This is an Amendment 01 document containing Questions and Answers for RFP ISD_361749_DA regarding concrete work at MAB Building 412. The document addresses four key questions from prospective offerors about the project scope and requirements.

The amendment clarifies that the project budget will be less than $250,000, with an anticipated start date of January 2025, weather permitting. Regarding technical details, the contractor will not need to protect downspouts near the concrete work area, as Fermilab/FRA will remove the ends before project initiation. The scope includes very light excavation work. This Q&A document provides supplemental information to the main solicitation for concrete pad installation to support HVAC systems at Building 412 at Fermi National Accelerator Laboratory in Batavia, Illinois.

View the file

Other files

File Type Posted
Amendment 01 to RFP 361749_2024_1203.pdf PDF
Business Visitor Registration Instructions and Directions.pdf PDF
Exhibit F Bid Bond FL-41 (Rev 12.22).pdf PDF
Exhibit R Concrete_Detail.pdf PDF
Exhibit B 010010_General_Requirements_3_2022_31_Installation.pdf PDF
Exhibit D FRA General Terms and Conditions for Construction (03.2024).pdf PDF
Exhibit G Payment Bond FL-42 (Rev 12.22).pdf PDF
Exhibit H Performance Bond FL-40 (Rev 12.22).pdf PDF
Exhibit I Fermilab Subcontractor Safety Information Questionnaire.pdf PDF
Exhibit K Proposal Certifications- Form PUR-466-Rev 1 (10142021).pdf PDF
Exhibit N Davis Bacon Wage Rates IL20240008 Mod 11 2024_1018.pdf PDF
Exhibit P Director Safety Letter.pdf PDF
Exhibit J Statement and Acknowledgment (Standard Form 1413) (Rev 42013).pdf PDF
Exhibit M Construction Environmental Safety and Health Certification (CESHC).pdf PDF
Exhibit Q FermiLab_Drawing_MAB_RTU_Replacement_1.pdf PDF
Exhibit T Pictures-front and rear of building.pdf PDF
1.0 Request for Proposal_ISD_361749_DA.pdf PDF
2.0 Price Proposal Form.pdf PDF
Summary of Required Solicitation Documents.pdf PDF
Exhibit A SOW_MAB Bldg_412_Install_pads_and_bollards.pdf PDF
Exhibit C 013100_ESH_Requirements_3-2022.pdf PDF
Exhibit E Construction Insurance Requirements 2024.pdf PDF
Exhibit L Subcontractor Annual Representations and Certifications (SARC) Form SARC (Rev. 3).pdf PDF
Exhibit O Sample Subcontract.pdf PDF
Exhibit S FESHM_4195_Special_Toxic_Hazards-Silica-FINAL.pdf PDF
Exhibit U Fermilab Site-Map MAB 412.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT 01 to RFP ISD_361749_DA MAB Building 412 Concrete Work

Responses to Prospective Offerors’ Questions

Question 1: Is there a cost estimate, budget or ballpark figure for the project listed?

Response 1: A cost estimate/budget will not be provided. The project will be less than $250,000.

Question 2: What is the anticipated start date?

Response 2: The anticipated start date is January, 2025 (weather permitting).

Question 3: Do the contractors need to worry about the downspouts that are near the area where the concrete will be?

Response 3: No, this is not in the scope of the project – the Subcontractor does not need to protect the downspouts. Fermilab/FRA will remove the ends prior to the start of the project.

Question 4: Is excavation needed as part of the project?

Response 4: Yes, very light excavation is needed for this project.