This is a technical specification document for equipment integration at the Dallas Consolidated Mail Outpatient Pharmacy (CMOP) facility in Lancaster, Texas, which is part of a larger Low to Medium Volume TCA and Sorting Loops Project under Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 15.
The document addresses the West KNAPP return puck conveyor system that operates through the new TCA (Totally Computerized Automation) area and specifies that this conveyor can be removed or modified to accommodate new equipment installation and design. The document notes that pucks are not tracked during return to puck ponds, but feeder spirals have readers that track pucks to loops and puck packing stations. A critical requirement is that if the feeder spirals are modified, the contractor must be capable of integrating modifications into the new system without degrading the existing KNAPP system performance. The CMOP processes approximately 90,000 prescriptions daily and requires reliable, efficient automation infrastructure to maintain operational performance and support anticipated increases in workload. The related solicitation (36C77026T0007) was updated with an RFP extended deadline of August 20, 2026.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1 day snapshot.xlsx | XLSX spreadsheet | |
| G. Dallas Manual Dispensing for New TCA.xlsx | XLSX spreadsheet | |
| H. Dallas TCA Products 07132026.xlsx | XLSX spreadsheet | |
| K. L034.00113-510A.pdf | ||
| I. Dallas_CMOP_Floor Plan.pdf | ||
| L. CHIP Programming job aid 1.pdf | ||
| B. Attachment 1 for Dallas CMOP TCA Low to Medium Volume.docx | DOCX document | |
| A. PWS TCA System Installation_Final_updated 7.8.26.docx | DOCX document | |
| E. BOT2000.pdf | ||
| RFP_36C77026R0007_extended.docx | DOCX document | |
| D. Past Performance Questionnaire.docx | DOCX document | |
| F. CAP1185CL-foil-lined- CAP1190CL-foam-lined.pdf | ||
| C. BUSINESS ASSOCIATE AGREEMENT.pdf | ||
| M. CHIP Program Deleting job aid 2.pdf | ||
| S06_Amendment_36C77026R0007.docx | DOCX document | |
| S05_Questions and Clarifications_R0007.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Note: The West KNAPP return puck conveyor that runs through the new TCA area, can be removed and or modified for ease of new equipment installation and design. Pucks are not tracked going back to the puck ponds. The feeder spirals all have readers that track pucks to the loops and puck packing. If these are modified, contractor must be able to integrate into the new system without de grading the KNAPP system.