IGCE CLIN BaseYear plus option years with No Pricing 2021(1Nov21).xlsx

XLSX spreadsheet 29 KB Posted

Attached to
Maintenance and Inspection of Fire Protection Systems
Solicitation number
W91QF523R0001
Issued by

About this file

This document contains an Independent Government Cost Estimate (IGCE) for a fire protection systems maintenance and inspection contract opportunity with the U.S. Army. The IGCE provides pricing worksheets for the base year and four option years for various fire protection systems inspection and maintenance tasks, including fire detection and alarm systems, wet pipe sprinkler systems, dry pipe sprinkler systems, pre-action automatic sprinkler systems, standpipe sprinkler systems, fire pumps, backflow prevention devices, parts, and central control and communications network maintenance. The related federal contract opportunity is solicitation number W91QF523R0001 from the Mission and Installation Contracting Command, Fort Lee, seeking proposals for base operation and support services for maintenance and inspection of fire protection systems at Fort Lee, Virginia. Proposals are due by December 16, 2022. The contract is set aside for competitive 8(a) small businesses. The IGCE provides pricing details to support the government's cost estimate for the required services.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

BASE YEAR PRICING WORKSHEET
POP: 1-JUL-2022 to 30-JUN-2023
ItemDescriptionQTYUnitUnit PriceTotal Amount
0001AAAnnual-Fire Detection and Alarm System ITM Tasks295EA
0001AB2 Year-Fire Detection and Alarm System ITM Tasks148EA
0001AC5 Year-Fire Detection and Alarm System ITM Tasks60EA
0001ADAnnual-Wet Pipe Sprinkler Systems ITM Tasks189EA
0001AE2 Year-Wet Pipe Sprinkler Systems ITM Tasks95EA
0001AF5 Year-Wet Pipe Sprinkler Systems ITM Tasks38EA
0001AG10 Year-Wet Pipe Sprinkler Systems ITM Tasks19EA
0001AH20 Year-Wet Pipe Sprinkler Systems ITM Tasks10EA
0001AJ50 Year-Wet Pipe Sprinkler Systems ITM Tasks4EA
0001AKAnnual-Dry Pipe Sprinkler Systems ITM Tasks34EA
0001AL2 Year-Dry Pipe Sprinkler Systems ITM Tasks17EA
0001AM5 Year-Dry Pipe Sprinkler Systems ITM Tasks7EA
0001AN10 Year-Dry Pipe Sprinkler Systems ITM Tasks4EA
0001AP20 Year-Dry Pipe Sprinkler Systems ITM Tasks2EA
0001AQ50 Year-Dry Pipe Sprinkler Systems ITM Tasks1EA
0001ARAnnual-Pre-Action Automatic Sprinkler Systems ITM Tasks13EA
0001AS2 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks7EA
0001AT5 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks14EA
0001AU10 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks3EA
0001AV20 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks1EA
0001AW50 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks1EA
0001AXSemi-Annual-Standpipe Sprinkler Systems ITM Tasks12EA
0001AY2 Year-Standpipe Sprinkler Systems ITM Tasks6EA
0001AZ5 Year-Standpipe Sprinkler Systems ITM Tasks3EA
0001BAMonthly-Fire Pumps ITM Tasks15EA
0001BB2 Year-Fire Pumps ITM Tasks8EA
0001BC5 Year-Fire Pumps ITM Tasks3EA
0001BDAnnual Backflow Prevention Devices ITM Tasks169EA
0001BE5 Year-Backflow Prevention Devices ITM Tasks34EA
0001BFUrgent Service Calls (Labor only)30EA
0001BGRoutine Service Calls (Labor only)30EA
0001BHParts1JA
0001BJReviews, Design and Specifications Requirements5EA
0001BKAnnual CMRA Reporting1EA
0001BLQuarterly - Joint Commission28EA
0001BMMonthly -Repair and Maintenance12EA
0001BNSemi-Annual Insp/Repair of Wet Chemical Systems126EA
0001BP5-12 Year Insp/Repair of Wet Chemical Systems11EA
0001BQSemi-Annual Insp/Repair of Dry Chemical Systems3EA
0001BR5-12 Year Insp/Repair of Dry Chemical Systems1EA
0001BSQuarterly Insp and Maint of Hood Wash Systems44EA
0001BTAnnual Insp/Repair of Clean Agent Systems5EA
0001BU2 Year Insp/Repair of Clean Agent Systems3EA
0001BV5 Year Insp/Repair of Clean Agent Systems1EA
0001BW10 Year-Fire Detection and Alarm System ITM Tasks19EA
0001BX20 Year-Fire Detection and Alarm System ITM Tasks10EA
0001BYAnnual Mass Notification Systems146EA
0001BZ2 Year - Mass Notification Systems73EA
0001CAMonthly Nitrogen Generation Systems2EA
0001CBAnnual Nitrogen Generation Systems2EA
0001CC2 Year - Nitrogen Generation Systems2EA
0001CD5 Year - Nitrogen Generation Systems2EA
0001CEWeekly Central Control Unit Maintenance104EA
0001CFMonthly Central Control Unit Maintenance24EA
0001CGQuarterly Central Control Unit Maintenance8EA
0001CHYearly Central Control Unit Maintenance2EA
0001CJWeekly Communications Network Maintenace104EA
0001CKMonthly Communications Network Maintenace24EA
0001CLQuarterly Communications Network Maintenace8EA
0001CMSemi-Annual Communications Network Maintenace4EA
TOTAL BASE YEAR
OPTION YEAR 1 PRICING WORKSHEET
POP: 1-JUL-2023 to 30-JUN-2024
ItemDescriptionQTYUnitUnit PriceTotal Amount
1001AAAnnual-Fire Detection and Alarm System ITM Tasks295EA
1001AB2 Year-Fire Detection and Alarm System ITM Tasks148EA
1001AC5 Year-Fire Detection and Alarm System ITM Tasks60EA
1001ADAnnual-Wet Pipe Sprinkler Systems ITM Tasks189EA
1001AE2 Year-Wet Pipe Sprinkler Systems ITM Tasks95EA
1001AF5 Year-Wet Pipe Sprinkler Systems ITM Tasks38EA
1001AG10 Year-Wet Pipe Sprinkler Systems ITM Tasks19EA
1001AH20 Year-Wet Pipe Sprinkler Systems ITM Tasks10EA
1001AJ50 Year-Wet Pipe Sprinkler Systems ITM Tasks4EA
1001AKAnnual-Dry Pipe Sprinkler Systems ITM Tasks34EA
1001AL2 Year-Dry Pipe Sprinkler Systems ITM Tasks17EA
1001AM5 Year-Dry Pipe Sprinkler Systems ITM Tasks7EA
1001AN10 Year-Dry Pipe Sprinkler Systems ITM Tasks4EA
1001AP20 Year-Dry Pipe Sprinkler Systems ITM Tasks2EA
1001AQ50 Year-Dry Pipe Sprinkler Systems ITM Tasks1EA
1001ARAnnual-Pre-Action Automatic Sprinkler Systems ITM Tasks13EA
1001AS2 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks7EA
1001AT5 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks14EA
1001AU10 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks3EA
1001AV20 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks1EA
1001AW50 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks1EA
1001AXSemi-Annual-Standpipe Sprinkler Systems ITM Tasks12EA
1001AY2 Year-Standpipe Sprinkler Systems ITM Tasks6EA
1001AZ5 Year-Standpipe Sprinkler Systems ITM Tasks3EA
1001BAMonthly-Fire Pumps ITM Tasks15EA
1001BB2 Year-Fire Pumps ITM Tasks8EA
1001BC5 Year-Fire Pumps ITM Tasks3EA
1001BDAnnual Backflow Prevention Devices ITM Tasks169EA
1001BE5 Year-Backflow Prevention Devices ITM Tasks34EA
1001BFUrgent Service Calls (Labor only)30EA
1001BGRoutine Service Calls (Labor only)30EA
1001BHParts1JA
1001BJReviews, Design and Specifications Requirements5EA
1001BKAnnual CMRA Reporting1EA
0001BLQuarterly - Joint Commission28EA
1001BMMonthly -Repair and Maintenance12EA
1001BNSemi-Annual Insp/Repair of Wet Chemical Systems126EA
1001BP5-12 Year Insp/Repair of Wet Chemical Systems11EA
1001BQSemi-Annual Insp/Repair of Dry Chemical Systems3EA
1001BR5-12 Year Insp/Repair of Dry Chemical Systems1EA
1001BSQuarterly Insp and Maint of Hood Wash Systems44EA
1001BTAnnual Insp/Repair of Clean Agent Systems5EA
1001BU2 Year Insp/Repair of Clean Agent Systems3EA
1001BV5 Year Insp/Repair of Clean Agent Systems1EA
1001BW10 Year-Fire Detection and Alarm System ITM Tasks19EA
1001BX20 Year-Fire Detection and Alarm System ITM Tasks10EA
1001BYAnnual Mass Notification Systems146EA
1001BZ2 Year - Mass Notification Systems73EA
1001CAMonthly Nitrogen Generation Systems2EA
1001CBAnnual Nitrogen Generation Systems2EA
1001CC2 Year - Nitrogen Generation Systems2EA
1001CD5 Year - Nitrogen Generation Systems2EA
1001CEWeekly Central Control Unit Maintenance104EA
1001CFMonthly Central Control Unit Maintenance24EA
1001CGQuarterly Central Control Unit Maintenance8EA
1001CHYearly Central Control Unit Maintenance2EA
1001CJWeekly Communications Network Maintenace104EA
1001CKMonthly Communications Network Maintenace24EA
1001CLQuarterly Communications Network Maintenace8EA
1001CMSemi-Annual Communications Network Maintenace4EA
TOTAL OPTION YEAR 1
OPTION YEAR 2 PRICING WORKSHEET
POP: 1-JUL-2024 to 30-JUN-2025
ItemDescriptionQTYUnitUnit PriceTotal Amount
2001AAAnnual-Fire Detection and Alarm System ITM Tasks295EA
2001AB2 Year-Fire Detection and Alarm System ITM Tasks148EA
2001AC5 Year-Fire Detection and Alarm System ITM Tasks60EA
2001ADAnnual-Wet Pipe Sprinkler Systems ITM Tasks189EA
2001AE2 Year-Wet Pipe Sprinkler Systems ITM Tasks95EA
2001AF5 Year-Wet Pipe Sprinkler Systems ITM Tasks38EA
2001AG10 Year-Wet Pipe Sprinkler Systems ITM Tasks19EA
2001AH20 Year-Wet Pipe Sprinkler Systems ITM Tasks10EA
2001AJ50 Year-Wet Pipe Sprinkler Systems ITM Tasks4EA
2001AKAnnual-Dry Pipe Sprinkler Systems ITM Tasks34EA
2001AL2 Year-Dry Pipe Sprinkler Systems ITM Tasks17EA
2001AM5 Year-Dry Pipe Sprinkler Systems ITM Tasks7EA
2001AN10 Year-Dry Pipe Sprinkler Systems ITM Tasks4EA
2001AP20 Year-Dry Pipe Sprinkler Systems ITM Tasks2EA
2001AQ50 Year-Dry Pipe Sprinkler Systems ITM Tasks1EA
2001ARAnnual-Pre-Action Automatic Sprinkler Systems ITM Tasks13EA
2001AS2 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks7EA
2001AT5 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks14EA
2001AU10 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks3EA
2001AV20 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks1EA
2001AW50 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks1EA
2001AXSemi-Annual-Standpipe Sprinkler Systems ITM Tasks12EA
2001AY2 Year-Standpipe Sprinkler Systems ITM Tasks6EA
2001AZ5 Year-Standpipe Sprinkler Systems ITM Tasks3EA
2001BAMonthly-Fire Pumps ITM Tasks15EA
2001BB2 Year-Fire Pumps ITM Tasks8EA
2001BC5 Year-Fire Pumps ITM Tasks3EA
2001BDAnnual Backflow Prevention Devices ITM Tasks169EA
2001BE5 Year-Backflow Prevention Devices ITM Tasks34EA
2001BFUrgent Service Calls (Labor only)30EA
2001BGRoutine Service Calls (Labor only)30EA
2001BHParts1JA
2001BJReviews, Design and Specifications Requirements5EA
2001BKAnnual CMRA Reporting1EA
2001BLQuarterly - Joint Commission28EA
2001BMMonthly -Repair and Maintenance12EA
2001BNSemi-Annual Insp/Repair of Wet Chemical Systems126EA
2001BP5-12 Year Insp/Repair of Wet Chemical Systems11EA
2001BQSemi-Annual Insp/Repair of Dry Chemical Systems3EA
2001BR5-12 Year Insp/Repair of Dry Chemical Systems1EA
2001BSQuarterly Insp and Maint of Hood Wash Systems44EA
2001BTAnnual Insp/Repair of Clean Agent Systems5EA
2001BU2 Year Insp/Repair of Clean Agent Systems3EA
2001BV5 Year Insp/Repair of Clean Agent Systems1EA
2001BW10 Year-Fire Detection and Alarm System ITM Tasks19EA
2001BX20 Year-Fire Detection and Alarm System ITM Tasks10EA
2001BYAnnual Mass Notification Systems146EA
2001BZ2 Year - Mass Notification Systems73EA
2001CAMonthly Nitrogen Generation Systems2EA
2001CBAnnual Nitrogen Generation Systems2EA
2001CC2 Year - Nitrogen Generation Systems2EA
2001CD5 Year - Nitrogen Generation Systems2EA
2001CEWeekly Central Control Unit Maintenance104EA
2001CFMonthly Central Control Unit Maintenance24EA
2001CGQuarterly Central Control Unit Maintenance8EA
2001CHYearly Central Control Unit Maintenance2EA
2001CJWeekly Communications Network Maintenace104EA
2001CKMonthly Communications Network Maintenace24EA
2001CLQuarterly Communications Network Maintenace8EA
2001CMSemi-Annual Communications Network Maintenace4EA
TOTAL OPTION YEAR 2
OPTION YEAR 3 PRICING WORKSHEET
POP: 1-JUL-2025 to 30-JUN-2026
ItemDescriptionQTYUnitUnit PriceTotal Amount
3001AAAnnual-Fire Detection and Alarm System ITM Tasks295EA
3001AB2 Year-Fire Detection and Alarm System ITM Tasks148EA
3001AC5 Year-Fire Detection and Alarm System ITM Tasks60EA
3001ADAnnual-Wet Pipe Sprinkler Systems ITM Tasks189EA
3001AE2 Year-Wet Pipe Sprinkler Systems ITM Tasks95EA
3001AF5 Year-Wet Pipe Sprinkler Systems ITM Tasks38EA
3001AG10 Year-Wet Pipe Sprinkler Systems ITM Tasks19EA
3001AH20 Year-Wet Pipe Sprinkler Systems ITM Tasks10EA
3001AJ50 Year-Wet Pipe Sprinkler Systems ITM Tasks4EA
3001AKAnnual-Dry Pipe Sprinkler Systems ITM Tasks34EA
3001AL2 Year-Dry Pipe Sprinkler Systems ITM Tasks17EA
3001AM5 Year-Dry Pipe Sprinkler Systems ITM Tasks7EA
3001AN10 Year-Dry Pipe Sprinkler Systems ITM Tasks4EA
3001AP20 Year-Dry Pipe Sprinkler Systems ITM Tasks2EA
3001AQ50 Year-Dry Pipe Sprinkler Systems ITM Tasks1EA
3001ARAnnual-Pre-Action Automatic Sprinkler Systems ITM Tasks13EA
3001AS2 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks7EA
3001AT5 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks14EA
3001AU10 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks3EA
3001AV20 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks1EA
3001AW50 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks1EA
3001AXSemi-Annual-Standpipe Sprinkler Systems ITM Tasks12EA
3001AY2 Year-Standpipe Sprinkler Systems ITM Tasks6EA
3001AZ5 Year-Standpipe Sprinkler Systems ITM Tasks3EA
3001BAMonthly-Fire Pumps ITM Tasks15EA
3001BB2 Year-Fire Pumps ITM Tasks8EA
3001BC5 Year-Fire Pumps ITM Tasks3EA
3001BDAnnual Backflow Prevention Devices ITM Tasks169EA
3001BE5 Year-Backflow Prevention Devices ITM Tasks34EA
3001BFUrgent Service Calls (Labor only)30EA
3001BGRoutine Service Calls (Labor only)30EA
3001BHParts1JA
3001BJReviews, Design and Specifications Requirements5EA
3001BKAnnual CMRA Reporting1EA
3001BLQuarterly - Joint Commission28EA
3001BMMonthly -Repair and Maintenance12EA
3001BNSemi-Annual Insp/Repair of Wet Chemical Systems126EA
3001BP5-12 Year Insp/Repair of Wet Chemical Systems11EA
3001BQSemi-Annual Insp/Repair of Dry Chemical Systems3EA
3001BR5-12 Year Insp/Repair of Dry Chemical Systems1EA
3001BSQuarterly Insp and Maint of Hood Wash Systems44EA
3001BTAnnual Insp/Repair of Clean Agent Systems5EA
3001BU2 Year Insp/Repair of Clean Agent Systems3EA
3001BV5 Year Insp/Repair of Clean Agent Systems1EA
3001BW10 Year-Fire Detection and Alarm System ITM Tasks19EA
3001BX20 Year-Fire Detection and Alarm System ITM Tasks10EA
3001BYAnnual Mass Notification Systems146EA
3001BZ2 Year - Mass Notification Systems73EA
3001CAMonthly Nitrogen Generation Systems2EA
3001CBAnnual Nitrogen Generation Systems2EA
3001CC2 Year - Nitrogen Generation Systems2EA
3001CD5 Year - Nitrogen Generation Systems2EA
3001CEWeekly Central Control Unit Maintenance104EA
3001CFMonthly Central Control Unit Maintenance24EA
3001CGQuarterly Central Control Unit Maintenance8EA
3001CHYearly Central Control Unit Maintenance2EA
3001CJWeekly Communications Network Maintenace104EA
3001CKMonthly Communications Network Maintenace24EA
3001CLQuarterly Communications Network Maintenace8EA
3001CMSemi-Annual Communications Network Maintenace4EA
TOTAL OPTION YEAR 3
OPTION YEAR 4 PRICING WORKSHEET
POP: 1-JUL-2026 to 30-JUN-2027
ItemDescriptionQTYUnitUnit PriceTotal Amount
4001AAAnnual-Fire Detection and Alarm System ITM Tasks295EA
4001AB2 Year-Fire Detection and Alarm System ITM Tasks148EA
4001AC5 Year-Fire Detection and Alarm System ITM Tasks60EA
4001ADAnnual-Wet Pipe Sprinkler Systems ITM Tasks189EA
4001AE2 Year-Wet Pipe Sprinkler Systems ITM Tasks95EA
4001AF5 Year-Wet Pipe Sprinkler Systems ITM Tasks38EA
4001AG10 Year-Wet Pipe Sprinkler Systems ITM Tasks19EA
4001AH20 Year-Wet Pipe Sprinkler Systems ITM Tasks10EA
4001AJ50 Year-Wet Pipe Sprinkler Systems ITM Tasks4EA
4001AKAnnual-Dry Pipe Sprinkler Systems ITM Tasks34EA
4001AL2 Year-Dry Pipe Sprinkler Systems ITM Tasks17EA
4001AM5 Year-Dry Pipe Sprinkler Systems ITM Tasks7EA
4001AN10 Year-Dry Pipe Sprinkler Systems ITM Tasks4EA
4001AP20 Year-Dry Pipe Sprinkler Systems ITM Tasks2EA
4001AQ50 Year-Dry Pipe Sprinkler Systems ITM Tasks1EA
4001ARAnnual-Pre-Action Automatic Sprinkler Systems ITM Tasks13EA
4001AS2 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks7EA
4001AT5 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks14EA
4001AU10 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks3EA
4001AV20 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks1EA
4001AW50 Year-Pre-Action Automatic Sprinkler Systems ITM Tasks1EA
4001AXSemi-Annual-Standpipe Sprinkler Systems ITM Tasks12EA
4001AY2 Year-Standpipe Sprinkler Systems ITM Tasks6EA
4001AZ5 Year-Standpipe Sprinkler Systems ITM Tasks3EA
4001BAMonthly-Fire Pumps ITM Tasks15EA
4001BB2 Year-Fire Pumps ITM Tasks8EA
4001BC5 Year-Fire Pumps ITM Tasks3EA
4001BDAnnual Backflow Prevention Devices ITM Tasks169EA
4001BE5 Year-Backflow Prevention Devices ITM Tasks34EA
4001BFUrgent Service Calls (Labor only)30EA
4001BGRoutine Service Calls (Labor only)30EA
4001BHParts1JA
4001BJReviews, Design and Specifications Requirements5EA
4001BKAnnual CMRA Reporting1EA
4001BLQuarterly - Joint Commission28EA
4001BMMonthly -Repair and Maintenance12EA
4001BNSemi-Annual Insp/Repair of Wet Chemical Systems126EA
4001BP5-12 Year Insp/Repair of Wet Chemical Systems11EA
4001BQSemi-Annual Insp/Repair of Dry Chemical Systems3EA
4001BR5-12 Year Insp/Repair of Dry Chemical Systems1EA
4001BSQuarterly Insp and Maint of Hood Wash Systems44EA
4001BTAnnual Insp/Repair of Clean Agent Systems5EA
4001BU2 Year Insp/Repair of Clean Agent Systems3EA
4001BV5 Year Insp/Repair of Clean Agent Systems1EA
4001BW10 Year-Fire Detection and Alarm System ITM Tasks19EA
4001BX20 Year-Fire Detection and Alarm System ITM Tasks10EA
4001BYAnnual Mass Notification Systems146EA
4001BZ2 Year - Mass Notification Systems73EA
4001CAMonthly Nitrogen Generation Systems2EA
4001CBAnnual Nitrogen Generation Systems2EA
4001CC2 Year - Nitrogen Generation Systems2EA
4001CD5 Year - Nitrogen Generation Systems2EA
4001CEWeekly Central Control Unit Maintenance104EA
4001CFMonthly Central Control Unit Maintenance24EA
4001CGQuarterly Central Control Unit Maintenance8EA
4001CHYearly Central Control Unit Maintenance2EA
4001CJWeekly Communications Network Maintenace104EA
4001CKMonthly Communications Network Maintenace24EA
4001CLQuarterly Communications Network Maintenace8EA
4001CMSemi-Annual Communications Network Maintenace4EA
TOTAL OPTION YEAR 4