ITB_25-16_Courthouse_Renovations_Draft_Contract_rev._6.30.26.doc

DOC document 2 MB Posted

Attached to
Old Courthouse Renovation 2nd Phase
Solicitation number
ITB: 26-16
Issued by
Gilchrist County, Florida

About this file

ITB 26-16: Gadsden County Courthouse Renovation Summary

This is a draft contract for the Gadsden County Board of County Commissioners for the renovation and restoration of the historic Gadsden County Courthouse located at 10 East Jefferson Street in Quincy, Florida, Phase II. The scope of work includes painting the exterior and repairing wood rot, removing non-historic paint from exterior steps and landings using gentle methods compliant with Standards of Integrity (SOI) guidelines, sealing exterior steps and landings, restoring eight cupola windows, cleaning and sealing Terrazzo flooring, and repairing or replacing the metal roof and eight exterior doors. Work must comply with historical restoration requirements approved by the Historical Restoration Society. The project is funded through a Special Category Grant from the Florida Division of Historical Resources (Grant No. 25.h.sc.100.009). The contract includes a projected timeline with contract execution scheduled for September 1-8, 2026, a pre-construction meeting on September 10, 2026, Notice to Proceed issuance on September 15, 2026, substantial completion by November 18, 2026 (90 consecutive calendar days), and final completion by December 18, 2026 (120 calendar days), with closeout activities extending through February 12, 2027.

The contract amount is not to exceed $460,000.00, with compensation paid monthly based on approved applications for payment. The County will retain five percent (5%) of each monthly payment, with remaining retainage released upon substantial completion less an estimated cost to complete punch list items. Liquidated damages are assessed at $750.00 per calendar day if substantial completion is not achieved within the specified timeframe. The contractor must provide a 100 percent Performance and Payment Bond and obtain required insurance coverage with the County and Engineer of Record listed as additional insureds. The contractor is responsible for all permits except County-issued permits, and the County retains the right to directly purchase materials for sales tax savings. A general contractor license is required for work in Florida, and the contractor must comply with E-Verify requirements and all applicable federal, state, and local laws and regulations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

file_0.wmf file_1.wmf file_2.wmf

ITB 26-16 Renovations and Restoration of Gadsden County Historic Court House, Phase II Appendix A: Draft Contract

GADSDEN COUNTY, a political subdivision of the State of Florida, by and through its Board of County Commissioners, situated at Suite 5-B East Jefferson Street, Gadsden County, Florida 32351 (the "County"), hereby contracts with (the "Contractor") whose principal place of business is at , whose Federal ID number is: and Unique Entity Identifier (UE) is ______________ (if applicable) and is a general contractor license _______________ who is licensed to perform all work in the State of Florida with the County’s ITB 26-16 (the “Project”), and other Contract Documents hereafter specified (the “Work”).

Project Description and Funding: Restoration and renovation of the Gadsden County Courthouse in Quincy, Florida. Work items include paint exterior and repair wood rot; remove non-historic paint on exterior steps and landing using the gentlest means possible in accordance with SOI Standards, and seal exterior steps and landing; restore eight cupola windows; clean and seal Terrazzo flooring; repair/replace metal roof; and repair/replace eight exterior doors.

Funding for the Project is from a Special Category Grant by the Division of Historical Resources, grant number 25.h.sc.100.009 for the Project “Old Courthouse Renovation 2nd Phase”.

The County and the Contractor, for the consideration herein set forth, agree as follows:

Section 1. Contract Documents.

The Contract Documents consist of this Agreement, the Exhibits described in Section 36 hereof, the Legal Advertisement, the ITB, the Bid, and any duly executed and issued addenda, Change Orders, Work Directive Changes, Field Orders, Work Authorizations, and amendments relating thereto. All of the foregoing Contract Documents are incorporated by reference and made a part of this Agreement (all of said documents, including the Agreement, sometimes being referred to herein as the "Contract Documents" and sometimes as the "Agreement"). A copy of the Contract Documents shall be maintained by the Contractor at the Project site at all times during the performance of the Work.

The Engineer of Record (EOR) is the initial interpreter of the Contract Documents, but is not the judge between the County and the Contractor. The County reserves the right to make final decisions considering the EOR’s recommendations or interpretations of the Contract Documents. The EOR does not have the authority to obligate or commit the County to fund additional expenditures or approve extensions of time over the approved Contract Time or Amount. However, the EOR’s interpretation as to the intent of the engineering drawings and specifications shall be final and not subject to interpretation by the County’s staff.

Any Work that may be reasonably inferred from the specifications as being required to produce the intended result shall be supplied whether or not it is specifically called for. In case of any inconsistency or conflict among the provisions of the Agreement and any other terms and conditions of any documents comprising the Contract Documents, the provisions of the Agreement shall control. Concerning the Contract Documents, the order of precedence shall be as follows: (1) Change Orders; (2) the Agreement, including amendments and Exhibits; (3) Field Orders; (4) the solicitation documents, including any addenda. The Contract Documents listed above represent the entire and integrated Agreement between the parties hereto, and supersede prior negotiations, representations, or agreements, either written or oral.

Work, materials, or equipment described in words that have a well-known technical or trade meaning, shall be deemed to refer to such recognized standards.

The County shall furnish to the Contractor up to one (1) set of the Contract Documents as are reasonably necessary for execution of the Work. Additional copies of the Contract Documents shall be furnished, upon request, at the cost of reproduction.

The Contractor agrees to bind specifically every Subcontractor to the applicable terms and conditions of the Contract Documents for the benefit of the County.

The Work provided by the Contractor for the Project shall be under the general direction of the EOR, or their successor, who shall act as the County's representative during the term of this Agreement. If the County’s representative is not a County employee, then County’s representative is not authorized to issue changes to the Contract Amount, Contract Time, or Scope of Work without express approval by the Department Director, County Administrator, or Board of County Commissioners.

The County’s representative, within the authority conferred by the Board of County Commissioners, shall initiate written Change Orders, and notification to the Contractor of any and all changes approved by the County in the Contractor’s: (1) compensation; (2) time and/or schedule of service delivery; (3) and any amendment (s) or other change(s) relative to the Work pursuant to this Contract or Change Orders pertaining thereto. Following County approval, the County’s representative shall coordinate issuance of any such documents. The County’s representative shall be responsible for acting on the County’s behalf to administer, coordinate, interpret and otherwise manage the contractual provisions and requirements set forth in this Contract or any amendments, or Change Orders issued hereunder.

Neither the Contractor nor any Subcontractor, Supplier, or other person or organization performing or furnishing any of the Work under a direct or indirect contract with the County shall have or acquire any title to or ownership rights to any of the Drawings, Specifications or other documents (or copies of any thereof) prepared by or bearing the seal of the EOR; and they shall not reuse any of them on extensions of the Project or any other project without written consent of the County or their EOR and the specific written verification or adaptation by the EOR.

Section 2. Scope of Work.

The Contractor agrees to furnish and pay for all management, supervision, financing, labor, materials, tools, transportation, fuel, supplies, utilities, equipment and services of every kind and type necessary to diligently, timely, and fully perform and complete in a good and workmanlike manner the Work required by this Agreement.

All materials and equipment shall be applied, installed, connected, erected, used, cleaned, and conditioned in accordance with the instructions of the applicable manufacturers, fabricator, or processors except as otherwise provided in the Contract Documents.

Section 3. Contract Amount In consideration of the faithful performance by the Contractor of the covenants in this Agreement to the full satisfaction and acceptance of the County, the County agrees to pay, or cause to be paid, to Contractor the following amount not to exceed (herein "Contract Amount"), in accordance with the terms of this Agreement: $ 460,000.00 or in WORDS: Four Hundred sixty thousand dollars and no cents.

Compensation and manner of payment of such compensation by the County for the Work rendered hereunder by the Contractor shall be prescribed in Exhibit C4. Basis for Compensation, which is attached hereto and made a part of hereof.

The Contractor shall notify the County and EOR in writing when 90 percent of the approved “not to exceed” amount has been reached.

The total amount is not to be construed as a “line-item” guarantee. If one category exceeds the budgeted amount, and another is less than the budgeted amount, they shall offset each other to the extent that the total is not exceeded.

If the Contract Amount includes an Allowance, the Contractor shall cause the Work covered by the Allowance to be done for such sums within the limits of the Allowance as the County may approve. The Contractor agrees that the Contract Amount includes such sums as they deem proper for costs and any profit on account of any Allowances. No demands for an additional sum for overhead, profit or “out of pocket” expenses will be allowed.

Any agreed upon changes to the Contract Amount must be accomplished by an approved, written Change Order in the form attached to this Agreement.

The County may subsequently identify items eligible for direct purchase for sales tax savings. The County shall, at its sole discretion, have the option to purchase directly from the supplier or vendor any supplies, materials or equipment included in the Contractor's bid for the Contract. The County reserves the right to require Contractor to assign to the County agreements with suppliers for such goods. The Contractor shall, from time to time submit, update and keep current, for consideration by the County, a list of all materials, supplies and equipment to be purchased, organized by supplier or vendor. Such list shall include a brief description of the materials, supplies and equipment and the name and address of the supplier or vendor. Suppliers or vendors reasonably anticipated to furnish material, supplies and equipment with an aggregate purchase value of less than $10,000 need not be listed. Goods not required for the performance of the Contract shall not be purchased under this Agreement. The County reserves the right to delete or add items from this Agreement when it is in the County's best interest. Upon approval by the County, the Contractor will provide a worksheet by electronic means which will include a Bid from the vendor detailing the description of the item to be purchased, total price and sales tax to be deducted. The County will then issue a purchase order directly to the vendor for the cost of the item less the sales tax. Upon completion of all direct purchases the Contractor will prepare a deductive Change Order reducing the Contract Amount by the total amount of the purchases, inclusive of all sales tax, shipping, handling, insurance, and other similar charges paid by Owner. Administrative costs incurred by the Contractor with this Agreement, including administering the purchases in the name of the County, shall be considered to be included in the base bid proposal for work. No addition shall be added to the Contract Amount because of the service provided by the Contractor in the purchase of property, materials, etc, in the name of the County.

Section 4. Bonds.

In accordance with Section 255.05, Florida Statutes, the Contractor shall record and provide Performance and Payment Bonds, in the form prescribed in the ITB Forms 18A and 18B, included with the Contractor’s Bid, in the amount of 100% of the Contract Amount, the costs of which are to be paid by Contractor. If the Contract is increased by a Change Order, it shall be the Contractor’s responsibility to ensure that the Performance and Payment Bonds are amended accordingly, and a copy of the amendment forwarded to the County. The Performance and Payment Bonds shall be underwritten by a surety authorized to do business in the State of Florida and otherwise acceptable to the County; provided, however, the surety shall be rated as "A-" or better as to general policy holders rating and Class V or higher rating as to financial size category and the amount required shall not exceed 5% of the reported policy holder’s surplus, all as reported in the most current Best Key Rating Guide, published by A.M. Best Company, Inc. of 75 Fulton Street, New York, New York 10038.

If the surety for any bond furnished by Contractor is declared bankrupt, becomes insolvent, its right to do business is terminated in the State of Florida, or it ceases to meet the requirements imposed by the Contract Documents, the Contractor shall, within five (5) calendar days thereafter, substitute another bond and surety, both of which shall be subject to the County's approval.

Section 5. Contract Time and Liquidated Damages Time is of the essence in the performance of the Work under this Agreement. The "Commencement Date" is established in the Notice to Proceed to be issued by the County. Written Notice to Proceed is contingent upon and will be done subsequent to the Contractor fully satisfying the County’s stated insurance and Bond submittal requirements. The Contractor shall commence the Work as agreed to in the Notice to Proceed, the “Commencement Date”. No Work shall be performed at the Project site prior to the Commencement Date. Any Work performed by the Contractor prior to the Commencement Date shall be at the sole risk of the Contractor. The Work shall be substantially completed within 90 consecutive calendar days from the commencement date as stated in the Notice to Proceed. The date of substantial completion of the Work (or designated portions thereof) is the date certified by the EOR when construction is sufficiently complete, in accordance with the Contract Documents, so the County can occupy or utilize the Work (or designated portions thereof) for the use for which it is intended. The Work shall be fully completed and ready for final acceptance by the County within 30 consecutive calendar days from the substantial completion date, unless otherwise agreed to by the parties (herein “Contract Time

The County and the Contractor recognize that, since time is of the essence for this Agreement, the County will suffer financial loss if the Work is not substantially completed within the time specified above, as said time may be adjusted as provided for herein. Should the Contractor fail to substantially complete the Work within the time period noted above, the

County shall be entitled to assess, as liquidated damages, but not as a penalty, $750.00 for each calendar day thereafter until substantial completion is achieved. The Project shall be deemed to be substantially completed on the date the EOR issues a Substantial Completion Certificate pursuant to the terms hereof. The Contractor hereby expressly waives and relinquishes any right which it may have to seek to characterize the above noted liquidated damages as a penalty, which the parties agree represents a fair and reasonable estimate of the County's actual damages at the time of contracting if the Contractor fails to substantially complete the Work in a timely manner.

When any period of time is referenced by days herein, it shall be computed to exclude the first day and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day shall be omitted from the computation, and the last day shall become the next succeeding day which is not a Saturday, Sunday or legal holiday. All days shall mean calendar day and not business day.

Section 6. Intent of Contract Documents

It is the intent of the Contract Documents to describe a functionally complete project (or portion thereof) to be constructed in accordance with the Contract Documents. Any work, materials or equipment that may reasonably be inferred from the Contract Documents as being required to produce the intended result shall be supplied whether or not specifically called for. When words which have a well-known technical or trade meaning are used to describe work, materials or equipment, such words shall be interpreted in accordance with that meaning. Reference to standard specifications, manuals or codes of any technical society, organization, or association or to the laws or regulations of any governmental authority having jurisdiction over the Project, whether such reference be specific or by implication, shall mean the latest standard specification, manual, code, law, or regulation in effect at the time the Work is performed, except as may be otherwise specifically stated herein.

If before or during the performance of the Work, Contractor discovers a conflict, error or discrepancy in the Contract Documents, Contractor immediately shall report same to EOR in writing and before proceeding with the Work affected thereby shall obtain a written interpretation or clarification from the EOR. If required, a Field Order or Change Order will be issued pursuant to Section 15 of this Agreement. If the Contractor performs any Construction activity knowing it involves a recognized error, inconsistency, or omission in the Contract Documents without such notice to the EOR and County, the Contractor shall assume responsibility for such performance and shall share in costs associated with any corrections. Contractor shall take field measurements and verify field conditions and shall carefully compare such field measurements and conditions and other information known to Contractor with the Contract Documents before commencing any portion of the Work.

Drawings are intended to show general arrangements, design and extent of Work and are not intended to serve as shop drawings. Specifications are separated into divisions for convenience of reference only and shall not be interpreted as establishing divisions for the Work, trades, subcontracts, or extent of any part of the Work. In the event of a discrepancy between or among the drawings, specifications or other Contract Document provisions, Contractor shall be required to comply with the provision which is the more restrictive or stringent requirement upon the Contractor, as determined by the EOR. Unless otherwise specifically mentioned, all anchors, bolts, screws, fittings, fillers, hardware, accessories, trim, and other parts required in connection with any portion of the Work to make a complete, serviceable, finished and first quality installation shall be furnished and installed as part of the Work, whether or not called for by the Contract Documents.

Section 7. Investigation and Utilities

Contractor shall have the sole responsibility of satisfying itself concerning the nature and location of the Work and the general and local conditions, and particularly, but without limitation, with respect to the following: those affecting transportation, access, disposal, handling and storage of materials; availability and quality of labor; water, sewer, and electric power; availability and condition of roads; work area; living facilities; climatic conditions and seasons; physical conditions at the work-site and the project area as a whole; topography and ground surface conditions; nature and quantity of the surface materials to be encountered; subsurface conditions; equipment and facilities needed preliminary to and during performance of the Work; and all other costs associated with such performance. The failure of Contractor to acquaint itself with any applicable conditions shall not relieve Contractor from any of its responsibilities to perform under the Contract Documents, nor shall it be considered the basis for any claim for additional time or compensation.

Contractor shall locate all existing roadways, railways, drainage facilities and utility services above, upon, or under the Project site, said roadways, railways, drainage facilities and utilities (surface and subsurface) being referred to in this Sub-Section 7.B. as the "Utilities". Contractor shall contact the owners of all Utilities to determine the necessity for relocating or temporarily interrupting any Utilities during the construction of the Project. Contractor shall schedule and coordinate its Work around any such relocation or temporary service interruption. Contractor shall be responsible for properly shoring, supporting, and protecting all Utilities at all times during the course of the Work. Relocation or shutdown of County facilities must be requested by the Contractor in writing a minimum of ten (10) calendar days prior to the proposed Work. The County shall have the final decision with respect to whether the relocation or shutdown is required and when the relocation or shutdown of facilities may take place. The Work may need to be performed at night or on weekends to minimize the interruption of service or to meet the operational needs of the County's facilities.

Section 8. Schedule

The Contractor, within ten (10) calendar days after receipt of a Notice of Award, shall prepare and submit to the County and EOR, for their review and approval, a progress schedule for the Project (herein "Progress Schedule"). The Progress Schedule shall relate to all Work required by the Contract Documents and shall provide for expeditious and practicable execution of the Work within the Contract Time. The Progress Schedule shall indicate the dates for starting and completing the various stages of the Work.

The Progress Schedule shall be updated monthly by the Contractor. All monthly updates to the Progress Schedule shall be subject to the County's and EOR review and approval. Contractor shall submit the updates to the Progress Schedule with its monthly Applications for Payment noted below. The County's and the EORs review and approval of the submitted Progress Schedule updates shall be a condition precedent to the County's obligation to pay Contractor.
Projected Timeline for Work Completion:

Contract Execution: September 1-8, 2026 Pre-Construction Meeting: September 10, 2026 Issuance of Notice to Proceed: September 15, 2026 Submit CPM construction schedule: 30 days from issuance of NTP Pre-construction Activities: September 16-30, 2026 Substantial Completion: November 18, 2026 Final Completion/Acceptance of work: December 18, 2026 Closeout Activities: January 1, 2027 through February 12, 2027

*Consecutive calendar days.

**The milestones and/or target dates are subject to change based on the actual date of the contract execution, the issuance of the Notice to Proceed (NTP), or other unknown factors.

Section 9. Progress Payments

Prior to submitting its first monthly Application for Payment, Contractor shall submit to the County and the EOR, for their review and approval, a schedule of values based upon the Contract Price, listing the major elements of the Work and the dollar value for each element. After its approval by the County and EOR, this schedule of values shall be used as the basis for the Contractor's monthly Applications for Payment. This schedule shall be updated and submitted each month to the EOR along with a completed and notarized copy of the Application for Payment form. No voluntary acceleration or early completion of the Work shall modify the time of payments to Contractor as set forth in the approved Schedule of Values.

Prior to submitting its first monthly Application for Payment, Contractor shall submit to the County and the EOR a complete list of all its proposed subcontractors and materialmen, showing the work and materials involved and the dollar amount of each proposed subcontract and purchase order. The first Application for Payment shall be submitted no earlier than thirty (30) days after the Commencement Date.

If payment is requested on the basis of materials and equipment not incorporated into the Project, but delivered and suitably stored at the site or at another location agreed to by the County in writing, the Application for Payment shall also be accompanied by a bill of sale, invoice or other documentation warranting that the County has received the materials and equipment free and clear of all liens, charges, security interests and encumbrances, together with evidence that the materials and equipment are covered by appropriate property insurance and other arrangements to protect the County's interest therein, all of which shall be subject to the County's satisfaction.

Contractor shall submit two (2) copies of its monthly Application for Payment to the EOR on or before the 25th day of each month for work performed during the previous month. Invoices received after the 25th day of each month shall be considered for payment as part of the next month's application. Within ten (10) calendar days after receipt of each Application for Payment, the EOR shall either:

indicate his approval of the requested payment;

indicate his approval of only a portion of the requested payment, stating in writing his reasons; therefore, or
return the Application for Payment to the Contractor indicating, in writing, the reason for refusing to approve payment and the action necessary to make the payment request proper.

In the event of a total denial and return of the Application for Payment by the EOR, the Contractor may make the necessary corrections and resubmit the Application for Payment. The County shall, within thirty (30) calendar days after County approval of an Application for Payment, pay the Contractor the amounts so approved. Provided, however, in no event shall the County be obligated to pay any amount greater than that portion of the Application for Payment approved by the EOR.

The County shall initially retain five percent (5%) of the gross amount of each monthly payment request or five percent (5%) of the portion thereof approved by the EOR for payment, whichever is less. Such sums shall be accumulated and released to Contractor as follows. Within 20 days after the EOR delivers the tentative punch list to Contractor as set forth in set forth in Section 26 herein, the County will pay the contractor the remaining contract balance including retainage previously withheld less an amount equal to 150 percent of the estimated cost to complete the items on the tentative punch list (the “remaining retainage”). The remaining retainage will be released to the Contractor with final payment.

Monthly payments to Contractor shall in no way imply or constitute approval or acceptance of Contractor's work.

Each Application for Payment shall be accompanied by a Release and Affidavit, in the form attached to this Agreement, showing that all materials, labor, equipment and other bills associated with that portion of the Work for which payment is being requested have been paid in full. The County shall not be required to make payment until and unless these affidavits are furnished by the Contractor.

Contractor agrees and understands that funding limitations exist and that the expenditure of funds must be spread over the duration of the Project at regular intervals based on the Contract Amount and Progress Schedule. Accordingly, prior to submitting its first monthly Application for Payment, Contractor shall prepare and submit for the County's and the EOR's review and approval, a detailed Project Funding Schedule, which shall be updated as necessary and approved by the County to reflect approved adjustments to the Contract Amount and Contract Time. No voluntary acceleration or early completion of the Work shall modify the time of payments to Contractor as set forth in the approved Project Funding Schedule.

Section 10. Payments Withheld

The EOR or the County may decline to approve any Application for Payment, or portions thereof, because of subsequently discovered evidence or subsequent inspections. The EOR or the County may nullify the whole or any part of any approval for payment previously issued and the County may withhold any payments otherwise due Contractor under this Agreement or any other agreement between the County and Contractor, to such extent as may be necessary in the County's opinion to protect it from loss because of:

Defective Work not remedied;

Third party claims filed or reasonable evidence indicating probable filing of such claims;

Failure of Contractor to make payment properly to subcontractors or for labor, materials or equipment;

Reasonable doubt that the Work can be completed for the unpaid balance of the Contract Amount;

Reasonable indication that the Work will not be completed within the Contract Time;

Unsatisfactory prosecution of the Work by the Contractor;

Failure to provide accurate and current "As-Builts"; or

Any other material breach of the Contract Documents.

If these conditions in Subsection 10.A are not remedied or removed, the County may, after three (3) days written notice, rectify the same at Contractor's expense. The County also may offset against any sums due Contractor the amount of any liquidated or unliquidated obligations of Contractor to the County, whether relating to or arising out of this Agreement or any other agreement between Contractor and the County.

Section 11. Final Payment

The County shall make final payment to Contractor within thirty (30) calendar days after the Work is finally inspected and accepted by both the County and the EOR in accordance with Section 26.A. herein, provided that Contractor first, and as an explicit condition precedent to the accrual of Contractor's right to final payment, shall have furnished the County with a properly executed and notarized copy of the Release and Affidavit, as well as, a duly executed copy of the Surety's consent to final payment and such other documentation that may be required by the Contract Documents and the County.

Contractor's acceptance of final payment shall constitute a full waiver of any and all claims by Contractor against the County arising out of this Agreement or otherwise relating to the Project, except those previously made in writing and identified by Contractor as unsettled at the time of the final Application for Payment. Neither the acceptance of the Work nor payment by the County shall be deemed to be a waiver of the County's right to enforce any obligations of Contractor hereunder or to the recovery of damages for defective Work not discovered by the EOR or the County at the time of final inspection.

Section 12. Submittals and Substitutions

Contractor shall carefully examine the Contract Documents for all requirements for approval of materials to be submitted such as a schedule of values, safety manual, shop drawings, data, test results, schedules, and samples. Contractor shall submit all such materials at its own expense and in such form as required by the Contract Documents in sufficient time to prevent any delay in the delivery of such materials and the installation thereof.

Whenever materials or equipment are specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular supplier, the naming of the item is intended to establish the type, function and quality required. Unless the name is followed by words indicating that no substitution is permitted, materials or equipment of other suppliers may be accepted by the County if sufficient information is submitted by Contractor to allow the County to determine that the material or equipment proposed is equivalent or better than to that named. Requests for review of substitute items of material and equipment will not be accepted by the County from anyone other than Contractor and all such requests must be submitted by Contractor to EOR within thirty (30) calendar days after Notice of Award is received by Contractor.

If Contractor wishes to furnish or use a substitute item of material or equipment, Contractor shall make application to the EOR for acceptance thereof, certifying that the proposed substitute shall perform adequately the functions and achieve the results called for by the general design, be similar and of equal substance to that specified and be suited to the same use as that specified. The application shall state that the evaluation and acceptance of the proposed substitute will not prejudice Contractor's achievement of substantial completion on time, whether or not acceptance of the substitute for use in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with the County for the Project) to adapt the design to the proposed substitute and whether or not incorporation or use of the substitute in connection with the Work is subject to payment of any license fee or royalty. All variations of the proposed substitute from that specified will be identified in the application and available maintenance, repair and replacement service shall be indicated. The application also shall contain an itemized estimate of all costs that will result, directly or indirectly, from acceptance of such substitute, including costs for redesign and claims of other contractors affected by the resulting change, all of which shall be considered by the EOR in evaluating the proposed substitute. The EOR may require Contractor to furnish at Contractor's expense additional data about the proposed substitute.

If a specific means, method, technique, sequence, or procedure of construction is indicated in or required by the Contract Documents, Contractor may furnish or utilize a substitute means, method, sequence, technique or procedure of construction acceptable to the EOR, if Contractor submits sufficient information to allow the EOR to determine that the substitute proposed is equivalent to that indicated or required by the Contract Documents. The procedures for submission to and review by the EOR shall be the same as those provided herein for substitute materials and equipment.

The EOR shall be allowed a reasonable time within which to evaluate each proposed substitute. The EOR shall be the sole judge of acceptability, and no substitute will be ordered, installed, or utilized without the EOR's and the County's prior written acceptance which shall be evidenced by either a Change Order or an approved Shop Drawing. The County may require Contractor to furnish at Contractor's expense a special performance guarantee or other surety with respect to any substitute. The EOR will record time required by the EOR and the EOR's consultants in evaluating substitutions proposed by Contractor and making changes in the Contract Documents occasioned thereby. Whether or not the County accepts a proposed substitute, Contractor shall reimburse the County for the charges of the EOR and the EOR's consultants for evaluating each proposed substitute, or such charges may be deducted from an application for payment, at the County’s sole discretion.

Section 13. Daily and Weekly Reports

Unless waived in writing by the County, Contractor shall complete and submit to EOR on a weekly basis a daily log of the Contractor's work for the preceding week in a format approved by the EOR and the County. The daily log shall document all activities of Contractor at the Project site including, but not limited to, the following:

Weather conditions showing the high and low temperatures during work hours, the amount of precipitation received on the Project site, and any other weather conditions which adversely affect the Work;

Soil conditions which adversely affect the Work;

The hours of operation by Contractor's and subcontractor's personnel;

The number of Contractor's and subcontractor's personnel present and working at the Project site, by subcontract and trade;

All equipment present at the Project site, description of equipment uses and designation of time equipment was used (specifically indicating any down time);

Description of Work being performed at the Project site;

Any unusual or special occurrences at the Project site;
Materials received at the Project site;

A list of all visitors to the Project site; and

Any problems that might impact either the cost or quality of the Work or the time of performance.

The daily log shall not constitute nor take the place of any notice required to be given by Contractor to the County or EOR pursuant to the Contract Documents.

Contractor shall maintain in a safe place at the Project site one record copy of the Contract Documents, including, but not limited to, all drawings, specifications, addenda, amendments, Change Orders, Work Directive Changes and Field Orders, as well as all written interpretations and clarifications issued by the EOR, in good order and annotated to show all changes made during construction. The annotated drawings shall be continuously updated by the Contractor throughout the prosecution of the Work to accurately reflect all field changes that are made to adapt the Work to field conditions, changes resulting from Change Orders, Work Directive Changes and Field Orders, and all concealed and buried installations of piping, conduit and utility services. All buried and concealed items, both inside and outside the Project site, shall be accurately located on the annotated drawings as to depth and in relationship to not less than two (2) permanent features (e.g. interior or exterior wall faces). The annotated drawings shall be clean, and all changes, corrections and dimensions shall be given in a neat and legible manner in a contrasting color. The "As-Built" record documents, together with all approved samples and a counterpart of all approved shop drawings shall be available to EOR for reference. Current and accurate “As-Built” record documents shall be submitted with each Application for Payment. Failure to provide current and accurate “As-Built” record drawings shall be reason for rejecting the Application for Payment. Upon completion of the Work and as a condition precedent to Contractor's entitlement to final payment, these "As-Built" record documents, samples and shop drawings shall be delivered to EOR by Contractor for the County.

The Contractor shall submit to the EOR one complete, certified set of all recorded changes made during Construction entitled ‘As-Built,’ dated and sealed by the Project Architect. Submittals shall be in both hardcopy and digital format and are due as a condition of Substantial Completion.

Certified “as-built information, which the Contractor must show on marked-up copies of the design drawings, prints, and other materials as specified above, shall include both authorized and unauthorized changes and any modifications to material types from that specified in the bid plans and Specifications. As a prerequisite to any payments, the Contractor shall make available to the EOR all “as-built” information pertinent to the design drawings each month prior to his submission of a monthly application for payment. The Contractor shall also obtain “as- built” cross-sections of the roadway, ditches, channels, and other drainage ways as shown in the Contract Documents at intervals not to exceed 100 ft. The Contractor shall set benchmarks on or within 100 ft. of each control structure constructed as part of the Project. A complete description including elevation and location of each control structure benchmark shall be provided to the EOR as part of the “as-built” information. The elevation shall be clearly and permanently indicated on each benchmark.

“As-built” dimensions and elevations shall be obtained by a Professional Land Surveyor registered in the State of Florida pursuant to Chapter 472, Florida Statutes. The “as- built” drawings shall be signed and sealed by the Contractor’s Professional Land Surveyor in accordance with Section 472.025, Florida Statutes.

All pertinent surveyors’ field survey notes containing the “as-built” data shall be sealed and submitted to the EOR for review and acceptance prior to authorization of the final payment.

“As-built” data shall be secured, and the accuracy of measurements shall be 0.01 ft.

All sub-surface improvements considered part of the Work as shown in the Contract Documents shall be “as-built” by the Contractor prior to backfilling.

Contractor shall keep all records and supporting documentation which concern or relate to the Work hereunder for a minimum of five (5) years from the date of termination of this Agreement or the date the Project is completed, whichever is later. The County, or any duly authorized agents or representatives of the County, shall have the right to audit, inspect and copy all such records and documentation as often as they deem necessary during the period of this Agreement and during the five (5) year period noted above; provided, however, such activity shall be conducted only during normal business hours.

In addition to other requirements provided herein, Contractor shall comply with public records laws embodied in chapter 119, Florida Statutes, and specifically shall:

Keep and maintain public records required by the County in order to perform the Scope of Services identified herein.

Upon request from the County provide the County with any requested public records or allow the requested records to be inspected or copied within a reasonable time by the County.

Ensure that public records that are exempt or confidential and exempt from public records disclosure requirements are not disclosed except as authorized by law for the duration of the Agreement term and thereafter if the Contractor does not transfer all records to the County.

Transfer, at no cost, to County all public records in possession of the Contractor upon termination of this Agreement and destroy any duplicate public records that are exempt or confidential and exempt from public records disclosure requirements. All records stored electronically must be provided to the County, upon request from the County, in a format that is compatible with the information technology systems of the County. If the Contractor keeps and maintains public records upon the conclusion of this Agreement, the Contractor shall meet all applicable requirements for retaining public records that would apply to the County.

If Contractor does not comply with a public records request, the County shall treat that omission as breach of this Agreement and enforce the contract provisions accordingly. Additionally, if the Contractor fails to provide records when requested, the Contractor may be subject to penalties under section 119.10, Florida Statutes and reasonable costs of enforcement, including attorney fees.

IF THE CONTRACTOR HAS QUESTIONS REGARDING THE APPLICATION OF CHAPTER 119, FLORIDA STATUTES, TO THE CONTRACTOR’S DUTY TO PROVIDE PUBLIC RECORDS RELATING TO THIS AGREEMENT, CONTACT THE CUSTODIAN OF PUBLIC RECORDS AT 850-875-8671, MEDIA@GADSDENCOUNTYFL.GOV, AND 9- B E. JEFFERSON STREET, QUINCY, FL 32351.

Section 14. Contract Time and Extensions

Contractor shall diligently pursue the completion of the Work and coordinate the Work being done on the Project by its subcontractors and materialmen, as well as coordinating its Work with all work of others at the Project Site, so that its Work or the work of others shall not be delayed or impaired by any act or omission by Contractor. Contractor shall be solely responsible for all construction means, methods, techniques, sequences, and procedures, as well as coordination of all portions of the Work under the Contract Documents, and the coordination of the County's suppliers and contractors as set forth in Section 17.B. herein.

Should Contractor be obstructed or delayed in the prosecution of or completion of the Work as a result of unforeseeable causes beyond the control of Contractor, and not due to its fault or neglect, including but not restricted to acts of God or of the public enemy, acts of government, fires, floods, epidemics, quarantine regulation, strikes or lockouts, Contractor shall notify the County in writing within forty-eight (48) hours after the commencement of such delay, stating the cause or causes thereof, or be deemed to have waived any right which Contractor may have had to request a time extension.

No interruption, interference, inefficiency, suspension or delay in the commencement or progress of the Work from any cause whatever, including those for which the County may be responsible, in whole or in part, shall relieve Contractor of his duty to perform or give rise to any right to damages or additional compensation from the County. Contractor expressly acknowledges and agrees that it shall receive no damages for delay. Contractor's sole remedy, if any, against the County will be the right to seek an extension to the Contract Time; provided, however, the granting of any such time extension shall not be a condition precedent to the aforementioned "No Damage For Delay" provision. This paragraph shall expressly apply to claims for early completion, as well as to claims based on late completion.

Section 15. Changes in the Work

The County shall have the right at any time during the progress of the Work to increase or decrease the Work. Promptly after being notified of a change, Contractor shall submit an itemized estimate of any cost or time increases or savings it foresees as a result of the change. Except in an emergency endangering life or property, or as expressly set forth herein, no addition or changes to the Work shall be made except upon written order of the County, and the County shall not be liable to the Contractor for any increased compensation without such written order. No officer, employee or agent of the County is authorized to direct any extra or changed work orally.

A Change Order, in the form attached to this Agreement, Exhibit H, shall be issued and executed promptly after an agreement is reached between Contractor and the County concerning the requested changes. Contractor shall promptly perform changes authorized by duly executed Change Orders. The Contract Amount and Contract Time shall be adjusted in the Change Order in the manner as the County and Contractor shall mutually agree.

If the County and Contractor are unable to agree on a Change Order for the requested change, Contractor shall, nevertheless, promptly perform the change as directed by the County in a written Work Directive Change. In that event, the Contract Amount and Contract Time shall be adjusted as directed by the County. If Contractor disagrees with the County's adjustment determination, Contractor must make a claim pursuant to Section 16 of this Agreement or else be deemed to have waived any claim on this matter it might otherwise have had.

In the event a requested change results in an increase to the Contract Amount, the amount of the increase shall be limited to the Contractor's reasonable direct labor and material costs and reasonable actual equipment costs as a result of the change (including allowance for labor burden costs) plus a maximum ten percent (10%) markup for all overhead and profit. However, where the Work involved is covered by unit prices contained in the Contract Documents or subsequently agreed upon, those unit prices shall be applied to the quantities of the items involved. In the event such change Work is performed by a Subcontractor, a maximum ten percent (10%) markup for all overhead and profit for all Subcontractors' and sub-subcontractors' direct labor and material costs and actual equipment costs shall be permitted, with a maximum five percent (5%) markup thereon by the Contractor for all of its overhead and profit, for a total maximum markup of fifteen percent (15%). All compensation due Contractor and any Subcontractor or sub-subcontractor for field and home office overhead is included in the markups noted above.
The County shall have the right to conduct an audit of Contractor's books and records to verify the accuracy of the Contractor's claim with respect to Contractor's costs associated with any Change Order.

The EOR shall have authority to order minor changes in the Work not involving an adjustment to the Contract Amount or an extension to the Contract Time and not inconsistent with the intent of the Contract Documents. Such changes may be affected by Field Order or by other written order. Such changes shall be binding on the Contractor.

Section 16. Claims and Disputes

A Claim is a demand or assertion by one of the parties seeking an adjustment or interpretation of the terms of the Contract Documents, payment of money, extension of time or other relief with respect to the terms of the Contract Documents. The term "Claim" also includes other disputes and matters in question between the County and Contractor arising out of or relating to the Contract Documents. The responsibility to substantiate a Claim shall rest with the party making the Claim.

Claims by the Contractor shall be made in writing to the County and EOR within forty-eight (48) hours after the first day of the event giving rise to such Claim or else the Contractor shall be deemed to have waived the Claim. Written supporting data shall be submitted to the County and EOR within fifteen (15) calendar days after the occurrence of the event, unless the County grants additional time in writing, or else the Contractor shall be deemed to have waived the Claim. All claims shall be priced in accordance with the provisions of Subsection 15.D.

Any dispute, action or proceeding arising out of or related to this Agreement shall be exclusively commenced in the state courts of Gadsden County, Florida, or where proper subject matter jurisdiction exists, in the United States District Court for the Northern District of Florida. Each party irrevocably submits and waives any objections to the exclusive personal jurisdiction and venue of such courts, including any objection based on forum non conveniens.

This Agreement and the rights and obligations of the parties shall be governed by the laws of the State of Florida without regard to its conflict of laws principles.

The Contractor shall proceed diligently with its performance as directed by the County, regardless of any pending Claim, action, suit, or administrative proceeding, unless otherwise agreed to by the County in writing. The County shall continue to make payments in accordance with the Contract Documents during the pendency of any Claim.

Section 17. Other Work

The County may perform other work related to the Project at the site by the County's own forces, have other work performed by utility owners or let other direct contracts.

If the fact that such other work is to be performed is not noted in the Contract Documents, written notice thereof will be given to Contractor prior to starting any such other work. If Contractor believes that such performance will involve additional expense to Contractor or require additional time, Contractor shall send written notice of that fact to the County and EOR within forty-eight (48) hours of being notified of the other work.