Exhibit A SOW_MAB Bldg_412_Install_pads_and_bollards.pdf

PDF 218 KB Posted

Attached to
MAB Building 412 Concrete Work
Solicitation number
ISD_361749_DA
Issued by

About this file

This document is a Statement of Work (SOW) for the installation of two concrete pads to support HVAC systems at Building 412 at the Fermi National Accelerator Laboratory (Fermilab) located in Batavia, Illinois. The SOW outlines the scope of work, which includes mobilization, providing all materials and labor to install the concrete pads, installing new replacement bollards and sleeves, and final clean-up and demobilization. The estimated schedule for the project is from October 31, 2024 to December 31, 2024.

The related federal contract opportunity is a solicitation for the MAB Building 412 Concrete Work project. Fermilab is requesting proposals for the installation of the two concrete pads and related work. Proposals are due on Monday, December 16, 2024 at 5pm CT. The project is located on the Fermilab site in DuPage County, Illinois. The Subcontractor shall provide all required supervision, labor, materials, tools, and equipment necessary to perform the work as described in the SOW and technical specifications.

View the file

Other files

File Type Posted
Amendment 01 to RFP 361749_2024_1203.pdf PDF
QandA_RFP 361749_2024_1203.pdf PDF
1.0 Request for Proposal_ISD_361749_DA.pdf PDF
2.0 Price Proposal Form.pdf PDF
Summary of Required Solicitation Documents.pdf PDF
Exhibit C 013100_ESH_Requirements_3-2022.pdf PDF
Exhibit E Construction Insurance Requirements 2024.pdf PDF
Exhibit L Subcontractor Annual Representations and Certifications (SARC) Form SARC (Rev. 3).pdf PDF
Exhibit O Sample Subcontract.pdf PDF
Exhibit S FESHM_4195_Special_Toxic_Hazards-Silica-FINAL.pdf PDF
Exhibit U Fermilab Site-Map MAB 412.pdf PDF
Exhibit B 010010_General_Requirements_3_2022_31_Installation.pdf PDF
Exhibit D FRA General Terms and Conditions for Construction (03.2024).pdf PDF
Exhibit G Payment Bond FL-42 (Rev 12.22).pdf PDF
Exhibit H Performance Bond FL-40 (Rev 12.22).pdf PDF
Exhibit I Fermilab Subcontractor Safety Information Questionnaire.pdf PDF
Exhibit K Proposal Certifications- Form PUR-466-Rev 1 (10142021).pdf PDF
Exhibit N Davis Bacon Wage Rates IL20240008 Mod 11 2024_1018.pdf PDF
Exhibit P Director Safety Letter.pdf PDF
Business Visitor Registration Instructions and Directions.pdf PDF
Exhibit F Bid Bond FL-41 (Rev 12.22).pdf PDF
Exhibit R Concrete_Detail.pdf PDF
Exhibit J Statement and Acknowledgment (Standard Form 1413) (Rev 42013).pdf PDF
Exhibit M Construction Environmental Safety and Health Certification (CESHC).pdf PDF
Exhibit Q FermiLab_Drawing_MAB_RTU_Replacement_1.pdf PDF
Exhibit T Pictures-front and rear of building.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOW TEMPLATE 04.24.2023

SOW DATE: 6/7/2024

PROJECT TITLE: Concrete work for The New HVAC Pads and Bollards for the replacement of EOL units. ID165368 Fims 412 FRA POINT OF CONTACT: Joseph M. Perona x4772 41904N COUNTY THAT WORK WILL BE COMPLETED IN: DuPage☒ Project and task 60-60.03.14.16.02-ISD-412

INTRODUCTION:

This project intends to obtain a qualified Subcontractor to perform installation of two concrete pads to support HVAC systems at Building 412 at Fermi National Accelerator Laboratory (Fermilab) located in Batavia, Illinois. Fermilab is operated by the Fermi Research Alliance (FRA). FRA will provide a Task Manager / Construction Coordinator (TM/CC) to provide oversight of the project.

The purpose of this statement of work (SOW) is to obtain the supervision, expertise, labor, materials, and equipment in relation to the work indicated below.

SCOPE OF WORK

1) Mobilize to MAB building 412.

2) Contractor to provide all materials needed, to install two concrete pads in separate locations. (Concrete details)

i) The contractors are to abide by FESHM Chapter 4195 Silica Hazards. (Attachment)

b) The front of the building (pic 1 Front of building)

i) The contractor is to provide framework and place rebar as needed.

ii) Installation of concrete pad. Dimensions, 22’X23’. (Pic 3 Contractor supplied drawing)

iii) The contractor is to make any final cuts or preparation for concrete pad.

iv) The contractor is to supply all material including black top or concrete to finish area.

c) The rear of building (pic 2 rear of building)

i) The contractor is to provide framework and place rebar as needed.

ii) Installation of concrete pad. Dimensions, 22’X23’ (Gravel drive) (Pic 3 Contractor supplied drawing)

3) Contractor to provide materials to install new replacement bollards and sleaves.

a) The front of building.

i) Provide and installation of 8 Bollards with plastic sleaves.

b) The rear of building

i) Provide and installation of 4 bollard with plastic sleaves.

4) Final clean up and inspections.

5) Demobilize.

GOVERNMENT FURNISHED PROPERTY

N/A

PLACE OF PERFORMANCE

Fermi National Accelerator Laboratory MAB, 412, Batavia, IL 60510.

ESTIMATED SCHEDULE/PERIOD OF PERFORMANCE

EST START DATE: 10/31/2024 EST END DATE: 12/31/2024

Statement of Work Infrastructure Services Division