J.2 Attachment Specifications-SaltLakePhase2.pdf
PDF 6 MB Posted
- Attached to
- Salt Lake District Office Renovation – Phase II
- Solicitation number
- 1240LT23R0024
- Issued by
-
Department of Agriculture Forest Service
About this file
This solicitation posting is for a federal contract opportunity with the Department of Agriculture Forest Service to renovate the Salt Lake District Office in Phase II. The solicitation involves remodeling two existing facilities that will serve as the future home of the Salt Lake Ranger District. Key work includes excavating and constructing a new east entry addition for one building, and selective demolition and finishes replacement for the interiors of both single-story structures. The contractor will bid on base items and optional tasks, such as site work, landscaping, and appliances. The performance period for the base work is 360 calendar days for one building and 180 days for the other. The solicitation number is 1240LT23R0024 and responses are due on an unspecified date.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
SALT LAKE RANGER DISTRICT OFFICE REMODEL, PHASE 2
1.1 SCOPE OF CONTRACT
A. This project consists of the remodeling of two existing facilities for the Salt Lake Ranger District Office. The facilities are owned and operated by the United States Forest Service as a part of the Unita Wasatch Cache National Forest and are located at 6944 S 3000 E (South Building) and 6914 S 3000 E (North Building) in Cottonwood Heights Utah.
1. The construction work will be arranged in base bid items with multiple optional bid items. The work will be phased to complete the North Building, described in Specification Section 000501, before completing the South Building, described in Specification Section 000502. The site repair work and landscaping for the entire campus are included in the scope of work as optional bid items. The contractor shall carefully review this section and the Schedule of Bid Items while bidding on the work to be done.
2. A general description of the work follows:
3. BASE Bid Items:
a. Base Bid Item #1: Bid Item 011900-1. Mobilization and bonding for the base bid items remodeling and addition to the north building. See spec 011900.
b. Base Bid Item #2: Bid Item 010250-1 Construction staking as described in specification 010250. Include construction staking needed for north building addition.
c. Base Bid Item #3: Bid Item 023701-1. Sedimentation and erosion control:
Provide sedimentation and erosion control for the North Building addition.
Refer to specification section 023701.
d. Base Bid Item #4: Bid Item 000501, Division 01 Work: Provide all coordination and management required to perform the specification Division 01 work for the remodel for the north building noted in the specifications including, but not limited to: utility coordination, project management, submittals, quality control, temporary facilities and control, all selective demolition costs, saw cutting and closeout procedures.
e. Base Bid Item #5: Bid Item 000501, Division 02 Work: Provide all materials and work for the remodel of the north building noted in the drawings and specifications Division 02 work including but not limited to: waste material disposal and hazardous waste disposal.
f. Base Bid Item #6 Bid Item 000501, Division 03 Work: Provide all materials and work for the remodel of the north building noted in the drawings and specifications Division 03 work including but not limited to: Reinforced concrete footings, foundations, slabs, sidewalks and stairs for the addition, skim coating of exterior foundations, and saw cutting and repairs to interior slabs on the lower floor. Include all prep including aggregate base, compaction, and finishing.
g. Base Bid Item #7 Bid Item 000501, Division 04 Work: Provide all materials and work for the remodel of the north building noted in the drawings and
J.2 Attachment-1240LT23R0024
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2
specifications Division 04 work including but not limited to: unit masonry repair, patching, and new unit masonry wainscotting for the building addition.
h. Base Bid Item #8 Bid Item 000501, Division 05 Work: Provide all materials and work for the remodel of the north building noted in the drawings and specifications Division 05 work including but not limited to: Steel framing, brackets and supports for the addition, steel countertop brackets, elevator ladder, sump pump covers, steel stair nosing, and pipe railings.
i. Base Bid Item #9 Bid Item 000501, Division 06 Work: Provide all materials and work for the remodel of the north building noted in the drawings specifications Division 06 work including but not limited to: rough carpentry for the addition including wall framing, sheathing, building wrap, building paper, roof joists, new wood stairs, new interior wall framing in existing building, finish carpentry, wood T&G ceilings, glue laminated beams and columns, wood cabinets and countertops.
j. Base Bid Item #10 Bid Item 000501, Division 07 Work: Provide all materials and work for the remodel of the north building noted in the drawings and specifications Division 07 work including but not limited to: damp proofing, thermal insulation, new and repaired TPO roofing, sheet metal flashing and trim, roof access door, composite siding for the addition, fire stopping, and joint sealants. Do not include optional siding replacement as shown in the drawings and covered in the optional items below.
k. Base Bid Item #11 Bid Item 000501, Division 08 Work: Provide all materials and work for the remodel of the north building noted in the drawings and specifications Division 08 work including but not limited to: Hollow metals doors and frames, flush wood doors, access doors and frames, aluminum framed entrances, aluminum framed windows, door hardware and glazing.
Do not include the optional bid item aluminum framed windows shown in the drawings. and covered in the optional items below.
l. Base Bid Item #12 Bid Item 000501, Division 09 Work: Provide all materials and work for the remodel of the north building noted in the drawings and specifications Division 09 work including but not limited to: Gypsum board, ceramic tiling, resilient tiling, rubber sports flooring, resilient base and accessories, tile carpeting, FRP wainscotting, acoustical ceilings, exterior and interior painting, staining, varnishing and high-performance coatings. Do not include work involving optional bid items noted below.
m. Base Bid Item #13 Bid Item 000501, Division 10, 11 and 12 Work: Provide all materials and work for the remodel of the north building noted in the drawings and specifications Division 10, 11 and 12 work including but not limited to: dimensional letter signs, panel signage, toilet and bath accessories, and fire protection specialties, slatwall, projection screens and protectors, base bid roller shades, solid surface countertops, knoxbox and entrance floor mats. Do not include appliances which are an optional bid item below.
n. Base Bid Item #14 Bid Item 000501, Division 14 Work: Provide all materials and work for the remodel of the north building noted in the drawings and
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-3
specifications Division 14 work including but not limited to: Provide and install the hydraulic elevator complete and installed, support and controls.
o. Base Bid Item #15 Bid Item 000501, Division 22 Work: Provide all materials and work for the remodel of the north building noted in the drawings and specifications Division 22 work including all plumbing complete including, but not limited to: sleeves, escutcheons, seals, valves, supply piping, hangers, supply, waste and vent piping, penetrations through the roof, pumps, water heaters, tanks, pans, drinking fountains, toilets, lavatories, sinks, showers, water boxes, connections and drains.
p. Base Bid Item #16 Bid Item 000501, Division 23 Work: Provide all materials and work for the remodel of the north building noted in the drawings specifications Division 23 work, heating, ventilation and air conditioning equipment and labor including but not limited to: motors, hangers, supports, ductwork, furnaces, condensing units, ductwork, curbs, diffusers, grilles, split system, thermostats and exhaust fans.
q. Base Bid Item #17 Bid Item 000501, Division 26, 27 and 28 Work: Provide all materials and work for the remodel of the north building noted in the drawings and specifications Division 26, 27 and 28 work, including but not limited to: conductors, raceways, identifications, lighting and controls, wiring devices, communications wiring and devices, pathways, fittings, cablings, conductors, access control, video surveillance, and fire alarm system. Site electrical work is not included in this line item and is shown in the optional bid items below.
r. Base Bid Item #18 Bid Item 000501, Division 31 and 32 Work: Provide all materials and work for the remodel of the north building noted in the drawings and specifications Division 31 and 32 work, including but not limited to: earthwork, project site prep and grading, excavation, helical piers, crushed aggregate base, backfilling and compaction.
4. OPTIONAL Bid Items The work will include but is not limited to:
a. Optional Bid Item #1: Bid Item 011900-2. Mobilization and bonding for all Optional Bid Items. Specification section 011900.
b. Optional Bid Item #2: Bid Item 023701-2 Construction staking as described in specification 010250-2 for all optional bid items. Include construction staking needed for north and south building landscaping, parking lots, sidewalks and south building addition.
c. Optional Bid Item #3: Bid item 023701-2 Sedimentation and erosion control for all optional bid items: Provide sedimentation and erosion control for the optional bid item work shown on the civil drawings. Refer to specification section 023701.
d. Optional Bid Item #4: Bid Item 017320-1. Site demolition as described in the civil drawing, C1 and in specification section 017320.
e. Optional Bid Item #5a: Bid Item 024102-1. Landscape demolition as shown in Sheet DE1 and described in specification section 024102.
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-4
f. Optional Bid Item #5b: Bid Item 024102-2. South building landscape demolition as shown in Sheet DE1 and described in specification section 024102.
g. Optional Bid Item #6: Bid Item 260500-1 Site electrical demolition and construction work as noted in drawing E3.2 and noted in specification 260500.
h. Optional Bid Item #7: Bid Item 033545-2. 4" thick concrete sidewalks, slabs;
Includes aggregate base material as shown in the civil design drawings and noted in the specification 033545.
i. Optional Bid Item #8: Bid Item 033545-3. Type A curbing as shown in the civil design drawing and noted in specification 033545.
j. Optional Bid Item #9: Bid Item 101400. Exterior signs as noted in the civil design drawings and described in specification 101400.
k. Optional Bid Item #10: Bid Item 312100-1. Project site preparation and grading for the north areas as shown on the civil drawings and noted in specification section 312100. Exclude the costs amount to excavate and backfill from a 5’ perimeter from the north building addition. That cost is to be included in the building bid.
l. Optional Bid Items #11: Bid Item 321200-1 Provide and install hot mix asphalt for the north parking areas as shown in the civil drawings and described in specification 321200.
m. Optional Bid Item #12: Bid Item 321204-1. Provide and install crushed aggregate base course, grading C for the north parking areas under roadways as shown in the civil drawings and described in specification section 321204.
n. Optional Bid Item #13: Bid Item 321713. Provide and install bollards: As shown in the civil drawing and described in specification section 321713.
o. Optional Bid Item #14: Bid Item 322622. Provide and install all wheelstops shown in the north areas in the civil drawings and described in specification section 322622.
p. Optional Bid Item #15: Bid Item 322640-1 Provide and install pavement markings - Parking stall lines 4" solid yellow non-reflective. See drawings and specification section 322640.
q. Optional Bid Item #16: Bid Item 322640-2. Provide and install pavement markings – ADA symbol as shown in the civil drawings. specification section 322640.
r. Optional Bid Item #17: Bid Item 322706-1. Pulverize asphalt pavement and reuse - area for north building construction. See civil drawings and specification section 322706.
s. Optional Bid Item #18: Bid Item 322313-1 Provide and install the chain link fencing as shown in the civil drawings and described in specification section 323113.
t. Optional Bid Item #19: Bid Item 323113-2. Provide and install the 24’ wide automatic sliding gate shown the civil drawings and described in specification section 323113.
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-5
u. Optional Bid Item #20: Bid Item 323113-3 Provide and install the pedestrian gate shown in the civil engineering design and noted in Specification section 323113.
v. Optional Bid Items #21a: Bid Item 26460-1 Dumpster pads, without screened enclosure as shown in the civil drawings and noted in spec section 026460.
Optional Bid Item #21b: Bid Item 026460-2 Dumpster pad with screened enclosure. See specification 026460.
w. Optional Bid Item #22a: Bid Item 000502, Division 01 Work: Provide all coordination and management required to perform the specification Division 01 work for the remodel for the south building noted in the specifications including, but not limited to: utility coordination, project management, submittals, quality control, temporary facilities and control, all selective demolition costs, saw cutting and closeout procedures.
x. Optional Bid Item #22b: Bid Item 000502, Division 02 Work: Provide all materials and work for the remodel of the south building noted in the drawings and specifications Division 02 work including but not limited to:
waste material disposal and hazardous waste disposal.
y. Optional Bid Item #22c Bid Item 000502, Division 03 Work: Provide all materials and work for the remodel of the south building noted in the drawings and specifications Division 03 work including but not limited to:
Reinforced concrete footings, foundations, slabs, stairs for the addition, and repairs to interior slabs. Include all prep including aggregate base, compaction, and finishing.
z. Optional Bid Item #22d Bid Item 000502, Division 04 Work: Provide all materials and work for the remodel of the south building noted in the drawings and specifications Division 04 work including but not limited to:
concrete unit masonry, repairs, patching for the building addition.
aa. Optional Bid Item #22e Bid Item 000502, Division 05 Work: Provide all materials and work for the remodel of the south building noted in the drawings and specifications Division 05 work including but not limited to:
Steel framing, brackets and supports for the addition and pipe railings.
bb. Optional Bid Item #22f Bid Item 000502, Division 06 Work: Provide all materials and work for the remodel of the south building noted in the drawings and specifications Division 06 work including but not limited to:
rough carpentry including wall framing, sheathing, building wrap, building paper, roof joists, beams and columns.
cc. Optional Bid Item #22g Bid Item 000502, Division 07 Work: Provide all materials and work for the remodel of the south building noted in the drawings and specifications Division 07 work including but not limited to:
dampproofing, thermal insulation, overhead door insulation, new and repaired TPO roofing, sheet metal flashing and trim, composite siding, fire stopping, and joint sealants.
dd. Optional Bid Item #22h Bid Item 000502, Division 08 Work: Provide all materials and work for the remodel of the south building noted in the drawings and specifications Division 08 work including but not limited to:
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-6
Hollow metals doors and frames, overhead doors, motors and controls, access doors and frames, aluminum framed windows, door hardware, and glazing.
ee. Optional Bid Item #22i Bid Item 000502, Division 09 Work: Provide all materials and work for the remodel of the south building noted in the drawings and specifications Division 09 work including but not limited to:
Gypsum board, resilient tiling, resilient base and accessories, acoustical ceilings, concrete coating, FRP wainscotting, exterior and interior painting, staining, varnishing and high-performance coatings.
ff. Optional Bid Item #22j Bid Item 000502, Division 10 Work: Provide all materials and work for the remodel of the south building noted in the drawings and specifications Division 10, work including but not limited to:
dimensional letter signs, panel signage and fire protection specialties. Do not include appliances which are an optional bid item below.
gg. Optional Bid Item #22k Bid Item 000502, Division 22 Work: Provide all materials and work for the remodel of the south building noted in the drawings and specifications Division 22 work including all plumbing complete including, but not limited to: sleeves, escutcheons, seals, valves, hangers, supply, waste and vent piping, mop sink, penetrations through the roof, gas piping, compressed air piping and compressor, water boxes, connections and drains.
hh. Optional Bid Item #22l Bid Item 000502, Division 23 Work: Provide all materials and work for the remodel of the south building noted in the drawings and specifications Division 23 work, heating, ventilation and air conditioning including but not limited to: demolition, motors, hangers, supports, ductwork, gas unit heaters, fans, thermostats and exhaust fans.
ii. Optional Bid Item #22k Bid Item 000502, Division 26, 27 and 28 Work:
Provide all materials and work for the remodel of the south building noted in the electrical drawings and specifications Division 26, 27 and 28 work, including but not limited to: conductors, raceways, identifications, lighting and controls, wiring devices, communications wiring and devices, pathways, fittings, cablings, conductors, access control. Site electrical work is not included in this line item and is shown in the optional bid items above.
jj. Optional Bid Item #22l Bid Item 000501, Division 31 and 32 Work: Provide all materials and work for the remodel of the south building noted in the drawings and specifications Division 31 and 32 work, including but not limited to: earthwork, project site prep and grading, excavation, crushed aggregate base, backfilling, compaction to 5’ beyond the addition perimeter.
kk. Optional Bid Item #23: Bid Item 024102-3. Remove the existing perimeter fence on the north, west and south sides of the site. See specification 024102.
ll. Optional Bid Item #24: Bid Item 03345-1 Provide and install new reinforced, 8” thick concrete drive including aggregate base, compaction and finishing for south building addition drive. Include sidewalks and drive approach. See civil drawings and specification section 033545. This line item must be awarded with the south building remodel.
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-7
mm. Optional Bid Item #25: Bid Item 101420. Provide and install concrete and cultured stone masonry sign base, connections and signs as shown in the landscape plans and described in specification section 101420.
nn. Optional Bid Item #26: Bid Item 312100-2 Project site preparation and grading for the south areas as shown on the civil drawings and noted in specification section 312100. Exclude the costs amount to excavate and backfill from a 5’ perimeter from the south building addition.
oo. Optional Bid Item #27: Bid Item 322706-2. Pulverize Asphalt Pavement and Reuse - Area for Building Construction. See civil drawings for the location of the south areas and specification section 322706.
pp. Optional Bid Item #28: Bid Item 321200-2 Provide and install Hot Mix Asphalt for the south areas as shown in the civil drawings and described in specification 321200.
qq. Optional Bid Item #29: Bid Item 321204-2. Provide and install Crushed Aggregate Base Course, Grading C for the south areas under roadways as shown in the civil drawings and described in specification section 321204.
rr. Optional Bid Item #30: Bid Item 323132 Provide and install wood composite fencing on north, west and south perimeters of the site. See civil drawings and specification section 323132.
ss. Optional Bid Item #31. Bid Item 328000-1. Provide and install all components for the irrigation system for the landscape irrigation system as shown in the landscape irrigation drawings and described in specification section 328000.
tt. Optional Bid Item #32: Bid Item 328000-2. Provide and install all components for the irrigation system for the landscape irrigation system, south building bid option 1 as shown in the landscape irrigation drawings and described in specification section 328000.
uu. Optional Bid Item #33: Bid Item 329310-1. Provide and install landscape materials for landscape exterior plants, landscape boulders and topsoil in areas shown on the landscaping plans and specified in section 329310.
vv. Optional Bid Item #34: Bid Item 329310-2. Provide and install landscape materials for landscape exterior plants, landscape boulders and topsoil, south building bid option 1 in areas shown on the landscaping plans and specified in section 329310.
ww. Optional Bid Item #35 Bid Item 329400-1. Provide and install landscape materials for landscape stone, wood mulch, weed barrier as shown in the details and plans on the landscaping design sheets and specified in section 329400.
xx. Optional Bid Item #36: Bid Item 329400-2. Provide and install the landscape materials for landscape stone, wood mulch, weed barrier, south building bid option 1 as shown in the details and plans on the landscaping design sheets and specified in section 329400.
yy. Optional Bid Item #37: Bid Item 312010. Provide and install the select borrow required to construct the landscape berm shown on the landscaping drawings and specified in section 312010.
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-8
zz. Optional Bid Item #38: Bid Item 329212-1. Provide and install landscape concrete landscape edger as shown in the landscaping sheets and specified in specification section 329212.
aaa. Optional Bid Item #39: Bid Item 329212-2. Provide and install landscape concrete landscape edger, south building bid option 1 as shown in the landscaping sheets and specified in specification section 329212.
bbb. Optional Bid Item #40: Bid Item 084113-1. Remove and replace North Building windows marked optional. Replace with fixed and operable aluminum framed windows, glazing, peel and stick membranes, framing.
Repair and paint interior walls damaged by window replacement. See specification section 084113.
ccc. Optional Bid Item #41: Bid Item 074646-1. Remove all existing wood siding and fascia from the North Building. Replace framing, weather barrier, sheathing, flashing, fiber cement siding, sealants, and trim. Paint as directed in specifications. See spec 074646.
ddd. Optional Bid Item #42: Bid Item 113100-1. Provide and install and 2 refrigerators and 2 microwaves for the North Building as described in specification section 113100.
eee. Optional Bid Item #43: Bid Item 113100-2. Provide and install and washer, dryer and refrigerator for the South Building as described in specification section 113100.
fff. Optional Bid Item #44: Bid Item 099113-1. Repaint concrete masonry exterior walls in Phase 2 of the South Building. See spec 099113.
ggg. Optional Bid Item #45: Bid item 072100-1: Provide 6” of fiberglass batt insulation between the 1st and 2nd floor of the North Building.
1.2 PROJECT LOCATION
A. The “North Building” is located at 6914 S 3000 E, Salt Lake City, UT 84121. The “South Building” is located at 6944 S 3000 E, Salt Lake City, UT 841221. The site is located in Salt Lake County. The site is also located within the area known as “Cottonwood Heights”
B. The Authority having Jurisdiction on the property is USDA Forest Service, a Federal Agency.
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. The contractor shall have full use of the north building premises for construction operations, including the use of the north portion of the project site during the construction period. The Contractor’s use of the premises is limited only by the Government’s right to perform work or to retain other contractors on portions of the Project.
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-9
2. The South building will be occupied during base bid, construction. The South Parking areas and fenced Government parking will be reserved for the employees during construction.
3. Work will not be started on the South Building until the North Building is completed.
4. The Contractor will be responsible for signing and limiting public access to their work area. Access shall be maintained to the facilities at the south of the Forest Service property through construction except as approved by the Contracting Officer for the purpose of reconstructing the access roads and parking areas. At least one access road shall be maintained at all times.
5. The Contractor shall not disrupt existing utility service (water, power, telecom, sewer, etc.) to and within the compound without coordination and approval in writing from the Contracting Officer’s Representative. Provide 48 hours’ notice prior to disrupting utilities to the other occupied areas of the site.
6. Water is available at the site for construction purposes. The contractor is responsible for any temporary connection hardware.
7. Electricity is available at the site for construction purposes. The Contractor will be responsible for coordinating the installation of temporary power for the site and the cost for the service.
8. Telephone service is not available and shall be the contractor’s responsibility.
9. Sewer lines are available to the contractor, if desired.
10. The Contractor shall provide temporary toilet facilities (porta-potties) at the site during all construction work. Toilet facilities shall be provided at a rate of one stool for every 10 workers assigned or working on site with a minimum of one required.
11. The contractor shall inform and enforce an “Anti-Idling” policy for vehicles on the site that requires vehicles will not idle for more than 2 minutes on the site. The contractor shall inform subcontractors and deliveries of this policy.
12. Work hours allowed shall be Monday-Friday 7AM-7PM. The contractor may work weekends if needed, 8AM-7PM.
1.4 GENERAL SITE CONDITIONS AND WEATHER
1. The elevation of the site is approximately 4800 feet above sea level. The construction site experiences cold temperatures with snow on the ground from November to February. Summer temperatures are warm but usually do not exceed 100 degrees.
2. In depth soil surveys have been performed and are available as an attachment to the specifications. See Geotechnical Report, prepared by GSH Engineering, SLC, UT, June 2021.
3. The contractor shall review the water table information included in the geotechnical study.
1.5 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the CO and Local Transportation Authority.
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-10
Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.
B. Signing and barricades shall be adequate to protect Forest Service employees and public.
The contractor shall take special care to adequately sign and protect areas of work and construction from persons using these areas.
1.6 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage work trailers on site.
Overnight camping on site will not be allowed.
B. Confine storage of materials and equipment as approved by the Contracting Officer. The Contractor is responsible for the security of all personal equipment and materials.
C. Contractor shall maintain access to the facilities for Forest Service contracting personnel.
D. No fuel storage is permitted on the site. Fuel trucks must be equipped with spill containment kits and portable berms that meet State and Federal regulations
1.7 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
1.8 ANTICIPATED START DATE
A. August 2023
1.9 CONTRACT TIME
A. 360 Calendar Days for the North Building
B. 180 Calendar days for the South Building, Phases 1 and 2
1.10 INSPECTION OF WORKSITE
A. The contractor will acknowledge that they have taken the necessary steps to ascertain the nature and location of the work and have investigated and satisfied themselves as to the general and local conditions that can affect the work and it’s cost. Any failure of the contractor to take actions described in this paragraph will not relieve the Contractor from
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-11
responsibility of properly estimating the difficulty and cost of successful performance of the work or for proceeding without additional expense to the Government.
1.11 SITE VISIT:
A. A site visit will be conducted on May 2, 2023 @ 1000am. For further information, contact tanya.spanfellner@usda.gov.
1.12 SPECIFICATIONS
A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.
Section 000501 - Remodel North Office Buildings Section 000502 - Remodel South Building Section 010250 - Construction Staking Section 011250 - Measurement And Payment With Asphalt Section 011900 - Mobilization Section 012500 - Utility Company Coordination Section 013100 - Project Management And Coordination Section 013300 - Submittal Procedures Section 014130 - Contractor’s Quality Control Section 015000 - Temporary Facilities And Controls Section 017320 - Selective Demolition Section 017700 - Closeout Procedures Section 023701 - Sediment And Erosion Control Measures Section 024100 - Waste Material Disposal Section 024102 - Landscape Waste Material Disposal Section 024113 - Selective Site Demolition Section 024117 - Hazardous Waste Disposal Section 026460 - Concrete Dumpster Pad Section 033000 - Cast-In-Place Concrete Section 033545 - Concrete Sidewalks And Curb & Gutters Section 042200 - Concrete Unit Masonry Section 047000 - Manufactured Masonry For Sign Bases Section 048100 - Unit Masonry Assemblies Section 055000 - Metal Fabrications Section 055213 - Pipe Railings Section 061000 - Rough Carpentry Section 061500 - Wood Tongue And Groove Ceiling Section 061600 - Sheathing Section 061753 - Shop-Fabricated Wood And Steel Trusses Section 061800 - Glued-Laminated Construction Section 062013 - Exterior Finish Carpentry Section 062023 - Interior Finish Carpentry
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-12
Section 064116 - Plastic-Laminate-Faced Architectural Cabinets Section 064300 - Wood Stairs Section 071113 - Dampproofing Systems Section 072100 - Thermal Insulation Section 074646 - Fiber-Cement Siding Section 075423 - Thermoplastic Polyolefin (Tpo) Roofing Section 076200 - Sheet Metal Flashing And Trim
Section 078413 - Penetration Firestopping Section 079200 - Joint Sealants Section 081113 - Hollow Metal Doors And Frames Section 081416 - Flush Wood Doors Section 083113 - Access Doors And Frames Section 083613 - Sectional Overhead Doors Section 084113 - Aluminum-Framed Entrances And Windows Section 087100 - Door Hardware Section 088000 - Glazing Section 092900 - Gypsum Board Section 092910 - Structural Concrete Panels Section 093000 - Tiling Section 095113 - Acoustical Panel Ceilings Section 096500 - Rubber Sports Flooring Section 096513 - Resilient Base And Accessories Section 096519 - Resilient Tile Flooring Section 096613 - Concrete Floor Coating Section 096813 - Tile Carpeting Section 097700 - Special Wall Finishes Section 099113 - Exterior Painting Section 099114 - Exterior Powder Coatings Section 099123 - Interior Painting Section 099300 - Staining And Transparent Finishing Section 099600 - High-Performance Coatings Section 101400 - Exterior Signs Section 101419 - Dimensional Letter Signage Section 101420 - Administrative Identification Sign – As (Hdpe) Section 101423 - Panel Signage Section 102800 - Toilet And Bath Accessories Section 105201 - Fire-Protection Specialties Section 112130 - Slatwall Panel Systems Section 113100 - Residential Appliances Section 115213 - Projection Screens Section 122413 - Roller Window Shades Section 123661.16 - Solid Surfacing Countertops Section 124813 - Entrance Floor Grilles And Frames Section 142400 - Machine Room-Less Hydraulic Passenger Elevators Section 220517 - Sleeves And Sleeve Seals For Plumbing Piping Section 220518 - Escutcheons For Plumbing Piping
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-13
Section 220523 - General-Duty Valves For Plumbing Piping Section 220523.12 - Ball Valves For Plumbing Piping Section 220529 - Hangers And Supports For Plumbing Piping And Equipment Section 220553 - Identification For Plumbing Piping And Equipment Section 220719 - Plumbing Piping Insulation Section 221116 - Domestic Water Piping Section 221316 - Sanitary Waste And Vent Piping Section 221429 - Sump Pumps Section 223400 - Fuel-Fired, Domestic-Water Heaters Section 224100 - Residential Plumbing Fixtures Section 224213.13 - Commercial Water Closets Section 224216.13 - Commercial Lavatories Section 224217 - Commercial Sinks Section 224716 - Pressure Water Coolers Section 230130.51 - Hvac Air-Distribution System Cleaning Section 230513 - Common Motor Requirements For Hvac Equipment Section 230517 - Sleeves And Sleeve Seals For Hvac Piping Section 230529 - Hangers And Supports For Hvac Piping And Equipment Section 230548 - Vibration And Seismic Controls For Hvac Section 230593 - Testing, Adjusting, And Balancing For Hvac Section 230713 - Duct Insulation Section 230923.12 - Control Dampers Section 231123 - Facility Natural-Gas Piping Section 233113 - Metal Ducts Section 233300 - Air Duct Accessories Section 233416 - Centrifugal Hvac Fans Section 233713.13 - Air Diffusers Section 235416.13 - Gas-Fired Furnaces Section 235533.16 - Gas-Fired Unit Heaters Section 236313 - Air-Cooled Refrigerant Condensers Section 238126 - Split-System Air-Conditioners Section 260500 - Common Work Results For Electrical Section 260519 - Low-Voltage Electrical Power Conductors And Cables Section 260533 - Raceways And Boxes For Electrical Systems Section 260553 - Identification For Electrical Systems Section 260923 - Lighting Control Devices Section 262726 - Wiring Devices Section 270500 - Common Work Results For Communications Section 270528 - Pathways For Communications Systems Section 271100 - Communications Equipment Room Fittings Section 271200 - Communications Copper Network Cabling Section 280500 - Common Work Results For Electronic Safety And Security Section 280513 - Conductors And Cables For Electronic Safety And Security Section 281300 - Access Control System
Section 282300 - Video Surveillance Section 283111 - Digital, Addressable Fire-Alarm System
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-14
Section 312000 - Earthwork Section 312010 - Select Borrow For Berm Construction Section 312100 - Project Site Preparation And Grading Section 312225 - Excavation & Embankment Section 312600 - Steel Helical Piers Section 321200 - Hot-Mix Asphalt Paving Section 321204 - Crushed Aggregate Base Or Surface Course Section 321713 - Bollards Section 322622 - Precast Concrete Curb Stops Section 322640 - Pavement Marking Section 322705 - Pavement Sawing Section 322706 - Asphalt Pavement Pulverizing Section 323113 - Chain-Link Fences And Gates Section 323132 - Wood Composite Fences Section 328000 - Irrigation System
Section 329212 - Concrete Edger Landscape Curbing Section 329310 - Exterior Plants, Landscape Boulders & Planting Media Section 329400 - Landscape Stone, Wood Mulch And Weed Barrier
END OF SECTION C
FEBRUARY 2022
Sustainable Products
The following is an example list of products that may be used in this contract for which biobased products are available. The list is not all inclusive. It is desirable that Contractors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.
Interior Paint and Coatings Exterior Paint and Coatings Epoxy Systems Grease Removers Wood Sealers and Stains Adhesive and Mastic Removers Cleaners Sealers Carpet Lumber Interior Wall and Ceiling Patch Floor Coverings (Non-Carpet) Wall Coverings Acoustical Composite Panels Plastic Lumber Composite Panels Countertops and Solid Surface Insulation Plastic Foams Loose Fill and Batt Paving and Concrete Forming Concrete and Asphalt Release Fluids Asphalt Restorers Concrete and Asphalt Cleaners Concrete Curing Agents Concrete Repair Materials Asphalt & Tar Removers Roofing Roof Coatings Adhesives Traffic and Zone Marking Paints Surface Guards, Molding, and Trim Erosion Control
REMODEL NORTH OFFICE BUILDINGS 000501-1
USDA FOREST SERVICE, R4
SALT LAKE RANGER DISTRICT REMODEL, PHASE 2
SECTION 000501 - REMODEL NORTH OFFICE BUILDINGS
PART 1 - GENERAL
1.1 SUMMARY
A. This work includes the remodel of 6914 S 3000 E, a facility owned by the Forest Service.
The building will be the future home of the Salt Lake Ranger District- Uinta Wasatch Cache National Forest.
1.2 REFERENCE SPECIFICATIONS
A. The publications listed below form a part of this specification to the extent referenced.
The publications are referred to in the text by the basic designation only.
2021 International Building Code 2021 International Existing Building Code 2021 International Plumbing Code 2021 International Mechanical Code 2021 International Fuel Gas Code 2021 International Energy Conservation Code 2020 National Electrical Code 2017 National Fire Protection Association Standards 13R and 13D.
2004 Americans with Disabilities Act/Architectural Barriers Act Guidelines (ADA/ABAG) (http://www.access-board.gov/adaag/html/adaag.htm)
1.3 MEASUREMENT AND PAYMENT:
A. The project includes the following base bid items as shown in the Schedule of Items:
Work is shown in the drawings and noted in the specifications. Work includes, but is not limited to:
Construct New North Building Stair and Elevator Entry. Demolish the east entrance stair of the north building including roof, concrete and steel stair, doors, brick veneer, mailboxes, and railings. Excavate and construct new east entry addition including concrete footings, foundations, slabs, helical piers, walk off grate, framing, wood accent entrance, furring, sheathing, roofing, windows, doors, hardware, face brick, composite siding, flashing, insulation, gypsum board, painting, wood stairs, railings, doors, hardware, ceramic tile, tongue and groove ceiling, hydraulic elevator, sump pumps, registers and ductwork.
See specification Section 260500 and electrical drawings for a description of demolition, electrical service, wiring, outlets, security, fire alarm, lighting and communications.
REMODEL NORTH OFFICE BUILDINGS 000501-2
Remodel existing interiors of 2 story facility. Demolish existing finishes, slabs, flooring, walls, casework, interior windows, ceilings, plumbing, fixtures, stairs, doors, hardware, HVAC systems, ductwork, diffusers and returns. See specification section 260500 and electrical drawings for a description of the demolition of wiring, outlets, lights, sensors, power and communications.
Provide and install new wood framing, concrete slab repair, gypsum board, ceramic tile, vinyl tile, base, stairs, doors, frames, hardware, interior windows, painting, ceilings, countertops, casework, toilet accessories, salvaged hand dryers, signage, screens, display racks, toilets, showers, lavatories, sinks, drinking fountains, water heater, mop sink, fans, furnaces, condensing units, ductwork, HVAC supply and returns. wiring, outlets, lights, sensors, power and communications.
B. OPTONAL BID ITEMS:
1. Optional bid items described n Section C are not included in the base bid. Refer to specification 000001.1.1.A.4 for a description of optional items including replacement of windows, exterior siding, insulation and appliances for the North Building.
C. Schedule of Values. The Contractor shall submit to the Government with the bid an initial Schedule of Values for the Work, allocating values as the contractor understands the work among all categories or portions of the Work to provide a complete and functional facility. The contractor shall include all work within 5’ of the building roof perimeter and concrete as described above. The Schedule of Values shall be prepared in such form and supported by data to substantiate its accuracy to the extent as the Government may require and shall be based upon the latest cost information available to Contractor.
1.4 RELATED WORK
A. The work shall be in accordance with the contract documents.
B. The work shall be in accordance with the following specifications. The subsidiary specifications are referred to in the text by the Section designation only.
PART 2 - PRODUCTS - Not Applicable
PART 3 - EXECUTION
3.1 GENERAL
A. Work shall be completed in accordance with the contract drawings and specifications.
B. APPLICABLE SPECIFICATION SECTIONS:
Section 000501 – Remodel North Office Building Section 011250 - Measurement And Payment Section 012500 - Utility Company Coordination
REMODEL NORTH OFFICE BUILDINGS 000501-3
Section 013100 - Project Management And Coordination Section 013300 - Submittal Procedures Section 014130 - Contractor’s Quality Control Section 015000 - Temporary Facilities And Controls Section 017320 – Selective Demolition Section 017700 - Closeout Procedures
Section 024100- Waste Material Disposal Section 024117- Hazardous Waste Disposal
Section 033000 - Cast-In-Place Concrete
Section 048100- Unit Masonry Assemblies
Section 055000 - Metal Fabrications Section 055213 - Pipe Railings
Section 061000 - Rough Carpentry Section 061500 – Wood Toungue and Groove Ceiling Section 061600 - Sheathing Section 061800 - Glued-Laminated Construction Section 062013 - Exterior Finish Carpentry Section 062023 - Interior Finish Carpentry Section 064116 - Plastic-Laminate-Faced Architectural Cabinets Section 064300- Wood Stairs
Section 071113 - Dampproofing Systems Section 072100 – Thermal Insulation Section 074646 – Fiber Cement Siding Section 075423 – Thermoplastic Polyolefin Roofing (TPO) Section 076200 - Sheet Metal Flashing And Trim Section 078413 - Penetration Firestopping Section 079200 - Joint Sealants
Section 081113 - Hollow Metal Doors and Frames Section 081416 - Flush Wood Doors Section 083113 - Access Doors And Frames Section 084113- Aluminum Framed Entrances and Storefronts Section 087100 - Door Hardware Section 088000 - Glazing
Section 092900 - Gypsum Board Section 093000 - Tiling Section 095113 - Acoustical Panel Ceilings Section 096500- Rubber Sports Flooring Section 096513 - Resilient Base And Accessories
REMODEL NORTH OFFICE BUILDINGS 000501-4
Section 096543 – Resilient Tile Flooring Section 096813 - Tile Carpeting Section 097700 - Special Wall Finishes Section 099113- Exterior Paintng Section 099123 - Interior Painting Section 099300 - Staining And Transparent Finishing Section 099600 - High-Performance Coatings
Section 101419 - Dimensional Letter Signage Section 101423 - Panel Signage Section 102800 - Toilet And Bath Accessories Section 105201 - Fire-Protection Specialties
Section 112130- Slatwall Display System Section 115213- Projection Screens
Section 123661.16- Solid Surfacing Countertops Section 124813 - Entrance Floor Grilles, And Frames Section 142400- Machineroomless Hydraulic Elevators
Section 220517 – Sleeves & Sleeve Seals for Plumbing Piping Section 220518 – Escutcheons for Plumbing Piping Section 220523.12 – Ball Valves for Plumbing Piping Section 220523 – General Duty Valves for Plumbing Piping Section 220529 – Hangers & Supports for Plumbing Piping & Equipment Section 220553 – Identification for Plumbing Piping & Equipment Section 220719 – Plumbing Piping Insulation Section 221116 –Domestic Water Piping Section 221316 – Sanitary Waste & Vent Piping Section 221429- Sump Pumps Section 223300 – Fuel Fired Domestic Water Heaters Section 224100 – Residential Plumbing Fixtures Section 224213 – Commercial Water Closets Section 224216 – Commercial Lavatories Section 224217- Commercial Sinks Section 224716 – Pressure Water Coolers
Section 230130.51- Existing Duct Cleaning Section 230513- Common Work Results for Motors Section 230517- Sleeves and Seals for Mechanical Section 230529- Hangers and Supports for HVAC Section 230548- Vibration Mitigation for HVAC Section 230593 – Testing, Adjusting, and Balancing Section 230713- Duct Insulation Section 230923.12 - Control Dampers Section 231123- Natural Gas Piping
REMODEL NORTH OFFICE BUILDINGS 000501-5
Section 233113 – Metal Ducts Section 233300 – Air Duct Accessories Section 233416- Exhaust Fans Section 233713.13 – Air Diffusers Section 235416.13 – Gas Fired Furnaces Section 236313 – Air Cooled Refrigerant Condensers Section 238126 - Split System Air Conditioners
Section 260500 - Common Work Results for Electrical Section 260519 - Low Voltage Electrical Power Conductors and Cables Section 260533 - Raceways And Boxes For Electrical Systems Section 260553 - Identification For Electrical Systems Section 260923 - Lighting Control Devices Section 262726 - Wiring Devices Section 265100 - Interior Lighting
Section 270500 - Common Work Results For Communications Section 270528 - Pathways For Communications Systems Section 271100 - Communications Equipment Room Fittings Section 271200 - Communications Copper Network Cabling
Section 280500 – Common Work Result for Electronic Safety and Security Systems Section 281300 - Access Control System Section 282300- Video Survelliance Section 283111 – Digital, Addressable Fire Alarm System
Section 31200 - Earthwork Section 312100 - Project Site Prep and Grading Section 312225 - Excavation & Embankment Section 312600- Helical Piers Section 321204 - Crushed Aggregate Base or Surface Course
3.2 OTHER APPLICABLE DOCUMENTS:
A. Geotechnical Report for Site, GSH Engineers, June 2021
B. Asbestos report, May 2021.
END OF SECTION 000501
FEBRUARY 2022
REMODEL SOUTH BUILDING 000502-1
SALT LAKE RANGER DISTRICT REMODEL, PHASE 2
SECTION 000502 - REMODEL SOUTH BUILDING
PART 1 - GENERAL
1.1 SUMMARY
A. This work includes the remodel of 2 facilities owned by the Forest Service. The buildings will be the future home of the Salt Lake Ranger District- Uinta Wasatch Cache National Forest.
1.2 REFERENCE SPECIFICATIONS
A. The publications listed below form a part of this specification to the extent referenced.
The publications are referred to in the text by the basic designation only.
2021 International Building Code 2021 International Existing Building Code 2021 International Plumbing Code 2021 International Mechanical Code 2021 International Fuel Gas Code 2021 International Energy Conservation Code 2020 National Electrical Code 2017 National Fire Protection Association Standards 13R and 13D.
2004 Americans with Disabilities Act/Architectural Barriers Act Guidelines (ADA/ABAG) (http://www.access-board.gov/adaag/html/adaag.htm)
1.3 MEASUREMENT AND PAYMENT:
A. The project includes the following base bid items and bid option items as shown in the Schedule of Items. The remodeling of this building is shown in the South Building drawing package and noted in these specifications.
1. Phase 1, South: The government will occupy the adjacent areas (bays) during remodel and construction of the new fire bay and remodel of Phase 1. Coordinate construction activities with the COR. Provide a clear schedule of activities to allow the Forest Service to plan workloads during construction. Work includes, but is not limited to:
Selective demolition and removal of the northeast portion of the building and construction of a fire engine bay including, concrete footings, foundations, CMU walls, framing, concrete stairs, slab, insulation, sheathing, overhead doors, motors and controls, finishes, coatings, new and repaired TPO roofing, framed walls, ceilings, flooring, expansion joints, painting, air compressor, plumbing, HVAC equipment, doors, frames, windows, composite siding, lighting, controls, communications and power. Phase 2 will not begin until Phase 1 is complete.
REMODEL SOUTH BUILDING 000502-2
2. Phase 2, South Building includes but is not limited to: The contractor will provide a temporary storage container for Forest Service Material as described in the demolition sheet DS101. The Government will occupy the adjacent east wing while the bays are being remodeled. Demolition includes CMU walls, partition and finishes. The contractor shall increase the hazardous storage area, paint, apply floor coatings, provide and install new heating equipment, power, lighting, insulation.
3. Optional Bid Items are shown in the Schedule of Items and include providing and installing residential appliances (washer, dryer and refrigerator) and repainting the CMU exteriors on the north and west elevations of the south building bays.
B. Schedule of Values. The Contractor shall submit to the Government with the bid an initial Schedule of Values for the Work, allocating values as the contractor understands the work among all categories or portions of the Work to provide a complete and functional facility. The contractor shall include all work within 5’ of the building roof perimeter and concrete as described above.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .