This document is an amendment to a solicitation for the Bloomington Lake - Midland Trail project. The purpose of this amendment is to document a site visit and provide answers to questions asked. The project involves hauling and placing 700 CY of gravel for the trailhead, as well as temporary traffic control. An option item includes hauling and placing 467 CY of gravel on Road #30457 from the junction to the trailhead. The project is located in Bear Lake County, Idaho and has an estimated magnitude of construction between $25,000 and $100,000. A pre-proposal site visit is scheduled, and proposals must be submitted electronically to the Forest Service by June 26, 2024. The period of performance is from September 1, 2024 to October 18, 2024.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

1240LT24Q0028

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

40LT

OGDEN UT 84401-2310

324 25TH ST

USDA-FS CSA INTERMOUNTAIN 8

06/21/20240004

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

04/12/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Amendment 0004 - The purpose of this amendment is to document the site visit and provide answers to questions asked. The offer due date is extended until June 26th, 2024. There are no other changes.

PROJECT NAME: BLOOMINGTON LAKE - MIDLAND TRAIL

PROJECT DESCRIPTION: Proposed work hauling and placing 700 CY of gravel for the trail head, as well as temporary traffic control. Option items include hauling, placing, 467 CY of gravel on Road #30457 from the junction to the trail head. Local traffic shall be closed during construction with temporary traffic control measures in place. This project shall follow related FP-14 requirements and the Forest Service Supplemental Specifications for

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

WESTLEY M. BISSON

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

1240LT24Q0028/0004

construction.

PROJECT LOCATION: The project is located on the

Bloomington Canyon access road #30409 off US

Highway 89 (42°10'35" N, 111°33'00" W) in Bear

Lake County, Idaho.

PRE-PROPOSAL SITE VISIT SCHEDULED? YES, SEE

SECTION L.

SUBMIT PROPOSALS TO WESTLEY.BISSON@USDA.GOV AND

NINI.ANDERSON@USDA.GOV. DO NOT MAIL PROPOSALS.

Period of Performance: 09/01/2024 to 10/18/2024

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Q:

A:

Q:

A:

Q:

A:

Q:

A:

Q:

A:

Q:

A:

Q:

A:

Q:

A:

Will the boulders be placed before or after the gravel is hauled and placed?

The boulders aquired from site during construction may be placed in an agreed upon location for future installation.

The water is for dust control on the access road as needed as well as for compacitng placed materials.

Where and how do we need to provide traffic control?

Contractor is required to submit a traffic control plan that meets MUTCD standards for our review. Advance warning signs for construction activities and trauck hauling, appropriate signs for road closure (Type III barricades) and trail closures must be placed. We need to send out public notices at least 2 weeks in advance of the dates/times of closure. Road will be closed from the Junction of FS road 409 and FS road 457.

Midland Trailhead Pre-bid Meeting 6/7/2024

Who Places the gravel once it is hauled?

The contractor is responsible for hauling and placing the gravel.

How far does the dust control need to be along the road?

Will the access road to the site be graded before gravel is hauled in?

Not unless there is an opportunity to smoothblade the road.

If the optional bid item is awarded, will the government grade that section of road before the gravel is hauled and placed there?

The contractor would be responsible for smoothblading, incidental to the installation of gravel. (Not a separate bid item). No testing will be required on the existing material.

For the compaction, do we provide testing and results?

The contractor will need testing to deterimine the required compaction effort for each material (i.e. 4 roller passes for base, 6 for surface aggregate, etc) Establish Roller pattern with testing on day 1. Random verification testing once material is placed for acceptance.

Can the water for dust control be taken from the site or does that need to be hauled in?

The water for dust control could be permitted, but the contractor would be responsibe for obtaining any required permits through the governing agency for the water source.