This document is a Bid Schedule for project 25-8400 - Raw Water Booster Pump Station Improvements. The bid covers eight distinct line items including mobilization/demobilization, general requirements, flow meter and piping replacement (with bypass pumping and demolition), wastewater subsurface disposal system cleaning and inspection, potable well and water main installation, pre-engineered metal building for parking canopy, office space improvements, and restroom improvements. Each line item includes electrical work, and some items also incorporate mechanical and plumbing components.

The bid schedule includes a $100,000 Owner's Allowance to be used only at the Owner's direction for unforeseen conditions or specific directives. Expenditures from this allowance will be processed through Change Orders with required time and materials documentation. Notably, the current bid total is listed as $0.00, suggesting that the actual dollar amounts for each line item are to be filled in by the bidder. The project appears to be a comprehensive infrastructure improvement effort focused on upgrading water-related facilities and associated support infrastructure.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM NO. TOTAL

$0.00Bid Total

*Staff has allocated an Owner's Allowance for this project. The Owner's Allowance is $100,000. This allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Expenditures of the Owner's

Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change.

Bid Schedule for: 25-8400 - Raw Water Booster Pump Station Improvements

DESCRIPTION

Mobilization/Demobilization

General Requirements

Flow Meter and Piping Replacement, including Bypass Pumping and Demolition (Including Electrical)

Wastewater Subsurface Disposal System Cleaning and Inspection

Potable Well, 1" HDPE Water Main, Valves, and Reverse Osmosis (RO) System (Including Electrical)

Pre-Engineered Metal Building (PEMB) for Parking Canopy (Including Mechanical and Electrical)

Office Space Improvements (Including Mechanical and Electrical)

Restroom Improvements (Including Mechanical, Electrical, and Plumbing)

BID SHEET