Attachment J.3
POWER SERVICES GROUP GOVERNMENT FURNISHED EQUIPMENT (GFE)
In support of the requirements of the Statement of Work and contract, below is a sample list of equipment that may be provided as GFE:
ELECTRICAL POWER DISTRIBUTION EQUIPMENT (EDE)
Vendor: Schneider Electric/Square D
Equipment: Switchboards, Switchgear, Panel boards, Circuit Breakers, Transformers, and Monitoring
Software and Hardware
Lead-time: Large Switchboards 4-5 months, Panel boards 1-3 months, Transformers 1-3 months
Switchgear 6-9 months
ENGINE GENERATOR (EG)
Vendor: Kohler
Equipment: Propane engine generators 20 kW to 100 kW
Diesel engine generators 15 kW to 1.5 MW
Automatic Transfer Switches, Load Banks, Day Tanks/Sub-Base Tanks and Mufflers
Voltages 480, 208, 240 three phase, 240 single phase
Lead-Time: 6-months
STATIC AUTOMATIC TRANSFER SWITCH (STS)
Vendor: L-3 Communications
Equipment: 480 volt, 200 amp to 600 amp
208 volt, 3 or 4-pole, 150 amp to 600 amp
Lead-Time: 158 - 365 days
UNINTERRUPTIBLE POWER SUPPLY (UPS)
Vendor: Eaton Electric
Equipment: 480 volt 30 KVA to 825 KVA
208 volt 10 KVA to 160 kVA
Battery strings, battery monitors, and bypass panels.
Lead-Time: small to medium UPSs and associated equipment 12-weeks
DIRECT CURRENT BACK-UP SYSTEM (DC BUS)
Vendor: Oceus
Equipment: 24 volt DC BUS, UXTM, ERMS, batteries, battery rack and strings
Lead-Time: 60-90 days
Note: Some equipment may have longer lead times than listed above.