IFB_TW_M_Construction_Schedule.pdf

PDF 2 MB Posted

Attached to
Taxiway M Reconstruction
Solicitation number
26-037-ITB
Issued by
Kenton County, Kentucky

About this file

This is an Invitation for Bids (IFB) Design Construction Schedule Report prepared by Connico for the Kenton County Airport Board regarding Taxiway M Reconstruction at Cincinnati/Northern Kentucky International Airport in Hebron, Kentucky. The project encompasses the demolition and reconstruction of approximately 35,000 square yards of Taxiway M and associated connector taxiways, along with rehabilitation and reconstruction of the South ARFF (Aircraft Rescue and Firefighting) station parking lot. The work is organized into four construction phases designed to maintain ARFF access throughout the project duration. The schedule report presents two bidding alternatives: Base Bid (2026 Construction) utilizing double shifts with a construction Notice to Proceed of August 17, 2026, and Alternate 1 (2027 Construction) utilizing normal shifts with a construction Notice to Proceed of April 5, 2027. A pre-bid meeting and site visit are scheduled for Thursday, June 11, 2026, at 10:00 am at CVG Centre Admin Offices. Written questions are due by 11:59 pm on Monday, June 22, 2026, with answers posted no later than Thursday, June 25, 2026. Bid submission deadline is Thursday, July 2, 2026, at 2:00 pm.

The Base Bid schedule shows probable construction substantial completion on December 11, 2026, though the owner has directed a contractual substantial completion date of November 22, 2026, with associated liquidated damages approximately three weeks earlier. The Alternate 1 schedule shows Phase 1 substantial completion on September 9, 2027. The Base Bid schedule carries the most risk due to winter weather conditions, zero schedule float, and stacked crews, while Alternate 1 carries the least risk for successful project completion. Market conditions noted in the report indicate significant shortages of skilled labor and increases in construction material prices, with contractors likely to seek material cost escalation clauses or inflate bid day pricing. For the Base Bid, CVG plans to independently procure long lead items (airfield lighting base cans and fixtures) to minimize delay risks, whereas the Alternate 1 contractor will procure these items over the winter following contract award. The schedule assumes a six-day work week with weather-related delays made up on Sundays and incorporates specified federal and state holidays as non-workdays.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CVG Taxiway M Reconstruction

IFB Design Construction Schedule Report

Report Date:

May 26, 2026

Cincinnati/Northern

Kentucky International

Airport

Hebron, KY

Prepared for:

C&S Companies

38777 Six Mile Rd, Suite 202 Livonia, MI 48152

PROPRIETARY & CONFIDENTIAL | AI/ML USE IS STRICTLY PROHIBITED

2594 N. Mount Juliet Road Mount Juliet, TN 37122

(615) 994-1980

May 26, 2026

Alan MacPherson, PE C&S Companies 38777 Six Mile Rd, Suite 202 Livonia, MI 48152

RE: CVG Taxiway M Reconstruction Cincinnati/Northern Kentucky International Airport Hebron, KY IFB Design Construction Schedule Report

Dear Alan:

We are pleased to present the final IFB Design Construction Schedule Report for the project referenced.

The Schedule Report has been drawn from the information noted in Exhibit A.

Included within the report are our Schedule Notes, which outline the general comments and criteria that were included in the schedule.

We appreciate the opportunity to collaborate with you on this project. Should you have any questions or need additional information, please contact us at your convenience.

Sincerely, The Connico Team

Lisa Heckendorn-Blake, PMP Subject Matter Expert lhblake@connico.com

Connico File No. 6731.25

Section 1 Introduction

Task Outline

Project Description

Market Information

Section 2 Schedule Notes

Section 3 Base Bid (2026 Construction)

Probable Construction

Summary Schedule

Base Bid (2026 Construction)

Probable Construction Detail

Schedule

Alternate 1 (2027 Construction)

Probable Construction

Summary Schedule

Alternate 1 (2027 Construction)

Probable Construction Detail

Schedule

Section 4 Exhibits

A - Document List

B - Quality Control Exhibit

Table of Contents

Connico

6731.25 CVG TW M Reconstruction

INTRODUCTION

TASK OUTLINE

➢ C&S Companies retained Connico as scheduling consultants to provide a probable construction schedule report for the CVG Taxiway M Reconstruction project at Cincinnati/Northern Kentucky International Airport in Hebron, KY. The schedule was based on plans, specifications, and other information, as noted in Exhibit A of this report.

➢ In providing scheduling services, the Client understands that Connico has no control over the activity durations or availability of labor, equipment, materials, market conditions or the contractor's method of construction. Connico’s opinions of probable durations are made based on Connico’s professional judgment and experience. Connico makes no warranty, expressed or implied that the duration of the work will not vary from Connico’s submitted schedule.

➢ The probable construction schedule report has been prepared based on information provided by others. Connico has not verified the accuracy and/or completeness of this information and shall not be responsible for any errors or omissions that may be incorporated because of erroneous information provided by others.

PROJECT DESCRIPTION

The project includes the demolition and reconstruction of approx. 35,000 SY of Taxiway M and associated connector taxiways. It also includes scope for the rehabilitation and reconstruction of the South ARFF station parking lot. The project is broken into multiple phases to maintain ARFF access throughout the duration of the project. The report includes two schedules, Base Bid (2026 Construction) and Alt 1 (2027 Construction). Base Bid (2026 Construction) schedule represents work done in 2026 with double work shift. Alt 1 (2027 Construction) schedule represents work done in 2027 with regular work shift.

MARKET INFORMATION

➢ The United States commercial construction market has experienced a notable slowdown along with some contracting segments in comparison to recent years. Contractor confidence has shown signs of decline. Contractor backlog is slightly lower, and some projects have been put on hold or canceled due to uncertainty regarding tariffs, immigration and a tightening in lending requirements.

➢ Construction projects continue to experience significant shortages of skilled labor and increases in construction material prices. Policy changes regarding tariffs and immigrant labor have exacerbated these issues. It does not appear that these factors will be alleviated in the near term, especially when coupled with inflationary pressures. It is anticipated that contractors will seek to negotiate material cost escalation clauses into their contracts or inflate bid day pricing to mitigate some of these risks. Consequently, the culmination of these factors has resulted in both bid day pricing inconsistencies as well as adding uncertainty to construction schedules. It is recommended that

Owners consider adding an escalation / tariff allowance to their budgeted project costs to help mitigate these market uncertainties.

➢ The schedule attempts to incorporate known impacts due to market conditions, material pricing, and labor impacts existing in the current market. However, the schedule cannot, and does not, reflect all potential economic impacts that may affect the construction market, cost, or duration of the work. The bidding and construction environment is in active flux as we continue to face uncertainty. Construction costs or durations may be affected by any of these conditions.

➢ The schedule alternatives presented here include two options that assume construction taking place in 2026 with double shifts, and in 2027 with normal shifts. Material prices, labor availability, and other economic factors that may differ between schedule alternatives will influence the overall cost of construction and are discussed in the accompanying Estimate Report.

DISCLAIMER

➢ Any modification, duplication, or use of this document without the express written consent of

Connico is prohibited and Connico assumes no responsibility for any such unauthorized use, duplication, or modification of this document.

➢ C&S Companies acknowledges that all deliverables, reports, analyses, and documents provided by

Connico are proprietary and confidential. Client agrees that Deliverables shall not be used, in whole or in part, as input, training data, prompt content, or analytical source material for any artificial intelligence system, large language model, machine learning platform, or automated analysis tool, whether proprietary or third-party, without prior express written consent.

➢ C&S Companies shall take reasonable steps to ensure that its employees, contractors, agents, and affiliates comply with this restriction. In the event of a breach, Client agrees to promptly notify

Connico and cooperate in assessing the scope of unauthorized use. Connico reserves the right to pursue all available legal and equitable remedies in connection with any violation of this provision.

SCHEDULE NOTES

GENERAL

➢ Connico did not perform a site observation in preparing this schedule.

➢ The project includes 4 construction phases as defined by C&S Companies, in accordance with the documents listed in Exhibit A. Construction phasing is designed so that ARFF access is maintained throughout construction, while also maximizing contractor efficiency. Phase 1 includes scope west of the FBO Ramp midpoint; Phase 2 includes scope east of the FBO Ramp midpoint.

Phase 1A and 2A intentionally exclude approx. 24’ of the TW M shoulder north of the taxiway so that ARFF vehicles can use the still-intact shoulder as an access route. This 24’ shoulder strip will be reconstructed in Phases 1B and 2B, respectively.

• Phase 1A – includes the reconstruction of the TW M mainline, along with reconstruction of the TW M shoulder both south of the taxiway and within 12’ north of the taxiway.

• Phase 1B – includes the remaining shoulder north of TW M, along with reconstruction of the South ARFF entryway pavement.

• Phase 2A – includes the reconstruction of the TW M mainline, along with reconstruction of the TW M shoulder both south of the taxiway and within 12’ north of the taxiway.

• Phase 2B – includes the reconstruction of TW M1, along with the remaining shoulder north of TW M.

➢ Two scheduling scenarios are presented, as requested by C&S. Specific workdays and work hours are explained in the following sections.

• Base Bid (2026 Construction) – contractor to work 6d x 24h weeks so that construction is completed in 2026.

• Alternate 1 (2027 Construction) – project to be performed in 2027 after the 2026-2027 winter shutdown period.

GENERAL ASSUMPTIONS

ASSUMPTIONS APPLICABLE FOR ALL SCHEDULE OPTIONS:

➢ The schedule was prepared utilizing Oracle Primavera Cloud

➢ The durations on the schedule are working days.

o Calendar day durations can be calculated using the Start and Finish dates. A useful source for this type of calculation is the following website:

https://www.timeanddate.com/date/duration.html

➢ The following holidays are included in the schedule as non-workdays:

o New Year’s Day o Martin Luther King, Jr. Day https://www.timeanddate.com/date/duration.html o President’s Day o Memorial Day o Juneteenth o Independence Day o Labor Day o Thanksgiving Day o Black Friday o Christmas Eve o Christmas Day

➢ For both schedule options, weather related/rain days were not incorporated into the schedule as non-workdays. The schedule assumes that working days lost due to weather will be made up on Sundays.

➢ Phasing quantities were determined using the IFB plans provided by C&S and were calculated using On-Screen Takeoff by Connico. Durations were based on the phasing quantities associated with each work activity.

➢ For the Base Bid schedule, CVG plans to procure long lead items independently, specifically airfield lighting base cans and fixtures, and provide these to the contractor to minimize the risk of delay due to contractor procurement.

ASSUMPTIONS APPLICABLE FOR BASE BID SCHEDULE (2026 CONSTRUCTION, DOUBLE SHIFTS):

➢ The designated start of construction (Construction Notice to Proceed) is August 17, 2026, as directed by C&S.

o To ensure that Phase 1 is completed prior to the Winter Shutdown, a Limited / Administrative NTP of July 27, 2026, was included in the schedule so that all administrative work is completed prior to construction NTP.

o To reduce the risk of long lead items delaying the construction schedule CVG plans to procure airfield lighting base cans and fixtures and provide them to the contractor for installation.

➢ The schedule is based on a six-day work week, with a 10-hour work shift during the day, and a

10-hour work shift overnight.

o Night shift activities are assumed to be, at most, 70% efficient as compared to day shift activities. Performing night shift activities would also impact the project’s overall cost.

➢ For the Base Bid, the probable construction schedule shows a Substantial Completion date of December 11, 2026. The Owner has directed a contractual Substantial Completion date of November 22, 2026, with associated liquidated damages, which is approximately three weeks earlier than the date shown in the probable construction schedule. The Owner acknowledges this discrepancy and is proceeding accordingly.

o It should be noted that air cargo traffic normally increases approximately 1 week prior to Thanksgiving (about November 20, 2026). In the Base Bid, TW M will be closed until Project Substantial Completion of December 11, 2026.

o Mainline and shoulder pavement construction activities will be occurring between November 20, 2026, and December 11, 2026.

o Because of the strict schedule requirements of the Base Bid, paving operations leaking into December carry risk that local asphalt plants may not be operational due to low temperatures.

ASSUMPTIONS APPLICABLE FOR ALTERNATE 1 SCHEDULE (2027 CONSTRUCTION, NORMAL SHIFTS):

➢ The Alternate 1 schedule includes Phase 1 and Phase 2 being completed in 2027.

➢ The designated start of construction (Construction Notice to Proceed) is April 5, 2027, as directed by C&S.

➢ The schedule is based on a six-day work week, with a 10-hour shift.

➢ For the Alternate 1 schedule, Project Substantial Completion for Phase 1 is shown as September 9, 2027.

➢ For the Alternate 1 schedule, there is no need for CVG to procure long lead items independently. The contractor will be able to procure long lead items over the winter, after award of the contract.

CONCLUSIONS

Alternate 1 carries the least risk for successful project completion; the Base Bid schedule carries the most risk. Base Bid schedule risks include winter weather conditions, zero schedule float, and stacked crews that may interfere with each other.

Reconstruction of the ARFF parking lot and the associated joint sealing is scheduled to take 1.5 months.

This duration makes a conservative assumption that joint sealing and parking lot reconstruction are done sequentially, not at the same time. If they are to be done concurrently, the duration will be reduced to just under one month. This work can be aligned with any of the other phases for the TW M reconstruction.

BASE BID (2026 CONSTRUCTION)

PROBABLE CONSTRUCTION

SUMMARY SCHEDULE

(Double Shifts)

CVG TW M Reconstruction - IFB Schedule Base Bid (2026 Construction)

Summary Construction Schedule

Printed On: 26-May-26 01:20 p.m.

Schedule Data Date: 01-Jun-26

Current Milestones

Progress Summary

Critical

CVG TW M Reconstruction - IFB Schedule Base Bid (2026 Construction)

Milestones

M-1000 Limited NTP (Pending Approval)

M-1010 Construction NTP

M-1020 Phase 1 Complete

M-1030 Phase 2 Complete

M-1040 Construction Substantial Completion

Phase Durations (Calendar Days)

D-1000 Phase 1A Duration

D-1020 ARFF Rehabilitation Duration

D-1010 Phase 1B Duration

D-1030 Phase 2A Duration

D-1040 Phase 2B Duration

Construction

Site Set-Up

Phase 1

Phase 1A

Phase 1B

ARFF Rehabilitation

Phase 2

Phase 2A

Phase 2B

116d 27-Jul-26 11-Dec-26

116d 27-Jul-26 11-Dec-26

0d 27-Jul-26 CC

0d 17-Aug-26 CC

0d 06-Oct-26

0d 11-Dec-26

0d 11-Dec-26

117d 17-Aug-26 11-Dec-26

34d 17-Aug-26 19-Sep-26

32d 21-Aug-26 22-Sep-26

14d 22-Sep-26 06-Oct-26

42d 09-Oct-26 20-Nov-26

24d 18-Nov-26 11-Dec-26

116d 27-Jul-26 11-Dec-26

8d 27-Jul-26 04-Aug-26

52d 05-Aug-26 06-Oct-26

41d 05-Aug-26 22-Sep-26

12d 22-Sep-26 06-Oct-26

26d 21-Aug-26 22-Sep-26

53d 09-Oct-26 11-Dec-26

36d 09-Oct-26 20-Nov-26

19d 18-Nov-26 11-Dec-26

2026 2027 Jul August September October November December January Feb

19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31

CVG TW M Reconstruction - IFB ScheCVG TW M Reconstruction - IFB ScheCVG TW M Reconstruction - IFB ScheCVG TW M Reconstruction - IFB ScheCVG TW M Reconstruction - IFB Sche

MilestonesMilestonesMilestonesMilestonesMilestones

Limited NTP (Pending Approval)Limited NTP (Pending Approval)Limited NTP (Pending Approval)Limited NTP (Pending Approval)Limited NTP (Pending Approval)

Construction NTPConstruction NTPConstruction NTPConstruction NTPConstruction NTP

Phase 1 CompletePhase 1 CompletePhase 1 CompletePhase 1 CompletePhase 1 Complete

Phase 2 CompletePhase 2 CompletePhase 2 CompletePhase 2 CompletePhase 2 Complete

Construction Substantial CompletioConstruction Substantial CompletioConstruction Substantial CompletioConstruction Substantial CompletionConstruction Substantial Completio

Phase Durations (Calendar Days)Phase Durations (Calendar Days)Phase Durations (Calendar Days)Phase Durations (Calendar Days)Phase Durations (Calendar Days)

Phase 1A DurationPhase 1A DurationPhase 1A DurationPhase 1A DurationPhase 1A Duration

ARFF Rehabilitation DurationARFF Rehabilitation DurationARFF Rehabilitation DurationARFF Rehabilitation DurationARFF Rehabilitation Duration

Phase 1B DurationPhase 1B DurationPhase 1B DurationPhase 1B DurationPhase 1B Duration

Phase 2A DurationPhase 2A DurationPhase 2A DurationPhase 2A DurationPhase 2A Duration

Phase 2B DurationPhase 2B DurationPhase 2B DurationPhase 2B DurationPhase 2B Duration

ConstructionConstructionConstructionConstructionConstruction

Site Set-UpSite Set-UpSite Set-UpSite Set-UpSite Set-Up

Phase 1Phase 1Phase 1Phase 1Phase 1

Phase 1APhase 1APhase 1APhase 1APhase 1A

Phase 1BPhase 1BPhase 1BPhase 1BPhase 1B

ARFF RehabilitationARFF RehabilitationARFF RehabilitationARFF RehabilitationARFF Rehabilitation

Phase 2Phase 2Phase 2Phase 2Phase 2

Phase 2APhase 2APhase 2APhase 2APhase 2A

Phase 2BPhase 2BPhase 2BPhase 2BPhase 2B

ID Name Planned Duration Start Finish

BASE BID (2026 CONSTRUCTION)

DETAIL SCHEDULE

(Double Shifts)

Detailed Construction Schedule

Printed On: 26-May-26 01:19 p.m.

Schedule Data Date: 01-Jun-26

Current Milestones

Progress Summary

Critical

CVG TW M Reconstruction - IFB Schedule Base Bid (2026 Construction)

Milestones

M-1000 Limited NTP (Pending Approval)

M-1010 Construction NTP

M-1020 Phase 1 Complete

M-1030 Phase 2 Complete

M-1040 Construction Substantial Completion

Phase Durations (Calendar Days)

D-1000 Phase 1A Duration

D-1020 ARFF Rehabilitation Duration

D-1010 Phase 1B Duration

D-1030 Phase 2A Duration

D-1040 Phase 2B Duration

Construction

Site Set-Up

PRE-1000 Mobilization

PRE-1010 Temporary Work Items (Barricades / SWPPP)

PRE-1020 Establish Haul Route

Phase 1

Phase 1A

Subgrade & Utilities

PH.1A-1010 Remove Pavement Markings

PH.1A-1020 Break / Remove Pavement

PH.1A-1030 P-152 Excavation / Rough Grading

PH.1A-1040 Drainage Demolition

PH.1A-1050 Electrical Removal

PH.1A-1060 Install Duct Bank

PH.1A-1070 Install Storm Drainage & Structures

PH.1A-1000 Utility Structure Adjustments

PH.1A-1080 Subgrade Preparation

Pavement

Mainline

PH.1A-1090 P-209 8" Placement

PH.1A-1100 Install Underdrains

PH.1A-1110 P-209 8" Compaction

PH.1A-1120 CL Light Conduit/Cans

PH.1A-1130 P-304 Cement Treated Base

PH.1A-1140 P-501 19" PCC Surface Course

PH.1A-1150 P-501 19" PCC Hand Pour

116d 27-Jul-26 11-Dec-26

116d 27-Jul-26 11-Dec-26

0d 27-Jul-26 CC

0d 17-Aug-26 CC

0d 06-Oct-26

0d 11-Dec-26

0d 11-Dec-26

117d 17-Aug-26 11-Dec-26

34d 17-Aug-26 19-Sep-26

32d 21-Aug-26 22-Sep-26

14d 22-Sep-26 06-Oct-26

42d 09-Oct-26 20-Nov-26

24d 18-Nov-26 11-Dec-26

116d 27-Jul-26 11-Dec-26

8d 27-Jul-26 04-Aug-26

5d 27-Jul-26 31-Jul-26

1d 01-Aug-26 01-Aug-26

2d 03-Aug-26 04-Aug-26

52d 05-Aug-26 06-Oct-26

41d 05-Aug-26 22-Sep-26

24d 05-Aug-26 01-Sep-26

2d 05-Aug-26 06-Aug-26

5d 17-Aug-26 21-Aug-26

2d 21-Aug-26 24-Aug-26

2d 21-Aug-26 24-Aug-26

2d 21-Aug-26 24-Aug-26

2d 24-Aug-26 26-Aug-26

3d 25-Aug-26 28-Aug-26

2d 28-Aug-26 01-Sep-26

2d 28-Aug-26 31-Aug-26

13d 01-Sep-26 16-Sep-26

7d 01-Sep-26 09-Sep-26

1d 01-Sep-26 01-Sep-26

2d 01-Sep-26 03-Sep-26

1d 02-Sep-26 03-Sep-26

2d 02-Sep-26 03-Sep-26

2d 03-Sep-26 04-Sep-26

2d 05-Sep-26 08-Sep-26

2d 05-Sep-26 08-Sep-26

2026 2027 Jul August September October November December January Feb

19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31

CVG TW M Reconstruction - IFB ScheCVG TW M Reconstruction - IFB ScheCVG TW M Reconstruction - IFB ScheCVG TW M Reconstruction - IFB ScheCVG TW M Reconstruction - IFB Sche

MilestonesMilestonesMilestonesMilestonesMilestones

Limited NTP (Pending Approval)Limited NTP (Pending Approval)Limited NTP (Pending Approval)Limited NTP (Pending Approval)Limited NTP (Pending Approval)

Construction NTPConstruction NTPConstruction NTPConstruction NTPConstruction NTP

Phase 1 CompletePhase 1 CompletePhase 1 CompletePhase 1 CompletePhase 1 Complete

Phase 2 CompletePhase 2 CompletePhase 2 CompletePhase 2 CompletePhase 2 Complete

Construction Substantial CompletioConstruction Substantial CompletioConstruction Substantial CompletioConstruction Substantial CompletionConstruction Substantial Completio

Phase Durations (Calendar Days)Phase Durations (Calendar Days)Phase Durations (Calendar Days)Phase Durations (Calendar Days)Phase Durations (Calendar Days)

Phase 1A DurationPhase 1A DurationPhase 1A DurationPhase 1A DurationPhase 1A Duration

ARFF Rehabilitation DurationARFF Rehabilitation DurationARFF Rehabilitation DurationARFF Rehabilitation DurationARFF Rehabilitation Duration

Phase 1B DurationPhase 1B DurationPhase 1B DurationPhase 1B DurationPhase 1B Duration

Phase 2A DurationPhase 2A DurationPhase 2A DurationPhase 2A DurationPhase 2A Duration

Phase 2B DurationPhase 2B DurationPhase 2B DurationPhase 2B DurationPhase 2B Duration

ConstructionConstructionConstructionConstructionConstruction

Site Set-UpSite Set-UpSite Set-UpSite Set-UpSite Set-Up

MobilizationMobilizationMobilizationMobilizationMobilization

Temporary Work Items (Barricades / SWPPP)Temporary Work Items (Barricades / SWPPP)Temporary Work Items (Barricades / SWPPP)Temporary Work Items (Barricades / SWPPP)Temporary Work Items (Barricades / SWPPP)

Establish Haul RouteEstablish Haul RouteEstablish Haul RouteEstablish Haul RouteEstablish Haul Route

Phase 1Phase 1Phase 1Phase 1Phase 1

Phase 1APhase 1APhase 1APhase 1APhase 1A

Subgrade & UtilitiesSubgrade & UtilitiesSubgrade & UtilitiesSubgrade & UtilitiesSubgrade & Utilities

Remove Pavement MarkingsRemove Pavement MarkingsRemove Pavement MarkingsRemove Pavement MarkingsRemove Pavement Markings

Break / Remove PavementBreak / Remove PavementBreak / Remove PavementBreak / Remove PavementBreak / Remove Pavement

P-152 Excavation / Rough GradingP-152 Excavation / Rough GradingP-152 Excavation / Rough GradingP-152 Excavation / Rough GradingP-152 Excavation / Rough Grading

Drainage DemolitionDrainage DemolitionDrainage DemolitionDrainage DemolitionDrainage Demolition

Electrical RemovalElectrical RemovalElectrical RemovalElectrical RemovalElectrical Removal

Install Duct BankInstall Duct BankInstall Duct BankInstall Duct BankInstall Duct Bank

Install Storm Drainage & StructuresInstall Storm Drainage & StructuresInstall Storm Drainage & StructuresInstall Storm Drainage & StructuresInstall Storm Drainage & Structures

Utility Structure AdjustmentsUtility Structure AdjustmentsUtility Structure AdjustmentsUtility Structure AdjustmentsUtility Structure Adjustments

Subgrade PreparationSubgrade PreparationSubgrade PreparationSubgrade PreparationSubgrade Preparation

PavementPavementPavementPavementPavement

MainlineMainlineMainlineMainlineMainline

P-209 8" PlacementP-209 8" PlacementP-209 8" PlacementP-209 8" PlacementP-209 8" Placement

Install UnderdrainsInstall UnderdrainsInstall UnderdrainsInstall UnderdrainsInstall Underdrains

P-209 8" CompactionP-209 8" CompactionP-209 8" CompactionP-209 8" CompactionP-209 8" Compaction

CL Light Conduit/CansCL Light Conduit/CansCL Light Conduit/CansCL Light Conduit/CansCL Light Conduit/Cans

P-304 Cement Treated BaseP-304 Cement Treated BaseP-304 Cement Treated BaseP-304 Cement Treated BaseP-304 Cement Treated Base

P-501 19" PCC Surface CourseP-501 19" PCC Surface CourseP-501 19" PCC Surface CourseP-501 19" PCC Surface CourseP-501 19" PCC Surface Course

P-501 19" PCC Hand PourP-501 19" PCC Hand PourP-501 19" PCC Hand PourP-501 19" PCC Hand PourP-501 19" PCC Hand Pour

ID Name Planned Duration Start Finish

Printed On: 26-May-26 01:19 p.m.

Schedule Data Date: 01-Jun-26

Current Milestones

Progress Summary

Critical

PH.1A-1160 Install CL Light Fixtures

Shoulders (South & 12' North)

PH.1A-1170 P-209 Variable Depth Placement

PH.1A-1180 P-209 Compaction

PH.1A-1190 Edge Light Conduit/Cans

PH.1A-1220 P-403 4" Asphalt Surface Course (2 Lifts)

PH.1A-1230 Install Edge Light Fixtures

Panel Replacements

PH.1A-1240 Replace PCC Panels

Parking Lot

PH.1A-1250 Regrading

PH.1A-1260 P-209 6" Placement & Compaction

PH.1A-1270 P-501 10" PCC

Final Work Items

PH.1A-1280 PCC Cure for ARFF Access (14d)

PH.1A-1290 Joint Sealing

PH.1A-1300 Turf Infield Restoration

PH.1A-1310 Pavement Markings

PH.1A-1320 Phase 1A Punch List

Phase 1B

Pre-Work Items

PH.1B-1000 Temporary Work Items (Barricades / SWPPP)

Subgrade & Utilities

PH.1B-1010 Remove Pavement Markings

PH.1B-1020 Break / Remove Pavement

PH.1B-1030 P-152 Excavation / Rough Grading

PH.1B-1040 Drainage Demolition

PH.1B-1050 Subgrade Preparation

PH.1B-1060 Install Storm Drainage & Structures

Pavement

Mainline Patch

PH.1B-1070 Sawcut / Remove Pavement

PH.1B-1080 CL Light Conduit/Can

PH.1B-1090 Prep / Choke Stone

PH.1B-1100 P-501 PCC Hand Pour

PH.1B-1110 Install CL Light Fixtures

Shoulders (ARFF Access South & 24' North)

PH.1B-1120 P-209 Variable Depth Placement

PH.1B-1130 P-209 Compaction

1d 08-Sep-26 09-Sep-26

7d 08-Sep-26 16-Sep-26

2d 08-Sep-26 10-Sep-26

2d 10-Sep-26 12-Sep-26

3d 10-Sep-26 14-Sep-26

1d 12-Sep-26 14-Sep-26

2d 14-Sep-26 16-Sep-26

2d 08-Sep-26 10-Sep-26

2d 08-Sep-26 10-Sep-26

5d 03-Sep-26 09-Sep-26

1d 03-Sep-26 04-Sep-26

1d 04-Sep-26 05-Sep-26

2d 05-Sep-26 09-Sep-26

12d 08-Sep-26 22-Sep-26

14d 08-Sep-26 22-Sep-26

2d 14-Sep-26 16-Sep-26

1d 14-Sep-26 15-Sep-26

1d 16-Sep-26 17-Sep-26

2d 17-Sep-26 19-Sep-26

12d 22-Sep-26 06-Oct-26

1d 22-Sep-26 23-Sep-26

1d 22-Sep-26 23-Sep-26

7d 23-Sep-26 01-Oct-26

1d 23-Sep-26 24-Sep-26

2d 23-Sep-26 25-Sep-26

1d 24-Sep-26 25-Sep-26

2d 25-Sep-26 29-Sep-26

1d 26-Sep-26 26-Sep-26

2d 29-Sep-26 01-Oct-26

7d 26-Sep-26 03-Oct-26

4d 26-Sep-26 30-Sep-26

1d 26-Sep-26 28-Sep-26

1d 28-Sep-26 28-Sep-26

1d 28-Sep-26 29-Sep-26

1d 29-Sep-26 30-Sep-26

1d 30-Sep-26 30-Sep-26

3d 30-Sep-26 03-Oct-26

1d 30-Sep-26 01-Oct-26

1d 01-Oct-26 02-Oct-26

2026 2027 Jul August September October November December January Feb

19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31

Install CL Light FixturesInstall CL Light FixturesInstall CL Light FixturesInstall CL Light FixturesInstall CL Light Fixtures

Shoulders (South & 12' North)Shoulders (South & 12' North)Shoulders (South & 12' North)Shoulders (South & 12' North)Shoulders (South & 12' North)

P-209 Variable Depth PlacementP-209 Variable Depth PlacementP-209 Variable Depth PlacementP-209 Variable Depth PlacementP-209 Variable Depth Placement

P-209 CompactionP-209 CompactionP-209 CompactionP-209 CompactionP-209 Compaction

Edge Light Conduit/CansEdge Light Conduit/CansEdge Light Conduit/CansEdge Light Conduit/CansEdge Light Conduit/Cans

P-403 4" Asphalt Surface Course (2 Lifts)P-403 4" Asphalt Surface Course (2 Lifts)P-403 4" Asphalt Surface Course (2 Lifts)P-403 4" Asphalt Surface Course (2 Lifts)P-403 4" Asphalt Surface Course (2 Lifts)

Install Edge Light FixturesInstall Edge Light FixturesInstall Edge Light FixturesInstall Edge Light FixturesInstall Edge Light Fixtures

Panel ReplacementsPanel ReplacementsPanel ReplacementsPanel ReplacementsPanel Replacements

Replace PCC PanelsReplace PCC PanelsReplace PCC PanelsReplace PCC PanelsReplace PCC Panels

Parking LotParking LotParking LotParking LotParking Lot

RegradingRegradingRegradingRegradingRegrading

P-209 6" Placement & CompactionP-209 6" Placement & CompactionP-209 6" Placement & CompactionP-209 6" Placement & CompactionP-209 6" Placement & Compaction

P-501 10" PCCP-501 10" PCCP-501 10" PCCP-501 10" PCCP-501 10" PCC

Final Work ItemsFinal Work ItemsFinal Work ItemsFinal Work ItemsFinal Work Items

PCC Cure for ARFF Access (14d)PCC Cure for ARFF Access (14d)PCC Cure for ARFF Access (14d)PCC Cure for ARFF Access (14d)PCC Cure for ARFF Access (14d)

Joint SealingJoint SealingJoint SealingJoint SealingJoint Sealing

Turf Infield RestorationTurf Infield RestorationTurf Infield RestorationTurf Infield RestorationTurf Infield Restoration

Pavement MarkingsPavement MarkingsPavement MarkingsPavement MarkingsPavement Markings

Phase 1A Punch ListPhase 1A Punch ListPhase 1A Punch ListPhase 1A Punch ListPhase 1A Punch List

Phase 1BPhase 1BPhase 1BPhase 1BPhase 1B

Pre-Work ItemsPre-Work ItemsPre-Work ItemsPre-Work ItemsPre-Work Items

Temporary Work Items (Barricades / SWPPP)Temporary Work Items (Barricades / SWPPP)Temporary Work Items (Barricades / SWPPP)Temporary Work Items (Barricades / SWPPP)Temporary Work Items (Barricades / SWPPP)

Subgrade & UtilitiesSubgrade & UtilitiesSubgrade & UtilitiesSubgrade & UtilitiesSubgrade & Utilities

Remove Pavement MarkingsRemove Pavement MarkingsRemove Pavement MarkingsRemove Pavement MarkingsRemove Pavement Markings

Break / Remove PavementBreak / Remove PavementBreak / Remove PavementBreak / Remove PavementBreak / Remove Pavement

P-152 Excavation / Rough GradingP-152 Excavation / Rough GradingP-152 Excavation / Rough GradingP-152 Excavation / Rough GradingP-152 Excavation / Rough Grading

Drainage DemolitionDrainage DemolitionDrainage DemolitionDrainage DemolitionDrainage Demolition

Subgrade PreparationSubgrade PreparationSubgrade PreparationSubgrade PreparationSubgrade Preparation

Install Storm Drainage & StructuresInstall Storm Drainage & StructuresInstall Storm Drainage & StructuresInstall Storm Drainage & StructuresInstall Storm Drainage & Structures

PavementPavementPavementPavementPavement

Mainline PatchMainline PatchMainline PatchMainline PatchMainline Patch

Sawcut / Remove PavementSawcut / Remove PavementSawcut / Remove PavementSawcut / Remove PavementSawcut / Remove Pavement

CL Light Conduit/CanCL Light Conduit/CanCL Light Conduit/CanCL Light Conduit/CanCL Light Conduit/Can

Prep / Choke StonePrep / Choke StonePrep / Choke StonePrep / Choke StonePrep / Choke Stone

P-501 PCC Hand PourP-501 PCC Hand PourP-501 PCC Hand PourP-501 PCC Hand PourP-501 PCC Hand Pour

Install CL Light FixturesInstall CL Light FixturesInstall CL Light FixturesInstall CL Light FixturesInstall CL Light Fixtures

Shoulders (ARFF Access South & 24' North)Shoulders (ARFF Access South & 24' North)Shoulders (ARFF Access South & 24' North)Shoulders (ARFF Access South & 24' North)Shoulders (ARFF Access South & 24' North)

P-209 Variable Depth PlacementP-209 Variable Depth PlacementP-209 Variable Depth PlacementP-209 Variable Depth PlacementP-209 Variable Depth Placement

P-209 CompactionP-209 CompactionP-209 CompactionP-209 CompactionP-209 Compaction

ID Name Planned Duration Start Finish

Printed On: 26-May-26 01:19 p.m.

Schedule Data Date: 01-Jun-26

Current Milestones

Progress Summary

Critical

PH.1B-1140 Edge Light Conduit/Cans

PH.1B-1170 P-403 4" Asphalt Surface Course (2 Lifts)

PH.1B-1180 Install Edge Light Fixtures

ARFF Full-Depth Pavement

PH.1B-1190 P-209 6" Placement

PH.1B-1200 P-209 6" Compaction

PH.1B-1210 P-501 10" PCC Hand Pour

Final Work Items

PH.1B-1220 Joint Sealing

PH.1B-1230 Pavement Markings

PH.1B-1240 Turf Infield Restoration

PH.1B-1250 Phase 1B Punch List

ARFF Rehabilitation

Joint Sealing

ARFF-1000 ARFF Joint Sealing - Phase 1

ARFF-1010 ARFF Joint Sealing - Phase 2

ARFF-1020 ARFF Joint Sealing - Phase 3

ARFF-1030 ARFF Joint Sealing - Phase 4

Reconstruction

ARFF-1040 Demolish Existing Pavement - Phase 1

ARFF-1050 Regrading - Phase 1

ARFF-1060 P-209 6" Placement & Compaction - Phase 1

ARFF-1070 P-501 10" PCC - Phase 1

ARFF-1080 Demolish Existing Pavement - Phase 2

ARFF-1090 Regrading - Phase 2

ARFF-1100 P-209 6" Placement & Compaction - Phase 2

ARFF-1110 P-501 10" PCC - Phase 2

Phase 2

Phase 2A

Pre-Work Items

PH.2A-1000 Temporary Work Items (Barricades / SWPPP)

Subgrade & Utilities

PH.2A-1010 Break / Remove Pavement

PH.2A-1020 Electrical Removal

PH.2A-1030 P-152 Excavation / Rough Grading

PH.2A-1040 Remove Pavement Markings

PH.2A-1050 Manhole Adjustments

PH.2A-1070 Subgrade Preparation

PH.2A-1060 Utility Structure Adjustments

1d 01-Oct-26 01-Oct-26

1d 02-Oct-26 02-Oct-26

1d 03-Oct-26 03-Oct-26

3d 28-Sep-26 30-Sep-26

1d 28-Sep-26 28-Sep-26

1d 29-Sep-26 29-Sep-26

1d 29-Sep-26 30-Sep-26

2d 03-Oct-26 06-Oct-26

1d 03-Oct-26 03-Oct-26

1d 03-Oct-26 03-Oct-26

1d 03-Oct-26 05-Oct-26

1d 05-Oct-26 06-Oct-26

26d 21-Aug-26 22-Sep-26

14d 21-Aug-26 08-Sep-26

4d 21-Aug-26 26-Aug-26

4d 26-Aug-26 29-Aug-26

4d 29-Aug-26 03-Sep-26

4d 03-Sep-26 08-Sep-26

12d 08-Sep-26 22-Sep-26

1d 08-Sep-26 09-Sep-26

1d 10-Sep-26 10-Sep-26

1d 10-Sep-26 10-Sep-26

2d 11-Sep-26 12-Sep-26

2d 12-Sep-26 15-Sep-26

1d 16-Sep-26 17-Sep-26

1d 17-Sep-26 18-Sep-26

3d 18-Sep-26 22-Sep-26

53d 09-Oct-26 11-Dec-26

36d 09-Oct-26 20-Nov-26

1d 09-Oct-26 10-Oct-26

1d 09-Oct-26 10-Oct-26

20d 10-Oct-26 03-Nov-26

7d 10-Oct-26 17-Oct-26

2d 17-Oct-26 20-Oct-26

2d 19-Oct-26 21-Oct-26

3d 19-Oct-26 21-Oct-26

2d 22-Oct-26 24-Oct-26

3d 24-Oct-26 28-Oct-26

4d 26-Oct-26 29-Oct-26

2026 2027 Jul August September October November December January Feb

19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31

Edge Light Conduit/CansEdge Light Conduit/CansEdge Light Conduit/CansEdge Light Conduit/CansEdge Light Conduit/Cans

P-403 4" Asphalt Surface Course (2 Lifts)P-403 4" Asphalt Surface Course (2 Lifts)P-403 4" Asphalt Surface Course (2 Lifts)P-403 4" Asphalt Surface Course (2 Lifts)P-403 4" Asphalt Surface Course (2 Lifts)

Install Edge Light FixturesInstall Edge Light FixturesInstall Edge Light FixturesInstall Edge Light FixturesInstall Edge Light Fixtures

ARFF Full-Depth PavementARFF Full-Depth PavementARFF Full-Depth PavementARFF Full-Depth PavementARFF Full-Depth Pavement

P-209 6" PlacementP-209 6" PlacementP-209 6" PlacementP-209 6" PlacementP-209 6" Placement

P-209 6" CompactionP-209 6" CompactionP-209 6" CompactionP-209 6" CompactionP-209 6" Compaction

P-501 10" PCC Hand PourP-501 10" PCC Hand PourP-501 10" PCC Hand PourP-501 10" PCC Hand PourP-501 10" PCC Hand Pour

Final Work ItemsFinal Work ItemsFinal Work ItemsFinal Work ItemsFinal Work Items

Joint SealingJoint SealingJoint SealingJoint SealingJoint Sealing

Pavement MarkingsPavement MarkingsPavement MarkingsPavement MarkingsPavement Markings

Turf Infield RestorationTurf Infield RestorationTurf Infield RestorationTurf Infield RestorationTurf Infield Restoration

Phase 1B Punch ListPhase 1B Punch ListPhase 1B Punch ListPhase 1B Punch ListPhase 1B Punch List

ARFF RehabilitationARFF RehabilitationARFF RehabilitationARFF RehabilitationARFF Rehabilitation

Joint SealingJoint SealingJoint SealingJoint SealingJoint Sealing

ARFF Joint Sealing - Phase 1ARFF Joint Sealing - Phase 1ARFF Joint Sealing - Phase 1ARFF Joint Sealing - Phase 1ARFF Joint Sealing - Phase 1

ARFF Joint Sealing - Phase 2ARFF Joint Sealing - Phase 2ARFF Joint Sealing - Phase 2ARFF Joint Sealing - Phase 2ARFF Joint Sealing - Phase 2

ARFF Joint Sealing - Phase 3ARFF Joint Sealing - Phase 3ARFF Joint Sealing - Phase 3ARFF Joint Sealing - Phase 3ARFF Joint Sealing - Phase 3

ARFF Joint Sealing - Phase 4ARFF Joint Sealing - Phase 4ARFF Joint Sealing - Phase 4ARFF Joint Sealing - Phase 4ARFF Joint Sealing - Phase 4

ReconstructionReconstructionReconstructionReconstructionReconstruction

Demolish Existing Pavement - Phase 1Demolish Existing Pavement - Phase 1Demolish Existing Pavement - Phase 1Demolish Existing Pavement - Phase 1Demolish Existing Pavement - Phase 1

Regrading - Phase 1Regrading - Phase 1Regrading - Phase 1Regrading - Phase 1Regrading - Phase 1

P-209 6" Placement & Compaction - Phase 1P-209 6" Placement & Compaction - Phase 1P-209 6" Placement & Compaction - Phase 1P-209 6" Placement & Compaction - Phase 1P-209 6" Placement & Compaction - Phase 1

P-501 10" PCC - Phase 1P-501 10" PCC - Phase 1P-501 10" PCC - Phase 1P-501 10" PCC - Phase 1P-501 10" PCC - Phase 1

Demolish Existing Pavement - Phase 2Demolish Existing Pavement - Phase 2Demolish Existing Pavement - Phase 2Demolish Existing Pavement - Phase 2Demolish Existing Pavement - Phase 2

Regrading - Phase 2Regrading - Phase 2Regrading - Phase 2Regrading - Phase 2Regrading - Phase 2

P-209 6" Placement & Compaction - Phase 2P-209 6" Placement & Compaction - Phase 2P-209 6" Placement & Compaction - Phase 2P-209 6" Placement & Compaction - Phase 2P-209 6" Placement & Compaction - Phase 2

P-501 10" PCC - Phase 2P-501 10" PCC - Phase 2P-501 10" PCC - Phase 2P-501 10" PCC - Phase 2P-501 10" PCC - Phase 2

Phase 2Phase 2Phase 2Phase 2Phase 2

Phase 2APhase 2APhase 2APhase 2APhase 2A

Pre-Work ItemsPre-Work ItemsPre-Work ItemsPre-Work ItemsPre-Work Items

Temporary Work Items (Barricades / SWPPP)Temporary Work Items (Barricades / SWPPP)Temporary Work Items (Barricades / SWPPP)Temporary Work Items (Barricades / SWPPP)Temporary Work Items (Barricades / SWPPP)

Subgrade & UtilitiesSubgrade & UtilitiesSubgrade & UtilitiesSubgrade & UtilitiesSubgrade & Utilities

Break / Remove PavementBreak / Remove PavementBreak / Remove PavementBreak / Remove PavementBreak / Remove Pavement

Electrical RemovalElectrical RemovalElectrical RemovalElectrical RemovalElectrical Removal

P-152 Excavation / Rough GradingP-152 Excavation / Rough GradingP-152 Excavation / Rough GradingP-152 Excavation / Rough GradingP-152 Excavation / Rough Grading

Remove Pavement MarkingsRemove Pavement MarkingsRemove Pavement MarkingsRemove Pavement MarkingsRemove Pavement Markings

Manhole AdjustmentsManhole AdjustmentsManhole AdjustmentsManhole AdjustmentsManhole Adjustments

Subgrade PreparationSubgrade PreparationSubgrade PreparationSubgrade PreparationSubgrade Preparation

Utility Structure AdjustmentsUtility Structure AdjustmentsUtility Structure AdjustmentsUtility Structure AdjustmentsUtility Structure Adjustments

ID Name Planned Duration Start Finish

Printed On: 26-May-26 01:19 p.m.

Schedule Data Date: 01-Jun-26

Current Milestones

Progress Summary

Critical

PH.2A-1080 Install Duct Bank

Pavement

Mainline

PH.2A-1090 P-209 8" Placement

PH.2A-1100 Install Underdrains

PH.2A-1110 P-209 8" Compaction

PH.2A-1120 CL Light Conduit/Cans

PH.2A-1130 P-304 Cement Treated Base

PH.2A-1140 P-501 19" PCC Surface Course

PH.2A-1150 Install CL Light Fixtures

PH.2A-1160 P-501 19" PCC Hand Pours

Shoulders (South & 12' North)

PH.2A-1190 P-209 Variable Depth Placement

PH.2A-1200 P-209 Compaction

PH.2A-1210 Edge Light Conduit/Cans

PH.2A-1220 P-403 4" Asphalt Surface Course (2 Lifts)

PH.2A-1230 Install Edge Light Fixtures

Final Work Items

PH.2A-1240 PCC Cure for ARFF Access (14d)

PH.2A-1250 Joint Sealing

PH.2A-1260 Pavement Markings

PH.2A-1270 Turf Infield Restoration

PH.2A-1290 Phase 2A Punch List

Phase 2B

Pre-Work Items

PH.2B-1000 Temporary Work Items (Barricades / SWPPP)

Subgrade & Utilities

PH.2B-1010 Mill / Remove Pavement

PH.2B-1020 P-152 Excavation / Rough Grading

PH.2B-1030 Drainage Demolition

PH.2B-1040 Subgrade Preparation

PH.2B-1050 Remove Pavement Markings

PH.2B-1060 Install Storm Drainage & Structures

PH.2B-1070 Replace Electrical Manhole & Duct Bank

Pavement

Mainline

PH.2B-1080 P-209 8" Placement & Compaction

PH.2B-1090 Install Underdrains

PH.2B-1110 CL Light Conduit/Can

3d 29-Oct-26 03-Nov-26

17d 28-Oct-26 17-Nov-26

11d 28-Oct-26 09-Nov-26

2d 28-Oct-26 29-Oct-26

5d 28-Oct-26 02-Nov-26

1d 30-Oct-26 31-Oct-26

2d 30-Oct-26 31-Oct-26

3d 31-Oct-26 04-Nov-26

3d 04-Nov-26 07-Nov-26

1d 07-Nov-26 09-Nov-26

2d 07-Nov-26 09-Nov-26

8d 07-Nov-26 17-Nov-26

2d 07-Nov-26 10-Nov-26

2d 10-Nov-26 11-Nov-26

4d 10-Nov-26 13-Nov-26

1d 12-Nov-26 13-Nov-26

2d 14-Nov-26 17-Nov-26

14d 04-Nov-26 20-Nov-26

14d 04-Nov-26 18-Nov-26

2d 14-Nov-26 16-Nov-26

1d 17-Nov-26 17-Nov-26

2d 17-Nov-26 18-Nov-26

2d 18-Nov-26 20-Nov-26

19d 18-Nov-26 11-Dec-26

1d 18-Nov-26 18-Nov-26

1d 18-Nov-26 18-Nov-26

14d 18-Nov-26 07-Dec-26

2d 18-Nov-26 20-Nov-26

1d 18-Nov-26 19-Nov-26

2d 19-Nov-26 23-Nov-26

1d 20-Nov-26 21-Nov-26

1d 20-Nov-26 20-Nov-26

5d 24-Nov-26 02-Dec-26

3d 02-Dec-26 07-Dec-26

6d 21-Nov-26 01-Dec-26

4d 21-Nov-26 28-Nov-26

1d 21-Nov-26 21-Nov-26

1d 21-Nov-26 23-Nov-26

1d 21-Nov-26 23-Nov-26

2026 2027 Jul August September October November December January Feb

19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31

Install Duct BankInstall Duct BankInstall Duct BankInstall Duct BankInstall Duct Bank

PavementPavementPavementPavementPavement

MainlineMainlineMainlineMainlineMainline

P-209 8" PlacementP-209 8" PlacementP-209 8" PlacementP-209 8" PlacementP-209 8" Placement

Install UnderdrainsInstall UnderdrainsInstall UnderdrainsInstall UnderdrainsInstall Underdrains

P-209 8" CompactionP-209 8" CompactionP-209 8" CompactionP-209 8" CompactionP-209 8" Compaction

CL Light Conduit/CansCL Light Conduit/CansCL Light Conduit/CansCL Light Conduit/CansCL Light Conduit/Cans

P-304 Cement Treated BaseP-304 Cement Treated BaseP-304 Cement Treated BaseP-304 Cement Treated BaseP-304 Cement Treated Base

P-501 19" PCC Surface CourseP-501 19" PCC Surface CourseP-501 19" PCC Surface CourseP-501 19" PCC Surface CourseP-501 19" PCC Surface Course

Install CL Light FixturesInstall CL Light FixturesInstall CL Light FixturesInstall CL Light FixturesInstall CL Light Fixtures

P-501 19" PCC Hand PoursP-501 19" PCC Hand PoursP-501 19" PCC Hand PoursP-501 19" PCC Hand PoursP-501 19" PCC Hand Pours

Shoulders (South & 12' North)Shoulders (South & 12' North)Shoulders (South & 12' North)Shoulders (South & 12' North)Shoulders (South & 12' North)

P-209 Variable Depth PlacementP-209 Variable Depth PlacementP-209 Variable Depth PlacementP-209 Variable Depth PlacementP-209 Variable Depth Placement

P-209 CompactionP-209 CompactionP-209 CompactionP-209 CompactionP-209 Compaction

Edge Light Conduit/CansEdge Light Conduit/CansEdge Light Conduit/CansEdge Light Conduit/CansEdge Light Conduit/Cans

P-403 4" Asphalt Surface Course (2 Lifts)P-403 4" Asphalt Surface Course (2 Lifts)P-403 4" Asphalt Surface Course (2 Lifts)P-403 4" Asphalt Surface Course (2 Lifts)P-403 4" Asphalt Surface Course (2 Lifts)

Install Edge Light FixturesInstall Edge Light FixturesInstall Edge Light FixturesInstall Edge Light FixturesInstall Edge Light Fixtures

Final Work ItemsFinal Work ItemsFinal Work ItemsFinal Work ItemsFinal Work Items

PCC Cure for ARFF Access (14d)PCC Cure for ARFF Access (14d)PCC Cure for ARFF Access (14d)PCC Cure for ARFF Access (14d)PCC Cure for ARFF Access (14d)

Joint SealingJoint SealingJoint SealingJoint SealingJoint Sealing

Pavement MarkingsPavement MarkingsPavement MarkingsPavement MarkingsPavement Markings

Turf Infield RestorationTurf Infield RestorationTurf Infield RestorationTurf Infield RestorationTurf Infield Restoration

Phase 2A Punch ListPhase 2A Punch ListPhase 2A Punch ListPhase 2A Punch ListPhase 2A Punch List

Phase 2BPhase 2BPhase 2BPhase 2BPhase 2B

Pre-Work ItemsPre-Work ItemsPre-Work ItemsPre-Work ItemsPre-Work Items

Temporary Work Items (Barricades / SWPPP)Temporary Work Items (Barricades / SWPPP)Temporary Work Items (Barricades / SWPPP)Temporary Work Items (Barricades / SWPPP)Temporary Work Items (Barricades / SWPPP)

Subgrade & UtilitiesSubgrade & UtilitiesSubgrade & UtilitiesSubgrade & UtilitiesSubgrade & Utilities

Mill / Remove PavementMill / Remove PavementMill / Remove PavementMill / Remove PavementMill / Remove Pavement

P-152 Excavation / Rough GradingP-152 Excavation / Rough GradingP-152 Excavation / Rough GradingP-152 Excavation / Rough GradingP-152 Excavation / Rough Grading

Drainage DemolitionDrainage DemolitionDrainage DemolitionDrainage DemolitionDrainage Demolition

Subgrade PreparationSubgrade PreparationSubgrade PreparationSubgrade PreparationSubgrade Preparation

Remove Pavement MarkingsRemove Pavement MarkingsRemove Pavement MarkingsRemove Pavement MarkingsRemove Pavement Markings

Install Storm Drainage & StructuresInstall Storm Drainage & StructuresInstall Storm Drainage & StructuresInstall Storm Drainage & StructuresInstall Storm Drainage & Structures

Replace Electrical Manhole & Duct BankReplace Electrical Manhole & Duct BankReplace Electrical Manhole & Duct BankReplace Electrical Manhole & Duct BankReplace Electrical Manhole & Duct Bank

PavementPavementPavementPavementPavement

MainlineMainlineMainlineMainlineMainline

P-209 8" Placement & CompactionP-209 8" Placement & CompactionP-209 8" Placement & CompactionP-209 8" Placement & CompactionP-209 8" Placement & Compaction

Install UnderdrainsInstall UnderdrainsInstall UnderdrainsInstall UnderdrainsInstall Underdrains

CL Light Conduit/CanCL Light Conduit/CanCL Light Conduit/CanCL Light Conduit/CanCL Light Conduit/Can

ID Name Planned Duration Start Finish

Printed On: 26-May-26 01:19 p.m.

Schedule Data Date: 01-Jun-26

Current Milestones

Progress Summary

Critical

PH.2B-1100 P-304 Cement Treated Base

PH.2B-1120 P-501 19" PCC Hand Pour

PH.2B-1130 Install CL Light Fixtures

Shoulders (24' North)

PH.2B-1140 P-209 Variable Depth Placement

PH.2B-1150 P-209 Compaction

PH.2B-1160 Edge Light Conduit/Cans

PH.2B-1190 P-403 4" Asphalt Surface Course (2 Lifts)

PH.2B-1200 Install Edge Light Fixtures

Final Work Items

PH.2B-1210 PCC Cure (14d)

PH.2B-1220 Joint Sealing

PH.2B-1230 Turf Infield Restoration

PH.2B-1240 Pavement Markings

PH.2B-1250 Phase 2B Punch List

1d 23-Nov-26 23-Nov-26

2d 23-Nov-26 25-Nov-26

1d 25-Nov-26 28-Nov-26

6d 21-Nov-26 01-Dec-26

2d 21-Nov-26 24-Nov-26

2d 25-Nov-26 28-Nov-26

1d 25-Nov-26 25-Nov-26

2d 28-Nov-26 30-Nov-26

1d 01-Dec-26 01-Dec-26

13d 25-Nov-26 11-Dec-26

14d 25-Nov-26 09-Dec-26

1d 09-Dec-26 10-Dec-26

1d 09-Dec-26 10-Dec-26

1d 10-Dec-26 10-Dec-26

1d 11-Dec-26 11-Dec-26

2026 2027 Jul August September October November December January Feb

19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31

P-304 Cement Treated BaseP-304 Cement Treated BaseP-304 Cement Treated BaseP-304 Cement Treated BaseP-304 Cement Treated Base

P-501 19" PCC Hand PourP-501 19" PCC Hand PourP-501 19" PCC Hand PourP-501 19" PCC Hand PourP-501 19" PCC Hand Pour

Install CL Light FixturesInstall CL Light FixturesInstall CL Light FixturesInstall CL Light FixturesInstall CL Light Fixtures

Shoulders (24' North)Shoulders (24' North)Shoulders (24' North)Shoulders (24' North)Shoulders (24' North)

P-209 Variable Depth PlacementP-209 Variable Depth PlacementP-209 Variable Depth PlacementP-209 Variable Depth PlacementP-209 Variable Depth Placement

P-209 CompactionP-209 CompactionP-209 CompactionP-209 CompactionP-209 Compaction

Edge Light Conduit/CansEdge Light Conduit/CansEdge Light Conduit/CansEdge Light Conduit/CansEdge Light Conduit/Cans

P-403 4" Asphalt Surface Course (2 Lifts)P-403 4" Asphalt Surface Course (2 Lifts)P-403 4" Asphalt Surface Course (2 Lifts)P-403 4" Asphalt Surface Course (2 Lifts)P-403 4" Asphalt Surface Course (2 Lifts)

Install Edge Light FixturesInstall Edge Light FixturesInstall Edge Light FixturesInstall Edge Light FixturesInstall Edge Light Fixtures

Final Work ItemsFinal Work ItemsFinal Work ItemsFinal Work ItemsFinal Work Items

PCC Cure (14d)PCC Cure (14d)PCC Cure (14d)PCC Cure (14d)PCC Cure (14d)

Joint SealingJoint SealingJoint SealingJoint SealingJoint Sealing

Turf Infield RestorationTurf Infield RestorationTurf Infield RestorationTurf Infield RestorationTurf Infield Restoration

Pavement MarkingsPavement MarkingsPavement MarkingsPavement MarkingsPavement Markings

Phase 2B Punch ListPhase 2B Punch ListPhase 2B Punch ListPhase 2B Punch ListPhase 2B Punch List

ID Name Planned Duration Start Finish

ALTERNATE 1 (2027 CONSTRUCTION)

SUMMARY SCHEDULE

(Normal Shifts)

CVG TW M Reconstruction - IFB Schedule Alt. 1 (2027 Construction)

Summary Construction Schedule

Printed On: 26-May-26 01:22 p.m.

Schedule Data Date: 01-Jun-26

Current Milestones

Progress Summary

Critical

CVG TW M Reconstruction - IFB Schedule Alt. 1 (2027 Construction)

Milestones

M-1000 Limited NTP (Pending Approval)

M-1010 Construction NTP

M-1020 Phase 1 Complete

M-1030 Phase 2 Complete

M-1040 Construction Substantial Completion

Phase Durations (Calendar Days)

D-1000 Phase 1A Duration

D-1020 ARFF Rehabilitation Duration

D-1010 Phase 1B Duration

D-1030 Phase 2A Duration

D-1040 Phase 2B Duration

Construction

Site Set-Up

Phase 1

Phase 1A

Phase 1B

ARFF Rehabilitation

Phase 2

Phase 2A

Phase 2B

224d 02-Nov-26 09-Sep-27

257d 02-Nov-26 09-Sep-27

0d 02-Nov-26 CC

0d 05-Apr-27 CC

0d 10-Jun-27

0d 09-Sep-27

0d 09-Sep-27

158d 05-Apr-27 09-Sep-27

53d 05-Apr-27 27-May-27

49d 14-Apr-27 01-Jun-27

17d 25-May-27 10-Jun-27

68d 15-Jun-27 21-Aug-27

30d 11-Aug-27 09-Sep-27

130d 12-Mar-27 09-Sep-27

15d 12-Mar-27 29-Mar-27

49d 05-Apr-27 10-Jun-27

39d 05-Apr-27 27-May-27

14d 25-May-27 10-Jun-27

41d 14-Apr-27 01-Jun-27

63d 15-Jun-27 09-Sep-27

49d 15-Jun-27 21-Aug-27

22d 11-Aug-27 09-Sep-27

Mar Apr May Jun Jul Aug Sep Oct Nov De

07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28

CVG TW M Reconstruction - IFB Schedule Alt. 1 CVG TW M Reconstruction - IFB Schedule Alt. 1 CVG TW M Reconstruction - IFB Schedule Alt. 1CVG TW M Reconstruction - IFB Schedule Alt. 1 CVG TW M Reconstruction - IFB Schedule Alt. 1

MilestonesMilestonesMilestonesMilestonesMilestones

Construction NTPConstruction NTPConstruction NTPConstruction NTPConstruction NTP

Phase 1 CompletePhase 1 CompletePhase 1 CompletePhase 1 CompletePhase 1 Complete

Phase 2 CompletePhase 2 CompletePhase 2 CompletePhase 2 CompletePhase 2 Complete

Construction Substantial CompletionConstruction Substantial CompletionConstruction Substantial CompletionConstruction Substantial CompletionConstruction Substantial Completion

Phase Durations (Calendar Days)Phase Durations (Calendar Days)Phase Durations (Calendar Days)Phase Durations (Calendar Days)Phase Durations (Calendar Days)

Phase 1A DurationPhase 1A DurationPhase 1A DurationPhase 1A DurationPhase 1A Duration

ARFF Rehabilitation DurationARFF Rehabilitation DurationARFF Rehabilitation DurationARFF Rehabilitation DurationARFF Rehabilitation Duration

Phase 1B DurationPhase 1B DurationPhase 1B DurationPhase 1B DurationPhase 1B Duration

Phase 2A DurationPhase 2A DurationPhase 2A DurationPhase 2A DurationPhase 2A Duration

Phase 2B DurationPhase 2B DurationPhase 2B DurationPhase 2B DurationPhase 2B Duration

ConstructionConstructionConstructionConstructionConstruction

Site Set-UpSite Set-UpSite Set-UpSite Set-UpSite Set-Up

Phase 1Phase 1Phase 1Phase 1Phase 1

Phase 1APhase 1APhase 1APhase 1APhase 1A

Phase 1BPhase 1BPhase 1BPhase 1BPhase 1B

ARFF RehabilitationARFF RehabilitationARFF RehabilitationARFF RehabilitationARFF Rehabilitation

Phase 2Phase 2Phase 2Phase 2Phase 2

Phase 2APhase 2APhase 2APhase 2APhase 2A

Phase 2BPhase 2BPhase 2BPhase 2BPhase 2B

ID Name Planned Duration Start Finish

ALTERNATE 1 (2027 CONSTRUCTION)

DETAIL SCHEDULE

(Normal Shifts)

Printed On: 26-May-26 01:21 p.m.

Schedule Data Date: 01-Jun-26

Current Milestones

Progress Summary

Critical

CVG TW M Reconstruction - IFB Schedule Alt. 1 (2027 Construction)

Milestones

M-1000 Limited NTP (Pending Approval)

M-1010 Construction NTP

M-1020 Phase 1 Complete

M-1030 Phase 2 Complete

M-1040 Construction Substantial Completion

Phase Durations (Calendar Days)

D-1000 Phase 1A Duration

D-1020 ARFF Rehabilitation Duration

D-1010 Phase 1B Duration

D-1030 Phase 2A Duration

D-1040 Phase 2B Duration

Construction

Site Set-Up

PRE-1000 Mobilization

PRE-1010 Temporary Work Items (Barricades / SWPPP)

PRE-1020 Establish Haul Route

Phase 1

Phase 1A

Subgrade & Utilities

PH.1A-1010 Remove Pavement Markings

PH.1A-1020 Break / Remove Pavement

PH.1A-1030 P-152 Excavation / Rough Grading

PH.1A-1040 Drainage Demolition

PH.1A-1050 Electrical Removal

PH.1A-1060 Install Duct Bank

PH.1A-1070 Install Storm Drainage & Structures

PH.1A-1000 Utility Structure Adjustments

PH.1A-1080 Subgrade Preparation

Pavement

Mainline

PH.1A-1090 P-209 8" Placement

PH.1A-1100 Install Underdrains

PH.1A-1110 P-209 8" Compaction

PH.1A-1120 CL Light Conduit/Cans

PH.1A-1130 P-304 Cement Treated Base

PH.1A-1140 P-501 19" PCC Surface Course

PH.1A-1150 P-501 19" PCC Hand Pour

224d 02-Nov-26 09-Sep-27

257d 02-Nov-26 09-Sep-27

0d 02-Nov-26 CC

0d 05-Apr-27 CC

0d 10-Jun-27

0d 09-Sep-27

0d 09-Sep-27

158d 05-Apr-27 09-Sep-27

53d 05-Apr-27 27-May-27

49d 14-Apr-27 01-Jun-27

17d 25-May-27 10-Jun-27

68d 15-Jun-27 21-Aug-27

30d 11-Aug-27 09-Sep-27

130d…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .