This past performance questionnaire is for a contractor that provided Interface Test Adapters (ITA) and related test equipment under a competitive, firm-fixed price contract. The contract was a multiple-award, indefinite delivery/indefinite quantity agreement with a 100% small business set-aside. The customer agency was the Department of the Air Force Materiel Command Air Force Sustainment Center. The evaluator is asked to provide ratings on contractor qualifications, ITA development and support, and price performance. Details are solicited on positive and negative performance, potential for future work, and contract terminations. The questionnaire aims to collect past performance information to support a small business solicitation for ITA and test equipment.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_2_Addendum_52.212-1_ITA_Revised_10Feb2022.pdf | ||
| ITO Attachment 1.1 _Revised10Feb2022.pdf | ||
| Contractor Questions-Answers_10Feb2022.pdf | ||
| Contractor Questions - Answers - 1 February.pdf | ||
| ITO Attachment 3.1.xlsx | XLSX spreadsheet | |
| ITO Attachment 1.1.pdf | ||
| ITO Attachment 1.2.pdf | ||
| Attachment_2_Addendum_52.212-1_ITA.pdf | ||
| Attachment_4_Decentralized_Ordering_Procedures.pdf | ||
| ITO Attachment 1.5.pdf | ||
| ITO Attachment 1.3.pdf | ||
| Solicitation_FA812622R0001_6January2022.pdf | ||
| Exhibit_A_CDRL_A001-A00B_ITA.pdf | ||
| Attachment_3_Addendum_52.212-2_ITA.pdf | ||
| ITO Attachment 3.1.xlsx | XLSX spreadsheet | |
| ITO Attachment 2.0.pdf | ||
| ITO Attachment 1.4.pdf | ||
| ITO Attachment 1.1.pdf | ||
| Attachment_2_Addendum_52.212-1_ITA.pdf | ||
| Attachment_1_Statement_of_Work (SOW)_ITA.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITO ATTACHMENT 1.2
PAST PERFORMANCE QUESTIONNAIRE
When filled in, this document is source selection sensitive information IAW FAR 3.104
SECTION 1: CONTRACT IDENTIFICATION
A. Contractor:_________________________________________________________________________
B. CAGE Code of contractor contract was awarded to: _________________________________
C. Contract number: _______________________________________
D. Contract type: ______________________________ (If multiple types (i.e. Firm-Fixed Price with Time & Material), list percentage and dollar amount of Firm-Fixed Price portion)
E. Was this a competitive contract? Yes _____ No _____
F. Period of performance: _________________________________________________________
G. Initial contract cost: $____________________________
H. Current/final contract cost: $_______________________________
I. Reasons for differences between initial contract cost and final contract costs:
J. Description of service provided:
SECTION 2: CUSTOMER OR AGENCY IDENTIFICATION
A. Customer or agency name: __________________________________________________________
B. Customer or agency description (if applicable): __________________________________________
C. Geographic description of services under this contract, i.e. local, nationwide, worldwide, other Commands:
SECTION 3: EVALUATOR IDENTIFICATION
A. Evaluator's name: ___________________________________________________________________ B. Evaluator's title: ____________________________________________________________________ C. Evaluator's phone number:____________________________________________________________ D. Evaluator’s e-mail: __________________________________________________________________ E. Number of years evaluator worked on subject contract: ____________________________________
SECTION 4: EVALUATION
Please indicate your satisfaction with the contractor’s performance by placing an “X” in the appropriate block using the scale provided to the right of each question. This scale is defined as follows:
CODE PERFORMANCE LEVEL
B BLUE/EXCEPTIONAL - The contractor’s performance meets contractual requirements and exceeds some or many (requirements) to the Government’s benefit. The contractual performance was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
G GREEN/SATISFACTORY – The contractor’s performance meets contractual requirements.
The contractual performance contained some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
Y YELLOW/MARGINAL – Performance does not meet some contractual requirements. The contractual performance reflects a serious problem for which the contractor has not yet identified corrective actions or the contractor’s proposed actions appear only marginally effective or were not fully implemented.
R RED/UNSATISFACTORY – Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
N NOT APPLICABLE - Unable to provide a score.
Subfactor 1 – Contractor Qualifications B G Y R N
P1. Did the contractor adequately provide a qualified, experienced program manager who is knowledgeable and able to meet program milestones, requirements, resolve problems, communicate with customer and report program status.
P2. Did the contractor adequately document and manage quality standards and maintain FAA requirements.
P3. Did the contractor adequately manage and smoothly transition resources and personnel during contract phase-in.
P4. Did the contractor adequately provide a knowledgeable, qualified and experienced FSR capable of providing technical analysis and guidance, troubleshooting assistance, and maintenance instruction/training.
Subfactor 2 – ITA Development and Support B G Y R N
S1. Did the contractor adequately manage and supply all parts, tools and support equipment needed to meet fleet requirements.
S2. Did the contractor adequately furnish FAA certified spares and parts in the proper configuration.
S3. Did the contractor adequately operate and maintain an inventory and supply ordering system.
S4. Did the contractor adequately provide parts and spares to locations away from the MOB, to restore aircraft to operational status.
Factor 3 - Price Performance B G Y R N
CP1. Were funds status reporting accurate and timely? If not, please explain.
CP2. Did the contractor submit timely proposals for additional customer and/or unscheduled requirements and perform within proposed prices? If not, please explain.
CP3. Did the contractor promote savings for the customer and ensure best value commercial pricing in proposals? Please explain.
CP4. Did the contractor adhere to contract price? If not, please explain.
1. Please discuss each and every response for which you indicated B/E (Blue/Exceptional), Y/M (Yellow/Marginal) or R/U (Red/Unsatisfactory) in response to the questions above (use additional sheets, if necessary).
2. Government Contracts Only: Has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations?
Yes___ Default___ Convenience___ Pending Terminations___ No ___
If yes, please explain (e.g., inability to meet cost, performance, or delivery schedules, etc).
SECTION 5: NARRATIVE SUMMARY
What were the contractor’s most positive aspects in the performance of the contract?
What were the contractor’s most negative aspect in the performance of the contract?
Would you have any reservations about soliciting this contractor in the future or having them perform one of your critical and demanding programs?
Please provide any additional comments concerning this contractor’s performance, as desired.
Evaluator’s Signature Date
Thank you for your prompt response and assistance!
Please return this completed questionnaire to:
jocelyn.johnson.2@us.af.mil and alaina.hill@us.af.mil mailto:jocelyn.johnson.2@us.af.mil
| 5.2.7. Price Assumptions Used in Development of Proposed Pricing |
| The Government will review information provided in the Price Volume regarding cost assumptions utilized in the development of proposed pricing. Such information will be used to understand Offerors’ proposed pricing basis of estimate. Additionally, the... |
| 5.2.8. Annual Price Changes |
| Proposed price increases greater than 5% per year shall be verified and addressed for reasonableness in this section. Offerors shall provide rationale for any proposed CLIN price increase greater than 5% from one year to another, or any proposed CLIN ... |
| 5.2.8. – Price Assumptions Used in Development of Proposed Pricing |
| 5.2.9. – Annual Price Changes |
| 6.3. Other Information Required |
| PAST PERFORMANCE PACKAGE ATTACHMENTS |
| Subfactor 1 – Contractor Qualifications |
| What were the contractor’s most positive aspects in the performance of the contract? |
| ___________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________... |
| What were the contractor’s most negative aspect in the performance of the contract? ____________________________________________________________________________________________________________________________________________________... |
| SAMPLE CONSENT LETTER |