Sheet1
| BASE PERIOD | |||||||
| CLIN | SUPPLIES OR SERVICES | QUANTITY | UNIT | UNIT PRICE | AMOUNT | ||
| 00001 | Reports from Site Visits and Conferences | 723 | EA | $0.00 | $0.00 | ||
| 00002 | CONUS Travel | 723 | EA | $0.00 | $0.00 | ||
| 00003 | OCONUS Travel | $0.00 | |||||
| 00003AA | Alaska | 15 | EA | $0.00 | $0.00 | ||
| 00003AB | Hawaii | 10 | EA | $0.00 | $0.00 | ||
| 00003AC | Puerto Rico | 10 | EA | $0.00 | $0.00 | ||
| 00003AD | Guam | 1 | EA | $0.00 | $0.00 | ||
| 00003AE | U.S. Virgin Islands | 2 | EA | $0.00 | $0.00 | ||
| 00003AF | Saipan | 1 | EA | $0.00 | $0.00 | ||
| 00003AG | American Samoa | 1 | EA | $0.00 | $0.00 | $0.00 | Total Travel Costs - Base Period |
| 00004 | Engineering Design Services | ||||||
| 00004AA | Superintendent Design Engineer | 9,504 | Hours | $0.00 | $0.00 | ||
| 00004AB | Electrical Engineer | 42,454 | Hours | $0.00 | $0.00 | ||
| 00004AC | Mechanical Engineer | 18,515 | Hours | $0.00 | $0.00 | ||
| 00004AD | Structural Engineer | 2,300 | Hours | $0.00 | $0.00 | ||
| 00004AE | Civil Engineer | 1,000 | Hours | $0.00 | $0.00 | ||
| 00004AF | Environmental Engineer | 1,000 | Hours | $0.00 | $0.00 | ||
| 00004AG | CAD Operator/ Designer | 46,020 | Hours | $0.00 | $0.00 | ||
| 00004AH | Clerical | 8,105 | Hours | $0.00 | $0.00 | $0.00 | Total Engineering Cost - Base Period |
| 00005 | Installation Services | - 0 | EA | TBN | $ 232,416,502.00 |
| OPTION PERIOD 1 | |||||||
| 00006 | Reports from Site Visits and Conferences | 537 | EA | $0.00 | $0.00 | ||
| 00007 | CONUS Travel | 537 | EA | $0.00 | $0.00 | ||
| 00008 | OCONUS Travel | $0.00 | |||||
| 00008AA | Alaska | 10 | EA | $0.00 | $0.00 | ||
| 00008AB | Hawaii | 10 | EA | $0.00 | $0.00 | ||
| 00008AC | Puerto Rico | 5 | EA | $0.00 | $0.00 | ||
| 00008AD | Guam | 1 | EA | $0.00 | $0.00 | ||
| 00008AE | U.S. Virgin Islands | 2 | EA | $0.00 | $0.00 | ||
| 00008AF | Saipan | 1 | EA | $0.00 | $0.00 | ||
| 00008AG | American Samoa | 1 | EA | $0.00 | $0.00 | $0.00 | Total Travel Costs - Option Period 1 |
| 00009 | Engineering Design Services | 1 | EA | $ - 0 | To Be Negotiated | ||
| 00009AA | Superintendent Design Engineer | 9,504 | Hours | $0.00 | $0.00 | ||
| 00009AB | Electrical Engineer | 42,454 | Hours | $0.00 | $0.00 | ||
| 00009AC | Mechanical Engineer | 18,515 | Hours | $0.00 | $0.00 | ||
| 00009AD | Structural Engineer | 2,300 | Hours | $0.00 | $0.00 | ||
| 000009AE | Civil Engineer | 1,000 | Hours | $0.00 | $0.00 | ||
| 00009AF | Environmental Engineer | 1,000 | Hours | $0.00 | $0.00 | ||
| 00009AG | CAD Operator/ Designer | 46,020 | Hours | $0.00 | $0.00 | ||
| 00009AH | Clerical | 8,105 | Hours | $0.00 | $0.00 | $0.00 | Total Engineering Cost - Option Period 1 |
| 00010 | Installation Services | - 0 | EA | TBN | $ 155,325,045.00 |
| OPTION PERIOD 2 | |||||||
| 00011 | Reports from Site Visits and Conferences | 537 | EA | $0.00 | $0.00 | ||
| 00012 | CONUS Travel | 537 | EA | $0.00 | $0.00 | ||
| 00013 | OCONUS Travel | $0.00 | |||||
| 00013AA | Alaska | 10 | EA | $0.00 | $0.00 | ||
| 00013AB | Hawaii | 10 | EA | $0.00 | $0.00 | ||
| 00013AC | Puerto Rico | 5 | EA | $0.00 | $0.00 | ||
| 00013AD | Guam | 1 | EA | $0.00 | $0.00 | ||
| 00013AE | U.S. Virgin Islands | 2 | EA | $0.00 | $0.00 | ||
| 00013AF | Saipan | 1 | EA | $0.00 | $0.00 | ||
| 00013AG | American Samoa | 1 | EA | $0.00 | $0.00 | $0.00 | Total Travel Costs - Option Period 2 |
| 00014 | Engineering Design Services | 1 | EA | $ - 0 | To Be Negotiated | ||
| 00014AA | Superintendent Design Engineer | 9,504 | Hours | $0.00 | $0.00 | ||
| 00014AB | Electrical Engineer | 42,454 | Hours | $0.00 | $0.00 | ||
| 00014AC | Mechanical Engineer | 18,515 | Hours | $0.00 | $0.00 | ||
| 00014AD | Structural Engineer | 2,300 | Hours | $0.00 | $0.00 | ||
| 000014AE | Civil Engineer | 1,000 | Hours | $0.00 | $0.00 | ||
| 00014AF | Environmental Engineer | 1,000 | Hours | $0.00 | $0.00 | ||
| 00014AG | CAD Operator/ Designer | 46,020 | Hours | $0.00 | $0.00 | ||
| 00014AH | Clerical | 8,105 | Hours | $0.00 | $0.00 | $0.00 | Total Engineering Cost - Option Period 2 |
| 00015 | Installation Services | - 0 | EA | TBN | $ 177,290,378.00 |
| Total cost - Base Year | $232,416,502.00 |
| Total Cost - Option Year 1 | $155,325,045.00 |
| Total Cost - Option Year 2 | $177,290,378.00 |
| Total Evaluated Price (TEP) | $565,031,925.00 |