About this file

This is Amendment #2 to an Invitation to Bid (ITB #32701-13876) issued by the State of Tennessee Department of Environment and Conservation for invasive species removal services at Savage Gulf State Park. The project encompasses approximately 110 acres across 21 treatment units and requires comprehensive vegetation management including mastication of vegetation under 15 inches diameter at breast height, cutting and stacking of larger materials, hand-removal in designated wetlands, stump treatment with approved herbicide, tree limb trimming to 16 feet along fence and field edges, and equipment rut repair. The amendment updates the project schedule with a pre-response conference scheduled for April 22, 2026 at 10:00 a.m. CT, questions and comments due by April 24, 2026 at 2:00 p.m. CT, and bids due by May 8, 2026 at 2:00 p.m. CT. The amendment extends the project completion date from the original June 20, 2026 to November 30, 2026 to allow time for contract execution and crew scheduling. The amendment also clarifies licensing requirements by accepting Tennessee BC, BC-29, and BC-B licenses and addresses questions regarding trail access and public notifications, confirming that no trails exist within the project area.

The amendment specifies that the previous specifications document dated April 10, 2026 is deleted in its entirety and replaced with an updated specifications document dated April 27, 2026. Bidders must possess a valid Tennessee State Building Construction license and provide proof of licensure upon award. The contract will be awarded to the lowest-cost responsive and responsible bidder based on unit pricing submitted on an F.O.B. destination basis. Bidders must comply with the Iran Divestment Act, provide documentation of sales and use tax registration with the Tennessee Department of Revenue, maintain appropriate insurance coverage including workers' compensation and commercial general liability with minimum limits of $1,000,000 per occurrence, and provide a payment bond equal to 25 percent of the maximum liability amount for bids exceeding $100,000. All revisions set forth in this amendment are effective upon release, and all other terms and conditions not expressly amended remain in full force and effect.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITB # 32701-13876 – Amendment # 2 Page 1 of 1

STATE OF TENNESSEE

DEPARTMENT OF ENVIRONMENT AND CONSERVATION

INVITATION TO BID # 32701-13876

AMENDMENT # 2

FOR SAVAGE GULF STATE PARK INVASIVE

SPECIES REMOVAL

DATE: APRIL 28, 2026

ITB # 32701-13876 IS AMENDED AS FOLLOWS:

1. This ITB Schedule of Events updates and confirms scheduled ITB dates. Any event, time, or date containing revised or new text is highlighted.

Event Time Date

Event Posted 8:00 am CT 4-13-2026

Pre-Response Conference 10:00 am CT 4-22-2026

Questions and Comments Due 2:00 pm CT 4-24-2026

Bids Due 2:00 pm CT 5-8-2026

2. State responses to questions and comments in the table below amend and clarify this ITB.

Any restatement of ITB text in the Question/Comment column shall NOT be construed as a change in the actual wording of the ITB document.

ITB

SECTION

PAGE

QUESTION / COMMENT STATE RESPONSE

1. Licensing requirements call for a TN BC or BC-29 license to perform the work.

May a BC-B license be accepted?

Yes.

2. Given the contract bid date and the required completion date, can an extension for completion date be granted to allow time for contract execution and crew scheduling?

The new completion date is November 30, 2026. Please see the updated specs document.

3. Will the park be closing trails from public access?

There are no trails within the project area.

4. If the trails remain open will the park place signage and announce spraying and heavy equipment operation ahead notifications to the public or will this be the responsibility of the contractor?

There are no trails within the project area.

3. Delete ITB attachment “Savage Gulf SP Invasive Species Removal Specs (4.10.26)” in its entirety and insert the following in its place (any sentence or paragraph containing revised or new test is highlighted):

“Savage Gulf SP Invasive Species Removal Specs (4.27.26)”

4. ITB Amendment Effective Date. The revisions set forth herein shall be effective upon release. All other terms and conditions of this ITB not expressly amended herein shall remain in full force and effect.