Identification
1.6.2 Markings on FOUO documents
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 31 23.13 20 Page 2
SECTION 01 31 23.13 20
ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM
05/17
PART 1 GENERAL
1.1 CONTRACT ADMINISTRATION
Utilize the Naval Facilities Engineering Command's (NAVFAC's) Electronic Construction and Facility Support Contract Management System (eCMS) for the transfer, sharing and management of electronic technical submittals and documents. The web-based eCMS is the designated means of transferring technical documents between the Contractor and the Government. Paper media or e-mail submission, including originals or copies, of the documents identified in Table 1 are not permitted, except where eCMS is unavailable or non-functional. Contact the Contracting Officer's Representative (COR) regarding availability of eCMS training and reference materials.
1.2 USER PRIVILEGES
The Contractor will be provided access to eCMS. All technical submittals and documents must be transmitted to the Government via the COR. Project roles and system roles will be established to control each user's menu, application, and software privileges, including the ability to create, edit, or delete objects.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals List of Contractor's Personnel; G
1.4 SYSTEM REQUIREMENTS AND CONNECTIVITY
1.4.1 General
The eCMS requires a web-browser (platform-neutral) and Internet connection. Obtain from an approved vendor an External Certification Authority (ECA), Primary Key Infrastructure (PKI) certificate, or other similar digital identification to support two-factor authentication and access to eCMS. Provide and maintain computer hardware and software for the eCMS access throughout the duration of the contract for all Contractor-designated users. Provide connectivity, speed, bandwidth, and access to the Internet to ensure adequate functionality. Neither upgrading of the Contractor's computer system nor delays associated from the usage of the eCMS will be justification or grounds for a time extension or cost adjustment to the Contract.
SECTION 01 31 23.13 20 Page 3
1.4.2 Contractor Personnel List
Within 20 calendar days of contract award, provide to the Contracting Officer a list of Contractor's personnel who will have the responsibility for the transfer, sharing and management of electronic design, technical submittals and documents and will require access to the eCMS. Project personnel roles to be filled in the eCMS include the Contractor's Project Manager, Designer of Record, Superintendent, Quality Control (QC) Manager, and Site Safety and Health Officer (SSHO). Personnel must be capable of electronic document management. Notify the COR immediately of any personnel changes to the project. The Contracting Officer reserves the right to perform a security check on all potential users. Provide the following information:
First Name Last Name E-mail Address Office Address Project Role (e.g. Project Manager, QC Manager, Superintendent)
1.4.3 Field Administration
Provide a tablet computer with a Common Access Card (CAC) reader at the job site for Government use only. The tablet computer must have a web-browser, built-in camera, and cellular data connectivity.
The tablet computer must be fully charged and made available at all times for Government use to facilitate the input of construction data at the job site. After completion of the work, reset the tablet computer to factory default settings. The tablet computer remains the property of the Contractor and must be removed from the site.
1.5 SECURITY CLASSIFICATION
In accordance with Department of Navy guidance, all military construction contract data are unclassified, unless specified otherwise by a properly designated Original Classification Authority (OCA) and in accordance with an established Security Classification Guide (SCG). Refer to the project's OCA when questions arise about the proper classification of information.
The eCMS and tablet computer must only be used for the transaction of unclassified information associated with construction projects. In conformance with the Freedom of Information Act (FOIA), Department of Defense Manual 5200.01-V4: DoD Information Security Program: Controlled Unclassified Information (CUI), and DoD requirements, any unclassified project documentation uploaded into the eCMS must be designated either "U
- UNCLASSIFIED" (U) or "FOUO - UNCLASSIFIED-FOR OFFICIAL USE ONLY"
(FOUO).
1.6 ECMS UTILIZATION
Establish, maintain, and update data and documentation in the eCMS throughout the duration of the contract.
1.6.1 Information Security Classification/Identification
The eCMS must be used for the transmittal of the following documents.
This requirement supersedes conflicting requirements
SECTION 01 31 23.13 20 Page 4 in other sections), however, submittal review times in Section 01 33 00 SUBMITTAL PROCEDURES remain applicable.
Table 1 - Project Documentation Types provides the appropriate U and FOUO designations for various types of project documents. Construction documents requiring FOUO status must be marked accordingly. Apply the appropriate markings before any document is uploaded into eCMS. Markings are not required on U documents.
Table 1 also identifies which eCMS application is to be used in the transmittal of data (these are subject to change based on the latest software configuration). If a designated application is not functional within 4 hours of initial attempt, defer to the Submittal application and submit the required data as an uploaded portable document (e.g. PDF), word processor, spreadsheet, drawing, or other appropriate format.
Hard copy or e-mail submission of these items is acceptable only if eCMS is documented to be not available or not functional. For Submittals, select the following:
Preparation by = Contractor personnel assigned to prepare the submittal Approval by = Contracting Officer Representative (COR) Returned by = Design Lead/Manager Forwarded to = Contractor project manager
Table 1 - Project Documentation Types
SUBJECT/NAME CLASS REMARKS ECMS APPLICATION
As-Built Drawings U Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
Document management, documents, submittals
Base Access Request/Approval
FOUO 1. Verify applicability with local installation security procedures via the Administrative Contracting Office
2. Redact Social Security Numbers (SSNs) prior to upload into eCMS, unless SSNs are required by the local security office to support security clearance investigations or verifications
Communications management, communications
Building Information Modeling (BIM)
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Document management, documents, submittals
SECTION 01 31 23.13 20 Page 5
Construction Permits U Refer to rules of the issuing activity, state or jurisdiction
Document management, documents, submittals
Construction Schedules (Activities and Milestones)
U After the schedule submittal is approved by the COR, import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Document management, Construction Schedules (Cost-Loaded)
FOUO Document management, documents, submittals
DD 1354 Transfer of Real Property
U Document management, documents, submittals
Daily Production Reports
FOUO Provide weather conditions, crew size, man-hours, equipment, and materials information
Site management, Daily Report
Daily Quality Control (QC) Reports
FOUO Provide QC Phase, Definable Features of Work Identify visitors
Site management, Daily Report
Designs and Specifications
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Document management, documents, submittals
Environmental Notice of Violation (NOV), Corrective Action Plan
U Refer to rules of the issuing activity, state or jurisdiction
Document management, documents, submittals
Environmental Protection Plan (EPP)
FOUO Document management, SECTION 01 31 23.13 20 Page 6
Jobsite Documentation, Bulletin Board, Labor Laws, SDS
U Document management, documents, submittals
Meeting Minutes FOUO Communication management, meeting minutes
Operations & Maintenance Support Information (OMSI/eOMSI), Facility Data Worksheet
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Document management, documents, submittals
Photographs U Subject to base/installation restrictions
Document management, documents, submittals
QCM Initial Phase Checklists
FOUO Site management, Checklists
QCM Preparatory Phase Checklists
FOUO Site management, Checklists
Quality Control Plans FOUO Document management, documents, submittals
QC Certifications U Document management, documents, submittals
QC Punch List U Site management, Punch lists
Red-Zone Checklist U Site management, Checklists
Rework Items List FOUO Site management, Punch lists
SECTION 01 31 23.13 20 Page 7
Request for Information (RFI) Post-Award
FOUO Communications management, RFIs
Safety Plan FOUO Site management, Daily Report
Safety - Activity Hazard Analyses (AHA)
FOUO Site management, Daily Report
Safety - Mishap Reports
FOUO Site management, Daily Report
SCIF/SAPF
Accreditation Support Documents
FOUO Note: Some Construction Security plans may be classified as Secret.
Classified information must not be uploaded into eCMS. Refer to the Site Security Manager, as applicable.
Document management, documents, submittals
Shop Drawings U Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
Document management, documents, submittals
Storm Water Pollution Prevention (Notice of Intent - Notice of Termination)
U Refer to rules of the issuing activity, state or jurisdiction
Document management, documents, submittals
Submittals and Submittal Log
U Document management, documents, submittals
Testing Plans, Logs, and Reports
FOUO Site management, QC inspection and testing plan
Training/Reference Materials
U Document management, SECTION 01 31 23.13 20 Page 8
Training Records (Personnel)
FOUO Document management, Utility Outage/Tie-In Request/Approval
FOUO Document management, documents, submittals
Warranties/BOD Letter FOUO Document management, documents, submittals
Quality Assurance Reports and Compliance Notices
FOUO GOV ONLY
Other Government-prepared documents
FOUO GOV ONLY
All Other Documents FOUO Refer to FOIA guidelines and contact the FOIA official to determine whether exemptions exist
As applicable
1.6.2 Markings on FOUO documents
a. Only FOUO documents being electronically uploaded into the eCMS (.docx, .xlsx, .pp and others as appropriate), and associated paper documents described in the paragraph CONTRACT ADMINISTRATION require FOUO markings as indicated in the subparagraphs below.
b. FOUO documents that are originally created within the eCMS application using the web-based forms (RFIs, Daily Reports, and others as appropriate) will be automatically watermarked by the eCMS software, and these do not require additional markings.
c. FOUO documents must be marked "UNCLASSIFIED//FOR OFFICIAL
USE ONLY" at the bottom of the outside of the front cover (if there is one), the title page, the first page, and the outside of the back cover (if there is one).
d. FOUO documents must be marked on the internal pages of the document as "UNCLASSIFIED//FOR OFFICIAL USE ONLY"' at top and bottom.
e. Where Installations require digital photographs to be designated FOUO, place the markings on the face of the photograph.
f. For visual documentation, other than
SECTION 01 31 23.13 20 Page 9 photographs and audio documentation, mark with either visual or audio statements as appropriate at both the beginning and end of the file.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
-- End of Section --
| 05/17 |
| 05/17 |