ITBCDS240985_Residential_Rehab_at_2612_NE_22nd_Ave_Clarke_-_Addendum_No._1.pdf
PDF 80 KB Posted
- Attached to
- Residential Rehab at 2612 NE 22nd Ave (Clarke)
- Solicitation number
- ITB#CDS/240985
- Issued by
- Marion County, Orlando City, Florida
About this file
This document is Addendum #1 issued by the City of Ocala for Solicitation Number ITB#CDS/240985, concerning a Residential Rehabilitation project at 2612 NE 22nd Ave (Clarke). The addendum provides critical updates for bidders, including access restrictions, painting specifications, and construction timeframe details. Specifically, access to the Clarke home is limited to December 16-19, 2024, and must be scheduled through City Project Manager Chris Lewis. Bidders are explicitly instructed not to contact the property owner directly.
The addendum clarifies interior painting requirements, specifying that the owner shall have one wall color and one trim/door color. The construction timeline is also defined, with contractors required to begin work within ten (10) calendar days after receiving the City's Notice to Proceed (NTP), and complete all work ready for final payment within ninety (90) days of the NTP. These specifications are part of a broader rehabilitation project for a residential property, targeting qualified Florida licensed General or Building Contractors to perform comprehensive renovation work in strict accordance with rehabilitation specifications and Florida Building Code guidelines.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum # 1
Date: December 16, 2024
To: All bidders
From: Brittany Craven, Buyer
Solicitation Number: ITB#CDS/240985
Solicitation Title: Residential Rehab at 2612 NE 22nd Ave (Clarke)
SECTION 1. ACCESS – Additional Info.
1. Access to the Clarke home shall only be scheduled through the City Project Manager, Chris Lewis Access shall be available 12/16/2024-12/19/2024.
2. The Project Manager can be contacted 352-425-7686 or clewis@ocalafl.gov.
3. Do not contact the owner.
SECTION 2. INTERIOR PAINTING - Clarification
1. Owner shall have 1 color for walls and 1 color for trim/doors.
SECTION 3. CONSTRUCTION TIMEFRAME - Correction
1. Construction Time: The required start time after the City-issued Notice to Proceed (NTP) shall be a maximum of ten (10) calendar days to begin work. Work will be completed and ready for final payment within ninety (90) days of the issued NTP.
File details come from the government source that posted it. Updated .