J.4 Statement of Work (1 Page).pdf

PDF 4 MB Posted

Attached to
Bloomington Lake - Midland Trail Federal contract opportunity
Solicitation number
1240LT24Q0028
Issued by
Department of Agriculture Forest Service

About this file

This document is a Statement of Work (SOW) for the Montpelier Ranger District Midland Trailhead Gravel FY24 project. The project is located in Bloomington Canyon in Bear Lake County, Idaho and involves hauling and placing 700 cubic yards of gravel for the trailhead, as well as temporary traffic control. An optional task includes hauling and placing an additional 467 cubic yards of gravel on Road #30457. The work shall follow FP-14 requirements and Forest Service Supplemental Specifications. The period of performance is 30 calendar days, with the base items estimated to be executed from July 8 to August 7, 2024 and the optional items from August 8 to August 15, 2024. This SOW is related to Solicitation Number 1240LT24Q0028 for the Bloomington Lake - Midland Trail project, which has an estimated construction value between $25,000 and $100,000.

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

Description:

**Attach images and extra work as necessary**

Text108: Montpelier Ranger District Midland Trailhead Gravel

FY24 TASK ORDER INFORMATION

Date: January 26, 2024

BRIEF DESCRIPTION OF PROJECT:

The project is located on the Bloomington Canyon access road #30409 off US Highway 89 (42°10'35" N, 111°33'00" W) in Bear Lake County, Idaho. Proposed work hauling and placing 700 CY of gravel for the trail head, as well as temporary traffic control. Option items include hauling, placing, 467 CY of gravel on Road #30457 from the junction to the trail head. Local traffic shall be closed during construction with temporary traffic control measures in place. This project shall follow related FP-14 requirements and the Forest Service Supplemental Specifications for construction.

Location: Bloomington Canyon in Bloomington, Bear Lake County, Idaho (44°10'35" N, 111°33'00" W)

Period of Performance:

Contract time begins on the effective date of the Notice to Proceed (NTP) and runs for 30 calendar days. Estimated time to start work is July 8 to August 7, 2024 for base items. Estimated time for Option Item 1 is from August 8 to August 15, 2024, adding 7 calendar days.

Reference contract for all other terms and conditions.