This document comprises the revised final engineering plans for water and sewer infrastructure improvements in Portsmouth, Virginia, prepared by Kimley-Horn and Associates, Inc. The Bunche Boulevard Water and Sewer Improvements project is located within the City of Portsmouth and covers approximately 4.47 acres within the limits of disturbance. The scope includes replacement of water and sanitary sewer mains and services up to meters and cleanouts along Bunche Boulevard, Avondale Road, Beechdale Road, Victory Boulevard, George Washington Highway, and associated side streets. Construction will also include jack and bore methodology under Victory Boulevard to install a proposed sewer force main. The project qualifies as a linear development project under Virginia DEQ Guidance Memo No. 15-2003 and will not result in significant changes to predevelopment runoff characteristics after final stabilization. The contract period is 360 days, with a mandatory pre-bid conference scheduled for June 23, 2026 at 3:00 p.m. EDT and electronic bids due July 9, 2026 at 2:00 p.m. EDT. A virtual public bid opening will occur via Microsoft Teams on July 10, 2026 at 2:30 p.m. EDT.
The project plans include comprehensive erosion and sediment control measures in accordance with the Virginia Erosion and Sediment Control Handbook, including silt fence barriers, inlet protection, temporary and permanent seeding, and stabilization requirements. Soil conditions at the site consist primarily of Tomotley-Urban Land Complex with 0 to 2 percent slopes, characterized as poorly drained with seasonal water saturation at 6 inches during winter months. The design documents specify detailed construction sequencing, pipe abandonment procedures, water and sewer system details, force main specifications, and permanent stabilization protocols. All denuded areas must be permanently seeded or sodded within seven days of reaching final grade. Bidders must submit documentation including Virginia Contractor License Number, Federal ID Number, W-9 forms, and demonstrate financial capability and bonding requirements. Addendum No. 1, issued June 11, 2026, modifies bid opening procedures and requires acknowledgment either prior to the bid due date or by attaching a signed acknowledgment to the bid submission.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
© 2019 Microsoft Corporation © 2019 HERE
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
Kimley-Horn and Associates, Inc.
Virginia Beach, Virginia
VICINITY MAP
N.T.S.
NORTH
C01
ENGINEER:
PORTSMOUTH CONTACTS:
UTILITY AND GOVERNING AGENCIES CONTACT LIST
JUNE 2025
VCWRLF PROJECT NO. C-515838
CITY FILE NO. RW2407
THIS PROJECT IS CONSIDERED A LINEAR DEVELOPMENT
PROJECT UNDER VIRGINIA DEQ GUIDANCE MEMO NO. 15-2003
6-02-2026
117106239
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
C02
NOTES
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
C02A
NOTES
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
GENERAL DETAILS
C03
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
GENERAL DETAILS
C04
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
GENERAL DETAILS
C05
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
WATER DETAILS
C06
INJECT FLOWABLE
FILL HERE (TYP.)EX. GRADE
OBSERVE
FILLING/VENT AIR
HERE (TYP.)
4" SCH. 40 PVC
RISER PIPE (TYP.) 2' MIN.
FILL
DIRECTION
FILL
DIRECTION
PIPE SLOPE
OBSERVATION
POINT
(HIGH POINT)
OBSERVATION AND
INJECTION POINT
(MID POINT)
INJECTION
POINT
(LOW POINT)
PIPE ABANDONMENT DETAIL
N.T.S.
FILL
DIRECTION
FILL
DIRECTION
(SEE PLUG DETAIL)
NOTES:
1. RESTORE DISTURBED SURFACE FEATURES IN ACCORDANCE WITH THE DETAILS INCLUDED IN THE
CONTRACT DRAWINGS TO MATCH EXISTING CONDITIONS.
2. ANY PLANTINGS REMOVED OR DISTURBED AS A RESULT OF FILL OPENINGS SHALL BE REPLACED TO
PRECONSTRUCTION CONDITIONS. THIS INCLUDES, BUT IS NOT LIMITED TO, TREES, SHRUBS, AND
PLANTING BEDS.
3. AT THE COMPLETION OF FILLING OPERATIONS, REMOVE RISER PIPES TO A MINIMUM OF 18" BELOW
GRADE OR AS REQUIRED FOR PLACEMENT OF SURFACE FEATURES, WHICHEVER IS GREATER.
BRICK/MORTAR PLUG
OR RESTRAINED CAP (TYP)
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
GRAVITY SEWER
DETAILS
C07
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
GRAVITY SEWER
DETAILS
C08
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
FORCE MAIN
DETAILS
C09
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
ESC CHECKLIST
C10
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
ESC NARRATIVE
AND DETAILS
C11
PROJECT DESCRIPTION:
THE BUNCHE BOULEVARD WATER AND SEWER IMPROVEMENTS
PROJECT IS LOCATED WITHIN THE BOUNDARIES OF THE CITY OF
PORTSMOUTH. THE SITE COVERS APPROXIMATELY 4.47 ACRES WITHIN
THE LIMITS OF DISTURBANCE. IMPROVEMENTS WILL BE MADE ALONG
BUNCHE BLVD, AVONDALE RD, BEECHDALE RD, VICTORY BLVD, GEORGE
WASHINGTON HIGHWAY, AND THE SIDE STREETS WITH AFFECTED
UTILITY CONNECTIONS . THE PROJECT CONSISTS OF REPLACING WATER
AND SANITARY SEWER MAINS AND SERVICES UP TO THE METERS AND
CLEANOUTS. ADDITIONALLY, CONSTRUCTION WILL INCLUDE JACK AND
BORE METHODOLOGY UNDER VICTORY BOULEVARD TO INSTALL THE
PROPOSED SEWER FORCE MAIN. THIS PROJECT COMPLIES WITH THE
DEFINITION OF A LINEAR DEVELOPMENT PROJECT AS IT INVOLVES THE
CONSTRUCTION OF NEW WATER AND SEWER PIPELINES. THE
INSTALLATION OF THE PIPELINES WILL NOT RESULT IN SIGNIFICANT
CHANGES TO THE PREDEVELOPMENT RUNOFF CHARACTERISTICS OF
THE LAND SURFACE AFTER THE COMPLETION OF CONSTRUCTION AND
FINAL STABILIZATION.
EXISTING SITE CONDITIONS:
THE EXISTING CONDITIONS ARE SHOWN ON SHEETS E00-E11.
ADJACENT AREAS:
AREAS BEYOND THE LIMITS OF WORK SHOWN ON THE PLANS SHALL NOT
BE IMPACTED BY THE DEVELOPMENT DURING OR FOLLOWING
CONSTRUCTION.
CRITICAL AREAS:
THERE NO CRITICAL AREAS ON SITE.
OFF-SITE AREAS:
NO OFF-SITE LAND DISTURBANCE IS PROPOSED.
SOILS:
TIDEWATER CITIES AREA, VIRGINIA
MAP UNIT: 24—TOMOTLEY-URBAN LAND COMPLEX, 0 TO 2 PERCENT
SLOPES
COMPONENT: TOMOTLEY (89%)
THE TOMOTLEY COMPONENT MAKES UP 70 PERCENT OF THE MAP UNIT.
SLOPES ARE 0 TO 2 PERCENT. THIS COMPONENT IS ON STREAM
TERRACES ON COASTAL PLAINS. THE PARENT MATERIAL CONSISTS OF
LOAMY ALLUVIAL SEDIMENTS. DEPTH TO A ROOT RESTRICTIVE LAYER IS
GREATER THAN 60 INCHES. THE NATURAL DRAINAGE CLASS IS POORLY
DRAINED. WATER MOVEMENT IN THE MOST RESTRICTIVE LAYER IS
MODERATELY HIGH. AVAILABLE WATER TO A DEPTH OF 60 INCHES IS
MODERATE. SHRINK-SWELL POTENTIAL IS LOW. THIS SOIL IS NOT
FLOODED. IT IS NOT PONDED. A SEASONAL ZONE OF WATER
SATURATION IS AT 6 INCHES DURING JANUARY, FEBRUARY, MARCH,
APRIL, DECEMBER. ORGANIC MATTER CONTENT IN THE SURFACE
HORIZON IS ABOUT 4 PERCENT. NONIRRIGATED LAND CAPABILITY
CLASSIFICATION IS 4W. THIS SOIL MEETS HYDRIC CRITERIA.
MAP UNIT: 27— URBAN LAND
COMPONENT: URBAN LAND (11%)
GENERATED BRIEF SOIL DESCRIPTIONS ARE CREATED FOR MAJOR SOIL
COMPONENTS. THE URBAN LAND IS A MISCELLANEOUS AREA.
BASED ON THE REPORT PROVIDED BY GET SOLUTIONS INC, A
TERRACON COMPANY, THE PROJECT SITE LIES WITHIN A MAJOR
PHYSIOGRAPHIC PROVINCE CALLED THE ATLANTIC COASTAL PLAIN.
NUMEROUS TRANSGRESSIONS AND REGRESSIONS OF THE ATLANTIC
OCEAN HAVE DEPOSITED MARINE, LAGOONAL, AND FLUVIAL (STREAM
LAIN) SEDIMENTS. THE REGIONAL GEOLOGY IS VERY COMPLEX, AND
GENERALLY CONSISTS OF INTERBEDDED LAYERS OF VARYING
MIXTURES OF SANDS, SILTS AND CLAYS. BASED ON OUR REVIEW OF
EXISTING GEOLOGIC AND SOIL BORING DATA, THE GEOLOGIC
STRATIGRAPHY ENCOUNTERED IN OUR SUBSURFACE EXPLORATIONS
GENERALLY CONSISTED OF MARINE DEPOSITED SANDS, SILTS AND
CLAYS.
EROSION AND SEDIMENT CONTROL MEASURES:
THE FOLLOWING EROSION AND SEDIMENT CONTROL MEASURES ARE
INCLUDED IN THE DESIGN, AND ALL MEASURES SHALL BE INSTALLED
AND MAINTAINED IN ACCORDANCE WITH THE VIRGINIA EROSION AND
SEDIMENT CONTROL HANDBOOK (VESCH).
SILT FENCE:
SILT FENCE SEDIMENT BARRIERS WILL BE USED WHERE THE SITE
IS DRAINING AWAY FROM EXISTING STORM DRAINS IN ORDER TO
FILTER ANY SEDIMENT-LADEN RUNOFF FROM SHEET FLOW.
INLET PROTECTION
INLET PROTECTION SHALL BE USED AT ALL EXISTING INLETS. IT
SHALL ALSO BE USED ON ALL PROPOSED INLETS ONCE
CONSTRUCTED.
TEMPORARY SEEDING
ALL AREAS THAT HAVE NOT REACHED FINAL GRADE AND WILL BE
LEFT DORMANT FOR MORE THAN 30 DAYS BUT LESS THAN ONE
YEAR WILL BE SEEDED WITH FAST GERMINATING TEMPORARY
VEGETATION IMMEDIATELY FOLLOWING GRADING. SELECTION OF
THE SEED MIXTURE WILL DEPEND ON THE TIME OF YEAR IT IS
APPLIED, BUT WILL BE IN ACCORDANCE WITH VESCH STANDARDS.
PERMANENT SEEDING/SODDING/FERTILIZATION
ALL DENUDED OPEN AREAS THAT HAVE REACHED FINAL GRADE
WILL BE PERMANENTLY SEEDED IMMEDIATELY FOLLOWING
CONSTRUCTION. PERMANENT SEEDING AND FERTILIZATION WILL
FOLLOW THE PLANTING SCHEDULE PROVIDED IN THE SITE PLANS.
ALL ON-SITE UNPAVED OPEN AREAS THAT HAVE REACHED FINAL
GRADE WILL BE PERMANENTLY SEEDED OR SODDED AND
FERTILIZED IMMEDIATELY FOLLOWING GRADING.
SEQUENCE OF CONSTRUCTION: REFER TO SEQUENCE OF
CONSTRUCTION ON SHEET C02.
PERMANENT STABILIZATION:
PERMANENT STABILIZATION SHALL BE PROVIDED FOR ALL DENUDED
AREAS THAT HAVE REACHED FINAL GRADE AND WILL BE DORMANT
MORE THAN ONE YEAR, WITHIN 7 DAYS, IN ACCORDANCE WITH THE
PERMANENT STABILIZATION SEEDING SCHEDULE PROVIDED ON SHEET
C13
MAINTENANCE:
IN GENERAL, ALL EROSION AND SEDIMENT CONTROL MEASURES WILL BE
CHECKED DAILY, AFTER EVERY SIGNIFICANT RAINFALL (0.5” IN A
24-HOUR DURATION), AND IN ACCORDANCE WITH THE STORMWATER
POLLUTION PREVENTION PLAN (SWPPP). THE FOLLOWING ITEMS WILL BE
CHECKED IN PARTICULAR:
1. INLET PROTECTION SHALL BE CHECKED REGULARLY FOR
SEDIMENT BUILDUP WHICH WILL PREVENT THE DRAINAGE
THROUGH THE DEVICE. IF INLET PROTECTION IS CLOGGED BY
SEDIMENT, IT SHALL BE REMOVED AND CLEANED OR REPLACED.
2. THE SILT FENCE BARRIERS SHALL BE CHECKED REGULARLY FOR
DETERIORATION OF THE FABRIC. SEDIMENT SHALL BE REMOVED
WHEN THE LEVEL OF SEDIMENT DEPOSITION REACHES HALF WAY
TO THE TOP OF THE BARRIER.
3. THE SEEDED AREAS SHALL BE CHECKED REGULARLY TO ENSURE
THAT A GOOD STAND IS MAINTAINED. AREAS SHALL BE FERTILIZED
AND RESEEDED AS NEEDED TO ESTABLISH AND MAINTAIN A GOOD
STAND OF VEGETATION.
EROSION AND SEDIMENT CONTROL NARRATIVE
SEED1
LAND USE SPECIES APPLICATION RATES
MINIMUM CARE LAWN TALL FESCUE1 175-200 LBS
COMMERCIAL OR RESIDENTIAL or
BERMUDAGRASS1 75 LBS
HIGH-MAINTENANCE LAWN TALL FESCUE1 200-250 LBS
or BERMUDAGRASS1 (seed) 40 LBS (UNHULLED) or 30 LBS (HULLED) BERMUDAGRASS1 (by other vegetative establishment method, see Std. & Spec. 3.34)
GENERAL SLOPE (3:1 OR LESS) TALL FESCUE1 128 LBS
RED TOP GRASS OR CREEPING RED FESCUE 2 LBS
SEASONAL NURSE CROP2 20 LBS
TOTAL 150 LBS
LOW-MAINTENANCE SLOPE TALL FESCUE1 93-108 LBS
(STEEPER THAN 3:1) BERMUDAGRASS1 0-15 LBS
RED TOP GRASS OR CREEPING RED FESCUE 2 LBS
SEASONAL NURSE CROP2 20 LBS
SERICEA LESPEDEZA3 20 LBS
TOTAL 150 LBS
1 - WHEN SELECTING VARIETIES OF TURFGRASS, USE THE VIRGINIA CROP IMPROVEMENT ASSOCIATION (VCIA) RECCOMENDED TURFGRASS VARIETY LIST. QUALITY SEED WILL BEAR A LABEL INDICATING THAT THEY ARE APPROVED BY VCIA. A CURRENT TURFGRASS VARIETY LIST IS AVAILABLE AT THE LOCAL COUNTY EXTENSION OFFICE OR THROUGH VCIA AT 804-746-4884 OR AT
HTTP://SUDAN.CSES.VT.EDU/HTML/TURF/TURF/PUBLICATIONS/PUBLICATIONS2.HTML
2 - USE SEASONAL NURSE CROPS IN ACCORDANCE WITH SEEDING DATES STATED BELOW:
FEBRUARY, MARCH-APRIL................................. ANNUAL RYE
MAY 1ST-AUGUST................................................ FOXTAIL MILLET
SEPTEMBER, OCTOBER-NOVEMBER 15TH...... ANNUAL RYE
NOVEMBER 16TH- JANUARY.............................. WINTER RYE
3 - MAY THROUGH OCTOBER, USE HULLED SEED. ALL OTHER SEEDING PERIODS, USE UNHULLED SEED. IF WEEPING LOVEGRASS IS USED, INCLUDE IN ANY SLOPE OR LOW MAINTENANCE MIXTURE DURING WARMER SEEDING PERIODS, INCREASE TO 30-40 LBS/ACRE.
FERTILIZER & LIME
· APPLY 10-20-10 FERTILIZER AT A RATE OF 500 LBS/ACRE (OR 12 LBS/1,000 SQ. FT.)
· APPLY PULVERIZED AGRICULTURAL LIMESTONE AT A RATE OF 2 TONS/ACRE (OR 90 LBS/1,000 SQ. FT.)
NOTE:
1. A SOIL TEST IS NECESSARY TO DETERMINE THE ACTUAL AMOUNT OF LIME REQUIRED TO ADJUST THE SOIL PH OF SITE.
2. INCORPORATE THE LIME AND FERTILIZER INTO THE TOP 4-6 INCHES OF THE SOIL BY DISKING OR BY OTHER MEANS.
3. WHEN APPLYING SLOWLY AVAILABLE NITROGEN, USE RATES AVAILABLE IN EROSION & SEDIMENT CONTROL TECHNICAL
BULLETIN #4, 2003 NUTRIENT MANAGEMENT FOR DEVELOPMENT SITES AT
HTTP://WWW.DCR.STATE.VA.US/SW/E&S.HTM#PUBS
TABLE 3.32-E
(REVISED JUNE 2003)
PERMANENT SEEDING SPECIFICATION FOR COASTAL PLAIN AREA
PS TABLE 3.31-B
(REVISED JUNE 2003)
TEMPORARY SEEDING SPECIFICATIONS QUICK REFERENCE FOR ALL REGIONS
APPLICATION DATES
SEPT. 1 - FEB. 15
FEB. 16 - APR. 30
MAY 1 - AUG. 31
SPECIES
50/50 MIX OF ANNUAL RYEGRASS
(LOLIUM MULTI-FLORUM) AND CEREAL
(WINTER) RYE (SECALE CEREALE)
ANNUAL RYEGRASS (LOLIUM
MULTI-FLORUM)
GERMAN MILLET
APPLICATION RATES
50-100 LBS/ACRE
60-100 LBS/ACRE
50 LBS/ACRE
SEED
TS
12' MIN.
EXISTING GROUND
B
70' MIN.
10' MIN.
A
10' MIN.
SECTION B-B
6'-7"
SECTION A-A
PLAN VIEW
3" MIN.
3" MIN.
B
70' MIN.
6" MIN. A
SIDE ELEVATION
3'
12' MIN.
10' MIN.
REINFORCED CONCRETE DRAIN SPACE
FILTER CLOTH
* MUST EXTEND FULL WIDTH
OF INGRESS AND EGRESS
OPERATION
POSITIVE DRAINAGE
TO SEDIMENT
TRAPPING DEVICE
VDOT #1 COURSE
AGGREGATE
EXISTING
PAVEMENT
WASHRACK
(OPTIONAL)
MOUNTABLE BERM
(OPTIONAL)FILTER CLOTH
5:1
EXISTING
PAVEMENT
STONE CONSTRUCTION ENTRANCE
C-SCM-03-1SOURCE: VA. DSWC, MD ESC STDSv1.1
SHEET FLOW INSTALLATION
(PERSPECTIVE VIEW)
POINTS A SHOULD BE HIGHER THAN POINT B.
DRAINAGEWAY INSTALLATION
(FRONT ELEVATION)
A B
FLOW
A
3'MAX.
FLOW
4"
FLOW
1. SET THE STAKES
3. STAPLE THE FILTER MATERAIL TO
STAKES AND EXTENT IT INTO THE
TRENCH.
4. BACKFILL AND COMPACT
THE EXCAVATED SOIL.
2. EXCAVATE A 4"x4" TRENCH
UPSLOPE ALONG THE LINE OF
STAKES.
FLOW
CONSTRUCTION OF SILT FENCE
WITHOUT WIRE SUPPORT
C-PCM-04-2BFAB. BARRIERS, SHERWOOD & WYANTv1.1
SPECIFIC APPLICATION
18" MIN. *
THIS METHOD OF INLET PROTECTION IS APPLICABLE WHERE HEAVY
CONCENTRATED FLOWS ARE EXPECTED BUT NOT WHERE PONDING
AROUND THE STRUCTURE MIGHT CAUSE EXCESSIVE INCONVENIENCE
OR DAMAGE TO ADJACENT STRUCTURES AND UNPROTECTED AREAS.
* GRAVEL SHALL BE VDOT #3, #357 OR #5 COARSE AGGREGATE.
SEDIMENT
RUNOFF WATER
WITH SEDIMENT
GRAVEL (12" MIN. DEPTH)
WIRE MESH
FILTERED
WATER
GRAVEL AND WIRE MESH
DROP INLET SEDIMENT FILTER
C-SCM-04-2SOURCE: VA. DSWCv1.1
* GRAVEL SHALL BE VDOT #3, #357 OR 5 COARSE AGGREGATE.
SPECIFIC APPLICATION
12"
THIS METHOD OF INLET PROTECTION IS APPLICABLE AT CURB INLETS WHERE
PONDING IN FRONT OF THE STRUCTURE IS NOT LIKELY TO CAUSE INCONVENIENCE
OR DAMAGE TO ADJACENT STRUCTURES AND UNPROTECTED AREAS.
WIRE MESH
FILTERED WATER
CURB INLET
GRAVEL* FILTER
RUNOFF WATER
SEDIMENT
CONCRETE GUTTER 12"
GRAVEL CURB INLET
SEDIMENT FILTER
C-SCM-04-5SOURCE: VA. DSWCv1.1
W
AS
H
IN
G
TO
N H
IG
H
W
AY
VICTORY BOULEVARD
E01
E02 E03
E04
E05
E06 E07 E08 E09
E10
G
EO
RG
E
AVONDALE ROAD
BU
N
C H
E BO
U
LEV
A
R D
BEECHDALE
RO
AD
D
EE
P C
R
EE
K B
O U
LE
V
A R
D
E11
E12
117106239
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
E00EXISTING CONDITIONS
INDEX
NORTH
AVONDALE ROAD
BU
N
C H
E
BO
U
LE
V A
R D
AVONDALE ROAD
117106239
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
E01
EXISTING CONDITIONS
NORTH
M
ATC
H
LIN
E (SEE SH
EET E02)
G
LE
N W
O O
D D
R
ALLARD ROAD
AVONDALE ROAD
AVONDALE ROAD
AVONDALE ROAD
117106239
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
E02
EXISTING CONDITIONS
NORTH
M
AT
C H
L
IN
E (S
EE
S
H
EE
T E0
1)
M
ATC
H
LIN
EET E03)
AVONDALE ROAD
BEECHDALE R
OAD
GUST LANE
GUST LANE
117106239
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
E03
EXISTING CONDITIONS
NORTH
M
AT
C H
L
IN
E (S
EE
S
H
EE
T E0
2) M
ATC
H
LIN
EET E04)
BEECHDALE R
OAD
BEECHDALE ROAD
BEECHW
OOD C
OURT
117106239
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
E04
EXISTING CONDITIONS
NORTH
M
AT
C H
L
IN
E (S
EE
S
H
EE
T E0
3) M
ATC
H
LIN
EET E05)
PR ROAD
BEECHDALE ROAD
V
IC
T O
R Y
B O
U L
E V
A R
D
B E
E C
H D
A L
E R
O A
D
117106239
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
E05
EXISTING CONDITIONS
N O
R
TH
MATCH LINE (SEE SHEET E04)
MATCH LINE (SEE SHEET E06)
VICTORY BOULEVARD
K E
N T
D R
IV
E
VICTORY BOULEVARD VICTORY BOULEVARD
117106239
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
E06
EXISTING CONDITIONS
NORTH
M
ATC
H
LIN
E (SEE SH
EET E05)
M
ATC
H
LIN
EET E07)
VICTORY BOULEVARD
VICTORY BOULEVARD
MILITARY ROAD
LO
X
LEY
R
O A
D
MILITARY ROAD
117106239
BUNCHE BOULEVARD
WATER AND SEWER IMPROVEMENTS
E07
EXISTING CONDITIONS
NORTH
M
ATC
H
LIN
E (SEE SH
EET E08)
M
AT
C H
L
IN
E (S
EE
S
H
EE
T E0
6)
| Sheets and Views |
| C02 NOTES |
| C02A NOTES |
| C03 GENERAL DETAILS |
| C04 GENERAL DETAILS |
| C05 GENERAL DETAILS |
| C06 WATER DETAILS |
| C07 GRAVITY SEWER DETAILS |
| C08 GRAVITY SEWER DETAILS |
| C09 FORCE MAIN DETAILS |
| C10 ESC CHECKLIST |
| C11 ESC NARRATIVE AND DETAILS |
| E00 EXISTING CONDITIONS INDEX |
| E01 EXISTING CONDITIONS |
| E02 EXISTING CONDITIONS |
| E03 EXISTING CONDITIONS |
| E04 EXISTING CONDITIONS |
| E05 EXISTING CONDITIONS |
| E06 EXISTING CONDITIONS |
| E07 EXISTING CONDITIONS |
File details come from the government source that posted it. Updated .