J-1 BUFFALO SNOW REMOVAL STATEMENT OF WORK 04_17_2024.pdf
PDF 128 KB Posted
- Attached to
- Buffalo Air Traffic Control Tower Snow Removal
- Solicitation number
- 697DCK-24-R-00412
About this file
This document is a Statement of Work (SOW) for snow removal services at the Buffalo Air Traffic Control Tower (ATCT) in Buffalo, New York. The SOW outlines the requirements for clearing snow from a 42,986 square foot parking lot, 900 feet of sidewalk, and access gates, as well as keeping all building exterior doors clear for emergency use. Snow is to be removed as needed, generally 2 inches or more, and the contractor is expected to respond within one hour of any FAA request for snow removal. The control tower operates 24/7, so it is critical that snow removal is completed to accommodate shift changes.
The related federal contract opportunity is a firm-fixed price procurement set-aside for a Total Small Business under NAICS code 561790 - Other Services to Buildings and Dwellings. The performance period is a base year plus four option years, beginning 10/1/2024. A site visit is scheduled for 6/17/2024 and all questions must be submitted by 6/19/2024. Proposals and customer satisfaction surveys are due by 6/28/2024, with the contract award date to be determined.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0001.pdf | ||
| BUFFALO SNOW REMOVAL STATEMENT OF WORK 06_25_2024.docx | DOCX document | |
| 697DCK-24-R-00412.pdf | ||
| J-3 - Customer Satisfaction Survey - 697DCK-24-R-00412.pdf | ||
| J-2 Attachment 2-WD 2015-4161 Dated 04292024.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
SNOW REMOVAL SERVICE
FOR BUFFALO AIR TRAFFIC CONTROL TOWER
1. The control tower is located at 165 Holtz Road, Cheektowaga, NY 14225. The work includes a parking lot that measures 42,986 square feet which accommodates approximately 150 cars, and 900 feet of sidewalk to be cleared and or salted. The area also includes 2 access gates, which require a clearance area behind gates to be kept clear to keep snow from interfering with gate operations. All seven building exterior doors will be kept clear of snow and ice for use in emergencies.
2. In general, snow is to be removed as needed to keep the parking lot and sidewalks open and safe, generally 2” or more. At times it may be necessary to salt the parking lots and sidewalks due to formation of ice or freezing rain. The contractor is expected to respond promptly (within one hour) to any request from the FAA for snow removal operations.
3. The control tower is manned 24 hrs. a day, 7 days per week. It is imperative that snow removal is completed to accommodate shift changes which are as follows:
5:30 AM to 8 AM each day
2 PM to 4 PM each day
11 PM each day
It is expected that the contractor will plow as needed without waiting for a call out.
Revised 04/17/2024
File details come from the government source that posted it. Updated .