J.3 Statement of Work and Specs (86 Pages).pdf

PDF 569 KB Posted

Attached to
Hailey House Water Damage Repair & Mold Remediation
Solicitation number
1240LT25Q0047
Issued by

About this file

This Statement of Work (SOW) details a mold remediation and water damage repair project for a Forest Service-owned house located at 220 3rd Ave S in Hailey, Idaho. The project requires comprehensive rehabilitation of water-damaged walls and ceilings, including removal and replacement of water-damaged sheetrock containing lead-based paint, insulation replacement, mudding, taping, texturing, and painting. Additional scope includes mold remediation in an upstairs room near a chimney, asbestos removal, and proper disposal of construction waste.

The project is scheduled for completion between July 1st and October 15th, 2025, with a 10-day construction window selected by the contractor. Key technical requirements involve handling lead-based paint and asbestos, maintaining proper containment, and following specific remediation procedures. The work will be performed while coordinating with the Contracting Officer's Representative (COR), and the contractor must provide all necessary labor, materials, and equipment. The estimated project value is between $25,000 and $100,000, with a pre-proposal site visit scheduled for August 8th, 2025, at the project location.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1

Section C - Description/Specifications/Statement of Work

GENERAL SPECIFICATIONS

Hailey House Mold Remediation and Water Damage Repair

1.1 SCOPE OF CONTRACT

A. This project includes all work to rehabilitate water-damaged walls and ceiling as well as remediate mold in a house owned by the Forest Service. The Contractor is responsible for providing all labor, materials, and equipment necessary to complete all bid items in this contract.

B. The work includes but is not limited to: removal and replacement of water damaged sheetrock that contains lead-based paint, removal and replacement of any damaged insulation, mudding and taping of replaced sheetrock, wall and ceiling texturing to match existing, painting repaired areas with paint that matches existing, and proper disposal of construction waste in three areas of the house – the living room entry wall, the kitchen ceiling, and an upstairs room wall that surrounds the chimney. It may be necessary to allow the studs and joists to dry before replacing insulation and sheetrock, Contractor is responsible to determine if this is necessary based on the specification requirements. The work will also include mold remediation for the upstairs room including allowing chimney walls to dry as necessary and coating with antimicrobial agents, and removal of asbestos adjacent to the chimney near the water damaged area. All work shall be completed in accordance with all specifications found in this contract and any related environmental regulations, and customary industry standards.

C. This project is to be completed while the building is occupied by tenants. Coordination and phasing of work with the COR and building occupants is required prior to performing any work. Staging and storage of materials are to be coordinated with the COR prior to the start of the project. Damages to any portion of the building outside areas described while this project is completed are to be repaired with matching finishes of what is currently installed at Contractor’s expense.

1.2 PROJECT LOCATION

A. The project is located at 220 3rd Ave S in Hailey, ID 83333.

1.3 SITE INFORMATION AND LIMITATIONS

A. The following site conditions are considered incidental to the contract and the Contractor will not be paid directly for any of the following items:

1. The Tenant will not be in the house during construction. The tenant will need a minimum 14-days’ notice before construction is to begin. The tenant’s furniture will remain in the house during construction.

2. Water is available at the site for construction purposes. Electrical utilities are also available at the site for construction purposes.

wbisson Cross-Out

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2

1.4 WORK CAMPS, STAGING AND STORAGE AREAS

A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage work trailers on site.

1.5 INSPECTION OF WORKSITE

A. The Contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

1.6 START DATE

A. * Flexible, as soon as possible.

1.7 CONTRACT TIME

A. Period of Performance: July 1st 2025-October 15, 2025

B. After award contractor will select a 10-day construction window within the Period of Performance during which all construction must be completed.

1.8 SPECIFICATIONS

A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.

SECTION 011250 - MEASUREMENT AND PAYMENT

SECTION 011400 - WORK RESTRICTIONS

SECTION 011900 - MOBILIZATION

SECTION 013300 - SUBMITTAL PROCEDURES

SECTION 017320 - SELECTIVE DEMOLITION

SECTION 024100 - WASTE MATERIAL DISPOSAL

SECTION 024134 - WORK INVOLVING LEAD-BASED PAINT (LBP)

SECTION 024200 - ASBESTOS ABATEMENT

SECTION 028500 - MOLD REMEDIATION

SECTION 061000 - ROUGH CARPENTRY

SECTION 072100 - BUILDING INSULATION

SECTION 092900 - GYPSUM BOARD

SECTION 096519 - RESILIENT TILE FLOORING

SECTION 099123 - INTERIOR PAINTING

SECTION 224213.13 - WATER CLOSETS

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-3

END OF SECTION C

May 2025

MEASUREMENT AND PAYMENT 011250-1

USDA FOREST SERVICE, R4

Hailey House Mold Remediation and Water Damage Repair

SECTION 011250 - MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 SUMMARY

A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.

B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.

1.2 DETERMINATION OF QUANTITIES

A. The following measurements and calculations shall be used to determine contract quantities for payment.

1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.

2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.

3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.

4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.

5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.

6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.

B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the Contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."

MEASUREMENT AND PAYMENT 011250-2

1.3 UNITS OF MEASUREMENT

A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:

1. Acre: Make longitudinal and transverse measurements for area computations horizontally.

2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.

3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.

4. Cubic Yard (CY): A measurement computed by one of the following methods:

a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.

b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.

c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.

Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

5. Each (EA): One complete unit, which may consist of one or more parts.

6. Gallons (GAL): The quantity shall be measured by any of the following methods:

a. Measured volume in container.

b. Metered volume by approved metering system.

c. Commercially package volume.

7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the Contractor.

8. Linear Foot (LF): Measurement of work along its length from point-to-point;

parallel to the base or foundation. Do not measure overlaps.

9. Lump Sum (LS): One complete unit.

10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.

11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.

12. Square Foot (SF): Measured on a plane parallel to the surface being measured.

13. Square Yard (SY): Measured on a plane parallel to the surface being measured.

14. Ton: Measured as a short ton consisting of 2,000 pounds.

1.4 METHOD OF MEASUREMENT

A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:

1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.

MEASUREMENT AND PAYMENT 011250-3

2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:

a. As a result of changes in the work authorized by the CO.

b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.

c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.

4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.

5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

END OF SECTION 011250

WORK RESTRICTIONS 011400-1

Hailey House Mold Remediation and Water Damage Repair

SECTION 011400 - WORK RESTRICTIONS

PART 1 - GENERAL

1.1 USE OF PREMISES

A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to living room, kitchen, and upstairs room with fireplace (areas needing drywall replaced and mold remediation).

2. Government Occupancy: Allow for Government occupancy of site.

3. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Occupants, Government employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

1.2 OCCUPANCY REQUIREMENTS

A. Full Government Occupancy: Government employees will occupy site and existing building during entire construction period. Cooperate with Government employees during construction operations to minimize conflicts and facilitate usage. Perform the Work so as not to interfere with occupant operations as much as practicable.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011400

MOBILIZATION 011900-1

Hailey House Mold Remediation and Water Damage Repair

SECTION 011900 - MOBILIZATION

PART 1 - GENERAL

1.1 SUMMARY

A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.

1.2 MEASUREMENT AND PAYMENT

A. The measurement shall be lump sum for mobilization. Payment shall be as follows:

1. Bond premiums will be reimbursed after receipt of the evidence of payment.

2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.

3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.

4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.

5. Progress payments for mobilization and preparatory work shall be subject to retainage.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 011900

SUBMITTAL PROCEDURES 013300-1

Hailey House Mold Remediation and Water Damage Repair

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.

B. See other specification section within this package for additional requirements on submittal.

1.2 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Allow 14 days for processing each re-submittal.

4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

C. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.

3. Include the following information on label for processing and recording action taken:

a. Project name.

b. Date.

SUBMITTAL PROCEDURES 013300-2

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. If more than one item is shown on submittal sheet, identify item.

D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.

1.3 MEASUREMENT AND PAYMENT

A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.

PART 2 - PRODUCTS

2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)

A. General: Prepare and submit Action Submittals required by individual Specification Sections.

1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Wiring diagrams showing factory-installed wiring.

f. Compliance with recognized trade association standards.

g. Compliance with recognized testing agency standards.

SUBMITTAL PROCEDURES 013300-3

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Include the following information, as applicable:

a. Dimensions.

b. Identification of products.

c. Fabrication and installation drawings.

d. Roughing-in and setting diagrams.

e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.

f. Notation of dimensions established by field measurement.

2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.

D. Contractor's Construction Schedule: The Contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.

E. Samples: Prepare physical units of materials or products, including the following:

1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies.

2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."

B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.

C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.

D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.

SUBMITTAL PROCEDURES 013300-4

E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.

PART 3 - EXECUTION

3.1 GENERAL

A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.

B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.

D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.

F. Requests for substitutions will only be considered if Contractor submits the following:

1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.

Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.

2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.

3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.

4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.

3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required

SUBMITTAL PROCEDURES 013300-5

submittals for the project - the table is to assist the Contractor and may not be all inclusive

– additional submittals may be required by specifications:

TABLE 013000-1

Spec.

Section Section Title Subsection Required Submittal

013300 Submittal Procedures 2.1D Construction Schedule 014100 Quality Control 3.5B Installer Qualifications 017320 Selective Demolition 1.4A Schedule of Selective Demolition

Activities 017320 Selective Demolition 1.4B Hazardous Waste Material

Manifest 024134 Work Involving Lead Based Paint 1.3A Health & Safety Plan 024134 Work Involving Lead Based Paint 1.3B RRP Records 024200 Asbestos Abatement 1.12B Qualifications 024200 Asbestos Abatement 1.12C Asbestos Work Plan 024200 Asbestos Abatement 1.12D Air Monitoring Plan 024200 Asbestos Abatement 1.12E Testing Laboratory (if used) 024200 Asbestos Abatement 1.12F Approved Landfill for Asbestos

Disposal 024200 Asbestos Abatement 1.12G Proof of Insurance for Asbestos

Abatement 024200 Asbestos Abatement 1.12H Evidence of Notification required by NESHAP 024200 Asbestos Abatement 1.12I Air Monitoring Results 024200 Asbestos Abatement 1.12J Waste Shipment Record required by NESHAP 024200 Asbestos Abatement 1.12K Final Report 028500 Mold Remediation 1.4E2 Preliminary Visual Assessment

Report 028500 Mold Remediation 1.4E3 Microbial Remediation Plan 028500 Mold Remediation 1.4E4 Respiratory Protection Program 028500 Mold Remediation 1.4E5 Worker Records 028500 Mold Remediation 1.4E6 Worker Training Certificates 028500 Mold Remediation 1.4F Certified Industrial Hygienist

Qualifications 028500 Mold Remediation 1.4G Microbial Remediation

Supervisor Qualifications 028500 Mold Remediation 1.4H Product Data for items identified in the Microbial Remediation Plan 028500 Mold Remediation 1.4I Daily Reports 028500 Mold Remediation 1.4J Closeout documents 072100 Building Insulation 1.3A Product Data 092900 Gypsum board 1.2.A Product Data 099123 Interior Paints and Coatings 1.3A Product Data & VOC Compliance 099123 Interior Paints and Coatings 1.3B Samples

SUBMITTAL PROCEDURES 013300-6

END OF SECTION 013300

SELECTIVE DEMOLITION 017320-1

Hailey House Mold Remediation and Water Damage Repair

SECTION 017320 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes demolition and removal of the following:

1. Selected portions of a building.

2. Repair procedures for selective demolition operations.

1.2 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.

B. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated.

C. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.

1.3 MATERIALS OWNERSHIP

A. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Government property, demolished materials shall become Contractor's property and shall be removed from Project site.

1.4 SUBMITTALS

A. Schedule of Selective Demolition Activities: Indicate detailed sequence of selective demolition and removal work, with starting and ending dates for each activity, including interruption of utility services.

B. Waste Manifests for materials deemed hazardous by the State of Idaho including refrigerant and fluorescent lights.

1.5 QUALITY ASSURANCE

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ANSI A10.6 and NFPA 241.

C. Pre-demolition Conference: Conduct conference at Project site with Contractor, subContractors, and Contracting Officer’s Representative.

SELECTIVE DEMOLITION 017320-2

1.6 PROJECT CONDITIONS

A. Conduct selective demolition so Government operations will not be disrupted. Provide not less than 72 hours' notice to CO of activities that will affect Government operations.

B. Maintain access to existing building amenities, pathways, and other adjacent occupied or used facilities.

1. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the COR.

C. Government assumes no responsibility for condition of areas to be selectively demolished.

1. Conditions existing at time of inspection for bidding purpose will be maintained by Government as far as practical.

D. Storage or sale of removed items or materials on-site will not be permitted.

1.7 MEASUREMENT AND PAYMENT

A. There will be no separate measurement or payment for work in this section. Payment will be included at the contract unit price for items shown on the Schedule of Items.

PART 2 - PRODUCTS

2.1 REPAIR MATERIALS

A. Use repair materials identical to existing materials.

1. If identical materials are unavailable or cannot be used for exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible.

2. Use materials whose installed performance equal or surpasses that of existing materials.

3. Salvage trim as needed and store for reinstallation.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped if necessary.

B. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to CO.

3.2 PREPARATION

SELECTIVE DEMOLITION 017320-3

A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

1. Erect temporary protection, such as walks, fences, railings, canopies, and covered passageways, where required by authorities having jurisdiction.

2. Protect existing site improvements, appurtenances, and landscaping to remain.

3.3 POLLUTION CONTROLS

A. Dust Control: Comply with governing environmental-protection regulations.

B. Cleaning: Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

3.4 SELECTIVE DEMOLITION

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations.

1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.

2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

3. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

4. Dispose of universal hazardous waste as required by EPA and State laws. A disposal site is listed above.

B. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse. Paint equipment to match new equipment.

2. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

C. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by CO, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.

3.5 PATCHING AND REPAIRS

A. General: Promptly repair damage to adjacent construction caused by selective demolition operations.

SELECTIVE DEMOLITION 017320-4

B. Repairs: Where repairs to existing surfaces are required, patch to produce surfaces suitable for new materials.

1. Completely fill holes and depressions in existing masonry walls that are to remain with an approved masonry patching material applied according to manufacturer's written recommendations.

C. Finishes: Restore exposed finishes of patched areas and extend restoration into adjoining construction in a manner that eliminates evidence of patching and refinishing.

D. Floors and Walls: Where walls or partitions that are demolished extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish color, texture, and appearance. Remove existing floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.

E. Ceilings: Patch and repair existing ceilings as necessary to provide an even-plane surface of uniform appearance.

3.6 UTILITY SERVICES

A. Existing Utilities: Maintain services indicated to remain and protect them against damage during selective demolition operations.

B. Do not interrupt existing utilities serving occupied or operating facilities unless authorized in writing by CO and authorities having jurisdiction. Provide temporary services during interruptions to existing utilities, as acceptable to CO and to authorities having jurisdiction.

1. Provide at least 72 hours notice to CO if shutdown of service is required during changeover.

C. Utility Requirements: Locate, identify, disconnect, and seal or cap off indicated utilities serving areas to be selectively demolished.

1. Arrange to shut off indicated utilities with utility companies.

2. If utility services are required to be removed, relocated, or abandoned, provide temporary utilities before proceeding with selective demolition that bypass area of selective demolition and that maintain continuity of service to other parts of building.

3. Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit after bypassing.

D. Utility Requirements: Do not start selective demolition work until utility disconnecting and sealing have been completed and verified.

3.7 DISPOSAL OF DEMOLISHED MATERIALS

A. General: Promptly dispose of demolished materials. Do not allow demolished materials to accumulate on-site.

SELECTIVE DEMOLITION 017320-5

B. Dispose of universal hazardous waste as required above.

C. Burning: Do not burn demolished materials.

D. Disposal: Transport demolished materials off Government property and legally dispose of them.

END OF SECTION 017320

WASTE MATERIAL DISPOSAL 024100-1

Hailey House Mold Remediation and Water Damage Repair

SECTION 024100 - WASTE MATERIAL DISPOSAL

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the loading, handling, hauling, and construction and demolition debris.

1.2 MEASUREMENT AND PAYMENT

A. There will be no separate measurement or payment for work in this Section. Waste material disposal is considered incidental to other items of work shown in the Schedule of Items.

PART 2 - PRODUCTS – NOT APPLICABLE

PART 3 - EXECUTION

3.1 WASTE MATERIAL TO BE HAULED TO A LANDFILL

A. All demolition materials, garbage, and other refuse generated shall be removed from the project site and legally disposed off of Government property in an approved landfill.

B. The Contractor is responsible for all costs and permits associated with landfill disposal.

C. The Government is not responsible for waste material upon its departure from the project site.

END OF SECTION 024100

WORK INVOLVING LEAD-BASED PAINT (LBP) 024134-1

Hailey House Mold Remediation and Water Damage Repair

SECTION 024134 - WORK INVOLVING LEAD-BASED PAINT (LBP)

PART 1 - GENERAL

1.1 DESCRIPTION OF WORK:

A. Work under this section includes those engineering controls which are necessary for surface preparation of materials to be resurfaced, or demolition/removal of materials, that are coated with lead-based paint (LBP).

B. This is a notification that the work under this contract will bring the Contractor into contact with LBP materials that may require worker protection.

C. The project is being performed at a dwelling unit subject to the U.S. Environmental Protection Agency’s (EPA’s) Renovation, Repair and Painting (RRP) Rule (40 CFR 745 Subpart E). All sections of the Rule shall be followed, except that information distribution requirements (40 CFR 745.84) are simplified because there are currently no occupants.

1.2 NOTICE OF HAZARD:

A. Exposure to airborne lead contaminants is a recognized hazard to human health. The Contractor shall assume that all painted surfaces on which work is required are coated with LBP.

1.3 SUBMITTALS:

A. Health and Safety Plan:

1. The Contractor shall provide a Health and Safety Plan for review and acceptance by the Contracting Officer. No work will commence until acceptance of the plan by the Contracting Officer.

2. The Health and Safety Plan will address, but not be limited to, the health-related standards and protective measures proposed to be utilized by the Contractor during work involving exposure to airborne lead contaminants.

3. The Health and Safety Plan will also identify the engineering and work practice controls proposed to be implemented by the Contractor. Such controls will be identified to assure the Government that there will be no release to the environment of lead contamination for which liability may be imposed on the Government.

B. RRP Records (40 CFR 745.86):

1. The Contractor shall provide a copy of the Firm Certification and the lead Certified Renovator before work commences.

2. Upon completion of the work, the Contractor shall provide a copy of all other records required by 40 CFR 745.86.

WORK INVOLVING LEAD-BASED PAINT (LBP) 024134-2

1.4 WORKER PROTECTION:

A. OSHA requirements for worker protection shall be followed in accordance with 29 CFR 1926.62, Lead Exposure in Construction.

1.5 WASTE ANALYSIS AND MANAGEMENT:

A. This project is being conducted at a residence. The wastes generated as part of this project’s LBP activities are considered household waste, and such wastes are excluded from RCRA’s hazardous waste management and disposal regulations. The Contractor shall be responsible for managing and disposing the LBP waste using best management practices described herein.

B. The Contractor shall segregate dust and small debris which may contain LBP. Such waste shall be double bagged, secured with tape.

C. Paint debris shall not be placed on unprotected ground and shall be shielded adequately to prevent dispersion by wind or rainwater.

D. The Contractor shall place lead-based paint chips, debris, and lead dust in double (4-mil) or single (6-mil) polyethylene bags that are air-tight and puncture-resistant.

E. Larger waste items which cannot be bagged shall be wrapped in plastic and secured with tape.

F. The Contractor will place all disposable cleaning materials, such as sponges, mop heads, filters, disposable clothing, and brooms in double (4-mil) or single (6-mil) plastic bags and seal.

G. The Contractor shall clean surfaces and equipment and bag large debris. The Contractor shall then remove plastic sheeting and tape from covered surfaces. Prior to removing the plastic sheeting, the Contractor shall lightly mist the sheeting in order to keep dust down and fold inward to from tight small bundles to bag for disposal. The Contractor shall place all plastic sheeting in double (4-mil) or single (6-mil) thick plastic bags and seal.

H. Contractor shall dispose of LBP waste in accordance with State solid waste regulations.

I. During the work, the Contractor shall not leave debris in the yard or nearby property, incinerate debris, dump waste by a road or in an unauthorized dumpster, or introduce lead-contaminated water into storm drains or sanitary sewers.

J. Waste shall be removed from the project site for proper disposal within one week of project completion. At no time will waste be allowed to accumulate on-site for a period of more than 30 days.

1.6 MEASUREMENT AND PAYMENT:

A. No separate measurement and/or payment will be made for this Section. This work will be included in a line items described in Section 099113.

WORK INVOLVING LEAD-BASED PAINT (LBP) 024134-3

PART 2 - PRODUCTS

2.1 MATERIALS:

A. Disposal bags and sheeting: Provide 4 mil or 6 mil thick plastic disposal bags and sheeting for wrapping LBP waste.

B. Disposal bins: Provide disposal bins for collection of waste prior to disposal by Contractor. All bins shall be secured when not in use to prevent deposit of unauthorized waste and debris.

C. Trisodium phosphate: Industry standard to mix with water for washing solutions on site.

PART 3 - EXECUTION

3.1 SITE PREPARATION:

A. The Contractor shall prepare the site in accordance with the Health and Safety Plan accepted by the Contracting Officer.

B. The Contractor is responsible for establishing and maintaining control measures sufficient to preclude any adverse effects to workers, Forest Service personnel and dependents, the public, and the environment.

3.2 REPAIR

A. The Contractor shall conduct all repair work in accordance with the Health and Safety Plan accepted by the Contracting Officer.

B. All waste will be handled in accordance with the provisions of this section 02094 and the directions of the Contracting Officer.

3.3 INSPECTION:

A. Contractor shall cooperate and coordinate all work with the Contracting Officer's inspection requirements. Inspection will center on compliance with the Health and Safety Plan accepted by the Contracting Officer.

3.4 CLEARANCE:

A. Contractor shall notify Contracting Officer of readiness for final inspection.

B. The visual inspection will occur no earlier than 24 hours after completion of the entire construction work.

C. Any visible debris will result in the Contractor recleaning the area at no additional cost to the Government.

3.5 DAILY CLEANUP

WORK INVOLVING LEAD-BASED PAINT (LBP) 024134-4

A. Daily cleanup shall be in accordance with the Health and Safety Plan accepted by the Contracting Officer. Any environmental cleanup caused by Contractor's failure to comply with the provisions of law, of this contract, or the accepted Health and Safety Plan shall be at Contractor's sole expense.

B. Do not allow any paint debris to enter industrial waste, storm drain or sanitary sewer lines.

3.6 HANDLING AND DISPOSAL OF NON-HAZARDOUS WASTE (AS DETERMINED

BY TESTING)

A. The Contractor shall comply with all Federal, State and local regulations concerning proper disposal of non-hazardous, solid waste.

B. The Contractor shall place lead-based paint chips, debris, and lead dust in double (4-mil) or single (6-mil) polyethylene bags that are air-tight and puncture-resistant. Pieces of wood or other types of substrates that do not fit into plastic bags will be wrapped and labeled "DANGER, LEAD DUST".

C. The Contractor will place all disposable cleaning materials, such as sponges, mop heads, filters, disposable clothing, and brooms in double (4-mil) or single (6-mil) plastic bags and seal.

D. The Contractor shall clean surfaces and equipment and bag large debris. The Contractor shall then remove plastic sheeting and tape from covered surfaces. Prior to removing the plastic sheeting, the Contractor shall lightly mist the sheeting in order to keep dust down and fold inward to from tight small bundles to bag for disposal. The Contractor shall place all plastic sheeting in double (4-mil) or single (6-mil) thick plastic bags and seal.

E. The Contractor shall bag and seal vacuum bags and filters in double (4-mil) or single (6-mil) thick plastic bags.

F. The Contractor shall place all contaminated clothing or clothing covers used during lead-based paint disturbing activities and during cleanup operations in plastic bags for disposal prior to leaving equipment room.

G. The Contractor shall place solvent residues and residues from strippers in drums made out of materials that cannot be dissolved or corroded by chemicals. Solvents will be tested by the Contractor to determine if they are hazardous.

H. Solvents, caustic and acid wastes must be segregated and not stored in the same containers.

I. The Contractor shall contain and properly dispose of all liquid waste, including lead-dust contaminated wash water.

J. The Contractor shall HEPA vacuum the exterior of all liquid waste containers prior to removing the waste containers from the work area and shall wet wipe the containers to ensure that there is no residual contamination. Containers should then be moved out of the work area into the designated storage area.

WORK INVOLVING LEAD-BASED PAINT (LBP) 024134-5

K. The Contractor shall carefully place the containers into the truck or dumpster used for disposal.

L. The Contractor shall ensure that all waste is transported in covered vehicles to an appropriately permitted landfill which accepts waste containing lead.

M. If the Contractor subcontracts the removing of the lead-based paint waste, he shall insure that the company removing the waste material adequately covers all loads so as to assure that no dust or debris is released.

3.7 HANDLING AND DISPOSAL OF HAZARDOUS WASTE (AS DETERMINED BY

TESTING)

A. The Contractor will be required to comply with the hazardous waste disposal regulations of RCRA Subtitle C, Managing Hazardous Waste.

B. If more than 220 pounds of hazardous waste will be generated from project activities during any calendar month, the Contractor shall apply for an EPA identification number from the appropriate Regional EPA office. If an EPA identification number application is required, it will be submitted on behalf of the US Forest Service; the US Forest Service will be listed as the generator and the generator’s address will be the project site address.

The U.S. Forest Service will assist the Contractor in contacting the appropriate EPA office to secure the identification.

C. Waste Containers: The Contractor will comply with EPA and DOT regulations for containers. The Contractor shall contact the state and local authorities to determine their criteria for containers. The more stringent regulation shall apply.

D. Waste Transportation: If the Contractor is not a certified hazardous waste transporter, a contract shall be entered into with a certified transporter to move the waste. The Contractor shall require the certified hazardous waste transport to follow RCRA regulation.

3.8 FINAL SITE CLEANUP

A. Clean all surfaces in the project area until no visible paint dust, debris, residue or chips remains.

B. Remove all dust and debris without dispersal and seal in heavy plastic bags.

C. Remove protective plastic sheeting and mist before folding it dirty side inward.

3.9 INSPECTION

A. Contractor shall notify Contracting Officer of readiness for final inspection.

B. Contractor’s Certified Renovator, accompanied by the Contracting officer, shall perform a visual inspection of the entire project area to determine if any visible dust and debris are present in or beyond the boundaries of the project area.

WORK INVOLVING LEAD-BASED PAINT (LBP) 024134-6

C. Any visible debris will result in the Contractor recleaning the area at no additional cost to the Government.

END OF SECTION 024134

ASBESTOS ABATEMENT 024200-1

Hailey House Mold Remediation and Water Damage Repair

SECTION 024200 - ASBESTOS ABATEMENT

PART 1 - GENERAL

1.1 SCOPE OF CONTRACT

A. The Sawtooth National Forest is preparing to repair the interior of the Hailey House located on the Ketchum Ranger District a structure.

B. Work shall consist of furnishing all labor, material, equipment, and supervision to perform asbestos removal and disposal in accordance with these specifications, the Environmental Protection Agency (EPA) Asbestos Hazard Emergency Response Act (AHERA), the EPA National Emission Standard for Hazardous Air Pollutants (NESHAP,) the Occupational Safety and Health Administration (OSHA), the National Institute for Occupational Safety and Health (NIOSH), the Department of Transportation (DOT), and other applicable federal, state, and local regulations.

1.2 DESCRIPTION OF WORK

A. A recent inspection by an accredited asbestos inspector has revealed the presence of friable asbestos in the building. This asbestos abatement project consists of the removal and disposal of all ACM identified in the report and air monitoring for the project conducted by an independent third party.

B. The asbestos inspection report for this project has identified the following asbestos containing materials: fiber board wall insulation located in the second floor room that is approximately 6 inches wide and 7 feet tall located in the corner of the wall surrounding the chimney which needs to be removed. The asbestos inspection report is included as a reference and further identifies the quantity and locations of the asbestos containing material.

C. The scope of the abatement work includes removal of all ACM noted in the inspection report and as shown in the drawings.

D. All asbestos abatement work will be performed prior to any building renovation or building demolition activities.

1.3 QUALIFICATIONS

A. The contracting firm shall provide documentation of the company’s qualifications in asbestos removal work and that the employed workers are trained and certified in accordance with federal regulations and applicable State regulations for the work areas in which they are accredited.

B. The asbestos Contractor (Contractor) must carry active “occurrence” type liability insurance while performing any work under this contract.

ASBESTOS ABATEMENT 024200-2

1.4 APPLICABLE REGULATIONS AND PUBLICATIONS

A. The regulations listed below form a part of this specification to the extent referenced.

The publications are referred to in the text by the basic designation only. The latest version of applicable regulations shall take precedence over the requirements of this specification when the regulation results in a higher standard of performance.

1. Code of Federal Regulations (CFR) Publications:

a. 29 CFR 1910.20 Access to Employee Exposure and Medical Records

b. 29 CFR 1910.134 Respiratory Protection

c. 29 CFR 1910.145 Specifications for Accident Prevention Signs and

Tags

d. 29 CFR 1910.1101 Asbestos - Occupational Safety and Health

Standards

e. 29 CFR 1926.1101 Asbestos - Safety and Health Regulations for

Construction

f. 40 CFR 61 Subpart A National Emission Standard for Hazardous Air

Pollutants

g. 40 CFR 61Subpart M National Emission Standard Subpart for Asbestos

h. 40 CFR 257 Criteria for Classification of Solid Waste Disposal

Facilities

i. 40 CFR 763 Asbestos and Asbestos Model Accreditation Plan

j. 40 CFR 763 Transport and Disposal of Asbestos Waste

k. 42 CFR 84 Approval of Respiratory Protective Devices

l…