ITB_FAC260769_Administration_Remodel__City_of_Ocala_Fiber_Network__Exhibit_A__Scope_of_Work.pdf

PDF 145 KB Posted

Attached to
Administration Remodel - City of Ocala Fiber Network
Solicitation number
ITB# FAC/260769
Issued by
Marion County, Orlando City, Florida

About this file

This is a Scope of Work document for the City of Ocala, Florida, ITB #FAC260769, for light construction services supporting the Facilities department's Administration Remodel project at the City of Ocala Fiber Network. The project encompasses interior wall construction, drywall finishing, baseboards replacement with 5-inch wood OGEE baseboards, interior door replacement with solid-core wood doors, HVAC system modification and balancing, LED lighting fixture upgrades, and carpet tile flooring installation in designated areas. The mandatory pre-bid meeting is scheduled for June 16, 2026, at 10:00 AM at the City of Ocala Fiber Network Administration, 3001 NE 21st Street, Ocala, FL 34470. The contract timeframe is 16 weeks after all permits have been issued, with the contractor required to mobilize and begin work no later than 10 calendar days after the Notice to Proceed. Normal working hours are 6:00 AM to 6:00 PM, Monday through Sunday, excluding holidays. The contractor must comply with all applicable Florida Building Code requirements and obtain necessary City permits including building, electrical, mechanical, plumbing, fire safety, and Certificate of Occupancy permits at no additional cost to the City.

Bids will be received on a lump sum basis with all direct and indirect costs included, and the award will be made to the lowest bidder meeting all requirements. The bidder must possess a valid General Contractor's License in the State of Florida and demonstrate five years of experience in interior wall construction and drywall finishing. Required insurance includes Commercial General Liability with limits of $1,000,000 per occurrence/$2,000,000 aggregate, Commercial Automotive Liability with a combined limit of $1,000,000, and Workers' Compensation and Employer's Liability per Florida statutory requirements. Liquidated damages of $250.00 per calendar day will be assessed for work not completed by the specified completion date. The contractor must perform a minimum of 30 percent of the work with their own forces, with sub-contractor services requiring advance approval from the City Project Manager. A five-year material and labor warranty is required from the date of substantial completion, and all invoices should be submitted to Charles Stewart, Project Manager, Facilities Management Department, with monthly invoicing required.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit A – SCOPE OF WORK CONTRACT# FAC/260769

A - 1

BACKGROUND

1. The City of Ocala requires the services of an experienced contractor to provide light construction services/goods supporting the Facilities department.

2. MANDATORY PRE-BID MEETING: Refer to the listing for the pre-bid meeting date, time, and location.

EXPERIENCE, LICENSING and REQUIREMENTS

1. Licensing Requirement: Bidder must possess a valid General Contractor’s License in the State of Florida to submit a bid for this project.

2. Experience Requirement: Bidder must possess five (5) years’ experience in providing Interior wall construction and drywall finishing.

3. Awarded Vendors shall comply with all applicable provisions of Section 787.06, Florida Statutes.

Specifically, all nongovernmental Vendors shall provide the City of Ocala with an affidavit signed by an officer or a representative under penalty of perjury attesting that the non-governmental entity does not use coercion for labor or services as defined in Section 786.06(2), Florida Statutes.

If not previously provided, the affidavit may be downloaded from the link below, completed, and notarized.

https://www.ocalafl.gov/home/showpublisheddocument/29503

INSURANCE REQUIREMENTS

1. Commercial General Liability: with limits of $1,000,000 per occurrence/$2,000,000 aggregate.

2. Commercial Automotive Liability: a combined limit of not less than $1,000,000.

3. Workers’ Compensation and Employer’s Liability: per Florida statutory requirements.

PERMIT REQUIREMENTS

1. Permits Required: Contractor will be responsible for obtaining the following City of Ocala permits at no additional cost to the City:

• Building

• Electrical

• Mechanical

• Plumbing

• Fire Safety

• Certificate of Occupancy

• All applicable permits pertaining to the scope of work/project

2. Construction Permit Applications: For construction permits and related documents, please visit:

https://www.ocalafl.org/government/city-departments-a-h/growth-management/building/construction-permits

CONSTRUCTION TIMEFRAME

1. Construction Time: The Contract time to Final Completion is 16 weeks after all permits have been issued. Contractor agrees, as a condition for submitting a bid, that this project will be completed in the time agreed upon between the City and the Contractor. The Contractor agrees to commence work on https://www.ocalafl.gov/home/showpublisheddocument/29503 https://www.ocalafl.org/government/city-departments-a-h/growth-management/building/construction-permits https://www.ocalafl.org/government/city-departments-a-h/growth-management/building/construction-permits

Exhibit A – SCOPE OF WORK CONTRACT# FAC/260769

A - 2 the date specified in a written “Notice to Proceed” by the City. Such “Notice to Proceed” will be issued at the pre-construction conference. The Contractor must be able to mobilize and begin construction no later than 10 calendar days after notification and complete the project by the time limit specified in the “Notice to Proceed.” At no time will the Contractor be allowed to lag behind.

LIQUIDATED DAMAGES

1. The Contractor shall pay the City $250.00 for each calendar day that expires after the time specified for completion, until work is completed.

2. Nothing in this section is intended to limit the right to obtain injunctive relief or any and all relief as may be appropriate. Permission allowing the Contractor to continue and finish any part of the work after the time fixed for its completion or after the date to which the time for completion may have been extended shall in no way operate as a waiver on the part of the City of any of its rights under this Agreement.

ANTICIPATED TASKS, DELIVERABLES AND HOURS

1. Anticipated Tasks: The Contractor may be required to perform the following types of services for the City of Ocala. This list is not an attempt to exclusively define those specific activities the Contractor will perform.

• The Contractor shall perform all work in accordance with the approved architectural plans, specifications, and all applicable project documents.

• All drywall repairs and new drywall installations shall be finished to match the existing wall texture, properly primed, and painted with a minimum of two (2) finish coats to provide a uniform, professional appearance. The interior of the building shall be painted throughout for consistency. Final paint colors will be provided by the City at a later date.

• Existing baseboards throughout the facility shall be removed and replaced with 5 ¼-inch wood OGEE (S-curve) baseboards. All baseboards shall be fully caulked, with nail holes properly filled, sanded, and prepared prior to painting.

• Interior doors shall be replaced with solid-core wood doors installed in metal frames. All remaining interior doors within the facility shall be replaced to match these specifications to maintain a consistent appearance throughout the building.

• All locksets and door hardware shall be supplied by the City of Ocala.

• Flooring shall be provided by the City of Ocala and shall consist of 24x24 carpet tile installed in a quarter-turn pattern throughout designated areas of the building in accordance with current City standards. Final flooring layout plans will be provided by the City at a later date.

• The existing HVAC system shall be modified, balanced, and adjusted as necessary to provide consistent heating and cooling throughout all renovated areas. All spaces shall include properly sized and located supply and return registers to maintain system performance. Contractor shall provide a final testing and balancing (T&B) report upon completion.

• All existing overhead lighting fixtures shall be replaced with flat-panel LED fixtures featuring adjustable correlated color temperature (CCT). Lighting upgrades shall be completed throughout the facility to maintain a consistent appearance and lighting standard.

• All work shall comply with the current Florida Building Code and all other applicable federal, state, and local codes, standards, and regulations. The Contractor shall be responsible for ensuring compliance across all applicable trades, including but not limited to building, electrical, plumbing, mechanical, fire protection, and life safety systems. All required inspections and

Exhibit A – SCOPE OF WORK CONTRACT# FAC/260769

A - 3 approvals from the Authority Having Jurisdiction (AHJ) shall be obtained prior to project completion.

2. Deliverables: The Contractor shall provide weekly reports of all Task Work Orders in progress.

Deliverables shall be accepted by the City of Ocala Project Manager before payment for such work.

3. Working Hours: The normal/standard working hours for this project are 6:00 AM – 6:00 PM Monday through Sunday, excluding holidays. Contractor shall provide (forty-eight) 48-hour advance notice to City Project Manager for work outside normal shift hours. The city may decline the request.

4. Emergency Work Hours: The Contractor must have available staff on site and prepared to begin work within two (2) hours' notification of any work deemed “Emergency” (this includes all storm-related emergencies). If the work is not completed or staff are not on site by Contract timelines, the Contract will be considered in default.

A. Upon declaration of default, the City will have full power to appropriate or use any or all suitable and acceptable materials and equipment on the site and may enter into an agreement with others to complete the work under the Contract or may use other methods to complete the work in an acceptable manner. The City will charge all costs that the City incurs because of the Contractor’s default, including the costs of completing the work under the Contract, against the Contractor.

B. If, after default notice by the City, and prior to any action by the City to otherwise complete the work under the Contract, the Contractor establishes their intent to prosecute the work in accordance with the City’s requirements, then the City may allow the Contractor to resume the work, in which case the City will deduct from any monies due or that may become due under the Contract, any costs to the City incurred by the delay, or from any reason attributable to the delay.

PROJECT SPECIFICATIONS

This project will require the Contractor to follow the following plans and specifications:

1. Plan Set for the project attached as an exhibit.

2. All work must be in compliance with the Florida Building Code, latest edition. For information please visit the following link: https://floridabuilding.org/c/default.aspx

3. The Contractor must have the above-listed documents in addition to up-to-date copies of shop drawings, plans and bid document at job sites at all times.

4. All material & construction equipment must meet OSHA Standard Specifications for construction, electrical, plumbing, and mechanical, latest edition. Substantial completion date will start the warranty period for each assigned project.

WRITTEN QUOTES

1. The Contractor shall submit a detailed written estimate of the proposed services prior to any work being performed by the Contractor. Written quotes shall be submitted within three (3) days of the initial request by the City. The Contractor shall submit an itemized not-to-exceed price, giving a full description of the project for each project covered by this Contract.

2. Written quotes shall list the location name and address. The project estimate shall list each and every item per bid specifications, i.e., items and quantity, and all hardware items used. Each quote shall be submitted to the City Project Manager by email with a clear sketch or drawing (if applicable).

https://floridabuilding.org/c/default.aspx

Exhibit A – SCOPE OF WORK CONTRACT# FAC/260769

A - 4

CONTRACTOR EMPLOYEES AND EQUIPMENT

1. An employee roster must be provided for all projects assigned.

2. Contractor must utilize competent employees in performing the work. Employees performing the work must be properly licensed or qualified as required by the scope/project.

3. The Contractor shall provide an assigned Project Manager, who will be the primary point of contact.

Contractor must provide a valid telephone number, email, and address at all times to the City Project Manager. The telephone must be answered during normal working hours or voicemail must be available to take a message.

4. At the request of the City, the Contractor must replace any incompetent, unfaithful, abusive, or disorderly person in their employment. The City and the Contractor must each be promptly notified by the other of any complaints received.

5. The employees of the Contractor must wear suitable work clothes and personal protective equipment as defined by OSHA (hard hats, bucket harnesses, etc.) and meeting Manual on Uniform Traffic Control Devices (MUTCD) and National Electrical Safety Code (NESC) requirements as indicated for all work conducted and be as clean and in as good appearance as the job conditions permit.

6. Contractor will operate as an independent Contractor and not as an agent, representative, partner or employee of the City of Ocala, and shall control their operations at the work site, and be solely responsible for the acts or omissions of their employees.

7. No smoking is allowed on City property or projects.

8. Contractor must possess/obtain all required equipment to perform the work. A list of equipment shall be provided to the City upon request.

9. All company vehicles and uniforms must have a visible company name/logo.

CITY OF OCALA RESPONSIBILITIES

1. The City of Ocala will furnish the following services/data to the Contractor for the performance of services:

A. Provide access to drawings, specifications, schedules, reports, and other information prepared by/for the City of Ocala pertinent to the Contractor’s responsibilities.

B. Access to City buildings and facilities to perform the work.

2. The City reserves the right to purchase any materials for the Contractor to use. The Contractor shall not charge a mark-up fee for material furnished by the City.

CONTRACTOR RESPONSIBILITIES

1. The Contractor shall complete all work performed under this Contract in accordance with policies and procedures of the City of Ocala and all applicable State and Federal laws, policies, procedures, and guidelines.

2. The Contractor shall obtain and pay for any and licenses, additional equipment, dumping and/or disposal fees, etc., required to fulfill this Contract.

3. Construction/Installation shall be in compliance with all requirements and instructions of applicable manufacturers.

Exhibit A – SCOPE OF WORK CONTRACT# FAC/260769

A - 5

4. If the Contractor is advised to leave a property by the property owner or their representative, the Contractor shall leave at once without altercation. Contractor shall then contact the City Project Manager within 24 hours and advise of the reason for not completing the assigned project.

5. Contractor will be responsible for inspectors’ overtime.

6. Contractor is responsible for any and all damages, including but not limited to buildings, curbing, pavement, landscaping, or irrigation systems caused by their activity. Should any public or private property be damaged or destroyed, the Contractor, at their expense, shall repair or make restoration as acceptable to the City of destroyed or damaged property no later than one (1) month from the date damage occurred.

7. Data collected by the Contractor shall be in a format compatible with or easily converted to the City’s databases. A sequential naming convention should be applied to the files and documentation provided to the City.

8. The Contractor shall ensure that all documents prepared under this Contract have been prepared on a Windows-based operating system computer using the most current version of Microsoft Office, which includes Word, Excel, Power Point, Access or any other software as specified and approved by City staff.

SUB-CONTRACTORS

1. Contractor must perform a minimum of 30% of the work with their own forces.

2. Services assigned to sub-contractors must be approved in advance by the City Project Manager.

CONSTRUCTION WORK AREAS

1. The City of Ocala is not responsible for providing property or lay down yards to the Contractor for their materials or equipment. If private property is used, the City requires a copy of the agreement between the property owner and the Contractor. Utilizing private property without written permission is prohibited.

SITE HOUSEKEEPING AND CLEANUP

1. Waste/Debris: The Contractor shall keep the premises free at all times from accumulation of waste materials and rubbish caused by operations and employees. Contractor will provide approved containers for collection and disposal of waste materials, debris, and rubbish. Contractor shall dispose of debris in a legal manner. At least once weekly, dispose of such waste materials, debris, and rubbish off-site.

2. Cleanup: Periodic cleanup to avoid hazards or interference with operations at the site, and to leave the site in a reasonable neat condition. Work site will be completely cleaned after each day of work. Sweep all roadways affected by the construction and where adjacent to work daily.

3. Water Use: The use of water to prevent the blowing of dust and debris during cutting operations and or cleaning operations is mandatory.

4. Individual Project Cleaning: At completion of each individual project, Contractor shall remove from the site all tools, equipment, surplus materials, debris, temporary facilities, scaffolding, and equipment.

The areas of work shall be swept thoroughly and all marks, stains, rust, dirt, paint drippings, and the like shall be removed from all new and existing work to the satisfaction of the Owner.

Exhibit A – SCOPE OF WORK CONTRACT# FAC/260769

A - 6

5. Final Cleaning: Upon completion of work, clean entire work area/project site as applicable.

A. Leave the work and adjacent areas affected in a clean condition satisfactory to the City Project Manager.

B. The Contractor shall clean and remove from the premises, all surplus and discarded materials, rubbish, and temporary structures, and shall restore in an acceptable manner all property, both public and private, which has been damaged during the prosecution of the work and shall have the work in a neat and presentable condition. Note: All debris shall be removed from the premises.

New construction debris, trash, etc., shall not be left or buried on site.

C. Broom clean exterior paved driveways and parking areas and hose clean sidewalks and concrete exposed surfaces if impacted by work or included in work area.

D. All furnishings and equipment shall be placed back in the original locations.

E. All work areas must be returned to their original condition.

SUBMITTALS

1. Submit copies of permits and approvals for construction as required by laws and regulations of governing agencies.

2. Submit temporary construction parking area plans, storage yard, storage trailer location, staging area plan, and plan for disposal of waste materials.

SAFETY

1. The Contractor is solely responsible for ensuring safety during construction, and for conformance to all applicable OSHA standards; and local, state, and national codes concerning safety provisions for their employees, sub-contractors, all building and site occupants, staff, public, and all persons in or around the work area.

2. Job site visits by City staff do not constitute approval, awareness, or liability for any hazardous condition.

3. Contractor shall be responsible for securing their equipment, materials, clothing, and other property.

4. Prior to completion, storage and adequate protection of all material and equipment will be the Contractor’s responsibility.

5. In no event shall the City be responsible for any damages to any of the Contractor's equipment, materials, property, or clothing lost, damaged, destroyed or stolen.

WARRANTY

1. Contractor will provide a five-year material and labor warranty from the date of substantial completion, against operational failure caused by defective material or workmanship which occurs during normal use.

2. All manufacturer warranty documentation and owner/operator manuals must be provided before final payment request.

INVOICING

1. All original invoices will be sent to: Charles Stewart, Project Manager, Facilities Management Department, 1805 NE 30th Avenue, Building 200, Ocala, FL 34470, email: Facilities@ocalafl.gov mailto:Facilities@ocalafl.gov

Exhibit A – SCOPE OF WORK CONTRACT# FAC/260769

A - 7

2. Contractor will invoice at least once a month.

PRICING AND AWARD

1. Bids will be received on a lump sum basis. Lump sum amount must include all direct and indirect costs to complete the project.

2. Award will be made to the lowest bidder meeting all requirements outlined herein.

3. AMOUNTS DUE TO THE CITY. Contractor/Vendor must be current and remain current in all obligations due to the City during the performance of services under the Agreement. Payments to Contractor/Vendor may be offset by any delinquent amounts due to the City or fees and/or charges owed to the City.

File details come from the government source that posted it. Updated .