(D) NEPA.pdf
PDF 263 KB Posted
- Attached to
- M2M &M12N Feeder Repairs
- Solicitation number
- 6012068
About this file
This document is a NEPA Environmental Checklist used to determine the environmental requirements associated with a proposed project to replace electrical feeders M2M, M12N, and switch SW204 at the Naval Submarine Base New London in Groton, Connecticut.
The project involves replacing 13.8KV electrical feeders and switch, as the existing feeder has failed. The work will be performed within existing ductbanks with no anticipated disturbance. The project is categorically excluded under NEPA, requiring only a 1-week review process. However, the project is subject to various environmental requirements, including stormwater management, wastewater discharge approval, hazardous materials management, and asbestos abatement. Specific design, construction, and operational requirements are detailed in the document. The project is part of a Multiple Award Construction Contract (MACC) with 7 pre-qualified contractors allowed to bid on the work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI 2 Responses.pdf | ||
| Amendment 0001.pdf | ||
| RFI Responses.pdf | ||
| Site Visit Log.pdf | ||
| (A) RFP Information Rev1.pdf | ||
| (I) General Requirements.pdf | ||
| (E) LESSA.pdf | ||
| (P) CERT-141.pdf | ||
| (M) Map to B135.pdf | ||
| (K) RFI Form.pdf | ||
| (H) FAR 52.204-24.pdf | ||
| (F) CT20240024 03 MAY 2024.pdf | ||
| (N) Building Contractors Guide to Taxes.pdf | ||
| (B) Specifications.pdf | ||
| (A) RFP Information.pdf | ||
| (O) 2016-R-0149.pdf | ||
| (L) Base Map.pdf | ||
| (J) ECMS.pdf | ||
| (G) Price Proposal Form.pdf | ||
| (C) Drawings.pdf |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NEPA ENVIRONMENTAL CHECKLIST – SUBASENLON
NEW FORM EFFECTIVE 07/10/2020. This NEPA Environmental Checklist (EC) is used to determine the environmental requirements associated with a proposed project. Complete the first 2 pages of the form, attach a site map and a SOW or 1391, and then submit to the PWD Environmental Division (EV). A complete EC with required attachments should be submitted a minimum of 15 days prior to project’s scheduled start date. If the project scope is modified or if project work has not been initiated within 1 year of the signature date, please contact EV for review/approval prior to initiating project activities.
GENERAL PROJECT INFORMATION
1 Activity Requesting: PWD NLON
2 Activity POC / Phone / email: Phil Damicis / 860-694-4987/ philip.damicis.civ@us.navy.mil
3 Name of Project: Repair Shore Power Feeders M2M/M12N & SW204
4 Project Number (if any): Eprojects #1765652
5 Project Location: Naval Submarine Base New London, Groton, CT
6 Project Type: Repair
7 Description of the Project: Replace 13.8KV Electrical Feeders M2M & M12N & Switch SW204
8 Why is this project needed? Existing electrical feeder has failed.
9 Date project scheduled to begin? 09/2023
PLANNING QUESTIONS
10a Total Project Area (sq. ft.) - (Include clear zones, soil disruption/disturbance area, lay down areas, etc)
4000 sf, Feeders to be run in existing ductbanks, no disturbance anticipated.
10b Percentage of Project Area - that is currently Impervious (asphalt, bldgs, etc.) 100
10c Percentage of Project Area - that will be Impervious once project completed 100
10d Percentage of Project Area - that will be disturbed (excavated, graded, etc) 0
11 How will Stormwater be managed in the long-term (post-construction)? No change
12 How will Sanitary Sewage (wastewater) be managed in the long-term? No change
13 Will there be actions conducted in the water (dredging, new pilings, removal etc.)? If so indicate state what action(s). No
14 Will there be actions conducted in an area under an Agriculture outlease? No
DESIGN RELATED QUESTIONS YES NO UNSURE
15 Will trees be removed?
16 Will emission-generating equipment (e.g. bull dozer, back hoe, etc.) be utilized during construction? If yes, please list equipment.
17 Will the project remove, install or utilize a petroleum storage tank, that is >=55-gallons?
18 Will the project remove or install an Oil Water Separator?
19 Will the project relocate excavated material at the Installation? If yes where is it going?
Will the construction / repair actions generate by-products (power washing water, haz. waste, state regulated waste such as asbestos, PCB items, transformers, capacitors, switches, light ballasts, lead paint chips, florescent bulbs, waste oil, solvents, etc)? If so indicate what type of waste(s) will be generated. Possible lead cable and asbestos fire wrap.
Will the construction / repair actions require de-watering from excavations, trenches or manholes? If yes, circle where de-watering will occur? Dewatering of manholes shown on drawings.
DESIGN RELATED QUESTIONS YES NO UNSURE
22 Will there be new hard pipe connections or modifications to existing hard pipe connections using water from Groton Utilities, the Thames, or wells?
Will new hard pipe connections or modifications to existing hard pipe connections discharge wastewater to the sanitary sewer, storm sewer or the Thames River? If so circle discharge type.
24 Will there be UST or AST installation, modification, or removal? If so indicate which type of tank and which action.
25 Will there be installation, repair, modification or removal of any system containing refrigerants
(e. g. freon, halon)?
26 Will there be modifications, destruction, or disturbance of the shoreline, streams, groundwater tables, surface water bodies, or wetlands? If so, explain.
Will there be any excavation and/or dewatering with the potential to impact the designated CT Coastal Zone (i.e., 1,000 feet inland from the MHW line)? If so, what type of activity will occur that can potentially impact the coastal zone area?
28 New proposed use and/or application of pesticides, rodenticides and herbicides? If so, indicate which type.
29 Will the project require pile driving?
OPERATIONAL RELATED QUESTIONS YES NO UNSURE
30 Will emission-generating equipment be installed (ex. paint booth, emergency generators)? If so, what type of equipment will be installed?
31 Will there be any new processes or maintenance activities conducted? If so, describe what they are.
ADDITIONAL COMMENTS
Type here:
SAME 4/11/2023
Checklist Preparer, phone number and e-mail (if Same as Question #2 – Type “SAME”) Date
NEPA ENVIRONMENTAL CHECKLIST – SUBASENLON
SUMMARY OF ENVIRONMENTAL REQUIREMENTS
(To Be Completed by Environmental Division Only) PLEASE NOTE: The Environmental review provided is only valid for 1 year. If the project scope has been modified or checklist has expired, please contact the SUBASENLON PW Environmental Division to re-evaluate the project.
Name of Project: Repair Shore Power Feeders M2M/M12N & SW204
Project Number: Eprojects #1765652
PLANNING REQUIREMENTS (Issues That Can Effect the Project’s Timeline, Cost, or Site Location) Environmental Aspect YES NO Environmental Requirement Project Impacts
National Env Policy Act (NEPA) CATEX CATEX = 1 week; EA = 12 months; EIS = 24 months Can’t award till NEPA complete
Threatened or Endangered Species Consultation with USFWS and/or NMFS required. Process may take 6 months
Marine Mammal Protection Act IHA or LOA Consultation with NMFS May take 4 to 18 months
Wetland Impacts Permits and possibly mitigation required. May take 7 months after
NEPA
Navigable Water Impacts Permits required. Takes 2-7 months after
NEPA
Agriculture Outlease Consultations with NAVFAC Real Estate required. Process may take 1 to 3 months.
Tree Mitigation Compensation for tree loss or mitigation is required. This may add costs to project.
Coastal Zone Mgmt Act Coastal Consistency Determination (CCD) is required. Process takes 90 days.
Cultural Resources Consultations with SHPO required. Process may take 1 to 6 months
Major Air Emission Source Permit is required. Process takes 6 months
Construction Emissions Air Conformity Record of Non-Applicability is required. This process takes a week.
Installation Restoration Land-use controls exist or Consultation w/ EPA required Process may take 4 months
Petroleum Contamination Follow guidance in CNRMA POL SOP. This may add costs to project.
DESIGN REQUIREMENTS (Issues To Be Addressed In Design Phase) Storm Water Best Mgmt
Practices, Erosion & Sediment Control
Required for projects that include excavation or other land disturbance. Refer to Requir 1. Incorporate into the design.
CT Storm Water Mgmt Permit Required for projects that will disturb ≥ 1 acre of land. Obtain before construction.
De-watering, Wastewater Mgmt Protective measures required for managing excess waters. Refer to Requir 2. Incorporate into the design.
Beach & Dune Management Protective measures required for impact beaches & dunes Incorporate into the design.
Spill Preventative Measures Secondary containment required for tanks ≥ 55 gal Incorporate into the design.
OPERATIONAL REQUIREMENTS (Issues To Be Addressed Prior To Use)
New Industrial Process Environmental Department Site Inspection required. Required before operation.
New Waste Generating Activity Environmental Department Site Inspection required. Required before operation.
ADDITIONAL REQUIREMENTS or COMMENTS Comment 1 The proposed action is within the scope of CATEX #8: Routine repair and maintenance of buildings, facilities, vessels, aircraft, ranges, and equipment associated with existing operations and activities. None of the exclusions from reliance on a CATEX applies in this case; therefore, the proposed action does not require further NEPA analysis.
The applicability of this CATEX determination is based on the full implementation of all environmental requirements identified below.
Requir 1 If excavation is required, work shall be executed in full compliance with the provisions of the General Permit for the Discharge of Stormwater from Small Municipal Separate Storm Sewer Systems (MS4 Permit), the SUBASENLON Stormwater Pollution Prevention Plan, and the SUBASENLON Stormwater Management Plan. Appropriate erosion and sediment control measures shall be used when performing work under the scope of this project.
Requir 2 PW NLON EV Division shall be notified immediately of any actions that require wastewater discharges under the scope of this project. No discharges shall occur without prior approval from with the PW NLON EV Division Wastewater Program Manager (x5159).
Requir 3 PW NLON EV Division Hazardous Waste Program Office (x4298) shall be notified prior to project start regarding any lead removal, recycling, and/or disposal.
Requir 4 If excavation is required, a dig permit shall be obtained from and approved by the PWD prior to initiation of any ground-disturbing activities. Soil management procedures as detailed in the dig permit and the SUBASE Soil Management SOP shall be followed. Soil that cannot be returned to its original location may need to be disposed of off-base at the contractor's expense.
Requir 5 No emissions of asbestos shall be generated in the execution of this project. Full compliance with the provisions of the federal Asbestos NESHAP is required, including proper management and disposal of all asbestos waste generated as a result of performing the prescribed work under this project.
Requir 6 Existing HAZMAT surveys shall be reviewed prior to any disturbance. If suspect hazardous materials (such as asbestos and lead paint) are present and are anticipated to be disturbed under the scope of the project, surveys shall be conducted by qualified individuals in advance of construction activity. All survey results shall be provided to the PW NLON EV Division.
Requir 7 Management, storage, and disposal of any regulated waste shall be coordinated in advance with the PW NLON EV Division Hazardous Waste Program Office (x4298).
- All regulated waste shall be manifested through the Hazardous Waste Program Office.
- Any regulated waste generated under the scope of this project shall be managed, stored, and disposed of in accordance with the SUBASENLON Hazardous Waste Management Plan and SUBASENLON policies and instructions.
- Non-regulated solid waste (i.e., general trash, construction debris, and recyclable items) shall be properly managed and disposed of in accordance with Federal, State, Navy, and local regulations.
Requir 8 Use of exterior storage and laydown areas in support of this project shall be done in compliance with SUBASENLON instructions and policies. Site must be evident of good housekeeping practices consistent with proper storm water management and control.
Christopher Koproski, Installation Environmental Program Director; x3976; christopher.r.koproski.civ@us.navy.mil
Environmental POC; phone number and email Signature and Date mailto:christopher.r.koproski.civ@us.navy.mil
| DESIGN RELATED QUESTIONS |
| DESIGN RELATED QUESTIONS |
| 2023-04-24T15:51:43-0400 | |
| KOPROSKI.CHRISTOPHER.R.1013633343 |
File details come from the government source that posted it. Updated .