Raw Water Booster Pump Station Improvements
Solicitation number
25-8400
Issued by
Collier County, Florida

About this file

This is a sealed bid solicitation document from Collier County, Florida, for the Raw Water Booster Pump Station Improvements Project (Bid No. 25-8400). The project encompasses comprehensive infrastructure upgrades at the North County Regional Water Treatment Plant in Naples, including flow meter replacement, office and restroom renovations, construction of a pre-engineered metal building parking canopy, installation of a potable well and reverse osmosis system, and wastewater subsurface disposal system inspection and cleaning. A non-mandatory pre-bid meeting and site visit are scheduled for August 29, 2025, at 9:00 a.m. at the North County Regional Water Treatment Plant, located at 8005 Vanderbilt Beach Road, Naples, Florida 34120. Sealed bids must be submitted electronically through the county's procurement portal at https://procurement.opengov.com/portal/collier-county-fl by October 3, 2025, at 3:00 p.m. local time. The anticipated project completion timeline is 365 consecutive calendar days from the Notice to Proceed.

The estimated project budget is $1,500,000, with a $100,000 Owner's Allowance reserved for unforeseen conditions and available only at the Owner's direction. Bidders must submit a 5% bid bond and are required to provide performance and payment bonds for 100% of the contract amount upon award. All bidders must be registered with the Florida Department of State, maintain valid business tax receipts, possess appropriate professional licenses, and comply with E-Verify requirements. Liquidated damages are assessed at $610 per calendar day for failure to achieve Substantial Completion within the specified timeframe. Work is restricted to 7:00 a.m. through 7:00 p.m., Monday through Friday. The procurement contains no specific set-aside designations for disadvantaged enterprises, and no incumbent vendors are identified. Collier County reserves the right to reject any bid and postpone the contract award for up to 180 days from the bid opening date.

View the file

Other files

File Type Posted
100%_Specifications_10-13-25_.pdf PDF
Image_1.JPG JPG image
Image_1.JPG JPG image
Image_2.JPG JPG image
3A_-_Architectural_Plans_(A-001)_-_100%_-_9-25-25.pdf PDF
100%_Specs_9-25-25.pdf PDF
3A_-_Architectural_Plans_(A-001)_-_100%_-_9-25-25.pdf PDF
3A_-_Architectural_Plans_(A-001)_-_100%_-_9-25-25.pdf PDF
100%_Specs_9-25-25.pdf PDF
25-8400_-_Solicitation_R1.pdf PDF
25-8400_-_Solicitation_R1.pdf PDF
25-8400_-_Solicitation_R1.pdf PDF
Construction_Bid_Instructions_Version_1.pdf PDF
Construction_Bid_Instructions_Version_1.pdf PDF
Construction_Bid_Instructions_Version_1.pdf PDF
Construction_Bid_Instructions_Version_1.pdf PDF
25-8400_-_Authorization_to_Advertise.pdf PDF
25-8400_-_Authorization_to_Advertise.pdf PDF
25-8400_-_Authorization_to_Advertise.pdf PDF
25-8400_Specs.pdf PDF
1_-_General_and_Civil_Plans_-_100%_-_4-11-25_.pdf PDF
25-8400_Bid_Schedule.pdf PDF
3B_-_Architectural_Plans_(A-101_to_A-104)_-_100%_-_4-9-25_.pdf PDF
6_-_Electrical_-_100%_-_4-15-25_.pdf PDF
PO_Terms_and_Conditions_Rev.3.pdf PDF
PO_Terms_and_Conditions_Rev.3.pdf PDF
25-8400_Bid_Schedule.pdf PDF
3B_-_Architectural_Plans_(A-101_to_A-104)_-_100%_-_4-9-25_.pdf PDF
6_-_Electrical_-_100%_-_4-15-25_.pdf PDF
PO_Terms_and_Conditions_Rev.3.pdf PDF
2_-_Structural_Plans_-_100%_-_4-9-25_.pdf PDF
4_-_Plumbing_Plans_-_100%_-_4-9-25_.pdf PDF
2_-_Structural_Plans_-_100%_-_4-9-25_.pdf PDF
6_-_Electrical_-_100%_-_4-15-25_.pdf PDF
Construction_Services_Agreement_2025_ver._3.pdf PDF
2_-_Structural_Plans_-_100%_-_4-9-25_.pdf PDF
3A_-_Architectural_Plans_(A-001)_-_100%_-_4-11-25_.pdf PDF
Construction_Services_Agreement_2025_ver._3.pdf PDF
1_-_General_and_Civil_Plans_-_100%_-_4-11-25_.pdf PDF
25-8400_Bid_Schedule.pdf PDF
2_-_Structural_Plans_-_100%_-_4-9-25_.pdf PDF
4_-_Plumbing_Plans_-_100%_-_4-9-25_.pdf PDF
6_-_Electrical_-_100%_-_4-15-25_.pdf PDF
5_-_Mechanical_-_100%_-_4-9-25_.pdf PDF
3B_-_Architectural_Plans_(A-101_to_A-104)_-_100%_-_4-9-25_.pdf PDF
5_-_Mechanical_-_100%_-_4-9-25_.pdf PDF
PO_Terms_and_Conditions_Rev.3.pdf PDF
3B_-_Architectural_Plans_(A-101_to_A-104)_-_100%_-_4-9-25_.pdf PDF
3B_-_Architectural_Plans_(A-101_to_A-104)_-_100%_-_4-9-25_.pdf PDF
Construction_Services_Agreement_2025_ver._3.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .